37-Sec 01 50 00 Construction Facilities and Temporary Controls.pdf

PDF 117 KB Posted

Attached to
82 W. Indian Lane - FEMA Demolition
Solicitation number
US.230082
Issued by
Montgomery County, Pennsylvania

About this file

This is a specification section for Construction Facilities and Temporary Controls applicable to the FEMA-funded demolition project at 82 West Indian Lane in West Norriton Township, Montgomery County, Pennsylvania. The specification outlines the contractor's responsibility to provide and maintain all temporary utilities, controls, and facilities throughout the construction period, including electricity, lighting, heat, ventilation, communications, water, and sanitary facilities. The contractor must establish temporary barriers, fencing, and enclosures to prevent unauthorized access and protect existing facilities and adjacent properties. Additional requirements include constructing and maintaining temporary access roads, providing parking areas for construction personnel, implementing water control and dust suppression measures, maintaining site cleanliness and waste removal, protecting installed work from damage, and providing security against vandalism and theft. The contractor must remove all temporary utilities, equipment, facilities, and materials prior to substantial completion, restore the site to specified conditions, and clean and repair any damage caused by temporary installations.

The specification does not include specific pricing terms, set-asides, incumbent information, or detailed funding amounts within this document section. However, the specification establishes that all costs associated with temporary utilities, sanitary facilities, barriers, fencing, access roads, parking, cleaning, and dust control are the contractor's responsibility at no additional cost to the owner beyond the base contract price. All work must be performed in accordance with the drawings and specifications, with dust control measures employed as directed by the Resident Project Representative. The contractor retains full responsibility for supervision, performance, and completion of all work related to temporary facilities and controls throughout the project duration.

View the file

Other files

File Type Posted
8-Doc 00 21 13 Instructions to Bidders.pdf PDF
14-Doc 00 61 13.16 Payment Bond.pdf PDF
1-00 82 W. Indian Lane FEMA Plans.pdf PDF
39-Sec 01 33 00 Submittals.pdf PDF
35-Sec 01 42 13 Organization and Reference Acronyms.pdf PDF
33-Sec 01 32 16 Construction Project Schedule.pdf PDF
42-Sec 01 70 00 Contract Closeout.pdf PDF
29-Doc 00 73 00 04 Appendix D - Hazard Mitigation Grant Conditions.pdf PDF
41-Sec 01 55 26 Traffic Regulation.pdf PDF
12-Doc 00 45 10 Bidders Acknowledgement Form.pdf PDF
9-Doc 00 45 13 Bidder Qualification Statement.pdf PDF
10-Doc 00 45 53 Agreement of Surety Company.pdf PDF
18-Doc 00 62 16 Certificate of Insurance.pdf PDF
27-Sec 01 11 13 Summary of Work.pdf PDF
7-Doc 00 21 13.1 Instructions for Electronic Bidding.pdf PDF
2-Doc 00 01 15 List of Drawing Sheets.pdf PDF
21-Doc 00 73 00 Supplementary Conditions.pdf PDF
28-Doc 00 73 00 01 Appendix A - Prevailing Wage Rates.pdf PDF
32-Sec 01 31 00 Coordination and Meetings.pdf PDF
31-Sec 01 29 00 Contract Considerations.pdf PDF
24-Doc 00 91 13 Addenda.pdf PDF
17-Doc 00 65 19.13 Contractors Affidavit.pdf PDF
15-Doc 00 61 19 Maintenance Bond.pdf PDF
49-Sec 32 92 00 Finish Grading, Seeding and Sodding.pdf PDF
26-Doc 00 73 00 - Supplementary Conditions.pdf PDF
50-Sec 31 23 33 Excavation, Backfill and Compaction.pdf PDF
4-Doc 00 01 10 Table of Contents.pdf PDF
13-Doc 00 52 00 Agreement.pdf PDF
16-Doc 00 61 13.13 Performance Bond.pdf PDF
45-Sec 02 41 16 Demolition.pdf PDF
40-Sec 01 56 39 Landscape Protection.pdf PDF
34-Sec 01 35 16 Alteration Project Procedures.pdf PDF
22-Doc 00 72 00 General Conditions.pdf PDF
19-Doc 00 65 19.19 Consent of Surety.pdf PDF
5-Doc 00 43 13 Bid Bond.pdf PDF
6-Doc 00 11 13 Advertisement for Bids.pdf PDF
25-Sec 01 00 00 Basic Requirements.pdf PDF
23-Doc 00 73 00 02 Appendix B - Public Works Employment Verification Form.pdf PDF
46-Sec 31 11 00 Clearing and Grubbing.pdf PDF
48-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
44-Sec 01 60 00 Material and Equipment.pdf PDF
20-Doc 00 65 19.16 Contractors Release of Liens.pdf PDF
3-Doc 00 01 01 Project Title Page.pdf PDF
38-Sec 01 40 00 Quality Control.pdf PDF
43-Sec 01 57 14 Erosion Control Blanket.pdf PDF
36-Sec 01 22 00 Measurement and Payment.pdf PDF
11-Doc 00 45 19 Non-Collusion Affidavit.pdf PDF
47-Sec 31 20 00 Earthwork.pdf PDF
30-Doc 00 73 00 03 Appendix C - Chapter 106 Permit.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

01 50 00-1

SECTION 01 50 00

PART 1 GENERAL

1.01 GENERAL

A. The Work of this Section shall be the responsibility of the contractor as noted in the Summary of Work (Section 01 11 13).

1.02 SECTION INCLUDES

A. Temporary Utilities: Electricity, lighting, heat, ventilation, communications service, water and sanitary facilities.

B. Temporary Controls: Barriers, enclosures and fencing, protection of the Work, water control and dust control.

C. Construction Facilities: Access roads, parking, progress cleaning, and project signage, and temporary buildings.

1.03 RELATED SECTIONS

A. Section 01 54 29: By-Pass Pumping.

B. Section 01 55 26: Traffic Regulation.

C. Section 01 57 13: Soil Erosion and Sediment Control.

D. Section 01 70 00: Contract Closeout.

1.04 TEMPORARY ELECTRICITY

A. Cost: By Contractor; provide and pay for power service required from utility source.

1.05 TEMPORARY SANITARY FACILITIES

A. Provide, maintain, and pay for required facilities and enclosures.

1.06 BARRIERS AND FENCING

A. Provide barriers and/or fencing to prevent unauthorized entry to construction areas and to protect existing facilities and adjacent properties from damage from construction operations and demolition.

B. Provide protection for plants designated to remain. Replace damaged plants.

C. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

1.07 WATER CONTROL

A. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.

01 50 00-2

B. Protect site from puddling or running water.

1.08 PROTECTION OF INSTALLED WORK

A. Protect installed Work and provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed Products. Control activity in immediate work area to prevent damage.

C. Prohibit traffic from landscaped areas.

1.09 SECURITY

A. Provide security and facilities to protect Work, existing facilities, and Owner’s operations from unauthorized entry, vandalism, or theft.

1.10 ACCESS ROADS

A. Construct and maintain temporary roads accessing public thoroughfares to serve construction area.

B. Extend and relocate as Work progress requires. Provide detours necessary for unimpeded traffic flow.

C. Provide and maintain access to fire hydrants, free of obstructions.

D. Provide means of removing mud from vehicle wheels before entering streets.

E. Designated existing on-site roads may be used for construction traffic.

1.11 PARKING

A. Provide temporary gravel surface parking areas to accommodate construction personnel.

B. When site space is not adequate, provide additional off-site parking as coordinated with

Engineer.

1.12 PROGRESS CLEANING AND WASTE REMOVAL

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.

B. Remove debris and rubbish from pipe chases, plenums, and other closed or remote spaces, prior to enclosing the space.

C. Collect and remove waste materials, debris, and rubbish from site periodically and dispose off-site.

1.13 PROJECT IDENTIFICATION – SIGN NOT REQUIRED

A. No other signs are allowed except those required by law.

01 50 00-3

1.14 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Remove temporary utilities, equipment, facilities, materials, prior to Substantial Completion inspection.

B. Remove underground installations to a minimum depth of 2 feet. Grade site as indicated.

C. Clean and repair damage caused by installation or use of temporary work.

D. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.

1.15 DUST CONTROL

A. Execute Work by methods to minimize raising dust from construction operations.

B. Provide positive means (i.e. use of sprinkling water or other methods approved by the Resident Project Representative) to prevent air-borne dust from dispersing into atmosphere.

C. Dust control measures shall be employed when required in the opinion of the Resident

Project Representative at no additional cost to Owner.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION