37-Sec 01 50 00 Construction Facilities and Temporary Controls.pdf
PDF 117 KB Posted
- Attached to
- 82 W. Indian Lane - FEMA Demolition
- Solicitation number
- US.230082
- Issued by
- Montgomery County, Pennsylvania
About this file
This is a specification section for Construction Facilities and Temporary Controls applicable to the FEMA-funded demolition project at 82 West Indian Lane in West Norriton Township, Montgomery County, Pennsylvania. The specification outlines the contractor's responsibility to provide and maintain all temporary utilities, controls, and facilities throughout the construction period, including electricity, lighting, heat, ventilation, communications, water, and sanitary facilities. The contractor must establish temporary barriers, fencing, and enclosures to prevent unauthorized access and protect existing facilities and adjacent properties. Additional requirements include constructing and maintaining temporary access roads, providing parking areas for construction personnel, implementing water control and dust suppression measures, maintaining site cleanliness and waste removal, protecting installed work from damage, and providing security against vandalism and theft. The contractor must remove all temporary utilities, equipment, facilities, and materials prior to substantial completion, restore the site to specified conditions, and clean and repair any damage caused by temporary installations.
The specification does not include specific pricing terms, set-asides, incumbent information, or detailed funding amounts within this document section. However, the specification establishes that all costs associated with temporary utilities, sanitary facilities, barriers, fencing, access roads, parking, cleaning, and dust control are the contractor's responsibility at no additional cost to the owner beyond the base contract price. All work must be performed in accordance with the drawings and specifications, with dust control measures employed as directed by the Resident Project Representative. The contractor retains full responsibility for supervision, performance, and completion of all work related to temporary facilities and controls throughout the project duration.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
01 50 00-1
SECTION 01 50 00
PART 1 GENERAL
1.01 GENERAL
A. The Work of this Section shall be the responsibility of the contractor as noted in the Summary of Work (Section 01 11 13).
1.02 SECTION INCLUDES
A. Temporary Utilities: Electricity, lighting, heat, ventilation, communications service, water and sanitary facilities.
B. Temporary Controls: Barriers, enclosures and fencing, protection of the Work, water control and dust control.
C. Construction Facilities: Access roads, parking, progress cleaning, and project signage, and temporary buildings.
1.03 RELATED SECTIONS
A. Section 01 54 29: By-Pass Pumping.
B. Section 01 55 26: Traffic Regulation.
C. Section 01 57 13: Soil Erosion and Sediment Control.
D. Section 01 70 00: Contract Closeout.
1.04 TEMPORARY ELECTRICITY
A. Cost: By Contractor; provide and pay for power service required from utility source.
1.05 TEMPORARY SANITARY FACILITIES
A. Provide, maintain, and pay for required facilities and enclosures.
1.06 BARRIERS AND FENCING
A. Provide barriers and/or fencing to prevent unauthorized entry to construction areas and to protect existing facilities and adjacent properties from damage from construction operations and demolition.
B. Provide protection for plants designated to remain. Replace damaged plants.
C. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.
1.07 WATER CONTROL
A. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.
01 50 00-2
B. Protect site from puddling or running water.
1.08 PROTECTION OF INSTALLED WORK
A. Protect installed Work and provide special protection where specified in individual specification sections.
B. Provide temporary and removable protection for installed Products. Control activity in immediate work area to prevent damage.
C. Prohibit traffic from landscaped areas.
1.09 SECURITY
A. Provide security and facilities to protect Work, existing facilities, and Owner’s operations from unauthorized entry, vandalism, or theft.
1.10 ACCESS ROADS
A. Construct and maintain temporary roads accessing public thoroughfares to serve construction area.
B. Extend and relocate as Work progress requires. Provide detours necessary for unimpeded traffic flow.
C. Provide and maintain access to fire hydrants, free of obstructions.
D. Provide means of removing mud from vehicle wheels before entering streets.
E. Designated existing on-site roads may be used for construction traffic.
1.11 PARKING
A. Provide temporary gravel surface parking areas to accommodate construction personnel.
B. When site space is not adequate, provide additional off-site parking as coordinated with
Engineer.
1.12 PROGRESS CLEANING AND WASTE REMOVAL
A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.
B. Remove debris and rubbish from pipe chases, plenums, and other closed or remote spaces, prior to enclosing the space.
C. Collect and remove waste materials, debris, and rubbish from site periodically and dispose off-site.
1.13 PROJECT IDENTIFICATION – SIGN NOT REQUIRED
A. No other signs are allowed except those required by law.
01 50 00-3
1.14 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS
A. Remove temporary utilities, equipment, facilities, materials, prior to Substantial Completion inspection.
B. Remove underground installations to a minimum depth of 2 feet. Grade site as indicated.
C. Clean and repair damage caused by installation or use of temporary work.
D. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.
1.15 DUST CONTROL
A. Execute Work by methods to minimize raising dust from construction operations.
B. Provide positive means (i.e. use of sprinkling water or other methods approved by the Resident Project Representative) to prevent air-borne dust from dispersing into atmosphere.
C. Dust control measures shall be employed when required in the opinion of the Resident
Project Representative at no additional cost to Owner.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
File details come from the government source that posted it. Updated .