44-Sec 01 60 00 Material and Equipment.pdf

PDF 135 KB Posted

Attached to
82 W. Indian Lane - FEMA Demolition
Solicitation number
US.230082
Issued by
Montgomery County, Pennsylvania

About this file

This is a Material and Equipment specification document (Section 01 60 00) applicable to the FEMA Demolition project at 82 West Indian Lane in West Norriton Township, Montgomery County, Pennsylvania. The specification establishes requirements for all products and equipment to be used on the project, including transportation, handling, storage, protection, and product substitution procedures. All materials and equipment must comply with manufacturer instructions and contract specifications, with interchangeable components sourced from the same manufacturer when replacing existing items. The document prohibits the use of materials removed from the existing premises unless explicitly authorized by contract documents. Products must be inspected upon receipt to verify compliance with specifications, correct quantities, and absence of damage. Storage must follow manufacturer guidelines with seals and labels maintained, sensitive products stored in weather-tight climate-controlled enclosures, and exterior fabricated products placed on sloped supports above ground to prevent deterioration.

The specification allows for product options when materials are specified by reference standards or description only, with manufacturers named in the specifications having no substitution options unless explicitly permitted. Substitution requests may be considered only when products become unavailable through no fault of the contractor and must include complete documentation demonstrating compliance and equivalence. All equipment furnished must be guaranteed by the manufacturer against defects in workmanship, design, and material for a minimum of 12 months from the date of continuous operation or 18 months from delivery, whichever occurs first. The manufacturer is responsible for providing all necessary parts for corrections, with the contractor responsible for installation. If equipment operation is interrupted due to defects requiring replacement, the 12-month guarantee restarts upon installation of the replacement item.

View the file

Other files

File Type Posted
8-Doc 00 21 13 Instructions to Bidders.pdf PDF
14-Doc 00 61 13.16 Payment Bond.pdf PDF
1-00 82 W. Indian Lane FEMA Plans.pdf PDF
39-Sec 01 33 00 Submittals.pdf PDF
35-Sec 01 42 13 Organization and Reference Acronyms.pdf PDF
33-Sec 01 32 16 Construction Project Schedule.pdf PDF
42-Sec 01 70 00 Contract Closeout.pdf PDF
29-Doc 00 73 00 04 Appendix D - Hazard Mitigation Grant Conditions.pdf PDF
41-Sec 01 55 26 Traffic Regulation.pdf PDF
12-Doc 00 45 10 Bidders Acknowledgement Form.pdf PDF
9-Doc 00 45 13 Bidder Qualification Statement.pdf PDF
10-Doc 00 45 53 Agreement of Surety Company.pdf PDF
18-Doc 00 62 16 Certificate of Insurance.pdf PDF
27-Sec 01 11 13 Summary of Work.pdf PDF
7-Doc 00 21 13.1 Instructions for Electronic Bidding.pdf PDF
2-Doc 00 01 15 List of Drawing Sheets.pdf PDF
21-Doc 00 73 00 Supplementary Conditions.pdf PDF
28-Doc 00 73 00 01 Appendix A - Prevailing Wage Rates.pdf PDF
32-Sec 01 31 00 Coordination and Meetings.pdf PDF
31-Sec 01 29 00 Contract Considerations.pdf PDF
24-Doc 00 91 13 Addenda.pdf PDF
17-Doc 00 65 19.13 Contractors Affidavit.pdf PDF
15-Doc 00 61 19 Maintenance Bond.pdf PDF
49-Sec 32 92 00 Finish Grading, Seeding and Sodding.pdf PDF
26-Doc 00 73 00 - Supplementary Conditions.pdf PDF
50-Sec 31 23 33 Excavation, Backfill and Compaction.pdf PDF
4-Doc 00 01 10 Table of Contents.pdf PDF
13-Doc 00 52 00 Agreement.pdf PDF
16-Doc 00 61 13.13 Performance Bond.pdf PDF
45-Sec 02 41 16 Demolition.pdf PDF
40-Sec 01 56 39 Landscape Protection.pdf PDF
34-Sec 01 35 16 Alteration Project Procedures.pdf PDF
22-Doc 00 72 00 General Conditions.pdf PDF
19-Doc 00 65 19.19 Consent of Surety.pdf PDF
5-Doc 00 43 13 Bid Bond.pdf PDF
6-Doc 00 11 13 Advertisement for Bids.pdf PDF
25-Sec 01 00 00 Basic Requirements.pdf PDF
37-Sec 01 50 00 Construction Facilities and Temporary Controls.pdf PDF
23-Doc 00 73 00 02 Appendix B - Public Works Employment Verification Form.pdf PDF
46-Sec 31 11 00 Clearing and Grubbing.pdf PDF
48-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
20-Doc 00 65 19.16 Contractors Release of Liens.pdf PDF
3-Doc 00 01 01 Project Title Page.pdf PDF
38-Sec 01 40 00 Quality Control.pdf PDF
43-Sec 01 57 14 Erosion Control Blanket.pdf PDF
36-Sec 01 22 00 Measurement and Payment.pdf PDF
11-Doc 00 45 19 Non-Collusion Affidavit.pdf PDF
47-Sec 31 20 00 Earthwork.pdf PDF
30-Doc 00 73 00 03 Appendix C - Chapter 106 Permit.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MATERIAL AND EQUIPMENT

01 60 00-1

SECTION 01 60 00

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Products.

2. Transportation and handling.

3. Storage and protection.

4. Product options.

5. Substitutions.

6. Equipment Guarantee

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 40 00: Quality Control

1.03 PRODUCTS

A. Do not use materials and equipment removed from existing premises, except as specifically permitted by the Contract Documents.

B. Provide interchangeable components of the same manufacturer for components being replaced.

1.04 TRANSPORTATION AND HANDLING

A. Transport and handle Products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to assure that Products comply with requirements, quantities are correct, and Products are undamaged.

C. Provide equipment and personnel to handle Products by methods to prevent soiling, disfigurement, or damage.

1.05 STORAGE AND PROTECTION

A. Store and protect Products in accordance with manufacturers’ instructions.

B. Store with seals and labels intact and legible.

C. Store sensitive Products in weather tight, climate controlled, enclosures in an environment favorable to Product.

01 60 00-2

D. For exterior storage of fabricated Products, place on sloped supports above ground.

E. Provide off-site storage and protection when site does not permit on-site storage or protection.

F. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of Products.

G. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.

H. Provide equipment and personnel to store Products by methods to prevent soiling, disfigurement, or damage.

I. Arrange storage of Products to permit access for inspection. Periodically inspect to assure

Products are undamaged and are maintained under acceptable condition.

1.06 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions:

Submit a request for substitution for any manufacturer not named in accordance with the following Article.

1.07 SUBSTITUTIONS

A. Substitutions may be considered when a Product becomes unavailable through no fault of the Contractor.

B. Document each request with complete data substantiating compliance of proposed

Substitution with Contract Documents.

C. A request constitutes a representation that Contractor:

1. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.

2. Will provide the same warranty for the Substitution as for the specified Product.

3. Will coordinate installation and make changes to other Work which may be required for the Work to be complete with no additional cost to Owner.

4. Waives claims for additional costs or time extension which may subsequently become apparent.

5. Will reimburse Owner and Engineer for review or redesign services associated with re-approval by authorities.

D. Substitutions will not be considered when they are indicated or implied on shop drawing or Product data submittals, without separate written request, or when acceptance will require

01 60 00-3 revision to the Contract Documents.

E. Substitution Submittal Procedure:

1. Submit three copies of request for Substitution for consideration. Limit each request to one (1) proposed Substitution.

2. Submit Shop Drawings, Product data, and certified test results attesting to the proposed Product equivalence. Burden of proof is on proposer.

3. Engineer will notify Contractor in writing of decision to accept or reject request.

F. For each equipment item in which the manufacturer was listed on the Bid Form, Engineer reserves the right to require Contractor to use the equipment item of the listed manufacturer.

1.08 EQUIPMENT GUARANTEE

A. All equipment furnished shall be guaranteed by the manufacturer to be free from all defects in workmanship, design and material for a period of not less than 12 months from the date that the equipment is placed in continuous operation or not less than 18 months from the date of delivery to the job site, whichever occurs first.

B. This guarantee shall be in addition to the correction period provided by Contractor under

Article 13, paragraph 13.07 of the General Conditions and the Maintenance Bond provided by Contractor under Paragraph 1.09 of the Supplementary Conditions.

C. The manufacturer shall furnish all parts necessary to correct defective work and Contractor shall be responsible for the installation of all parts.

D. If the continuous operation of a piece of equipment is interrupted due to a defect requiring the replacement of the equipment, or part thereof, the equipment manufacturer's 12-month guarantee shall restart from the beginning when the required replacement item is installed and the equipment is returned to continuous operation.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION