This amendment modifies a solicitation for construction services. The Department of Veterans Affairs seeks to upgrade infrastructure for its Enterprise Human Resources Management system at its location in Chillicothe, Ohio. The amendment extends the deadline for submitting additional technical questions to November 30th at noon and pushes back the bid due date from December 4th to December 18th at noon Mountain Time. Bids received after the revised due date and time will not be accepted. The amendment aims to allow offerors more time to pose questions and submit final bids for the infrastructure upgrade project.

View the file

Other files

File Type Posted
Abstract of offers - Chillicothe Bid Opening 01172024 signed.pdf PDF
S06 - Amendment 0009 Bid Opening.pdf PDF
S06 - Amendment 0008 Extend due date to 01172024.pdf PDF
S06 - 36C77623B0058 0007.pdf PDF
S06 - Amendment 0007 Att 10 - 14.063_024-EP100 - ELECTRICAL PLAN - BASEMENT FLOOR.pdf PDF
S06 - Amendment 0007 Att 13 - 14.116_E616.31 - PANELBOARD SCHEDULES.pdf PDF
S06 - Amendment 0007 Att 4 - Chiillicothe VA Lead Paint Survey Report.pdf PDF
S06 - Amendment 0007 Att 7 - 000-TS100 - CAMPUS TECHNOLOGY SITE PLAN.pdf PDF
S06 - Amendment 0007 Att 6 - 000-TN500 - TECHNOLOGY DETAILS.pdf PDF
S06 - Amendment 0007 Att 3 - 2023-01 AHERA.pdf PDF
S06 - Amendment 0007 Att 11 - 14.077_031-EP100 - ELECTRICAL PLAN - GROUND FLOOR.pdf PDF
S06 - Amendment 0007 Att 16 - 026-TN100 - BASEMENT PLAN -TECHNOLOGY.pdf PDF
S06 - Amendment 0007 Att 14 - 018-TN209 - TECHNOLOGY ENLARGEMENT.pdf PDF
S06 - Amendment 0007 Att 8 - 13.038_030-MD101 - MECHANICAL DEMOLITION PLAN - FIRST FLOOR.pdf PDF
S06 - Amendment 0007 Att 12 - 14.080_035-EP100 - ELECTRICAL PLAN - BASEMENT.pdf PDF
S06 - Amendment 0007 Att 1 Technical questions Round 2 responses.pdf PDF
S06 - Amendment 0007 Att 2 - Final SWP3.pdf PDF
S06 - Amendment 0007 Att 15 - 018-TN210 - TECHNOLOGY ENLARGEMENT.pdf PDF
S06 - Amendment 0007 Att 5 - 000-TN400 - TECHNOLOGY RISER DIAGRAMS.pdf PDF
S06 - Amendment 0007 Att 9 - 14.062_023-EP101 - ELECTRICAL PLAN - FIRST FLOOR.pdf PDF
Amendment 0005 36C77623B0058.pdf PDF
Amendment 0005 - Attachment Addendum 1.zip ZIP file
Amendment 0005 - Attachment - Vendor Questions_Responses final.pdf PDF
Amendment 0004 36C77623B0058.pdf PDF
Amendment 0003 36C77623B0058.docx DOCX document
Att 10 Volume 10 - Technology_Combined.pdf PDF
Att 8 Volume 8 - Electrical_Combined.pdf PDF
Att 6 Volume 6 - Mechanical_Combined.pdf PDF
Att 9 Volume 9 - Electrical_Combined.pdf PDF
Att 13 Volume 13 - Fiber_Combined.pdf PDF
Att 4 Volume 4 - Architectural_Combined.pdf PDF
Att 5 Volume 5 - Fire Suppression_Combined.pdf PDF
Att 14 S04 - Site Visit sign in 10-11-2023.pdf PDF
Att 7 Volume 7 - Mechanical_Combined.pdf PDF
Att 12 Volume 12 - Fiber_Combined.pdf PDF
Att 11 Volume 11 - Technology_Combined.pdf PDF
Att 3 Volume 3 - Architectural_Combined.pdf PDF
Att 2 Volume 2 - Civil_Combined (1).pdf PDF
36C77623B0058 0002.docx DOCX document
Att 1 Volume 1 - General and Civil_Combined.pdf PDF
DBA Wage Rates Construction - Ross Cty.pdf PDF
36C77623B0058 0001.docx DOCX document
Attachment 04 - DBA Wage Determination.pdf PDF
Updated _Specifications_Combined.pdf PDF
Attachment 08 - SOW attach Volume 1 Part 3.pdf PDF
Attachment 09 - SOW attach Volume 1 Part 4.pdf PDF
Attachment 04 - Wage Rate Determination - Chillicothe.pdf PDF
Attachment 11 - SOW attach Volume 1 Part 6.pdf PDF
Attachment 19 - SOW attach Volume 3 Part 4.pdf PDF
Attachment 17 - SOW attach Volume 3 Part 2.pdf PDF
Show 40 more

Latest 50 of 65 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 2

538-21-701

36C776

Department of Veterans Affairs Program Contracting Activity Central

6100 Oak Tree Blvd, Suite 490 Independence OH 44131

36C776

Department of Veterans Affairs Program Contracting Activity Central

6100 Oak Tree Blvd, Suite 490 Independence OH 44131

To all Offerors/Bidders

36C77623B0058

09-29-2023

X

X X

December 18, 2023/12:00N Mountain Time

X 0

AMENDMENT 0006 ISSUED TO ACCEPT ADDITIONAL TECHNICAL QUESTIONS.

TECHNICAL QUESTIONS MUST BE RECEIVED BY THURSDAY 11/30/2023, NLT 12:00N MOUNTAIN TIME.

AMENDMENT 0006 ALSO EXTENDS THE BID DUE DATE FROM MONDAY 12/04/2023 TO MONDAY 12/18/2023.

BIDS MUST BE RECEIVED NLT 12:00N MOUNTAIN TIME. BIDS SUBMITTED AFTER THIS TIME/DATE WILL NOT BE ACCEPTED.

JENNIFER SALERNO-DICIUCCIO

CONTRACTING OFFICER

36C77623B0058 EHRM Infrastructure Upgrades Construction

IFB AMENDMENT 0006 DOES THE FOLLOWING:

- Opens up another round of Technical Questions – DUE NLT NOON Mountain Time on November 30, 2023.

- Extends the bid due date from December 04, 2023, to December 18, 2023.