This solicitation package is for a construction project to renovate an outpatient mental health clinic at a Department of Veterans Affairs medical center. The project involves demolishing and renovating approximately 28,000 square feet on the first and second floors as well as 3,000 square feet in the basement to construct new outpatient mental health clinics. The scope of work includes renovating the basement wing and first and second floors along with supporting work in the basement and attic. Exterior improvements such as a new elevator and shaft are part of the project. Bids are due on a date to be specified in the solicitation for a firm fixed price construction contract valued between $10-20 million. The contract is set aside exclusively for verified Service-Disabled Veteran-Owned Small Businesses and has a maximum completion time of 588 calendar days from notice to proceed.

View the file

Other files

File Type Posted
Award Announcement 36C24420C0112.pdf PDF
General Decision Number PA20200083.pdf PDF
36C24420B0003 0003.pdf PDF
00 01 15 - List of Drawing Sheets - ADD-01.pdf PDF
07 Architecture.pdf PDF
36C24420B0003 Amendment 0002.pdf PDF
10 22 26.13 - Operable Partitions - ADD-01.pdf PDF
RFI LOG_542-18-106_08052020.r2.pdf PDF
Sign In Sheet no. 3 B4A B 07162020.pdf PDF
Sign In Sheet B4A B 07162020.pdf PDF
03 Structural 54218106_Drawings_ADD-01_080320.pdf PDF
08 Interiors 54218106_Drawings_ADD-01_080320.pdf PDF
07 13 52 - Modified Bituminous Sheet Waterproofing - ADD-01.pdf PDF
07 60 00 - Flashing and Sheet Metal - ADD-01.pdf PDF
01 33 23 - Shop Drawings Product Data Samples - ADD-01.pdf PDF
00 01 10 - TOC - ADD-01.pdf PDF
11 Plumbing 54218106_Drawings_ADD-01_080320.pdf PDF
ADD-01 Narrative.pdf PDF
10 21 13 - Toilet Compartments - ADD-01.pdf PDF
07 27 27 - Fluid-Applied Membrane Air Barrier Vapor Retardg - ADD-01.pdf PDF
00 General 54218106_Drawings_ADD-01_080320.pdf PDF
11 73 00 - Ceiling Mounted Patient Lift System - ADD-01.pdf PDF
36C24420B0003 Amendment 0001 - Attachment.pdf PDF
36C24420B0003 AMENDMENT 0001.pdf PDF
36C24420B0003 MAP for Site Visit.pdf PDF
04 Structural 54218106_Drawings_FinalCD_013120.pdf PDF
10 Mechanical 54218106_Drawings_FinalCD_013120.pdf PDF
06 Interiors 54218106_Drawings_FinalCD_013120.pdf PDF
09 Plumbing 54218106_Drawings_FinalCD_013120.pdf PDF
08 Fire Protection 54218106_Drawings_FinalCD_013120.pdf PDF
02 Hazardous 54218106_Drawings_FinalCD_013120.pdf PDF
07 Equipment 54218106_Drawings_FinalCD_013120.pdf PDF
01 General 54218106_Drawings_FinalCD_013120.pdf PDF
05 Architectural 54218106_Drawings_FinalCD_013120.pdf PDF
11 Electrical 54218106_Drawings_FinalCD_013120.pdf PDF
03 Civil Landscape 54218106_Drawings_FinalCD_013120.pdf PDF
54218106-Spec-Vol 3_FinalCD_013120.pdf PDF
36C24420B0003.docx DOCX document
PCRA 3-2019 building 4.pdf PDF
54218106-Spec-Vol 2_FinalCD_013120.pdf PDF
54218106-Spec-Vol 1_FinalCD_013120.pdf PDF
COVID Guidelines.pdf PDF
54218106-Spec-Vol 4_FinalCD_013120.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F E

C F

E C

FEC

FEC

F E

C F

E C

F E

C

1 2 3 4 5

6 7

8 9 10 11 12

AA

BB

CC

D.2D.2

E.2E.2

E.8

E.8

F.8F.8

HH

II

JJ

DD

EE

F

F

GG

6.86.2

G.5G.5

C.2

ROOF

ROOF

ROOF

DN

DN

UP

CONSULT

WOMENS

WAITING

ELEC

TOILET

TOILET

NEURO

PSYCH/

TESTING

NEURO

PSYCH/

TESTING

NEURO

PSYCH/

TESTING

NEURO

PSYCH/

TESTING

NEURO

PSYCH/

TESTING

NEURO

PSYCH/

TESTING

NEURO

PSYCH/

TESTING

NEURO

PSYCH/

TESTING

STORAGE

206A

STORAGE

210A

STORAGE

213A

STORAGE

213B

GROUP

THERAPY

EAST STAIR

214A

NURSE/

TRIAGE

215A

CHECK-IN

CLERKS

TOILETS

TOILETS

STAFF ROOM

VJO / TCM /

TBI

SUD CONSULT

OFFICE

SUD CONSULT

OFFICE

TOILET

TOILET

BIO-FEEDBACK

TREATMENT

BIO-FEEDBACK

DR. PEKALA

BIO-FEEDBACK

DANIELLE

BIO-FEEDBACK

OFFICE

STORAGE

226B

WEST STAIR

219A

SUD CONSULT

OFFICE

SUD CONSULT

OFFICE

SUD CONSULT

OFFICE

SUD CONSULT

OFFICE

SUD CONSULT

OFFICE

IT

ELEC

SUD CONSULT

OFFICE

SUD CONSULT

OFFICE

SUD CONSULT

OFFICE

HOTEL

CONSULT

HOTEL

CONSULT

STORAGE

230A

EAST

CORRIDOR

200E

CENTER

CORRIDOR

200C

WEST

CORRIDOR

200W

C.1

A440

CONFERENCE

WAITING/

BREAK-OUT

200A

A440

W01W01 W01

0 13

BIO-FEEDBACK

INTAKE

226A

BIO-FEEDBACK

WAITING

HAC

219B

A. REFER TO GI002 “CONSTRUCTION PERIOD SCHEDULING OF WORK – GENERAL NOTES”

REGARDING THE VA’S DISCRETION IN SELECTING WORK TO BE DONE AFTERHOURS/OFF-

HOURS.

B. REFER TO GI002 “CONSTRUCTION PERIOD SCHEDULING OF WORK – ADDITIONAL NOTES FOR

STERILE PROCESSING SERVICE (SPS)” REGARDING WORK IN, ADJACENT TO, OR THAT MAY

AFFECT SPS.

C. GENERAL ARRANGEMENT AND OVERALL PLANS ARE INTENDED TO GIVE AN OVERVIEW OF

WORK. REFER TO CORRESPONDING DRAWINGS ACROSS ALL DISCIPLINES FOR FULL EXTENT

OF WORK.

EXISTING CONSTRUCTION

TO REMAIN

NEW PARTITION WALL

AREA NOT IN CONTRACT

MATCHLINE

FIRE EXTINGUISHER

CABINET - REFER TO

DETAIL 1/A515

SURFACE MOUNTED FIRE

EXTINGUISHER CABINET

REFER TO DETAIL 2/A515

2 HOUR FIRE &

SMOKE

SEPARATION

1 HOUR FIRE &

SMOKE

SEPARATION

1 2 3 4 5 6 7 8 9 10

1 2 3 4 5 6 7 8 9 10

A

B

C

D

E

F

A

B

C

D

E

F

CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Drawing Title

Approved: Project Director

Phase Project Title Project Number

Building Number

Drawing NumberLocation

Issue Date Checked Drawn

VA FORM 08-6231

FULLY SPRINKLERED

FINAL CONSTRUCTION DOCUMENTS - NOT FOR CONSTRUCTION

31 JAN 2020

GENERAL ARRANGEMENT

PLAN - SECOND FLOOR

RENOVATE BUILDING 4A&B FLOORS

OUTPATIENT MENTAL HEALTH CLINIC

VA Medical Center, Coatesville PA

RFR ARCH

542-18-106

A012

FINAL CONSTRUCTION

DOCUMENTS SUBMISSION

1/8" = 1'-0"

GENERAL ARRANGEMENT PLAN - SECOND FLOOR

PLAN GENERAL NOTES

PLAN LEGEND

0 4' 8' 16'

Revisions: Date:

FINAL CONCEPT DOCUMENTS SUBMISSION 15 JAN 2019

50% CONSTRUCTION DOCUMENTS SUBMISSION 16 APR 2019

MOD - 50% CONSTRUCTION DOCUMENTS SUBMISSION 21 JUN 2019

100% CONSTRUCTION DOCUMENTS SUBMISSION 3 JAN 2020

FINAL CONSTRUCTION DOCUMENTS SUBMISSION 31 JAN 2020