This solicitation package is for a construction project to renovate building 4A and 4B at the Coatesville VA Medical Center in Coatesville, Pennsylvania. The project scope includes demolishing approximately 28,000 square feet of existing space on the first and second floors to construct a new outpatient mental health clinic, as well as renovating 3,000 square feet in the basement wing. Work will be completed according to VA design guides and applicable building codes.

The solicitation is set aside exclusively for service-disabled veteran-owned small businesses verified through the Center for Veterans Enterprise. The construction work is divided into three items: general construction, electrical work, and mechanical work including HVAC, plumbing, and fire protection. The estimated contract value is between $10-20 million. Interested contractors must be able to provide 100% performance and payment bonds and a 20% bid guarantee. The contract type will be firm-fixed price with an anticipated award date in 2020. The maximum completion schedule is 588 calendar days from notice to proceed.

View the file

Other files

File Type Posted
Award Announcement 36C24420C0112.pdf PDF
General Decision Number PA20200083.pdf PDF
36C24420B0003 0003.pdf PDF
00 01 15 - List of Drawing Sheets - ADD-01.pdf PDF
07 Architecture.pdf PDF
36C24420B0003 Amendment 0002.pdf PDF
10 22 26.13 - Operable Partitions - ADD-01.pdf PDF
RFI LOG_542-18-106_08052020.r2.pdf PDF
Sign In Sheet no. 3 B4A B 07162020.pdf PDF
Sign In Sheet B4A B 07162020.pdf PDF
03 Structural 54218106_Drawings_ADD-01_080320.pdf PDF
A012 54218106_Drawings_FinalCD_013120.pdf PDF
08 Interiors 54218106_Drawings_ADD-01_080320.pdf PDF
07 13 52 - Modified Bituminous Sheet Waterproofing - ADD-01.pdf PDF
07 60 00 - Flashing and Sheet Metal - ADD-01.pdf PDF
00 01 10 - TOC - ADD-01.pdf PDF
11 Plumbing 54218106_Drawings_ADD-01_080320.pdf PDF
ADD-01 Narrative.pdf PDF
10 21 13 - Toilet Compartments - ADD-01.pdf PDF
07 27 27 - Fluid-Applied Membrane Air Barrier Vapor Retardg - ADD-01.pdf PDF
00 General 54218106_Drawings_ADD-01_080320.pdf PDF
11 73 00 - Ceiling Mounted Patient Lift System - ADD-01.pdf PDF
36C24420B0003 Amendment 0001 - Attachment.pdf PDF
36C24420B0003 AMENDMENT 0001.pdf PDF
36C24420B0003 MAP for Site Visit.pdf PDF
04 Structural 54218106_Drawings_FinalCD_013120.pdf PDF
10 Mechanical 54218106_Drawings_FinalCD_013120.pdf PDF
06 Interiors 54218106_Drawings_FinalCD_013120.pdf PDF
09 Plumbing 54218106_Drawings_FinalCD_013120.pdf PDF
08 Fire Protection 54218106_Drawings_FinalCD_013120.pdf PDF
02 Hazardous 54218106_Drawings_FinalCD_013120.pdf PDF
07 Equipment 54218106_Drawings_FinalCD_013120.pdf PDF
01 General 54218106_Drawings_FinalCD_013120.pdf PDF
05 Architectural 54218106_Drawings_FinalCD_013120.pdf PDF
11 Electrical 54218106_Drawings_FinalCD_013120.pdf PDF
03 Civil Landscape 54218106_Drawings_FinalCD_013120.pdf PDF
54218106-Spec-Vol 3_FinalCD_013120.pdf PDF
36C24420B0003.docx DOCX document
PCRA 3-2019 building 4.pdf PDF
54218106-Spec-Vol 2_FinalCD_013120.pdf PDF
54218106-Spec-Vol 1_FinalCD_013120.pdf PDF
COVID Guidelines.pdf PDF
54218106-Spec-Vol 4_FinalCD_013120.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Coatesville VA Medical Center

Coatesville, Pennsylvania 19320 Renovate Building 4 A & B Floors Outpatient Mental Health Clinic

Bancroft Architects + Engineers 05-01-17

Contract No. 36C24418C0144 Station Project No. 542-18-106 Bancroft-AE Project No. 18-102 01 33 23-1 08-03-2020

SECTION 01 33 23

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

PART 1 – GENERAL

1.1 DESCRIPTION

A. This specification defines the general requirements and procedures for submittals. A submittal is information submitted for VA review to establish compliance with the contract documents.

B. Detailed submittal requirements are found in the technical sections of the contract specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective technical specifications at no additional cost to the government.

C. VA approval of a submittal does not relieve the Contractor of the responsibility for any error which may exist. The Contractor is responsible for fully complying with all contract requirements and the satisfactory construction of all work, including the need to check, confirm, and coordinate the work of all subcontractors for the project.

Non-compliant material incorporated in the work will be removed and replaced at the Contractor’s expense.

1.2 DEFINITIONS

A. Preconstruction Submittals: Submittals which are required prior to issuing contract notice to proceed or starting construction. For example, Certificates of insurance; Surety bonds; Site-specific safety plan; Construction progress schedule; Schedule of values; Submittal register; List of proposed subcontractors.

B. Shop Drawings: Drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work. Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be integrated and coordinated.

C. Product Data: Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions, and brochures, which describe and illustrate size, physical appearance, and other characteristics of materials, systems, or equipment for some portion of the work. Samples of warranty language when the contract requires extended product warranties.

Renovate Building 4 A & B Floors Outpatient Mental Health Clinic

Bancroft-AE Project No. 18-102 01 33 23-2 08-03-2020

D. Samples: Physical examples of materials, equipment, or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged. Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project. Field samples and mock-ups constructed to establish standards by which the ensuing work can be judged.

E. Design Data: Calculations, mix designs, analyses, or other data pertaining to a part of work.

F. Test Reports: Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work. Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

G. Certificates: Document required of Contractor, or of a manufacturer, supplier, installer, or subcontractor through Contractor. The purpose is to document procedures, acceptability of methods, or personnel qualifications for a portion of the work.

H. Manufacturer's Instructions: Pre-printed material describing installation of a product, system, or material, including special notices and MSDS concerning impedances, hazards, and safety precautions.

I. Manufacturer's Field Reports: Documentation of the testing and verification actions taken by manufacturer's representative at the job site on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must indicate whether the material, product, or system has passed or failed the test.

J. Operation and Maintenance Data: Manufacturer data that is required to operate, maintain, troubleshoot, and repair equipment, including manufacturer's help, parts list, and product line documentation. This data shall be incorporated in an operations and maintenance manual.

K. Closeout Submittals: Documentation necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a phase of construction on a multi-phase contract.

Renovate Building 4 A & B Floors Outpatient Mental Health Clinic

Bancroft-AE Project No. 18-102 01 33 23-3 08-03-2020

1.3 SUBMITTAL REGISTER

A. The submittal register will list items of equipment and materials for which submittals are required by the specifications. This list may not be all inclusive and additional submittals may be required by the specifications. The Contractor is not relieved from supplying submittals required by the contract documents but which have been omitted from the submittal register.

B. The submittal register will serve as a scheduling document for submittals and will be used to control submittal actions throughout the contract period.

C. The VA will provide the initial submittal register in electronic format. Thereafter, the Contractor shall track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the

VA.

D. The Contractor shall update the submittal register as submittal actions occur and maintain the submittal register at the project site until final acceptance of all work by Contracting Officer.

E. The Contractor shall submit formal monthly updates to the submittal register in electronic format. Each monthly update shall document actual submission and approval dates for each submittal.

1.4 SUBMITTAL SCHEDULING

A. Submittals are to be scheduled, submitted, reviewed, and approved prior to the acquisition of the material or equipment.

B. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow time for potential resubmittal.

C. No delay costs or time extensions will be allowed for time lost in late submittals or resubmittals.

D. All submittals are required to be approved prior to the start of the specified work activity.

1.5 SUBMITTAL PREPARATION

A. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

B. Collect required data for each specific material, product, unit of work, or system into a single submittal. Prominently mark choices, options, Renovate Building 4 A & B Floors Outpatient Mental Health Clinic

Bancroft-AE Project No. 18-102 01 33 23-4 08-03-2020 and portions applicable to the submittal. Partial submittals will not be accepted for expedition of construction effort. Submittal will be returned without review if incomplete.

C. If available product data is incomplete, provide Contractor-prepared documentation to supplement product data and satisfy submittal requirements.

D. All irrelevant or unnecessary data shall be removed from the submittal to facilitate accuracy and timely processing. Submittals that contain the excessive amount of irrelevant or unnecessary data will be returned with review.

E. Provide a transmittal form for each submittal with the following information:

1. Project title, location and number.

2. Construction contract number.

3. Date of the drawings and revisions.

4. Name, address, and telephone number of subcontractor, supplier, manufacturer, and any other subcontractor associated with the submittal.

5. List paragraph number of the specification Section and sheet number of the contract drawings by which the submittal is required.

6. When a resubmission, add alphabetic suffix on submittal description.

For example, submittal 18 would become 18A, to indicate resubmission.

7. Product identification and location in project.

F. The Contractor is responsible for reviewing and certifying that all submittals are in compliance with contract requirements before submitting for VA review. Proposed deviations from the contract requirements are to be clearly identified. All deviations submitted must include a side by side comparison of item being proposed against item specified. Failure to point out deviations will result in the VA requiring removal and replacement of such work at the Contractor's expense.

G. Stamp, sign, and date each submittal transmittal form indicating action taken.

Renovate Building 4 A & B Floors Outpatient Mental Health Clinic

Bancroft-AE Project No. 18-102 01 33 23-5 08-03-2020

H. Stamp used by the Contractor on the submittal transmittal form to certify that the submittal meets contract requirements is to be similar to the following:

Renovate Building 4 A & B Floors Outpatient Mental Health Clinic

Bancroft-AE Project No. 18-102 01 33 23-6 08-03-2020

| CONTRACTOR |

| (Firm Name) |

| Approved |

| Approved with corrections as noted on submittal data and/or |

| attached sheets(s) |

| SIGNATURE: |

| TITLE: |

| DATE: |

1.6 SUBMITTAL FORMAT AND TRANSMISSION

A. [ADD-01] Electronic Submittal Procedures: Provide submittals in electronic format, with the exception of material samples. Use PDF as the electronic format, unless otherwise specified or directed by the

Contracting Officer.

1. [ADD-01] Shop drawing and product data submittals shall be transmitted to Architect in electronic (PDF) format using Submittal

Exchange website services furnished to the Contractor by the VA.

a. [ADD-01] The intent of electronic submittals is to expedite the construction process by reducing paperwork, improving information flow, and decreasing turnaround time. All submittals, RFIs, Instructions to Contractors (ITCs), daily

Renovate Building 4 A & B Floors Outpatient Mental Health Clinic

Bancroft-AE Project No. 18-102 01 33 23-7 08-03-2020 reports, meeting minutes, test reports, photos, inspection reports, closeout documents and other pertinent project information shall be posted on Submittal Exchange by the

Contractor.

b. [ADD-01] The electronic submittal process is not intended for color samples, color charts, or physical material samples.

2. [ADD-01] Procedures:

a. [ADD-01] Submittal preparation – Contractor may use any or all of the following options:

i. [ADD-01] Subcontractors and suppliers provide electronic

(PDF) submittals to Contractor via website.

ii. [ADD-01] Subcontractors and Suppliers provide paper submittals to General Contractor who electronically scans and converts to PDF format.

iii. [ADD-01] Subcontractors and Suppliers provide paper submittals to Scanning Service which electronically scans and converts to PDF format.

b. [ADD-01] Contractor shall review and apply electronic stamp certifying that the submittal complies with the requirements of the Contract Documents including verification of manufacturer / product, dimensions and coordination of information with other parts of the work.

c. [ADD-01] Contractor shall transmit each submittal to Architect using the website.

d. [ADD-01] Architect / Engineer review comments will be made available on the website for downloading. Contractor will receive email notice of completed review.

e. [ADD-01] Distribution of reviewed submittals to subcontractors and suppliers is the responsibility of the Contractor.

B. Compile the electronic submittal file as a single, complete document.

Name the electronic submittal file specifically according to its contents.

C. Electronic files must be of sufficient quality that all information is legible. Generate PDF files from original documents so that the text included in the PDF file is both searchable and can be copied. If

Renovate Building 4 A & B Floors Outpatient Mental Health Clinic

Bancroft-AE Project No. 18-102 01 33 23-8 08-03-2020 documents are scanned, Optical Character Resolution (OCR) routines are required.

D. [ADD-01] Not used. E-mail electronic submittal documents smaller than

5MB in size to e-mail addresses as directed by the Contracting Officer.

E. [ADD-01] Not used. Provide electronic documents over 5MB through an electronic FTP file sharing system. Confirm that the electronic FTP file sharing system can be accessed from the VA computer network. The

Contractor is responsible for setting up, providing, and maintaining the electronic FTP file sharing system for the construction contract period of performance.

F. Provide hard copies of submittals when requested by the Contracting

Officer. Up to 3 additional hard copies of any submittal may be requested at the discretion of the Contracting Officer, at no additional cost to the VA.

G. [ADD-01] Cost: The full cost of the Submittal Exchange website service will be covered by the VA.

1.7 SAMPLES

A. Submit two sets of physical samples showing range of variation, for each required item.

B. Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified.

C. When color, texture, or pattern is specified by naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.

D. Before submitting samples, the Contractor is to ensure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.

E. The VA reserves the right to disapprove any material or equipment which previously has proven unsatisfactory in service.

F. Physical samples supplied maybe requested back for use in the project after reviewed and approved.

Renovate Building 4 A & B Floors Outpatient Mental Health Clinic

Bancroft-AE Project No. 18-102 01 33 23-9 08-03-2020

1.8 OPERATION AND MAINTENANCE DATA

A. Submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.

B. In the event the Contractor fails to deliver O&M Data within the time limits specified, the Contracting Officer may withhold from progress payments 50 percent of the price of the item with which such O&M Data are applicable.

1.9 TEST REPORTS

SRE may require specific test after work has been installed or completed which could require Contractor to repair test area at no additional cost to contract.

1.10 VA REVIEW OF SUBMITTALS AND RFIS

A. The VA will review all submittals for compliance with the technical requirements of the contract documents. The Architect-Engineer for this project will assist the VA in reviewing all submittals and determining contractual compliance. Review will be only for conformance with the applicable codes, standards and contract requirements.

B. Period of review for submittals begins when the VA COR receives submittal from the Contractor.

C. Period of review for each resubmittal is the same as for initial submittal.

D. VA review period is 15 working days for submittals.

E. VA review period is 10 working days for RFIs.

F. The VA will return submittals to the Contractor with the following notations:

1. "Approved": authorizes the Contractor to proceed with the work covered.

2. "Approved as noted": authorizes the Contractor to proceed with the work covered provided the Contractor incorporates the noted comments and makes the noted corrections.

3. "Disapproved, revise and resubmit": indicates noncompliance with the contract requirements or that submittal is incomplete. Resubmit with appropriate changes and corrections. No work shall proceed for this item until resubmittal is approved.

4. "Not reviewed": indicates submittal does not have evidence of being reviewed and approved by Contractor or is not complete. A submittal

Renovate Building 4 A & B Floors Outpatient Mental Health Clinic

Bancroft-AE Project No. 18-102 01 33 23-10 08-03-2020 marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals after taking appropriate action.

1.11 APPROVED SUBMITTALS

A. The VA approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory.

B. VA approval of a submittal does not relieve the Contractor of the responsibility for any error which may exist. The Contractor is responsible for fully complying with all contract requirements and the satisfactory construction of all work, including the need to check, confirm, and coordinate the work of all subcontractors for the project.

Non-compliant material incorporated in the work will be removed and replaced at the Contractor’s expense.

C. After submittals have been approved, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

D. Retain a copy of all approved submittals at project site, including approved samples.

1.12 WITHHOLDING OF PAYMENT

Payment for materials incorporated in the work will not be made if required approvals have not been obtained.