- Solicitation number
- 36C24125R0077Solicitation
About this file
This file is a Pre-Bid Request for Information (RFI) responses document for the Department of Veterans Affairs West Roxbury Campus Boiler Plant Replacement and Controls Upgrade project (Solicitation 36C24125R0077, Project 523A4-20-208). The document addresses 80+ clarification questions submitted by prospective bidders regarding technical specifications, drawings, construction requirements, and project scope.
Key technical clarifications address pressure relief valve (PRV) capacities (3,000 and 26,000 lbs/hr), steam relief valve setpoints (75 psig), condensate pump specifications (15 gpm), and micropile design loads governing per Foundation Note 2 (150 kips compression, 40 kips tension, 15 kips lateral for battered piles). The contractor must engage a Professional Geotechnical Engineer full-time during pile installation and use vacuum excavation within 5 feet of existing utilities. Significant scope clarifications confirm no temporary boilers are required—temporary steam will be provided via new piping systems—and utilities (steam, electrical, water) will be partially provided by the government at no cost, with the contractor responsible for filling a 60,000-gallon water tank and providing #2 Ultra Low Sulfur Diesel fuel for boiler testing. The contractor must drain and properly dispose of 90% full underground fuel oil tanks, refill them post-cleaning, and coordinate new utility installations with National Grid. Construction phasing is defined by Drawing GI002, and the contractor must submit cost-loaded schedules post-award per specification 01 32 15. Personnel requirements specify that the Project Manager and Site Superintendent cannot be dual-hatted roles, though the Infection Control Manager may be. Subcontracting plan requirements apply per FAR 52.219-9 and VAAR 852.219-70, with no minimum self-performance percentage mandated. The project includes asbestos abatement (1,500 linear feet of thermal system insulation plus mudded fittings), equipment relocation by others, and compliance with BABA requirements (FAR 52.225-11 and 52.225-12). A Project Labor Agreement will be provided post-award, and offerors must utilize the provided Exhibit D for pricing with Schedule of Values acceptable as supporting documentation.
View the file
Other files
Show 40 more
Latest 50 of 81 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Drawing | Spec Section | Paragraph | Question | Answer |
| MP605 | Drawing indicates 8-PRV-3 with flow rate of 12,000 lbs/hr but the equipment schedule on M702 indicates it as 3,000 lbs/hr. Please clarify the design capability. | 3,000lbs/hr is the correct capacity | ||
| MP605 | Drawing indicates 8-PRV-4 with flow rate of 38,000 lbs/hr but the equipment schedule on M702 indicates it as 26,000 lbs/hr. Please clarify the design capacity. | 26,000lbs/hr is the correct capacity | ||
| M702 | SRV-12 for PRV-3 and PRV-4 are scheduled for 29,000 lbs/hr which matches design required capacity on M702. However, the max capacity shown is 5,849 and 45,662 which is above the capacity of the SRV, or does not meet required capacity if M605 capacities are correct. Please confirm setpoint. | 75 psig | ||
| M703 | Note 1 on M-703 trap schedule is calling for all traps to be supplied with Armstrong TVS4000 trap valve station which is available in 1/2" and 3/4", however the traps are scheduled at larger sizes. Please clarify the intent for larger size traps . | Provide conventional trap assemblies per trap details on drawing MP503 | ||
| M703 | M703 schedule for the stream driven condensate pump lists 15 gpm (per pump). Is the total condensate load 15 gpm or 30 gpm ? | 15 gpm | ||
| S-001 | Foundation Note 2 states: "Contractors geotechnical engineer shall be present on site full time during pile installation.". Please confirm that a contractor field engineer with a civil engineer degree will be acceptable to satisfy the requirements of this note. | Per S-001, Foundation Note 2, Contractor's Professional Geotechnical Engineer needs to be present for pile installation. | ||
| S-001 | 31 62 20 | 1.10.B.1 | Foundation Note 2B states: "Pile design is based on 150 kips in compression, 40 kips in tension and 1 kip lateral, per pile.". Spec 3162 20, para 1.10.B.1 states: "The micropile shall have allowable axial compression capacity of not less than 20 tons, an allowable tension capacity of not less than 5 tons and allowable lateral capacity of 3 tons per pile.". Please clarify what are the design loads for the DMP's to be based on. | Loads on S-001, Foundations, Note 2 govern. Disregard design loads in specification section 31 62 00. |
| S-001 | Foundation Note 2C states: " Battered pile design is based on 15 kips in lateral load per pile.". Please confirm if the additional lateral loading is resolved in the battering of the DMP's or if the DMP's must be designed with an allowable lateral capacity of 15 kips. | Battered piles need to provide a minimum of 15 kips lateral load resistance each. | ||
| The geotechnical report was not provided with the bid documents. Please provide. | See Geotechnical Report - Attachemnts 1 through 8 A0004 | |||
| SF1442 | Page 12/46 requires a complete project schedule submittal in accordance with specification 01 32 15 16.15. Please confirm that cost loading will not be required with this proposal schedule. Typically we are receiving pricing on the proposal due date, and it does not leave sufficient time to add cost loading to the schedule on bid day. | Confirm cost loading is not required for proposal, it will be required once contract is awarded. Submitted schedule should be represent all work activities for project. | ||
| SF1442 | Page 14/46, Factor 4, Veterans Preference outlines a cost evaluation, differing veteran status program. Please clarify what the necessary qualifying criteria is when a non-veteran owned company proposed to use SDVOSB or VOSB as subcontractors, in order to achieve the 1% less partial credit. | In order to receive Veterans Preference, the SD/VOSB-owned company must be registered as a SD/VOSB on the Small Business Search site at https://search.certifications.sba.gov/. | ||
| Please confirm that the prime contractor will not be responsible for MA DEP Emissions Permitting. | Yes | |||
| Please provide POC for utilities companies that will be providing new utility services to the project as the prime contractor is responsible for utility fees. | National Grid - Thomas Brouwer |
thomas.brouwer2@nationalgrid.com Will utilities (water, electric, steam) be provided to the contractor, without charge, during the life of the project ? Refer to specification 01 00 00 Section 1.18 Availability and Use of Utility Services for Electrical & Water.
Steam will be provided at no cost.
| 01 00 00 | page 9 | Item 37 requires the contractor to drain and properly dispose of oil from (2) existing UG 25,000 gallon tanks. Please confirm how much oil should be assumed to be removed from each tank. | Assume tanks are 90% full. Ensure to follow MASS DEP for transferring fuel and final manifest provided to VA once disposed. |
| 01 00 00 | page 9 | Item 37 makes note that the contractor is required to refill, with #2 fuel oil, the (2) existing 25,000 gallon UG storage tanks. Please confirm this contractor requirement . | Yes, the contractor is being asked to refill the tanks with #2 Ultra Low Sulfur Diesel that is equal or less than 15ppm after the tanks are drained and cleaned. |
| 01 00 00 | page 9 | Item 39 requires a containment wall around the new fuel oil tank. Is this containment to be a tank supplier containment wall ? We have not seen details for this containment. | Please refer to the structural drawings for the fuel oil containment. |
| 01 00 00 | page 9 | Please confirm the requirements of item #40 which includes providing all #2 fuel oil for boiler plant testing and for filling the 30,000 gallon tank to a full level after testing. | Contractor to provide #2 Ultra Low Sulfur Diesel that is equal or less than 15ppm for both testing of boilers and 30,000 gallon tank |
| 01 00 00 | Will the contractor be required to provide all the natural gas during boiler plant testing ? | Contractor is responsible to coordinate the natural gas systems with National Grid | |
| 01 00 00 | page 9 | Item #45 requires a new 60,000 gallon water storage tank to be installed. Will the government or the contractor be responsible for the costs to fill the tank ? | Yes contractor is responsible to fill the 60,000 gallon tank |
| 01 00 00 | page 10 | Item 69 requires the installation of a 10 foot high blast wall at the property line. Please indicate where this fence is shown on the drawings, including details and applicable specification section. | Refer to Civil drawings |
| Is the prime contractor required to self perform a minimum percentage of work ? If yes, what is the required percentage. | This solicitation is full and open competition and there is no minimum percentage of work required. However, there is a requirement for a Subcontracting Plan upon award in accordance with FAR 52.219-9 and VAAR 852.219-70. |
Please note for requirement on percentage of work under CFR 125.8 for Joint Ventures under Mentor-Protégé Program (MPP) - CFR under performance of work is that the small business partner of the JV must perform 40% of the work that is performed by the JV. So if the JV performs 15% of the work (excluding material), the small business would need to perform 40% of the 15%.
(c) Performance of work.
(1) For any contract set aside or reserved for small business that is to be performed by a joint venture between a small business protégé and its SBA-approved mentor authorized by § 125.9, the joint venture must perform the applicable percentage of work required by § 125.6, and the small business partner to the joint venture must perform at least 40% of the work performed by the joint venture. Except as set forth in paragraph (c)(4) of this section, the 40% calculation for protégé workshare follows the same rules as those set forth in § 125.6 concerning supplies, construction, and mixed contracts, including the exclusion of the same costs from the limitation on subcontracting calculation (e.g., cost of materials excluded from the calculation in construction contracts).
(2) The work performed by the small business partner to a joint venture must be more than administrative or ministerial functions so that it gains substantive experience.
(3) The amount of work done by the partners will be aggregated and the work done by the small business protégé partner must be at least 40% of the total done by the partners. In determining the amount of work done by a mentor participating in a joint venture with a small business protégé, all work done by the mentor and any of its affiliates at any subcontracting tier will be counted.
(4) Work performed by a similarly situated entity will not count toward the requirement that a protégé must perform at least 40% of the work performed by a joint venture.
| Infection Control Requirements | Please advise on any requirements and qualifications for the infection control manager | No qualifications for Infection Control Manager, however personnel assigned must be competent in understanding Infection Control measures as there is minimal work within the Medical Center. Most of project scope is exterior and away from Medical Center in which refer to Infection Control Requirements with ICRA/PCRA. Refer to Specifications Volume I page 171 |
| Dual Hatting of Roles | Please advise if any of the following roles can be dual-hatted and performed by one person or if these roles and positions need to be separate: Project Manager, Superintendent, Quality Control Manager, Infection Control Manager, Site Safety & Health Officer (SSHO). | Infection Control Manager can be dual hatted |
Project Manager & Site Superintendent cannot be dual hatted SSHO cannot be dual hatted refer to Specification 01 35 26 Section 1.7.C/D Refer to Specification 01 45 00 for Quality Control on CQC team, roles cannot be dual hatted.
| 282300-10(2.3) | Is there adequate capacity in the existing PACs Server Hardware, Standard Workstation hardware & Communications Work Stations required for this project? | Existing hardware is adequate for the new door controllers; however, Contractor shall provide licenses required for the additional doors to be controlled/monitored as part of this project. Please note: Door controllers shall be Hirsch Mx Controllers and operate on Hirsch Velocity 3.7 software. | ||
| 282300-10(2.3) | Is the project proprietary Exacq Technologies video management software? | Yes. | ||
| 283100 | Please provide the contact information of the campus fire alarm vendor. | Encore Fire Protection is campus fire alarm vendor. Refer to website www.encorefireprotection.com for coordination as fire alarm and suppression system have different POCs | ||
| CD101.T, CS101 | Referencing Drawing No. CD101.T, “remove and replace concrete curbs”; Drawing CS101 “new vertical slipform concrete curb”. From google earth we have identified all of the curb on-site to be granite curb, therefore should we replace granite with granite curb and where new curb is required should we use granite curb? If concrete curb is preferred can we use precast concrete curb? | Existing granite curb shall be removed and stockpiled on site. See attachment CD101 A0004 will be revised to confirm material matches existing condition. New concrete curb shall remain slipform concrete curb for bid purposes. | ||
| CD101 | Referencing Drawing CD101, “Remove existing elec. To limits shown”, do we need to excavate and remove ductbank/conduit or is the intent to disconnect and pull wires? | Design intent is to disconnect and remove the existing site light pole, light fixture, and concrete foundation. Prior to removal of wiring, contractor shall verify no other existing site lighting to remain is affected by this disconnection and removal. Contractor shall modify existing underground wiring and conduit as required to maintain the integrity of the existing circuitry, i.e., maintaining any other site lights on same circuit. If no other loads exist on circuit, associated wiring shall be removed back to source. Existing aboveground abandoned conduit shall be cut at 12” below grade and capped. | ||
| CD101 | Referencing Drawing CD101, “Remove existing gas line to limits shown”. Note 9 | |||
| indicates “National Grid will complete gas construction and demolition from the connection to the proposed meter and exterior to the building.” Please confirm “Remove existing gas line to limits shown” will be performed by National Grid | Utility company will perform the gas work indicated on the plans. | |||
| CS101 | Drawing CD101 calls for “Remove Existing Chain Link Fence” and in the same location Drawing CS101 calls for “New 8’ High Steel Anti-Climb Security Fence.” Note 9 on CS101 indicates “Upon mobilizing and prior to demolition, secure site at location of proposed security fence with temporary security fencing.” From Google Maps Image Captured Sep 2025 there is (new looking) Anti-Climb Security Fence in this area located along Spring Street and down the north side of the site along Moville Street. Please clarify are we to remove this fence | CD101 has been revised to confirm fence type. Fence shall be removed and reconstructed as significant earthworks in the area impact the functionality of the existing fence. Contractor may propose keeping a portion of the existing fence to assist in the temporary security fencing. See attachment CD101 A0004 | ||
| Does the site already have a NPDES dewatering permit? | Refer to attachment MA MS4 Permit A0004 & MA MSR Admin A0004 | |||
| S-001F | Drawing S-001 Foundation Note 2 states: Contractors geotechnical engineer shall be present on site full time during pile installation. Please confirm if a field engineer with a civil engineer degree will be sufficient to observe the DMPs install | Per S-001, Foundation Note 2, Contractor's Professional Geotechnical Engineer needs to be present for pile installation. | ||
| S-001F | Drawing S-001 Foundation Note 2B states: Pile design is based on 150 kips in compression, 40 kips in tension and 1 kip lateral per pile. Specification section 31 62 20 Article 1.10.B.1 states: The micropile shall have an allowable axial compression capacity of not less than 20 tons, an allowable tension capacity of not less than 5 tons and allowable lateral capacity of 3 tons per pile. Please clarify the loads that the DMPs will be designed based on. | Loads on S-001, Foundations, Note 2 govern. Disregard design loads in specification section 31 62 00. | ||
| S-001F | Drawing S-001 Foundation Note 2C states: Battered pile design is based on 15 kips in lateral load per pile. Please confirm weather the additional lateral loading is resolved in the battering of the DMPs or if the DMPs must be designed with an allowable lateral capacity of 15 kips. | Battered piles need to provide a minimum of 15 kips lateral load resistance each. | ||
| 316220 | The geotechnical report is missing from the project specification. This will be required to access the depth and condition of the rock. | See Geotechnical Report - Attachemnts 1 through 8 A0004 | ||
| AE102.3 | Not all partitions are tagged with wall types, please provide remaining partition wall type tags. | Floor plans have been revised to tag all wall types. Refer to attachment AE101_3 A0004, AE101_5 A0004, AE102_3 A0004, AE103_3 A0004, AE401 A0004, AE503 A0004, AE604 A0004 | ||
| AF101.3 | If no ceiling finish is listed in the room finish schedule, should we assume exposed structure? If exposed should it be painted? | The roof structure is scheduled to be shop primed. At spaces without a ceiling scheduled, exposed structure should be painted with an intermediate epoxy coat followed by a polyurethane finish coat. | ||
| Bid Form requires a detail and summary level labor and material breakdown. It will be nearly impossible to provide that level of detail at the time of Bid. Can this information be provided at the time of procurement ? | Offerors shall put forth their best effort on the bid form to include labor and material breakdown per division. |
At the time of award, the awardee will be required to provide a detailed cost loaded schedule with subcontractors in accordance with specifications.
| Please confirm that this this solicitation, and all projects documents included within, are not CUI, and therefore the Executive Order 13556 does not apply, and offerors are not required to be fully compliant under DFARS 252.20-7019 and NIST SP 800-171 | Executive Order 13556, along with FAR clauses 52.240-91 and 52.240-93, and VAAR clause 852.204-70, are applicable. As this solicitation is for the Department of Veterans Affairs, DFARS clause 252.204-7019 is not applicable. | |
| Please confirm if the Infection Control Manager is a stand alone full time position | Infection Control Manager can be dual hatted | |
| Please confirm the frequency of inspections for the CQC – full time onsite, 1x per week, 2x per week, etc. | Refer to Specification 01 45 00 for Quality Control on CQC team which notes frequency depending on roles | |
| M-705 | Louvers-The spec calls for Blast Louvers, we cannot exceed 60” width on any of our blast Louvers. |
The openings that are over 60” width will require a minimum 6” wide structural divider in the openings. Please advise.
| DR#: 202500538004 | Please provide basis of design or approved equal. | |||
| Asbestos abatement is required for this job. A hazmat plan was included but not an asbestos survey, please include an asbestos survey. | See attachment Hazmat A0004 and Regulated Building Materials Survey Report A0004 | |||
| For excavation activities associated with this project, please clarify whether standard mechanical excavation is acceptable when working in areas where existing underground utilities are present, or if alternative methods are required to protect critical campus infrastructure. | Due to the critical nature and density of existing underground utilities throughout the campus, excavation within proximity (5 feet or less) to known or suspected utility lines shall utilize vacuum excavation (vac truck) or other non-destructive digging methods to expose utilities prior to performing mechanical excavation. Contractors shall plan work accordingly and include associated costs within their proposal. | |||
| S-561 | Drawing Detail 2 indicates a pre-engineered storage shed with precast concrete block walls. Please clarify if the sheds are intended to remain open or if doors and additional enclosure are required. | Both storage sheds shall include fully enclosed rear walls and overhead rolling doors at the front opening. Contractors shall include all necessary components required for installation as part of the shed system. | ||
| ES101.01 | Electrical drawings show overhead bay lighting within the equipment shed. Please confirm if additional electrical receptacles are required. | The equipment shed shall include four (4) quad receptacles, connected to the same circuit as the overhead lighting unless otherwise required by code, only for equipment shed (Lot #3). Receptacles are not required in the salt storage shed (Lot #2). Include all assiocated equipment to include transformer. Clarification of pads are noted in updated plan ES101.1 A0004 | ||
| Is there a BABA/Build-America, Buy America compliance required? If yes is it required that iron and steel are produced (melting, coating, etc.) in the U.S., and that manufactured products must be made in the U.S. with over 55% domestic content? | FAR 52.225-12 and 52.225-11 are applicable to this solicitation. | |||
| ED111.1 | Key note #18 notes, "relocation of equipment by others". Please provide a schedule/clarification of equipment being relocated by others | Refer to Drawing GI002 and Specification Section 01 00 00, Part 1.3.A.9 for roles, responsibilities, and sequencing of relocating the existing boiler control system from the ash tower to the plant break room. | ||
| RFP Subfactor B. | A list of major subcontractors: 1. Are we to list the potential subcontractors (more than one per trade) or list the subcontractor we are carrying for that particular trade? 2. Please define "major subcontractors" for the architectural category requested. | List the subcontractor the offeror is carrying for that particular trade and provide all the required information per Subfactor B. Per the Statement of work and RFP, all proposed key personnel and subcontractors shall be used for this project and substitutions must be approved by the Contracting Officer's Representative and the Contracting Officer. |
For purposes of Subfactor B, a major subcontractor is the subcontractor the offeror intends to utilize to perform the primary scope of work associated with the listed trade categories. For the architectural category, the offeror shall identify the subcontractor responsible for performing the architectural construction scope associated with the project (e.g., walls, doors, finishes, ceilings, and other architectural building modifications required to support the boiler replacement work). Offerors shall submit the required Exhibit B – Subcontractor Information and Consent Form for the proposed subcontractor.
| Will there be another site visit scheduled ? A few of the Demolition Subcontractors have asked. | No | ||
| G1002 | Per G1002 “relocate existing storage tents and bins. Per 01 00 00-4 item 8, “provide new”. Please clarify and if new provide design information. Please provide pad details for these items. | Existing storage tents to be demolished and diposed of by contractor. VA will move existing dumpsters and bins. Existing storage bins (concrete) to be demolished by contractor. Contractor to furnish and install new storage tents. | |
| PLA — FAR 52.222-33 Alt III, 52.222-34 Alt I | Please provide a copy of the Project Labor Agreement (PLA) to allow trade contractors to accurately price labor costs and other project requirements. | In accordance with FAR 52.222-33 Alt III and 52.222-34 Alt I, a PLA is required after award of the contract. A copy of a PLA will not be provided, the awardee must follow the requirements of FAR 52.222-34 Alt I. | |
| Spec 01 00 00 — Exhibit D | Please confirm that a Schedule of Values (SOV) for each of the major trades will be acceptable in lieu of line-item pricing on the Exhibit D cost breakdown spreadsheet. | Utilize Exhibit D for pricing, offerors can include SOV as back-up documentation. | |
| Spec 01 00 00 — Exhibit D | If a SOV for major trades is not acceptable, please clarify the intent of requiring line-item detail at this stage of procurement and identify how the Government will use this information. | Utilize Exhibit D for pricing, offerors can include SOV as back-up documentation. | |
| Spec 02 21 13 — Geotechnical Report | The structural drawings general notes reference a Geotechnical Report by R.W. Gillespie dated December 16, 2021, stated to be included in the Specifications. This report has not been located in the provided documents. Please confirm whether this report has been made available and provide it if so. Note: the provided borings do not reach bedrock depths, which limits subsurface pricing certainty. | See Geotechnical Report - Attachemnts 1 through 8 A0004 | |
| Spec 31 63 00 / Structural Drawings — Micropile Loads | Please clarify the required design load capacities of the drilled micropiles. The Specifications and the Structural Drawings general notes provide different capacities. Please issue a reconciled, governing value. | Loads on S-001, Foundations, Note 2 govern. | |
| Drawing ED111.1 — Relocation by Others | Drawing ED111.1, Keynote #18 references relocation of equipment by others. Please provide a complete list of all equipment to be relocated by others, including responsible party and anticipated timing relative to contractor phasing. | Refer to Drawing GI002 and Specification Section 01 00 00, Part 1.3.A.9 for roles, responsibilities, and sequencing of relocating the existing boiler control system from the ash tower to the plant break room. | |
| Spec 01 00 00 / Drawing GI002 — Phase Definitions | Please provide detailed definitions of each of the five (5) required construction phases, including specific work activities, start and end criteria, and which building systems must remain operational during each phase. | Drawing GI002 describes the Construction Phasing Plan in detail. | |
| Spec 01 00 00 / Drawing GI002 — Phase Approval Criteria | Per Spec 01 00 00 Section 1.3, the phasing plan is subject to final VA approval and will not be grounds for a change order. Please identify the evaluation criteria the Government will use to approve or reject a contractor-submitted phasing plan, and confirm whether post-award Government-required modifications will entitle the contractor to time and cost adjustments. | For bidding purposes no alternation to the phasing plan as noted on Drawing GI0002. | |
| Spec 01 32 16.15 — Schedule Milestones | Are there intermediate schedule milestones required beyond the final completion date? Does the contract include incentive or disincentive clauses for early or late completion? | The contractor is responsible for determining intermediate schedule milestones that are based upon the major construction phases shown in the contract documents. |
Contract is Firm Fixed Price.
| Spec 23 52 39 — Temporary Boiler Capacity | Regarding the requirement to provide temporary steam boilers to supply Building 21 (Research Building) during construction: What is the required steam capacity (lbs/hr), operating pressure, and supply temperature? | There are no temporary boilers required for this project. Temporary steam and condensate return will be provided by new piping systems as shown on drawings MT101.3, MT301.3, MT501 |
| Spec 23 52 39 — Temporary Boiler Duration & Redundancy | What is the duration temporary steam must be maintained to Building 21? Are redundant temporary boilers required for backup? | There are no temporary boilers required for this project. Temporary steam and condensate return will be provided by new piping systems as shown on drawings MT101.3, MT301.3, MT501 |
| Spec 23 52 39 — Temporary Steam Design & Connections | Who provides the engineering design for temporary steam interconnections? What are the connection points at Building 21, and are existing drawings available for those tie-in locations? | There are no temporary boilers required for this project. Temporary steam and condensate return will be provided by new piping systems as shown on drawings MT101.3, MT301.3, MT501 |
| Spec 01 50 00 — Temporary Electrical Power | Will the Government provide temporary electrical power for the contractor? If so, at what voltage, amperage, and location on site? | Refer to specification 01 00 00 Section 1.18 Availability and Use of Utility Services for Electrical & Water. |
Steam will be provided at no cost.
| Spec 01 50 00 — Temporary Natural Gas | Who provides temporary natural gas supply for temporary boilers — the contractor or Government coordination with National Grid? What is the required natural gas pressure and volume (BTU/hr)? | There are no temporary boilers required for this project. Temporary steam and condensate return will be provided by new piping systems as shown on drawings MT101.3, MT301.3, MT501 |
| Spec 01 50 00 — Temporary Water & Sewer | Who provides temporary water and sanitary sewer during construction? What are the estimated monthly utility costs and who bears them? | There are no temporary boilers required for this project. Temporary steam and condensate return will be provided by new piping systems as shown on drawings MT101.3, MT301.3, MT501 |
| Spec 02 21 13 / 02 41 00 — As-Built Drawings | Will the Government provide as-built drawings for the existing boiler plant, steam tunnels, and utility routing? Per Spec 01 00 00, the contractor must accept existing conditions with no change order recourse — this documentation is essential baseline for accurate pricing. | The Government has provided the available contract drawings and specifications identifying the existing conditions and demolition scope applicable to this project. No additional as-built drawings are available for distribution under this solicitation. |
Offerors shall base their proposals on the information provided in the contract documents and site conditions observable during the site visit. Any unforeseen or latent physical conditions encountered during performance that differ materially from those indicated in the contract may be addressed in accordance with FAR 52.236-2, Differing Site Conditions, as incorporated in the contract.
Spec 02 21 13 / 02 41 00 — Environmental Assessments Will the Government provide Phase I/II Environmental Site Assessment reports? If not, the contractor has no basis to price unknown environmental conditions under the 'existing conditions' no-recourse clause. The Government has not completed a Phase I or Phase II Environmental Site Assessment for this project. Offerors shall base their proposals on the information provided in the solicitation documents and site conditions observable during the site visit.
Any unforeseen or latent physical conditions encountered during performance that differ materially from those indicated in the contract may be addressed in accordance with FAR 52.236-2, Differing Site Conditions, as incorporated in the contract.
| Spec 02 82 11 / 02 83 33.13 — ACM Quantities | What is the total estimated quantity of asbestos-containing material (ACM) beyond the 5 boilers and approximately 1,500 LF of fiberglass insulation identified in the Mabbett survey? Are there known ACM conditions in concealed spaces (above ceilings, in walls, underground) not identified in the survey? | Asbestos containing TSI and mudded fittings were identified and are included in the 1,500 linear feet abatement quantity. TSI is assumed to be present inside wall penetrations. The asbestos abatement contractor shall be responsible for all demolition work required to properly access all asbestos materials for abatement. All demolition debris shall be disposed of as asbestos. Areas above hard ceilings, inside walls and below grade were not accessible for inspection. Any suspect materials encountered during demolition activities that were not previously identified as being non-ACM, should be assumed to be ACM unless sample results prove otherwise. |
| Spec 23 09 11 — Control System Design Responsibility | Regarding relocation of the existing boiler control system from the ash tower to the existing plant breakroom: Will the Government or the contractor provide the design for new control logic? What is the scope of existing PLC programming that must be replicated? | See specification 01 00 00 1.3 item #9 |
| Spec 23 09 11 — Controls Contractor Coordination & Testing | Will Automated Control Concepts, LLC (existing controls contractor) be available for coordination during this work, and at whose cost? Who performs FAT/SAT testing for the relocated control system? What is the required interface between relocated controls and the new Hawk/TRANE systems? | See specification 01 00 00 1.3 item #9: The contractor shall coordinate this effort with Automated Control Concepts, LLC. The cost of this relocation is the contractor's responsibility. |
| Spec 23 50 11 — Fuel Oil Disposal | What is the total volume of fuel oil in the two existing tanks requiring disposal? Has the existing fuel oil been tested for contamination? | Each tank is 25,000 lbs. Assume tanks are 90% full. Ensure to follow MASS DEP for transferring fuel and final manifest provided to VA once disposed. |
Yes, fuel is tested yearly, report attached.
Spec 23 50 11 — Fuel Oil Supply Responsibility The specification requires the contractor to 'provide all fuel oil for project operations.' Does this include temporary boiler fuel, new boiler commissioning/testing fuel, and ongoing plant operation post-startup? What is the estimated fuel consumption (gallons/day) for the commissioning period, and who pays for fuel after project acceptance? There are no temporary boilers required for this project.
The fuel consumption will be based on the duration of the commissioning of the boilers which is being provided by a third party.
The VA will be responsible for any fuel cost post acceptance.
| Spec 31 63 00 / Div 05 — Geotechnical Investigation | Will the Government provide a geotechnical investigation report with soil borings, lab testing results, and bearing capacity analysis for the new central energy building? If contractor-performed, is the geotechnical investigation included in the base bid or is it a reimbursable cost? | See Geotechnical Report - Attachemnts 1 through 8 A0004 |
| Spec 31 63 00 / Div 05 — Foundation Design Loads | What are the design loads for the new central energy building including all four boilers, deaerator, fuel tank, and associated equipment? Are there known soil conditions (contamination, high water table, ledge) that affect micropile design? | Micropiles are to be designed for 150 kips compression, 40 kips tension, and 1 kip lateral. Battered piles are to be designed to provide 15 kips lateral resistance per pile. Additional design loads can be provided during construction if required. Water table and ledge were both encountered during boring process. See Geotechnical Report - Attachemnts 1 through 8 A0004 |
| Drawings indicate that boiler roof stack guy wires are not finalized, can the drawing/sketch for the final layout and plan be provided. | See attached plans - |
S-0002 A0004, S0003 A0004, S-552 A0004, SF101.3A A0004, SF111.3A A0004, SF121.3A A0004, SF131.3A A0004, SF141.3A A0004, SS101.1 A0004
EP141.3A A004
MH121.3A A0004, MH131.3A A0004, MQ141.3A A0004, PP141.3A A0004