3-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf

PDF 94 KB Posted

Attached to
234 McKean Road Demolition (26-00182)
Solicitation number
Not on record
Issued by
Montgomery County, Pennsylvania

About this file

This is a specification document for Section 01 31 00 - Coordination and Meetings, which establishes the procedural and administrative requirements for the 234 McKean Road Demolition project in Horsham Township, Pennsylvania. The section outlines the contractor's responsibilities for coordinating all construction activities, including scheduling, submittals, and work sequencing to ensure efficient installation of interdependent construction elements. Key requirements include providing field engineering services to establish elevations, lines, and levels using recognized survey practices; verifying setbacks, easements, and drawing dimensions; and constructing work based on established stakeout. A mandatory preconstruction meeting will be held at Kohler Park (1100 Limekiln Pike, Ambler, PA 19002) on Thursday, April 2, 2026, at 11:00 AM, with required attendance from the owner, contractor's superintendent, major subcontractors, the engineer, and the resident project representative. The engineer will prepare and distribute meeting minutes within five working days to all participants.

Progress meetings will be scheduled throughout the project on an as-needed basis, with the resident project representative arranging meetings, preparing agendas, and presiding. The contractor's superintendent and major subcontractors must attend, with agenda items including review of work progress, field observations and decisions, submittal status, fabrication and delivery schedules, progress schedule maintenance, corrective measures, quality standards, and effects of proposed changes on coordination. Meeting minutes will be distributed within five working days to the owner, engineer, and all participants. This coordination framework applies to the demolition of an existing residential structure, detached garage, two sheds, removal of an asphalt driveway, capping of a domestic water well, abandonment of the sanitary service line, temporary restoration of a stream crossing damaged by flooding, and grading and permanent stabilization of all disturbed areas.

View the file

Other files

File Type Posted
11-Doc 00 43 13 - BID BOND.pdf PDF
18-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
9-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
16-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
21-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
44-X2 ES Plan.pdf PDF
51-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
42-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
43-Doc 00 65 19.16 - SUBCONTRACTORS RELEASE OF LIENS.pdf PDF
13-Doc 00 52 00 - AGREEMENT.pdf PDF
22-Doc 00 65 19.13 - SUBCONTRACTORS AFFIDAVIT.pdf PDF
6-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
20-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
41-Doc 00 73 00 5 - Appendix B - Public Works Employment Verification Form.pdf PDF
7-Sec 31 11 00 - CLEAR AND GRUB.pdf PDF
45-X1 Demo Plan.pdf PDF
25-Doc 00 41 00 - BID FORM - EBID.pdf PDF
12-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
46-X3 ES Notes and Details.pdf PDF
30-Sec 01 56 39. - LANDSCAPE PROTECTION.pdf PDF
50-Sec 31 23 33 - Excavation, Backfill and Compaction.pdf PDF
34-Doc 00 91 13 - ADDENDA.pdf PDF
48-Doc 00 11 13 - ADVERTISEMENT FOR BIDS - 234 McKean Road Demo.pdf PDF
33-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
19-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
37-Doc 00 62 76 - Application for Payment.pdf PDF
29-Doc 00 73 00 2 - Appendix A - cover sht.pdf PDF
5-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
31-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
40-Sec 02 41 16 - DEMOLITION.pdf PDF
49-X4 Easement Exhibit.pdf PDF
27-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
1-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
17-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
8-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
28-Doc 00 63 63 - Change Order.pdf PDF
26-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
24-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
32-Doc 00 45 10 - BIDDER’S ACKNOWLEDGEMENT FORM.pdf PDF
47-Doc 00 73 00 3 - Appendix A - Prevailing Wage Determination.pdf PDF
10-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
14-Doc 00 73 00 4 - Appendix B - cover sht.pdf PDF
39-Doc 00 21 13.1-Instr for Electronic Bidding.pdf PDF
35-Doc 00 21 13.2 - PennBid - How To Submit a Bid.pdf PDF
15-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
36-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
23-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
38-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
4-Sec 32 93 00 Landscaping.pdf PDF
52-Doc 00 73 00 1 - SUPPLEMENTARY CONDITIONS.pdf PDF
Show 40 more

Latest 50 of 97 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COORDINATION AND MEETINGS

01 31 00-1

SECTION 01 31 00

COORDINATION AND MEETINGS

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of this Section Includes:

1. Coordination and Project conditions.

2. Field engineering.

3. Preconstruction meeting.

4. Progress meetings.

1.02 RELATED SECTIONS

A. This section not used.

1.03 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial Completion and for portions of Work designated for Owner’s occupancy.

C. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner’s activities.

1.04 FIELD ENGINEERING

A. Contractor shall provide stakeout as required for construction activities.

B. Verify set-backs and easements; confirm drawing dimensions and elevations.

C. Provide field engineering services. Establish elevations, lines, and levels, utilizing recognized engineering survey practices.

D. Construct Work based on elevations, lines and locations as established, utilizing stakeout.

1.05 PRECONSTRUCTION MEETING

A. Engineer will schedule a meeting at the Project site after the Effective Date of the Agreement and prior to commencement of Work and Contractor occupancy, prepare an agenda with copies for participants, and preside at the meeting.

B. Attendance Required: Owner, Owner’s Designated Representative, Project Manager, Engineer, Resident Project Representative, Contractor, Contractor’s Superintendent, major Subcontractors, and others deemed required by Owner and/or law.

C. Agenda:

1. Designation of personnel representing the parties in Contract, and the Engineer.

2. Distribution of Contract Documents.

3. Scheduling.

4. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.

5. Procedures and processing of field decisions, submittals, substitutions, applications for payments, Change Orders, and Contract closeout procedures.

6. Use of premises by Owner and Contractor.

COORDINATION AND MEETINGS

01 31 00-2

D. Engineer shall record minutes and distribute copies within five (5) working days after meeting to Owner and all other participants.

1.06 PROGRESS MEETINGS

A. Meetings shall be scheduled throughout progress of the Work on an as-needed basis.

B. Resident Project Representative will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

C. Attendance Required: Contractor's superintendent, major Subcontractors and suppliers, Owner, Engineer, as appropriate to agenda topics for each meeting.

D. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems which impede planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of off-site fabrication and delivery schedules.

7. Maintenance of progress schedule.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Coordination of projected progress.

11. Maintenance of quality and work standards.

12. Effect of proposed changes on progress schedule and coordination.

13. Other business relating to Work.

E. Resident Project Representative shall record minutes and distribute copies within five (5) working days after meeting to Owner, Engineer and all other participants.

PART 2 - PRODUCTS

2.01 Not Used

PART 3 - EXECUTION

3.01 Not Used

END OF SECTION