19-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf

PDF 90 KB Posted

Attached to
234 McKean Road Demolition (26-00182)
Solicitation number
Not on record
Issued by
Montgomery County, Pennsylvania

About this file

This is a Measurement and Payment specification document for the Horsham Township project located in Pennsylvania, detailing the procedures and payment methodology for demolition and site restoration work. The project scope encompasses the complete demolition of a residential home, detached garage, two sheds, and an asphalt driveway; capping of a domestic water well in coordination with the Montgomery County Department of Health; abandonment of a sanitary sewer service lateral at the main with removal of the grinder pump and on-lot capping; and restoration of disturbed areas through topsoil placement, seeding, and permanent vegetation establishment. A mandatory pre-bid meeting is scheduled for Thursday, April 2, 2026, at 1100 Limekiln Pike, Ambler, PA 19002 (Kohler Park) at 11:00 AM. The measurement and payment structure utilizes unit price methodology based on the contract's Schedule of Bid Items, with the Resident Project Representative responsible for all measurements and quantity computations in accordance with the Drawings and Project Manual.

The contract employs a lump sum payment approach for demolition, water well capping, and sanitary sewer lateral abandonment, with each item inclusive of all necessary materials, labor, and equipment. Topsoil placement, permanent vegetation, hauling, and material disposal are specified as incidental costs not subject to separate line item payment and must be included within the base contract pricing. The contractor bears full responsibility for arranging proper disposal of all demolished and waste materials at a permitted facility, as the owner has not pre-arranged a disposal site. All work must be performed in strict accordance with the Drawings, Project Manual, and the Agreement's Schedule of Bid Items, with backfill required to be debris-free, compacted, and void-free to prevent settlement.

View the file

Other files

File Type Posted
11-Doc 00 43 13 - BID BOND.pdf PDF
18-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
9-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
16-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
21-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
44-X2 ES Plan.pdf PDF
51-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
3-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
42-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
43-Doc 00 65 19.16 - SUBCONTRACTORS RELEASE OF LIENS.pdf PDF
13-Doc 00 52 00 - AGREEMENT.pdf PDF
22-Doc 00 65 19.13 - SUBCONTRACTORS AFFIDAVIT.pdf PDF
6-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
20-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
41-Doc 00 73 00 5 - Appendix B - Public Works Employment Verification Form.pdf PDF
7-Sec 31 11 00 - CLEAR AND GRUB.pdf PDF
45-X1 Demo Plan.pdf PDF
25-Doc 00 41 00 - BID FORM - EBID.pdf PDF
12-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
46-X3 ES Notes and Details.pdf PDF
30-Sec 01 56 39. - LANDSCAPE PROTECTION.pdf PDF
50-Sec 31 23 33 - Excavation, Backfill and Compaction.pdf PDF
34-Doc 00 91 13 - ADDENDA.pdf PDF
48-Doc 00 11 13 - ADVERTISEMENT FOR BIDS - 234 McKean Road Demo.pdf PDF
33-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
37-Doc 00 62 76 - Application for Payment.pdf PDF
29-Doc 00 73 00 2 - Appendix A - cover sht.pdf PDF
5-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
31-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
40-Sec 02 41 16 - DEMOLITION.pdf PDF
49-X4 Easement Exhibit.pdf PDF
27-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
1-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
17-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
8-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
28-Doc 00 63 63 - Change Order.pdf PDF
26-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
24-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
32-Doc 00 45 10 - BIDDER’S ACKNOWLEDGEMENT FORM.pdf PDF
47-Doc 00 73 00 3 - Appendix A - Prevailing Wage Determination.pdf PDF
10-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
14-Doc 00 73 00 4 - Appendix B - cover sht.pdf PDF
39-Doc 00 21 13.1-Instr for Electronic Bidding.pdf PDF
35-Doc 00 21 13.2 - PennBid - How To Submit a Bid.pdf PDF
15-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
36-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
23-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
38-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
4-Sec 32 93 00 Landscaping.pdf PDF
52-Doc 00 73 00 1 - SUPPLEMENTARY CONDITIONS.pdf PDF
Show 40 more

Latest 50 of 97 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MEASUREMENT AND PAYMENT

01 22 00-1

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.01. SECTION INCLUDES

A. Measurement and payment criteria applicable to the Work performed under a unit price payment method.

1.02. PROCEDURE

A. All measurements for payment will be based on completed work, performed in strict accordance with the Drawings and Project Manual, and with the Agreement’s “Schedule of Bid Items”.

B. The Resident Project Representative shall take all measurements and compute quantities relative to all work completed under the Agreement in accordance with the methods included in this section. CONTRACTOR shall assist by providing necessary equipment and personnel as required.

C. In cases where the payment clause for an item in this section relating to any unit or lump sum price requires that the said unit or lump sum price cover and be considered compensation for certain work or material essential to the item, this same work or material shall not be measured or paid for under any other item which may appear elsewhere in this section.

PART 2 - PRODUCTS

Not Used

PART 3 - EXECUTION

3.01. DEMOLITION

A. Measurement is lump sum and constitutes furnishing all materials and equipment necessary to complete the work associated with this contract.

B. Payment shall be made at the contract unit price as determined in the Bid Schedule and in accordance with the schedule specified in Section 02 41 16 “Demolition”. This is a lump sum item for the entire contract. This price shall include furnishing all materials, labor and equipment necessary to complete the work associated with this contract. This item shall include demolition, removal and disposal of all buildings, including foundation slabs, concrete patio, and paver patio, as necessary to complete the work. Backfill shall be free of debris, compacted, and free of voids so that settlement doesn’t occur.

3.02. CAPPING OF DOMESTIC WATER WELL

A. Measurement will be lump sum and constitutes furnishing all materials and equipment necessary to complete the work associated with this contract.

B. Payment shall be made at the contract unit price listed in the Bid Schedule. This is a lump sum item for the entire contract. This price shall include furnishing all materials, labor and equipment necessary to complete the work associated with this contract. It shall include all necessary coordination with the Montgomery County Department of Health.

MEASUREMENT AND PAYMENT

01 22 00-2

3.03. SANITARY SEWER LATERAL ABANDONMENT

A. Measurement will be determined in the field per abandoning the service lateral at the main and removal of the grinder pump and capping of the lateral on-lot. This constitutes furnishing all materials, labor and equipment necessary to complete the work associated with this contract.

B. Payment shall be made at the contract unit price as determined in the Bid Schedule and in accordance with the HWSA details for abandonment provided on the plans. This is a lump sum item for the entire contract. This price shall include furnishing all materials, labor and equipment necessary to complete the work associated with this contract. This item shall include abandoning the service lateral at the main and removal of the grinder pump and capping of the lateral on-lot.

3.04. TOPSOIL

A. There will be no separate line item for topsoil. The topsoil is to be placed in all areas where buildings, patios, retaining walls etc. have been removed. Topsoil shall be placed to provide proper drainage per direction of the Engineer. This shall be for furnishing all labor, materials, and equipment necessary for the installation and fine grading of the topsoil. Topsoil shall be in accordance with Section 32 92 00. All topsoil required to compete the work shall be included.

Payment for topsoil will not be made as it will be made incidental to all other work.

3.05. PERMANENT VEGETATION

A. There will be no separate line item for permanent vegetation. This shall constitute furnishing all labor, materials, equipment, to rake, seed, and fertilize mulch to establish vegetation for all disturbed areas and as directed by the Engineer. Work shall be in accordance with Section 32 92 00. All vegetation required to compete the work shall be included in this item. Payment for permanent vegetation will not be made as it will be made incidental to all other work.

3.06. HAULING AND DISPOSAL OF MATERIAL

A. There will be no separate line item for hauling of demolished and/or waste material from the site. There will be no separate line item for disposal of demolished and/or waste material.

Hauling and disposal includes all labor, materials, equipment, fees and permits to remove all demolished and/or waste material from the site and for proper disposal at a permitted facility.

The OWNER has not arranged a facility for disposal. Contractor shall be responsible for proper disposal of all demolished and/or waste materials. No demolished and/or waste material shall remain on the project site. Payment for hauling and disposal of material will not be made as hauling and disposal of material will be made incidental to all other work.

END OF SECTION