10-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf

PDF 109 KB Posted

Attached to
234 McKean Road Demolition (26-00182)
Solicitation number
Not on record
Issued by
Montgomery County, Pennsylvania

About this file

This is a Contract Considerations specification document (Section 01 29 00) for Horsham Township, Pennsylvania, establishing administrative and procedural requirements for a demolition project at 234 McKean Road. The project scope includes demolition of an existing residential home, detached garage, two sheds, asphalt driveway removal, domestic water well capping, sanitary service line abandonment, temporary stream crossing restoration, and site grading and stabilization. A mandatory pre-bid meeting is scheduled for Thursday, April 2, 2026, at 1100 Limekiln Pike, Ambler, PA 19002, beginning at 11:00 AM. The contractor must submit a preliminary Schedule of Values in duplicate within 10 days after the Effective Date of the Agreement and submit monthly applications for payment on EJCDC Form C-620 in three copies, utilizing the Schedule of Values for line item documentation. Payment applications must include payroll certification forms and updated construction progress schedules, with final payment applications requiring a Waiver of Liens or Contractor's Affidavit, Release, and Statement of Surety Company.

The contract establishes change order procedures including Stipulated Price Change Orders, Unit Price Change Orders, Work Change Directives on EJCDC Form C-940, and Time and Material Change Orders, with the Contractor required to submit cost estimates within 15 days of a Proposal Request. All line items in the Schedule of Values must include a direct proportional amount of the Contractor's overhead and profit. The Engineer retains authority to issue minor changes not involving Contract Price or Time adjustments through supplemental instructions. The document references Document 00 52 00 for Agreement and Contract Price terms, Section 01 22 00 for Measurement and Payment, Section 01 33 00 for Schedule of Values submittals, and Section 01 60 00 for product substitutions and options. No alternates are specified for this project. Detailed records of all work performed on a Time and Material basis must be maintained with full supporting documentation for Engineer evaluation and cost substantiation.

View the file

Other files

File Type Posted
11-Doc 00 43 13 - BID BOND.pdf PDF
18-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
9-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
16-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
21-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
44-X2 ES Plan.pdf PDF
51-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
3-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
42-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
43-Doc 00 65 19.16 - SUBCONTRACTORS RELEASE OF LIENS.pdf PDF
13-Doc 00 52 00 - AGREEMENT.pdf PDF
22-Doc 00 65 19.13 - SUBCONTRACTORS AFFIDAVIT.pdf PDF
6-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
20-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
41-Doc 00 73 00 5 - Appendix B - Public Works Employment Verification Form.pdf PDF
7-Sec 31 11 00 - CLEAR AND GRUB.pdf PDF
45-X1 Demo Plan.pdf PDF
25-Doc 00 41 00 - BID FORM - EBID.pdf PDF
12-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
46-X3 ES Notes and Details.pdf PDF
30-Sec 01 56 39. - LANDSCAPE PROTECTION.pdf PDF
50-Sec 31 23 33 - Excavation, Backfill and Compaction.pdf PDF
34-Doc 00 91 13 - ADDENDA.pdf PDF
48-Doc 00 11 13 - ADVERTISEMENT FOR BIDS - 234 McKean Road Demo.pdf PDF
33-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
19-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
37-Doc 00 62 76 - Application for Payment.pdf PDF
29-Doc 00 73 00 2 - Appendix A - cover sht.pdf PDF
5-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
31-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
40-Sec 02 41 16 - DEMOLITION.pdf PDF
49-X4 Easement Exhibit.pdf PDF
27-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
1-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
17-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
8-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
28-Doc 00 63 63 - Change Order.pdf PDF
26-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
24-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
32-Doc 00 45 10 - BIDDER’S ACKNOWLEDGEMENT FORM.pdf PDF
47-Doc 00 73 00 3 - Appendix A - Prevailing Wage Determination.pdf PDF
14-Doc 00 73 00 4 - Appendix B - cover sht.pdf PDF
39-Doc 00 21 13.1-Instr for Electronic Bidding.pdf PDF
35-Doc 00 21 13.2 - PennBid - How To Submit a Bid.pdf PDF
15-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
36-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
23-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
38-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
4-Sec 32 93 00 Landscaping.pdf PDF
52-Doc 00 73 00 1 - SUPPLEMENTARY CONDITIONS.pdf PDF
Show 40 more

Latest 50 of 97 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT CONSIDERATIONS

01 29 00-1

SECTION 01 29 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Schedule of values.

2. Application for payment.

3. Change procedures.

4. Alternates.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Document 00 52 00: Agreement: Contract Price

2. Section 01 22 00: Measurement and Payment

3. Section 01 33 00: Submittals: Schedule of Values.

4. Section 01 60 00: Material and Equipment: Product substitutions and options.

1.03 SCHEDULE OF VALUES

A. Submit a printed schedule on Contractor's standard form or electronic media printout.

B. Submit preliminary Schedule of Values in duplicate within 10 days after Effective Date of the Agreement.

C. Format: See Supplementary Conditions

D. Include in each line item, the amount of allowance. For unit cost allowances, identify quantities taken from Contract Documents multiplied by the unit cost to achieve the total for the item.

E. Include within each line item, a direct proportional amount of Contractor's overhead and profit.

F. Revise schedule to list approved Change Orders, with each Application for Payment.

1.04 APPLICATIONS FOR PAYMENT

A. Submit three (3) copies of each application on EJCDC Form C-620.

B. Content and Format: Utilize Schedule of Values for listing items in Application for Payment.

C. Payment Period: Monthly

D. Waiver of Liens or Contractor's Affidavit, Contractor's Release and Statement of Surety Company (with Final Payment Application only)

E. Include Payroll Certification forms with each Payment Application.

F. Include an updated construction progress schedule.

1.05 CHANGE PROCEDURES

A. Engineer will advise of minor changes in the Work not involving an adjustment to Contract Price or Contract Time as authorized by Paragraph 9.5 of the General Conditions by issuing supplemental instructions.

01 29 00-2

B. Engineer may issue a Proposal Request which includes a detailed description of a proposed change with supplementary or revised Drawings and specifications. Contractor will prepare and submit an estimate within 15 days relative to changes in Contract Price and/or Contract Time.

C. Contractor may propose changes by submitting a request for change to Engineer, describing the proposed change and its full effect on the Work. Include a statement describing the reason for the change, and the effect on the Contract Price and Contract Time with full documentation and a statement describing effect on Work by any other contractors. Document any requested substitutions in accordance with Section 01 60 00.

D. Stipulated Price Change Order: Based on Proposal Request and Contractor's fixed price quotation or Contractor's request for a Change Order as approved by Engineer.

E. Unit Price Change Order: For contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of work which are not predetermined, the Change Order will be executed based on Contractor's proposed unit prices and quantities of units as approved by Engineer.

F. Work Change Directive: Engineer may issue a directive, on EJCDC Form C-940 Work Change

Directive signed by Owner, instructing Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work, and designate method of determining any change in Contract Price or Contract Time. Promptly execute the change.

G. Time and Material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract. Engineer will determine the change allowable in Contract Price and Contract Time as provided in the Contract Documents.

H. Maintain detailed records of Work done on Time and Material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in the Work.

I. Change Order Form: Doc 00 63 63 Change Order.

J. Execution of Change Orders: Engineer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

1.06 ALTERNATES

A. None

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION