21-Sec 01 11 13 - SUMMARY OF WORK.pdf
PDF 97 KB Posted
- Attached to
- 234 McKean Road Demolition (26-00182)
- Solicitation number
- Not on record
- Issued by
- Montgomery County, Pennsylvania
About this file
This is a Summary of Work document for a demolition and site restoration project in Pennsylvania, specifically for the 234 McKean Road property in Horsham Township. The project scope encompasses the complete demolition of an existing residential home, detached garage, two sheds, and asphalt driveway removal. Additional work includes capping a domestic water well, abandoning a sanitary sewer lateral at the main with removal of the grinder pump and capping of the lateral, temporary restoration of a stream crossing/access point damaged by previous flooding, and grading and permanent stabilization of all disturbed areas to match surrounding topography. The prior property owner will be granted access to retrieve solar panels from the house roof, items from the garage, and a tow-behind camper. A mandatory pre-bid meeting is scheduled for Thursday, April 2, 2026, at Kohler Park, 1100 Limekiln Pike, Ambler, PA 19002, beginning at 11:00 AM. Contractors must submit a complete construction schedule prior to commencing work.
The contractor is responsible for protecting all existing utilities including water, gas, electric, communications, sanitary sewer, and storm sewer infrastructure during operations and must comply with Pennsylvania Act 287 (1974) as amended by Act 121 (2008) to establish exact utility locations. At least forty-eight hours' advance notice must be provided to all property owners and residents prior to work initiation. All work must be conducted in strict compliance with OSHA Construction Workplace Safety Standards. The site will remain unoccupied by the owner during the construction period, and no other concurrent work by the owner or other parties is anticipated. No products will be supplied by the owner, and no future work is proposed beyond this contract scope.
View the file
Other files
Show 40 more
Latest 50 of 97 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY OF WORK
01 11 13-1
SECTION 01 11 13
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Description of Work.
2. Work by Owner.
3. Work by other parties.
4. Owner supplied Products.
5. Contractor use of site [and premises].
6. Future work.
7. Work sequence of construction.
8. Owner occupancy.
1.02 DESCRIPTION OF WORK
A. This project involves demolition of an existing residential home, detached garage, two sheds, along with the removal of an asphalt driveway. A domestic water well will need to be capped, and a sanitary sewer lateral will need to be abandoned at the main with the grinder pump removed on the property and the lateral capped. The site will require temporary restoration of an existing stream crossing/access point damaged by previous flooding. All disturbed areas are to be graded to match the surrounding topography and permanently stabilized.
The prior property owner shall be granted access once the temporary access is established. They need to remove solar panels from the roof of the house. There are also items they need to retrieve from the garage as well as a tow behind camper.
1.03 WORK BY OWNER
A. No other work is being planned by Owner at the site during construction of the Work under this contract.
1.04 WORK BY OTHER PARTIES
A. No other work by other parties is anticipated in the immediate vicinity during construction of the Work under this contract.
1.05 OWNER SUPPLIED PRODUCTS
A. No Products are to be supplied and paid for by Owner.
1.06 CONTRACTOR USE OF SITE AND PREMISES
A. The Work under this contract must be accomplished while the existing roadway and utilities are in use. The work that is involved with the existing roadway and utilities must be done so that system operations will not be jeopardized.
B. Contractor shall take all necessary precautions to protect all existing water, gas, electric, communications, sanitary sewer, storm sewer, or other facilities encountered during the course of his operations, to guard against disruption of service. Before beginning Work, Contractor shall determine the location of each facility which is questionable. The location of utilities shown on the Drawings represents the best information available; however, it is the responsibility of Contractor to establish the exact location in accordance with the
01 11 13-2 requirements of Pennsylvania Act 287 (1974) as last amended by Act 121 (2008). A Utility User's List is noted on the Drawings.
C. Contractor will be responsible to notify all property owners and residents at least forty-eight
(48) hours prior to the start of construction on or near their properties.
D. Contractor shall conduct all Work in strict compliance with OSHA Construction Workplace
Safety Standards.
1.07 FUTURE WORK
A. No future work is proposed as part of this contract.
1.08 WORK SEQUENCE OF CONSTRUCTION
A. The contractor shall submit a complete construction schedule prior to the start of any work.
1.09 OWNER OCCUPANCY
A. Owner will not occupy the site and premises during the period of the work.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION