15-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf
PDF 91 KB Posted
- Attached to
- 234 McKean Road Demolition (26-00182)
- Solicitation number
- Not on record
- Issued by
- Montgomery County, Pennsylvania
About this file
This file is a Contract Closeout specification section (01 70 00) applicable to the Horsham Township 234 McKean Road Demolition project in Pennsylvania. The specification establishes mandatory procedures for project completion, including final inspection certification, punchlist resolution, and final cleaning requirements. The contractor must maintain on-site record documents throughout construction, including marked-up drawings, specifications, addenda, change orders, shop drawings, and product data reflecting actual work performed. A mandatory pre-bid meeting is scheduled for Thursday, April 2, 2026, at 1100 Limekiln Pike, Ambler, Pennsylvania 19002, at 11:00 AM. The project scope encompasses demolition of an existing residential home, detached garage, two sheds, and asphalt driveway removal, along with domestic water well capping and sanitary service line abandonment. Site restoration includes temporary stream crossing repairs and grading of disturbed areas to match surrounding topography with permanent stabilization.
The closeout procedures require submission of written certification that contract documents have been reviewed and work is complete and ready for engineer review, followed by engineer final inspection and punchlist preparation. Final payment is contingent upon final completion and acceptance. Documentation requirements prior to final payment include payroll certifications for subcontractors and suppliers (if price exceeds $25,000), waivers of liens from all subcontractors and suppliers, maintenance bonds, outstanding change orders with supporting documentation, and test or sample results. Final cleaning must include equipment sanitation, filter cleaning or replacement, debris removal from drainage systems, site sweeping, and removal of all waste, surplus materials, and construction facilities. All operating products and equipment must be adjusted to ensure proper function prior to project closeout.
View the file
Other files
Show 40 more
Latest 50 of 97 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT CLOSEOUT
01 70 00-1
SECTION 01 70 00
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Closeout procedures.
2. Final cleaning.
3. Adjusting.
4. Project record documents.
5. Operation and maintenance manual.
6. Spare parts and maintenance Products.
7. Other documentation.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 50 00: Construction Facilities and Temporary Controls: Progress cleaning.
1.03 CLOSEOUT PROCEDURES
A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's review.
B. Engineer shall make a final inspection and prepare a punchlist of items remaining to be completed or corrected prior to final acceptance in accordance with Article 14, paragraph
14.06 of the General Conditions.
C. Complete all items on the punchlist, plus any new items that may be subsequently added, as soon as possible and within the Contract Time.
D. Provide submittals to Engineer that are required by governing or other authorities.
E. Submit final Application for Payment identifying total adjusted Contract Price, previous payments, and remaining amount due.
F. Final Payment will not be made until final completion and acceptance of the Work.
1.04 FINAL CLEANING
A. Execute final cleaning prior to final Project inspection.
B. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.
C. Clean or replace filters of operating equipment.
D. Clean debris from gutters and drainage systems.
E. Clean site; sweep paved areas, rake clean landscaped surfaces.
F. Remove waste and surplus materials, rubbish, and construction facilities from the site.
1.05 ADJUSTING
A. Adjust operating Products and equipment to ensure smooth and unhindered operation.
01 70 00-2
1.06 PROJECT RECORD DOCUMENTS
A. Maintain on-site one set of the following record documents; record actual revisions to the Work:
1. Drawings and Specifications.
2. Addenda.
3. Change Orders and other modifications to the Contract.
4. Reviewed Shop Drawings, Product data, and samples.
5. Manufacturer’s instructions for assembly, installation and adjusting.
B. Ensure entries are complete and accurate, enabling future reference by Owner.
C. Store record documents separate from documents used for construction.
D. Record information concurrent with construction progress.
E. Specifications: Legibly mark and record at each Product section description of actual Products installed, including the following:
1. Manufacturer's name and product model and number.
2. Product substitutions or alternates utilized.
3. Changes made by Addenda and modifications.
F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:
1. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
2. Field changes of dimension and detail.
3. Details not on original Contract Drawings.
G. Submit documents to Engineer with claim for final Application for Payment.
1.07 OTHER DOCUMENTATION
A. Provide data and documentation properly completed and executed prior to final Application for Payment as Engineer may reasonably require including:
1. Payroll Certification forms by Contractor and all Subcontractors (if price exceeds $25,000).
2. Waiver of Liens by all Subcontractors and Suppliers or Contractor's Affidavit, Contractor's Release of Liens and Consent of Surety to Final Payment.
3. Maintenance Bond.
4. Any Change Orders with supporting documentation which remain to be submitted.
5. Test and/or sample results.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION