16-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf

PDF 115 KB Posted

Attached to
234 McKean Road Demolition (26-00182)
Solicitation number
Not on record
Issued by
Montgomery County, Pennsylvania

About this file

This is a Construction Facilities and Temporary Controls specification section (01 50 00) for a demolition project in Horsham Township, Pennsylvania, specifically the 234 McKean Road Demolition project. The specification establishes contractor responsibilities for temporary site management including barriers, fencing, water control, dust control, access roads, parking, and progress cleaning throughout the construction phase. Key requirements include providing a 6-foot-high fence around the construction site equipped with vehicular gates and locks, maintaining excavations free of water through grading and pumping equipment, implementing dust control measures through sprinkling or approved methods, and maintaining the site in clean and orderly condition with weekly debris removal. The contractor must provide temporary electricity, lighting, and security for the work area, protect existing facilities and landscaped areas from damage, maintain access to Montgomery Township Public Works buildings, and manage construction vehicle mud removal before street entry. A mandatory pre-bid meeting is scheduled for Thursday, April 2, 2026, at 1100 Limekiln Pike, Ambler, Pennsylvania, with bid submissions due by September 9, 2025.

The project scope encompasses demolition of an existing residential home, detached garage, two sheds, and an asphalt driveway, along with capping a domestic water well and abandoning the sanitary service line at the main. All disturbed areas must be graded to match surrounding topography and permanently stabilized, with temporary restoration of an existing stream crossing damaged by previous flooding. Cost responsibilities are assigned to the contractor for temporary electricity, with all temporary utilities, equipment, and facilities to be removed prior to final payment inspection and all damage caused by temporary installations to be repaired. The specification does not identify explicit pricing terms, set-asides, or funding sources within the document itself, though the broader solicitation indicates requirements for performance bonds, payment bonds, prevailing wage compliance, and public works employment verification.

View the file

Other files

File Type Posted
11-Doc 00 43 13 - BID BOND.pdf PDF
18-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
9-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
21-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
44-X2 ES Plan.pdf PDF
51-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
3-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
42-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
43-Doc 00 65 19.16 - SUBCONTRACTORS RELEASE OF LIENS.pdf PDF
13-Doc 00 52 00 - AGREEMENT.pdf PDF
22-Doc 00 65 19.13 - SUBCONTRACTORS AFFIDAVIT.pdf PDF
6-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
20-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
41-Doc 00 73 00 5 - Appendix B - Public Works Employment Verification Form.pdf PDF
7-Sec 31 11 00 - CLEAR AND GRUB.pdf PDF
45-X1 Demo Plan.pdf PDF
25-Doc 00 41 00 - BID FORM - EBID.pdf PDF
12-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
46-X3 ES Notes and Details.pdf PDF
30-Sec 01 56 39. - LANDSCAPE PROTECTION.pdf PDF
50-Sec 31 23 33 - Excavation, Backfill and Compaction.pdf PDF
34-Doc 00 91 13 - ADDENDA.pdf PDF
48-Doc 00 11 13 - ADVERTISEMENT FOR BIDS - 234 McKean Road Demo.pdf PDF
33-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
19-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
37-Doc 00 62 76 - Application for Payment.pdf PDF
29-Doc 00 73 00 2 - Appendix A - cover sht.pdf PDF
5-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
31-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
40-Sec 02 41 16 - DEMOLITION.pdf PDF
49-X4 Easement Exhibit.pdf PDF
27-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
1-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
17-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
8-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
28-Doc 00 63 63 - Change Order.pdf PDF
26-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
24-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
32-Doc 00 45 10 - BIDDER’S ACKNOWLEDGEMENT FORM.pdf PDF
47-Doc 00 73 00 3 - Appendix A - Prevailing Wage Determination.pdf PDF
10-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
14-Doc 00 73 00 4 - Appendix B - cover sht.pdf PDF
39-Doc 00 21 13.1-Instr for Electronic Bidding.pdf PDF
35-Doc 00 21 13.2 - PennBid - How To Submit a Bid.pdf PDF
15-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
36-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
23-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
38-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
4-Sec 32 93 00 Landscaping.pdf PDF
52-Doc 00 73 00 1 - SUPPLEMENTARY CONDITIONS.pdf PDF
Show 40 more

Latest 50 of 97 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

01 50 00-1

SECTION 01 50 00

PART 1 GENERAL

1.01 GENERAL

A. The Work of this Section shall be the responsibility of the contractor as noted in the Summary of Work (Section 01 11 13).

1.02 SECTION INCLUDES

A. Temporary Controls: Barriers, enclosures and fencing, protection of the Work, water control and dust control.

B. Construction Facilities: Access roads, parking, and progress cleaning.

1.03 RELATED SECTIONS

A. Section 01 55 26: Traffic Regulation.

B. Section 01 57 13: Soil Erosion and Sediment Control.

C. Section 01 70 00: Contract Closeout: Final cleaning.

1.04 TEMPORARY ELECTRICITY

A. Cost: By Contractor; provide and pay for power service required from utility source.

1.05 TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES

A. Provide and maintain lighting for construction operations and for security purposes.

B. Provide branch wiring from power source to distribution boxes with lighting conductors, pigtails, and lamps as required.

C. Maintain lighting and provide routine repairs.

D. Permanent building lighting may [not] be utilized during construction. [Repair, clean, and replace lamps at end of construction.]

1.11 BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas, to allow for Owner's use of site, and to protect existing facilities and adjacent properties from damage from construction operations and demolition.

B. Provide protection for plants designated to remain. Replace damaged plants.

C. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

1.12 FENCING

A. Construction: Contractor's option.

01 50 00-2

B. Provide 6 foot high fence around construction site; equip with vehicular gates with locks.

C. CONTRACTOR provide OWNER keys for all gate locks.

1.13 WATER CONTROL

A. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.

B. Protect site from puddling or running water.

1.16 PROTECTION OF INSTALLED WORK

A. Protect installed Work and provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed Products. Control activity in immediate work area to prevent damage.

C. Prohibit traffic from landscaped areas.

1.17 SECURITY

A. Provide security and facilities to protect Work and existing facilities from unauthorized entry, vandalism, or theft.

1.18 ACCESS ROADS

A. Utilize existing paths/roads within site.

B. Provide means of removing mud from vehicle wheels before entering streets.

C. Maintain access to the remaining buildings utilized by Montgomery Township Public Works.

1.19 PARKING

A. Plenty of area on-site for parking

B. Maintain access to the remaining buildings utilized by Montgomery Township Public Works.

1.20 PROGRESS CLEANING AND WASTE REMOVAL

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.

B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing the space.

C. Broom and vacuum clean interior areas prior to start of surface finishing, and continue cleaning to eliminate dust.

D. Collect and remove waste materials, debris, and rubbish from site [periodically] [weekly] and dispose off-site.

01 50 00-3

E. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.

1.21 PROJECT IDENTIFICATION

A. No signs are allowed without Owner permission except those required by law.

1.22 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Remove temporary utilities, equipment, facilities, materials, prior to Final Application for Payment inspection.

B. Remove underground installations to a minimum depth of 2 feet. Grade site as indicated.

C. Clean and repair damage caused by installation or use of temporary work.

D. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.

1.23 DUST CONTROL

A. Execute Work by methods to minimize raising dust from construction operations.

B. Provide positive means (i.e. use of sprinkling water or other methods approved by the Resident Project Representative) to prevent air-borne dust from dispersing into atmosphere.

C. Dust control measures shall be employed when required in the opinion of the Resident

Project Representative at no additional cost to Owner.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION