W912QR22R0028_Specs_PH1_Vol3-0000.pdf

PDF 8 MB Posted

Attached to
Renovation of WPAFB Air Force Materiel Command Headquarters; Phase 1
Solicitation number
W912QR22R0028
Issued by

About this file

This document provides details for a federal construction contract opportunity with the U.S. Army Corps of Engineers Louisville District. The contract is for Phase 1 of the renovation of the Air Force Materiel Command Headquarters Building at Wright-Patterson Air Force Base in Ohio, with an estimated value between $100-250 million. Scope of work includes interior and exterior repairs, HVAC, plumbing, electrical and telecommunications upgrades, and improvements to the thermal envelope. The solicitation is anticipated for release on November 10, 2022 via SAM.gov and will utilize best value tradeoff source selection. Proposals are due in early 2023, with contract award by mid-2023 and work completion in late 2025. Offerors must be registered in SAM and have adequate financial resources. The point of contact for the solicitation is listed.

View the file

Other files

File Type Posted
W912QR22R0028_CUI_CF_Plans-0004.pdf PDF
W912QR22R0028_CUI_CF_Specs-0004.pdf PDF
W912QR22R0028_CUI_CF_Plans-0003.pdf PDF
W912QR22R0028_CUI_CF_Specs-0003.pdf PDF
W912QR22R0028_CUI_CF_CIDV2_FFE-0003.pdf PDF
W912QR22R0028_CUI_CF_Specs_Vol2-0002.pdf PDF
W912QR22R0028_CUI_CF_Plans_Vol7-0002.pdf PDF
W912QR22R0028_CUI_CF_Specs_Vol4-0002.pdf PDF
W912QR22R0028_CUI_Pre bid contractors site visit requested photos - 1 Dec 2022.pdf PDF
W912QR22R0028_CUI_CF_Specs_Vol3-0002.pdf PDF
W912QR22R0028_CUI_CF_CIDV2_FFE-0002.pdf PDF
W912QR22R0028_CUI_CF_Plans_Vol5-0002.pdf PDF
W912QR22R0028_CUI_CF_Plans_Vol4-0002.pdf PDF
W912QR22R0028_CUI_CF_Plans_Vol3-0002.pdf PDF
W912QR22R0028_CUI_CF_CIDV1_SID-0002.pdf PDF
W912QR22R0028_CUI_CF_Specs_Vol5-0002.pdf PDF
W912QR22R0028_CUI_CF_Plans_Vol1-0002.pdf PDF
W912QR22R0028_CUI_CF_Plans_Vol6-0002.pdf PDF
W912QR22R0028_CUI_Site Visit Attendee list - AFMC HQ Project 1 DEC 22.pdf PDF
W912QR22R0028_CUI_CF_Specs_Vol1-0002.pdf PDF
W912QR22R0028_CUI_CF_Plans_Vol2-0002.pdf PDF
W912QR22R0028_CUI_CF_Plans_Vol8-0002.pdf PDF
W912QR22R0028_AFMC_Phase 1_CID_V2_FFE-0001.pdf PDF
JA - AFMC HQ - Reno Trane Chillers - SAM Redacted.pdf PDF
W912QR22R0028_Plans_PH1_Vol8-0000.pdf PDF
W912QR22R0028_Plans_PH1_Vol2-0000.pdf PDF
JA - AFMC HQ Reno - FFE Basis of Design - SAM Redacted.pdf PDF
W912QR22R0028_Specs_PH1_Vol1-0000.pdf PDF
REDACTED - SPE - Signed Class JA for Basis of Design Items.pdf PDF
JA - AFMC HQ Reno - Fire Alarm System - Brand Name - SAM Redacted.pdf PDF
W912QR22R0028_Specs_PH1_Vol2-0000.pdf PDF
W912QR22R0028_Plans_PH1_Vol7-0000.pdf PDF
JA - AFMC HQ Reno - Integrated Sec Platform - Brand Name - SAM Redacted.pdf PDF
W912QR22R0028_Plans_PH1_Vol1-0000.pdf PDF
W912QR22R0028_Specs_PH1_Vol5-0000.pdf PDF
W912QR22R0028_Specs_PH1_Vol4-0000.pdf PDF
W912QR22R0028_Plans_PH1_Vol4-0000.pdf PDF
W912QR22R0028_Plans_PH1_Vol5-0000.pdf PDF
JA - AFMC HQ Reno - Brand Name Siemens Talon or Johnson Controls - SAM Redacted.pdf PDF
W912QR22R0028_Plans_PH1_Vol6-0000.pdf PDF
W912QR22R0028_Plans_PH1_Vol3-0000.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Controlled by: USACE-LRL-ED-MA CUI Category(ies):

LDC or Distribution Statement: N/A POC: Blake Gevedon Contracting Specialist william.b.gevedon@usace.army.mi 502.315.6791

Materials shall be submitted to potential offerors currently certified in the Joint Certification Program (JCP) only.

W912QR22R0028_Specs_PH1_Vol3-0000

Solicitation For Repair/Renovate AFMC Headquarters Building (B10262) Phase 1 -

P2: 475429

Design-Bid-Build

Specifications 90% Final Revised Specification Submittal Vol. 3 of 5

10 November 2022

W912QR22R0028

ARIMS: 200A

Disposition: Maintain for 15yrs after construction

US Army Corps of Engineers Louisville District

Rev00 Repair/Renovate AFMC

Headquarters Building (B10262) Phase 1 -

90% Final Revised Specification Submittal Project Number: ZHTV160500-262

P2 # 475429 Fiscal Year 2023

Solicitation Number: W912QR22R0028

20 October 2022

CONTROLLED

UNCLASSIFIED

INFORMATION

Volume 3 of 5

SPECIFICATIONS

Controlled by: USACE Controlled by: Louisville District CUI Category: CUI Basic Distribution/Dissemination Controls: Distribution B POC: Steve Skaggs, 502-315-6368

THIS PAGE INTENTIONALLY LEFT BLANK

P2#475429 Repair/Reno AFMC HQ 10262 CUI Wright-Patterson AFB –Phase 1

PROJECT TABLE OF CONTENTS Page 1 CUI 90% Final Revised

PROJECT TABLE OF CONTENTS

VOLUME 1

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 10 00 PRICE BREAKOUT SCHEDULE

00 80 00.00 06 SPECIAL PROVISIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 08/15 SUMMARY OF WORK

01 32 01.00 06 07/18 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 33 29.00 06 11/17 SUSTAINABILITY REPORTING

01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS

01 35 43 12/20 GENERAL ENVIRONMENTAL PROTECTION

REQUIREMENTS (WPAFB)

01 35 53 08/19 SPECIAL SECURITY PROCEDURES

01 42 00 02/19 SOURCES FOR REFERENCE

PUBLICATIONS

01 45 00.15 10 11/16 RESIDENT MANAGEMENT SYSTEM

CONTRACTOR MODE (RMS CM)

01 45 04.10 06 CONTRACTOR QUALITY CONTROL

01 45 35 11/20 SPECIAL INSPECTIONS

01 46 00.00 06 04/20 TOTAL BUILDING COMMISSIONING

01 50 00 11/20 TEMPORARY CONSTRUCTION

FACILITIES AND CONTROLS

01 74 19 02/19 CONSTRUCTION WASTE MANAGEMENT

AND DISPOSAL

01 78 23 08/15 OPERATION AND MAINTENANCE DATA

VOLUME 2

DIVISION 02 - EXISTING CONDITIONS

02 41 00 05/10 DEMOLITION AND DECONSTRUCTION

PROJECT TABLE OF CONTENTS Page 2 CUI 90% Final Revised

DIVISION 03 - CONCRETE

03 01 00 02/18 REHABILITATION OF CONCRETE

03 30 00 02/19 CAST-IN-PLACE CONCRETE

03 33 00 11/09 CAST-IN-PLACE ARCHITECTURAL

CONCRETE

03 35 43 12/21 POLISHED CONCRETE FINISHING

03 62 15.00 06 07/16 FLOWABLE FILL

DIVISION 04 - MASONRY

04 20 00 11/15 UNIT MASONRY

04 72 00 09/20 CAST STONE MASONRY

DIVISION 05 - METALS

05 05 20.00 27 02/21 POST-INSTALLED CONCRETE AND

MASONRY ANCHORS

05 05 23.16 08/18 STRUCTURAL WELDING

05 12 00 08/18 STRUCTURAL STEEL

05 30 00 05/15 STEEL DECKS

05 40 00 05/15 COLD-FORMED METAL FRAMING

05 50 13 05/17 MISCELLANEOUS METAL FABRICATIONS

05 50 14 08/18 STRUCTURAL METAL FABRICATIONS

05 51 00 02/17 METAL STAIRS

05 51 00.01 05/22 PREFABRICATED ALUMINUM STAIRS

05 51 33 02/16 METAL LADDERS

05 52 00 02/18 METAL RAILINGS

05 52 16 12/21 METAL EGRESS BARRIER GATES

05 75 00 05/21 DECORATIVE FORMED METAL

PROJECT TABLE OF CONTENTS Page 3 CUI 90% Final Revised

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 08/16 ROUGH CARPENTRY

06 16 00 10/20 SHEATHING

06 20 00 08/16 FINISH CARPENTRY

06 41 16.00 10 08/10 PLASTIC-LAMINATE-CLAD

ARCHITECTURAL CABINETS

06 61 16 08/10 SOLID SURFACING FABRICATIONS

06 64 00 11/19 PLASTIC PANELING

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 01 50.19 05/20 PREPARATION FOR REROOFING

07 13 53 02/16 ELASTOMERIC SHEET WATERPROOFING

07 17 00 08/22 BENTONITE WATERPROOFING

07 17 10 08/22 BENTONITE INJECTION

WATERPROOFING

07 21 13 02/16 BOARD INSULATION

07 21 16 11/11 MINERAL FIBER BLANKET INSULATION

07 22 00 02/16 ROOF AND DECK INSULATION

07 24 00 05/11 POLYMER-BASED EXTERIOR FINISH

SYSTEMS (EFS)

07 27 10.00 10 08/19 BUILDING AIR BARRIER SYSTEM

07 27 19.01 05/17 SELF-ADHERING AIR BARRIERS

07 27 26 05/17 FLUID-APPLIED MEMBRANE AIR

BARRIERS

07 27 36 05/17 SPRAY FOAM AIR BARRIERS

07 42 13 05/11 METAL WALL PANELS

07 42 17 06/20 INSULATED-CORE METAL WALL BACKUP

PANEL SYSTEM

07 42 93 05/22 SOFFIT PANELS

07 44 56 06/20 MINERAL-FIBER-REINFORCED

CEMENTITIOUS PANELS

PROJECT TABLE OF CONTENTS Page 4 CUI 90% Final Revised

07 52 00 05/12 MODIFIED BITUMINOUS MEMBRANE

ROOFING

07 54 23 02/13 THERMOPLASTIC POLYOLEFIN (TPO)

ROOFING

07 60 00 05/17 FLASHING AND SHEET METAL

07 61 15.00 20 08/16 ALUMINUM STANDING SEAM ROOFING

07 71 00 05/20 ROOF SPECIALTIES

07 72 10 11/19 ROOFTOP FALL ARREST SYSTEM

07 72 30 ROOF ACCESSORIES

07 72 53 07/20 SNOW GUARDS

07 81 00 02/11 SPRAY-APPLIED FIREPROOFING

07 81 23 05/20 INTUMESCENT FIREPROOFING

07 84 00 05/10 FIRESTOPPING

07 92 00 08/16 JOINT SEALANTS

07 95 13.13 12/20 INTERIOR EXPANSION JOINT COVER

ASSEMBLIES

07 95 13.16 01/21 EXTERIOR EXPANSION JOINT COVER

ASSEMBLIES

DIVISION 08 - OPENINGS

08 08 13 07/20 FIRE-RESISTANT GLAZING

08 11 13 02/10 STEEL DOORS AND FRAMES

08 14 00 08/16 WOOD DOORS

08 31 00 05/17 ACCESS DOORS AND PANELS

08 33 13 05/09 COILING COUNTER DOORS

08 33 23 11/19 OVERHEAD COILING DOORS

08 33 26 01/21 OVERHEAD COILING GRILLES

08 34 60 05/22 HORIZONTAL SLIDING WINDOW

08 34 73 02/15 SOUND CONTROL DOOR ASSEMBLIES

08 41 13 08/18 ALUMINUM-FRAMED ENTRANCES AND

STOREFRONTS

PROJECT TABLE OF CONTENTS Page 5 CUI 90% Final Revised

08 44 00 05/19 CURTAIN WALL AND GLAZED

ASSEMBLIES

08 71 00 02/16 DOOR HARDWARE

08 81 00 05/19 GLAZING

08 85 10 08/09 DECORATIVE FILM FOR GLASS

08 88 13 FIRE-RESISTANT STOREFRONT

GLAZING

08 91 00 05/11 METAL WALL LOUVERS

VOLUME 3

DIVISION 09 - FINISHES

09 22 00 02/10 SUPPORTS FOR PLASTER AND GYPSUM

BOARD

09 22 16 01/21 EXTRUDED ALUMINUM PARTITION

CLOSURE

09 23 00 08/16 GYPSUM PLASTERING

09 24 23 08/17 CEMENT STUCCO

09 29 00 08/16 GYPSUM BOARD

09 30 10 08/17 CERAMIC, QUARRY, AND GLASS

TILING

09 51 00 08/17 ACOUSTICAL CEILINGS

09 54 70 05/21 METAL PANEL CEILING SYSTEM

09 62 38 08/17 STATIC-CONTROL FLOORING

09 65 00 08/10 RESILIENT FLOORING

09 66 13 08/16, CHG 2: 11/18 PRECAST TERRAZZO TREADS

09 66 16 08/16 TERRAZZO FLOOR TILE

09 67 23.13 11/19 STANDARD RESINOUS FLOORING

09 68 00 11/17 CARPETING

09 72 00 08/17 WALLCOVERINGS

09 84 20 08/16 ACOUSTICAL WALL PANELS

09 90 00 05/11 PAINTS AND COATINGS

PROJECT TABLE OF CONTENTS Page 6 CUI 90% Final Revised

09 96 00 11/14 HIGH-PERFORMANCE COATINGS

09 96 46 11/19 INTUMESCENT PAINTING

DIVISION 10 - SPECIALTIES

10 11 00 08/17 VISUAL DISPLAY UNITS

10 14 00.10 08/17 EXTERIOR SIGNAGE

10 14 00.20 08/20 INTERIOR SIGNAGE

10 21 13 08/17 TOILET COMPARTMENTS

10 26 00 08/17 WALL AND DOOR PROTECTION

10 28 13 08/17 TOILET ACCESSORIES

10 44 16 11/19 FIRE EXTINGUISHERS

10 45 13 10/20 DEFIBRILLATOR CABINETS AND

DEFIBRILLATORS

10 51 13.10 05/11 METAL LOCKERS - SPECIAL PURPOSE

10 99 00 11/19 MISCELLANEOUS ITEMS

DIVISION 11 - EQUIPMENT

11 10 10 09/20 MODULAR ACCESS RAMPS

11 13 13 04/20 LOADING DOCK BUMPER

11 13 19.13 08/09 LOADING DOCK LEVELERS

DIVISION 12 - FURNISHINGS

12 24 13 08/17 ROLLER WINDOW SHADES

12 36 00 08/18 COUNTERTOPS

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 73 05/20 BRACING FOR EQUIPMENT

PROJECT TABLE OF CONTENTS Page 7 CUI 90% Final Revised

DIVISION 14 - CONVEYING EQUIPMENT

14 21 23 05/20 ELECTRIC TRACTION PASSENGER

ELEVATORS

14 42 50 05/20 VERTICAL WHEELCHAIR LIFTS

DIVISION 21 - FIRE SUPPRESSION

21 12 00 05/11 STANDPIPE SYSTEMS

21 13 13.00 10 05/09 WET PIPE SPRINKLER SYSTEM, FIRE

PROTECTION

21 13 19 08/20 DELUGE SPRINKLER SYSTEMS, FIRE

PROTECTION

21 30 00 04/08 FIRE PUMPS

DIVISION 22 - PLUMBING

22 00 00 11/15 PLUMBING, GENERAL PURPOSE

22 11 16.11 WATER SERVICE TAPS AND SERVICE

LINE INSTALLATION

22 11 16.13 CROSS CONNECTION CONTROL AND

BACKFLOW PREVENTION

22 13 19.23 GREASE TRAPS

22 31 00 02/09 WATER SOFTENERS, CATION-EXCHANGE

(SODIUM CYCLE)

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 08/18 AIR SUPPLY, DISTRIBUTION,

VENTILATION, AND EXHAUST SYSTEMS

23 01 30.41 02/15 HVAC SYSTEM CLEANING

23 05 15 02/14 COMMON PIPING FOR HVAC

23 05 93.00 06 08/16 TESTING, ADJUSTING, AND

BALANCING (TAB) OF HVAC

23 07 00 02/13 THERMAL INSULATION FOR

MECHANICAL SYSTEMS

PROJECT TABLE OF CONTENTS Page 8 CUI 90% Final Revised

23 09 00 02/19 INSTRUMENTATION AND CONTROL FOR

HVAC

23 09 13 11/15 INSTRUMENTATION AND CONTROL

DEVICES FOR HVAC

23 09 23.02 02/19 BACNET DIRECT DIGITAL

CONTROL FOR HVAC AND OTHER

BUILDING CONTROL SYSTEMS

23 11 25 11/08 FACILITY GAS PIPING

23 21 23 08/17 HYDRONIC PUMPS

23 23 00 10/07 REFRIGERANT PIPING

23 25 00 11/08 CHEMICAL TREATMENT OF WATER FOR

MECHANICAL SYSTEMS

23 64 10 11/16 WATER CHILLERS, VAPOR

COMPRESSION TYPE

23 64 26 08/09 CHILLED, CHILLED-HOT, AND

CONDENSER WATER PIPING SYSTEMS

23 81 00 05/18 DECENTRALIZED UNITARY HVAC

EQUIPMENT

23 82 01.00 10 04/08 WARM AIR HEATING SYSTEMS

VOLUME 4

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.21 11/17 CYBERSECURITY FOR FACILITY

RELATED CONTROL SYSTEMS FIRE AND

LIFE SAFETY (FLS)

25 05 11.23 11/17 CYBERSECURITY FOR FACILITY-

RELATED CONTROL SYSTEMS ENERGY

MANAGEMENT CONTROL SYSTEM (EMCS)

25 05 11.26 11/17 CYBERSECURITY FOR FACILITY-

RELATED CONTROL SYSTEMS UTILITY

CONTROL SYSTEM (UCS)

25 05 11.26 02 11/17 CYBERSECURITY FOR FACILITY-

RELATED CONTROL SYSTEMS BUILDING

CONTROL SYSTEM (BCS)

25 05 11.28 11/17 CYBERSECURITY FOR FACILITY-

RELATED CONTROL SYSTEMS

ELECTRONIC SECURITY SYSTEM (ESS)

PROJECT TABLE OF CONTENTS Page 9 CUI 90% Final Revised

25 08 10 04/06 UTILITY MONITORING AND CONTROL

SYSTEM TESTING

25 10 10 02/19 UTILITY MONITORING AND CONTROL

SYSTEM (UMCS) FRONT END AND

INTEGRATION

DIVISION 26 - ELECTRICAL

26 08 00 08/08, CHG 1: 02/15 APPARATUS INSPECTION AND TESTING

26 20 00 08/19 INTERIOR DISTRIBUTION SYSTEM

26 23 00 05/15 LOW-VOLTAGE SWITCHGEAR

26 24 13 05/15 SWITCHBOARDS

26 28 01.00 10 10/07 COORDINATED POWER SYSTEM

PROTECTION

26 29 23 02/20 ADJUSTABLE SPEED DRIVE (ASD)

SYSTEMS UNDER 600 VOLTS

26 32 15.00 05/20 ENGINE-GENERATOR SET STATIONARY

15-2500 KW, WITH AUXILIARIES

26 36 23 05/20 AUTOMATIC TRANSFER SWITCHES AND

BY-PASS/ISOLATION SWITCH

26 41 00 11/13 LIGHTNING PROTECTION SYSTEM

26 42 14.00 10 08/09 CATHODIC PROTECTION SYSTEM

(SACRIFICIAL ANODE)

26 51 00 05/20 INTERIOR LIGHTING

26 56 00 05/20 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 05 14.00 10 04/06 CABLE TELEVISION PREMISES

DISTRIBUTION SYSTEM

27 10 00 08/11 BUILDING TELECOMMUNICATIONS

CABLING SYSTEM

27 41 00 10/20 AUDIOVISUAL SYSTEMS

27 51 19 01/22 SOUND MASKING SYSTEMS

PROJECT TABLE OF CONTENTS Page 10 CUI 90% Final Revised

VOLUME 5

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 08 10 05/16 ELECTRONIC SECURITY SYSTEM

ACCEPTANCE TESTING

28 10 05 05/16 ELECTRONIC SECURITY SYSTEMS

(ESS)

28 31 76 08/11 INTERIOR FIRE ALARM AND MASS

NOTIFICATION SYSTEM

DIVISION 31 - EARTHWORK

31 00 00.00 06 07/18 EARTHWORK

31 11 00 11/18 CLEARING AND GRUBBING

31 31 16.13 08/16 CHEMICAL TERMITE CONTROL

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 16.71 02/17 COLD MILLING ASPHALT PAVING

32 05 33 08/17 LANDSCAPE ESTABLISHMENT

32 11 20 08/17 BASE COURSE FOR RIGID AND

SUBBASES FOR FLEXIBLE PAVING

32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS

32 12 16 08/09 HOT-MIX ASPHALT (HMA) FOR ROADS

32 13 13.06 06 06/18 PORTLAND CEMENT CONCRETE

PAVEMENT FOR ROADS AND SITE

FACILITIES

32 15 00 05/17 AGGREGATE SURFACING

32 16 19 05/18 CONCRETE CURBS, GUTTERS AND

SIDEWALKS

32 17 23 08/16 PAVEMENT MARKINGS

32 17 26 01/21 TACTILE WARNING SURFACING

32 31 13 11/16 CHAIN LINK FENCES AND GATES

32 31 13.10 11/16 CHAIN LINK FENCES AND GATES (FOR

BUILDING INTERIORS)

PROJECT TABLE OF CONTENTS Page 11 CUI 90% Final Revised

32 31 13.53 02/20 HIGH-SECURITY FENCES (CHAIN LINK

AND ORNAMENTAL) AND GATES

32 92 19 08/17 SEEDING

32 92 23 04/06, CHG 1: 08/21 SODDING

32 93 00 08/17, CHG 1: 08/21 EXTERIOR PLANTS

DIVISION 33 - UTILITIES

33 01 10.13 PRESSURE AND LEAKAGE TESTS

33 01 30.13 ACCEPTANCE TESTING FOR SANITARY

SEWERS

33 11 00 PIPING AND ACCESSORIES – GENERAL

PROVISIONS

33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE

33 11 00.15 DUCTILE IRON PIPE AND FITTINGS

33 30 00 05/18 SANITARY SEWERAGE

33 40 00 02/10 STORM DRAINAGE UTILITIES

33 46 13 04/08 FOUNDATION DRAINAGE SYSTEM

33 46 16 05/18 SUBDRAINAGE PIPING

33 51 15 08/19 NATURAL-GAS / LIQUEFIED

PETROLEUM GAS DISTRIBUTION

PIPELINES

33 52 10 11/18 FUEL SYSTEMS PIPING

33 56 10 05/19 FACTORY-FABRICATED FUEL STORAGE

TANKS

33 61 13.13 02/16 PREFABRICATED UNDERGROUND

HYDRONIC ENERGY DISTRIBUTION

33 71 02 02/15 UNDERGROUND ELECTRICAL

DISTRIBUTION

33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT

(OSP)

PROJECT TABLE OF CONTENTS Page 12 CUI 90% Final Revised

DIVISION 34 - TRANSPORTATION

34 71 13.19 02/20 CRASH RATED ACTIVE VEHICLE

BARRIERS AND CONTROLS

-- End of Project Table of Contents --

Wright-Patterson AFB – Phase 1

SECTION 09 22 00

SUPPORTS FOR PLASTER AND GYPSUM BOARD

02/10

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM A463/A463M (2010; R 2015) Standard Specification for Steel Sheet, Aluminum-Coated, by the Hot-Dip Process

ASTM A653/A653M (2020) Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process

ASTM C645 (2014; E 2015) Nonstructural Steel Framing Members

ASTM C754 (2020) Standard Specification for Installation of Steel Framing Members to Receive Screw-Attached Gypsum Panel Products

ASTM C841 (2003; R 2013) Installation of Interior Lathing and Furring

ASTM C847 (2014a) Standard Specification for Metal Lath

NATIONAL ASSOCIATION OF ARCHITECTURAL METAL MANUFACTURERS (NAAMM)

NAAMM EMLA 920 (2009) Guide Specifications for Metal Lathing and Furring

UNDERWRITERS LABORATORIES (UL)

UL Fire Resistance (2014) Fire Resistance Directory

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 .00 06 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SECTION 09 22 00 Page 1 CUI 90% Final Revised

SD-02 Shop Drawings

Metal Support Systems

Submit for the erection of metal framing, furring, and ceiling suspension systems. Indicate materials, sizes, thicknesses, and fastenings.

SD-03 Product Data

Metal Support Systems

Recycled Content for Metal Support Systems ; S

1.3 DELIVERY, STORAGE, AND HANDLING

Deliver materials to the job site and store in ventilated dry locations permitting easy access for inspection and handling. If materials are stored outdoors, stack materials off the ground, supported on a level platform, and fully protected from the weather. Handle materials carefully to prevent damage. Remove damaged items and provide new items.

PART 2 PRODUCTS

2.1 MATERIALS

Provide steel materials for metal support systems with galvanized coating ASTM A653/A653M , G-60 ; aluminum coating ASTM A463/A463M , T1-25 ; or a 55-percent aluminum-zinc coating.

Provide metal support systems containing a minimum of 20 percent recycled content. Provide data identifying percentage of recycled content for metal support systems .

2.1.1 Materials for Attachment of Lath

2.1.1.1 Suspended and Furred Ceiling Systems and Wall Furring

ASTM C841, and ASTM C847.

2.1.1.2 Non-load Bearing Wall Framing

NAAMM EMLA 920.

2.1.2 Materials for Attachment of Gypsum Board

2.1.2.1 Suspended and Furred Ceiling Systems

ASTM C645.

2.1.2.2 Non-load Bearing Wall Framing and Furring

ASTM C645 and as indicated on Drawings , but not thinner than 0.0329 inch thickness regardless of the ASTM certified third party testing statement for equivalent thicknesses.

2.1.2.3 Furring Structural Steel Columns

ASTM C645 and as indicated on Drawings . Steel (furring) clips and support

SECTION 09 22 00 Page 2 angles listed in UL Fire Resistance may be provided in lieu of steel studs for erection of gypsum board around structural steel columns.

2.1.2.4 Z-Furring Channels with Wall Insulation

Not lighter than 26 gauge galvanized steel, Z-shaped, with 1-1/4 inch and 3/4 inch flanges and furring depth as required by the insulation thickness provided.

PART 3 EXECUTION

3.1 INSTALLATION

3.1.1 Systems for Attachment of Lath

3.1.1.1 Suspended and Furred Ceiling Systems and Wall Furring

ASTM C841, except as indicated otherwise.

3.1.1.2 Non-load Bearing Wall Framing

NAAMM EMLA 920, except provide framing members 16 inches o.c. unless indicated otherwise.

3.1.2 Systems for Attachment of Gypsum Board

3.1.2.1 Suspended and Furred Ceiling Systems

ASTM C754, except provide framing members 16 inches o.c. unless indicated otherwise.

3.1.2.2 Non-load Bearing Wall Framing and Furring

ASTM C754, except as indicated otherwise.

3.1.2.3 Furring Structural Steel Columns

Install studs or galvanized steel clips and support angles for erection of gypsum wallboard around structural steel columns in accordance with the UL Fire Resistance , design number(s) of the fire resistance rating indicated.

3.1.2.4 Z-Furring Channels with Wall Insulation

Install Z-furring channels vertically spaced not more than 24 inches o.c.

Locate Z-furring channels at interior and exterior corners in accordance with manufacturer's printed erection instructions. Fasten furring channels to masonry and concrete walls with powder-driven fasteners or hardened concrete steel nails through narrow flange of channel. Space fasteners not more than 24 inches o.c.

3.2 ERECTION TOLERANCES

Provide framing members which will be covered by finish materials such as wallboard, plaster, or ceramic tile set in a mortar setting bed, within the following limits:

a. Layout of walls and partitions: 1/4 inch from intended position;

SECTION 09 22 00 Page 3

b. Plates and runners: 1/4 inch in 8 feet from a straight line;

c. Studs: 1/4 inch in 8 feet out of plumb, not cumulative; and

d. Face of framing members: 1/4 inch in 8 feet from a true plane.

Provide framing members which will be covered by ceramic tile set in dry-set mortar, latex-portland cement mortar, or organic adhesive within the following limits:

a. Layout of walls and partitions: 1/4 inch from intended position;

b. Plates and runners: 1/8 inch in 8 feet from a straight line;

c. Studs: 1/8 inch in 8 feet out of plumb, not cumulative; and

d. Face of framing members: 1/8 inch in 8 feet from a true plane.

-- End of Section --

SECTION 09 22 00 Page 4

SECTION 09 22 16

EXTRUDED ALUMINUM PARTITION CLOSURE

01/21

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM B221 (2014) Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes

ASTM B221M (2013) Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes (Metric)

CALIFORNIA DEPARTMENT OF PUBLIC HEALTH (CDPH)

CDPH SECTION 01350 (2010; Version 1.1) Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources using Environmental Chambers

UNDERWRITERS LABORATORIES (UL)

UL 2818 (2013) GREENGUARD Certification Program For Chemical Emissions For Building Materials, Finishes And Furnishings

1.2 SUMMARY

This section includes gypsum board accessories or noise control components as shown on the architectural drawings.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 .00 06 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-02 Shop Drawings

Shop drawings

SD-03 Product Data

SECTION 09 22 16 Page 1 CUI Corrected Final

Manufacturer's Technical Data

SD-04 Samples

Samples

SD-07 Certificates

Certification from Manufacturer

Indoor Air Quality for Field-Applied Caulk ; S

1.4 SUBMITTAL INFORMATION

A. Manufacturer's Literature and Data:

1. Product Data: Submit manufacturer's technical data and brochures for each type of specified component required, including detail drawings, and installation instructions.

B. Shop Drawings:

1. Shop drawings must show dimensions, sizes, thickness, alloys, tempers, finishes, joining, attachments, and relationship of adjoining work.

C. Samples:

1. Samples must include three, 12-inch samples of each type of partition closure and finish as specified and accessories.

D. Certification:

1. Submit certification from manufacturer of accessory attesting that products comply with specified requirements including finish as specified.

E. Qualification Data:

1. Firms specified in "Quality Assurance" Article must demonstrate their capabilities and experience by including lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.

1.5 CERTIFICATIONS

Provide sealant/ caulk products certified to meet indoor air quality emissions requirements of CDPH SECTION 01350 . Give preference to certifications by UL 2818 (Greenguard) Gold, SCS Global Services Indoor Advantage Gold or provide certification or validation by other third-party program that products meet the requirements of this section. Provide current product certification documentation from certification body. When product does not have certification, provide validation that product meets the indoor air quality product requirements cited herein.

1.6 QUALITY ASSURANCE

Manufacturer: Firm with manufacturing and delivery capacity required for the project, shall have successfully completed at least ten projects within the past five years, utilizing systems, materials and techniques as

SECTION 09 22 16 Page 2 herein specified.

Fabricator must own and operate its own manufacturing facilities for all metal components. Systems consisting of components from a variety of manufacturers will not be considered or accepted.

1.7 DELIVERY, STORAGE, AND HANDLING

All materials shall be protected during fabrication, shipment, site storage and erection to prevent damage from other trades. Store accessories inside a well-ventilated area, away from uncured concrete and masonry, and protected from the weather, moisture, soiling, abrasion, extreme temperatures, and humidity.

PART 2 PRODUCTS

2.1 SYSTEM DESCRIPTION

Extruded aluminum partition closures must be pre-assembled and spring loaded to provide a tight fit for vertical junctures of partitions and window walls. Finish to match storefront mullions finish. Sound test to a composite STC of 37 with acoustical blankets for sound attenuation.

2.2 MATERIALS

Aluminum extrusions: 6063-T5 temper, tensile strength 31 KSI ( ASTM B221, ASTM B221M). Provide in widths to fit the partition type engaging a window. Install in lengths to fit installed vertical window openings

Acoustical blankets for sound attenuation. Factory-supplied caulk must be installed in the field for acoustical performance purposes.

Accessories:

1. Window Mate End Caps - Provide in widths to fit the partition type engaging a window. Install in lengths to fit installed vertical window openings.

General: Provide metals free from surface blemishes where exposed to view in finished unit. Surfaces that exhibit pitting, seam marks, roller marks, stains, and discolorations, or other imperfections on finished units are not acceptable. All metal must be of the highest-grade commercial type.

2.3 FABRICATION

Provide extruded aluminum in required lengths and size to fit specified openings.

2.4 FINISHES

All material must be factory finished to match storefront frames .

PART 3 EXECUTION

3.1 INSPECTION

Examination of Surfaces: Installer must examine conditions under which work is to be performed and must notify contractor and COR in writing of

SECTION 09 22 16 Page 3 unsatisfactory conditions.

Verify that field measurements and block-out dimensions are as shown on shop drawings.

3.2 CLEANING

Clean all surfaces following installation. If necessary use only a mild soap or detergent solution as recommended by the manufacturer.

3.3 PROTECTION

Procedures: Protect the finished work from damage during the remainder of the construction period.

Damage to finished work: Finished units must be without damage.

-- End of Section --

SECTION 09 22 16 Page 4

SECTION 09 23 00

GYPSUM PLASTERING

08/16

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C28/C28M (2010) Gypsum Plasters

ASTM C35 (2001; R 2014) Inorganic Aggregates for Use in Gypsum Plaster

ASTM C206 (2014) Standard Specification for Finishing Hydrated Lime

ASTM C472 (1999; R 2014) Physical Testing of Gypsum, Gypsum Plasters and Gypsum Concrete

ASTM C631 (2009; R 2014) Bonding Compounds for Interior Gypsum Plastering

ASTM C842 (2005; E 2010; R 2010) Application of Interior Gypsum Plaster

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 .00 06 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-03 Product Data

Gypsum Base Coat Plaster

Gypsum Finish Coat Plaster

SD-04 Samples

Sample Panel ; G

Submit four 36 inch square panels of varying texture for the Contracting Officer's approval.

Gypsum Plaster Full Size Sample

SECTION 09 23 00 Page 1

SD-08 Manufacturer's Instructions

Ready-Mix Gypsum Plaster

Submit manufacturer's printed mixing instructions for ready-mix plaster.

1.3 QUALITY ASSURANCE

1.3.1 Sample Panel s

Erect sample panel at the building site, or as otherwise directed.

Finished gypsum plaster work must match the approved sample panel.

1.4 DELIVERY, STORAGE, AND HANDLING

Deliver manufactured materials in the manufacturers' original unbroken packages or containers which are labeled plainly with the manufacturers' names and brands. Keep cementitious materials dry and stored off the ground, under cover, and away from sweating walls and other damp surfaces until ready for use. Keep materials wrapped and separate from off-gassing materials, such as paints and adhesives. Do not use materials that have visible moisture or biological growth.

1.5 GYPSUM PLASTER FULL SIZE SAMPLE

After selection of an acceptable texture to match existing, construct a sample wall at location in one of the existing stairwells as directed by the Contracting Officer minimum size of 4 feet in height, by 4 feet in length, using existing plaster surface sand gypsum plaster. Provide and protect the sample wall from damage during the length of the contract .

1.6 SCHEDULING AND ENVIRONMENTAL REQUIREMENTS

Commence application only after the area scheduled for gypsum plastering work is completely weathertight. The heating, ventilating, and air-conditioning systems must be complete and in operation prior to application of the plaster. If the mechanical system cannot be activated before veneer plastering is begun, the plastering may proceed in accordance with an approved plan to maintain the environmental requirements specified below. Apply plaster prior to the installation of finish flooring and acoustic ceiling.

PART 2 PRODUCTS

2.1 MATERIALS

Conform to the specifications, standards, and requirements specified herein. Provide asbestos-free materials.

2.2 GYPSUM BASE COAT PLASTER

Gypsum Ready-Mixed Plaster Base Coat.

2.3 GYPSUM FINISH COAT PLASTER

ASTM C28/C28M.

SECTION 09 23 00 Page 2

2.3.1 High Strength Gypsum Gauging Plaster Finish Coat

ASTM C28/C28M, gypsum gauging plaster, except plaster must have a compressive strength of not less than 4,500 psi when tested dry in accordance with ASTM C472.

2.4 HYDRATED LIME

ASTM C206, Type S.

2.5 AGGREGATES

2.5.1 Sand for Gypsum Base Coats

ASTM C35.

Sand Gradation: Percentage retained by weight (plus or minus 2 percent) on each sieve.

Sieve Size Maximum Minimum

No. 4 4760 microns 0 0

No. 8 2380 microns 5 0

No. 16 1190 microns 30 5

No. 30 590 microns 65 30

No. 50 300 microns 95 65

No. 100 150 microns 100 90

2.6 WATER

Use only potable water, free of mineral and organic substances that affect the hardening and durability of the plaster or stucco.

2.7 PROPORTIONING

Unless specified otherwise, materials are specified on a volume basis and must be measured in approved containers, to ensure that the specified proportions will be controlled and accurately maintained during the progress of the work. Measuring materials with shovels (shovel count) is not be permitted. Prepare ready-mix gypsum plaster for use by the addition of water only.

2.7.1 Gypsum Base Coat Plaster

Use of sand or lightweight aggregate is optional in gypsum plaster basecoats, except provide (1) sand for Keene's cement and high strength gypsum-gauged finish coats and (2) lightweight aggregate when necessary for a required fire resistance rating.

SECTION 09 23 00 Page 3

2.7.2 Gypsum Plaster Finish Coat

2.7.2.1 Lime-Putty Gypsum-Gauged (White Coat)

Use over sand and gypsum plaster. Mix finish coat in the proportions of one part of gypsum gauging plaster to a volume of hydrated lime or lime putty.

This mix is approximately equivalent to one 100 lb . bag of gypsum gauging plaster to:

a. Not more than four 50 lb . bags of hydrated lime, or

b. Not more than 4-1/2 cu ft of lime putty, or

c. Not more than 35 gal lons of lime putty.

Mix finish in accordance with manufacturer's printed instructions.

2.8 MIXING

2.8.1 Job-Mixed Materials

Mix materials in mechanical mixers except finish coats containing lime may be hand mixed. Mechanical mixers must be an approved type that accurately and uniformly controls the quantity of water. When mixing by hand, mix dry plaster aggregate to a uniform color in the mixing box, add water, and hoe the plaster immediately into the water and mix thoroughly to a proper consistency.

2.8.1.1 Water

Water used for rinsing and cleaning containers and tools must not be used in mixing the materials.

2.8.1.2 Sand

Sand proportions must be damp and in loose condition. A volume of damp loose sand must contain a minimum of 80 lb . of dry sand in one cu ft .

2.8.1.3 Mixing (Do's)

Mix the material while the mixer is in continuous operation in the following sequence:

a. Add maximum close to 90 percent of estimated quantity of water.

b. Add cement and approved admixtures. Add lime prior to cement.

c. Add remainder of sand.

d. Mix with remainder of water as required. Mix until the mixture is uniform in color and consistency.

2.8.1.4 Mixing (Don'ts)

Avoid excessive mixing and agitation. Discard gypsum plaster which has begun to set before it is used; do not permit retempering. Do not use frozen, caked, or lumped materials. Empty mixers and mixing boxes after

SECTION 09 23 00 Page 4 each batch is mixed, and keep free of old plaster.

2.8.2 Ready-Mixed Packaged Materials

Mix ready-mixed packaged gypsum plaster in accordance with manufacturer's printed instructions.

2.9 BONDING AGENT

ASTM C631, interior application.

PART 3 EXECUTION

3.1 SURFACE PREPARATION

A. Clean surfaces before application of gypsum plaster of projections, dust, loose particles, grease, bond breakers, and foreign matter. Do not apply plaster directly to surfaces (1) of masonry or concrete that have been coated with bituminous compound or other waterproofing agents, or (2) that have been painted or previously plastered. Before plaster work is started, wet masonry and concrete surfaces thoroughly with a fine fog spray of clean water to produce a uniformly moist condition. Check metal grounds, corner beads, screeds, and other accessories carefully for alignment before starting work. Do not apply gypsum plaster to surfaces containing frost.

B. Anticipate that both existing plaster and painted finishes contain asbestos containing materials and proceed accordingly.

C. For cracks, break away any loose pieces of plaster and lightly sand the surface with a medium-grit sandpaper. Wipe the area clean with a clean towel. Fill the crack with base plaster. If the crack is over 1/4 inch wide, place a piece of fiberglass tape over the crack and base plaster. Allow the base plaster to dry. Apply a second coat of finish plaster, feathering it out along the wall. Allow the finish plaster to dry. Sand the surface with a fine-grit sandpaper after the finish plaster has dried until surface matches existing adjacent.

D. For holes break away loose plaster and wipe the area lean with a towel. Fill the hole with a base coat of plaster using a medium-width trowel. Scrape the plaster compound so that it sits 1/4 inch below the finished surface of the plaster. Allow the plaster to set, but not dry. Apply a second coat of finish plaster using a trowel. If the hole is larger than 4 inches , scrape the plaster out until it is just below the existing surface of the wall. Otherwise, smooth the plaster using the straight end of the trowel until it is flush with the rest of the wall and smooth in appearance. Apply a third coat of finish plaster, if necessary, once the previous coat has set but not dried.

Smooth the plaster until it is seamless against the rest of the wall using a trowel. Once the plaster has dried completely, lightly sand with fine-grit sandpaper if he plaster did not dry completely smooth.

3.2 WORKMANSHIP

3.2.1 Slump Tests

Apply Plaster by hand. Subsequent to determining water content to meet the specified slump, do not add additional water to the mix. Conduct the slump test according to the following procedure:

SECTION 09 23 00 Page 5

3.2.2 Application

Apply gypsum plaster in three coats, except as follows:

Gypsum plaster applied to masonry using the two-coat double-up method.

Apply base coats with sufficient pressure and ensure plaster is sufficiently plastic to provide a strong bond to bases. Work base coats into screeds at intervals from 5 to 8 f eet . Plaster must not be continuous across expansion and control joints occurring in walls, partitions, and ceilings. Finish work level, plumb, square, and true, within a tolerance of 1/8 inch in 8 f eet , without waves, cracks, blisters, pits, crazing, discoloration, projections, or other imperfections. Form plaster work carefully around angles and contours, and well-up to screeds. Take special care to prevent sagging and consequent dropping of applications. There must be no visible junction marks in finish coat where one day's work adjoins another.

3.2.3 Curing

3.2.3.1 Gypsum Plaster

Before the plaster has set, provide environmental controls to prevent the plaster from drying too fast. After the plaster has set, provide for rapid drying to develop high strength.

3.3 GYPSUM PLASTER WORK

ASTM C842.

3.3.1 Gypsum Plaster Thickness Requirements

Match original thickness .

3.3.2 Gypsum Plaster Basecoat Work

3.3.2.1 Gypsum Two-Coat System

Apply the first coat to cover the base with sufficient material and pressure to form a good bond on the wall or ceiling base. Before the first coat has set and without scratching or cracking the surface, apply a second coat (double back) of the same material proportion as the base coat to the screeds. Straighten to a true surface without application of water, and cross rake or scratch to receive the finish coat.

3.3.3 Gypsum Plaster Finish Coats

Moderately moisten or fog spray base coat of plaster that has become dry before finish coat is applied. Accelerate plaster, if necessary, to provide a setting time of not more than 4 hours from the time the plaster is mixed.

3.3.3.1 Lime-Putty and Gypsum-Gauged Finish Coats

Apply lime-putty gypsum-gauged finish white coat or aggregated white coat and high strength gypsum gauged finish over the base coat, scratch in thoroughly, lay on well, double back, and fill out to a true, even surface. Allow the finish to dry a few minutes, then trowel well with

SECTION 09 23 00 Page 6 water. Apply maximum pressure in order to compact the finish coat and provide a smooth finish free from blemishes and irregularities. Apply trowel finish coats of gypsum-gauged lime-putty over properly prepared base coats as thin as possible and 1/16 to 1/8 inch thick for conventional plaster system, except as necessary in spots to level out hollows in base coat.

3.4 PATCHING AND POINTING

Cut out and patch loose, cracked, damaged, or defective gypsum plaster.

Patch must match existing work in texture, color and finish flush with previously applied gypsum plaster surfaces. Point work abutting or adjoining finish work in a neat manner. Remove droppings or spatterings from surfaces. Leave clean and in a condition to receive paint or other finish. Remove protective covering from floors and other surfaces, and rubbish and debris from the interior and exterior of the building.

-- End of Section --

SECTION 09 23 00 Page 7

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 09 23 00 Page 8

SECTION 09 24 23

CEMENT STUCCO

08/17

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C150/C150M (2021) Standard Specification for Portland Cement

ASTM C206 (2014) Standard Specification for Finishing Hydrated Lime

ASTM C897 (2015) Aggregate for Job-Mixed Portland Cement-Based Plasters

ASTM C926 (2018b) Standard Specification for Application of Portland Cement-Based Plaster

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 .00 06 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Proportions and Mixing

SD-04 Samples

Sample Panel ; G

1.3 QUALITY ASSURANCE

Submit a SAMPLE PANEL as follows: One 12 inch square stucco panel showing finish texture and color and exposed reinforcement at the edges, one 12 inch square of reinforcement, and a 12 inch length of each accessory proposed, prior to proceeding with stucco work. Following acceptance by the Contracting Officer, a sample panel of stucco, constructed at the jobsite, and located as directed, to demonstrate installation procedures, texture and color, prior to proceeding with any stucco work will be required. P anel size must be a minimum of 4 feet wide by 4 feet high;

containing each type accessory proposed for use and constructed in the

SECTION 09 24 23 Page 1 vertical position. Each phase of installation such as removal of existing loose stucco, preparation of the base concrete wall, scratch coat, brown coat, finish coat and curing procedures must be demonstrated in the construction of the panel. Submit one 12 inch length of each accessory proposed for use, prior to constructing the sample panel.

1.4 DELIVERY, STORAGE, AND HANDLING

Deliver packaged materials to the site in the original packages and containers with labels intact and seals unbroken. Keep cementitious materials dry and stored off the ground, under cover and away from damp surfaces until ready to be used. Aggregate must be covered to prevent the absorption or loss of moisture.

1.5 ENVIRONMENTAL REQUIREMENTS

Do not apply stucco when the ambient temperature is 40 degrees F or lower, or when a drop in temperature below 40 degrees F is expected within 48 hours after application.

PART 2 PRODUCTS

2.1 PORTLAND CEMENT

Portland cement must conform to ASTM C150/C150M, gray Portland cement Type I.

2.2 LIME

Lime must conform to ASTM C206, Type S.

2.3 SAND

Sand aggregate for job-mixed base coat and job-mixed finish coat stucco must conform to ASTM C897.

2.4 WATER

Provide clean, fresh, potable water, free from amounts of oils, acids, alkalis and organic matter that would be injurious to the stucco.

PART 3 EXECUTION

3.1 INSTALLATION

Do not install building construction materials that show visual evidence of biological growth.

Within boundaries of the Phase of the project under reconstruction, sound all existing stucco coatings over the original board-formed cast-in-place concrete walls to identify areas that are not sound and are delaminating from the concrete substrate.

Remove loose stucco by hand using a trowel or scraping tool. Remove only as much as is required to leave soundly bound stucco in place.

Brush all loose materials off remaining wall.

SECTION 09 24 23 Page 2

3.2 PREPARATION OF SURFACES

Preparation of surfaces for application of stucco to solid bases such as stone, masonry or concrete must conform to the applicable requirements of

ASTM C926.

3.3 PROPORTIONS AND MIXING

Proportions and mixing for job-mixed base coat and finish coat must conform to the applicable requirements of ASTM C926. Mixing of mill-mixed finish coat must be in accordance with the manufacturer's directions.

Submit detailed description of the proposed job-mix proportions for base and finish coats; including identification of thickness of coats.

3.4 STUCCO APPLICATION

Stucco must be applied in three coats to a thickness to match the existing application, to the finished stucco surface of the existing , to the finished stucco surface of the existing , including moderate texture match existing variations. Stucco application must conform to the applicable requirements of ASTM C926 and the following:

3.4.1 Workmanship

Items or features of the work in connection with or adjoining the stucco must be in place, plumb, straight, and true prior to beginning the stucco work. Concrete and m asonry surfaces to receive stucco must be evenly dampened immediately prior to application of stucco. Each stucco coat must be applied continuously in one general direction, without allowing mortar to dry at edges. Where it is impossible to work the full dimension of a wall surface in a continuous operation, jointing must be made at a break, opening, or other natural division of the surface. Edges to be joined must be dampened slightly to produce a smooth confluence. Exterior corners of stucco must be slightly rounded. Stucco on soffit surfaces must be pitched forward to form a drip.

3.4.2 Scratch Coat

Apply scratch coat under sufficient pressure to form good keys. Before the scratch coat has set, it must be lightly scratched in one direction and vertical surfaces must be scratched in the horizontal direction only.

The scratch coat must be fog cured for a minimum of 72 hours.

3.4.3 Brown Coat

Evenly dampen the scratch coat to obtain uniform suction before the brown coat is applied. There must be no visible water on the surface when the brown coat is applied. The brown coat must be applied to the scratch coat with sufficient pressure to force the stucco into the scratches and must be brought to a plumb, true, even plane with rod or straightedge. When set sufficiently, the brown coat must be uniformly floated with a dry float to promote densification of the coat and to provide a surface receptive to bonding of the finish coat. Brown coat must be fog cured for a minimum of 72 hours.

3.4.4 Finish Coat

Dampen surfaces of the brown coat not more than 1 hour before the finish coat is to be applied to a uniform wetness with no free-standing water on

SECTION 09 24 23 Page 3 the surface. The finish coat must have a rough-textured finish to match existing adjacent and must conform to the approved sample. Fog cure the finish coat for a minimum of 48 hours. Take care to prevent staining.

3.4.5 Surface Tolerance

When a 10 foot straightedge is placed at any location on the finished surface of the stucco, excluding rough-textured finish, the surface must not vary more than 1/8 inch from the straightedge.

3.5 CURING AND PROTECTION

Perform fog curing by applying a fine mist of water to the stucco.

Exercise care during fog curing to avoid erosion damage of the stucco surfaces. Do not use a solid stream of water. Fog not less than three times daily. Protect the stucco from the direct rays of the sun during severe drying conditions using canvas, cloth or other approved sheet material.

3.6 PATCHING AND POINTING

Replace or patch loose, cracked, damaged or defective work as directed.

Patching must match existing work in texture and color and must be finished flush.

-- End of Section --

SECTION 09 24 23 Page 4

SECTION 09 29 00

GYPSUM BOARD

08/16

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI A108.11 (1992; Reaffirmed 2005) Specifications for Interior Installation of Cementitious Backer Units

ASTM INTERNATIONAL (ASTM)

ASTM C475/C475M (2017) Standard Specification for Joint Compound and Joint Tape for Finishing Gypsum Board

ASTM C840 (2018b) Standard Specification for Application and Finishing of Gypsum Board

ASTM C919 (2012; R 2017) Standard Practice for Use of Sealants in Acoustical Applications

ASTM C954 (2018) Standard Specification for Steel Drill Screws for the Application of Gypsum Panel Products or Metal Plaster Bases to Steel Studs from 0.033 in. (0.84 mm) to

0.112 in. (2.84 mm) in Thickness

ASTM C1002 (2018) Standard Specification for Steel Self-Piercing Tapping Screws for the Application of Gypsum Panel Products or Metal Plaster Bases to Wood Studs or Steel Studs

ASTM C1047 (2014a) Standard Specification for Accessories for Gypsum Wallboard and Gypsum Veneer Base

ASTM C1177/C1177M (2017) Standard Specification for Glass Mat Gypsum Substrate for Use as Sheathing

ASTM C1178/C1178M (2013) Standard Specification for Glass Mat Water-Resistant Gypsum Backing Panel

ASTM C1396/C1396M (2017) Standard Specification for Gypsum Board

ASTM C1629/C1629M (2018a) Standard Classification for Abuse-Resistant Nondecorated Interior

SECTION 09 29 00 Page 1

Gypsum Panel Products and Fiber-Reinforced Cement Panels

ASTM C1766 (2015; R2019) Standard Specification for Factory-Laminated Gypsum Panel Products

ASTM D226/D226M (2017) Standard Specification for Asphalt-Saturated Organic Felt Used in Roofing and Waterproofing

ASTM D412 (2016) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension

ASTM D624 (2000; R 2012) Standard Test Method for Tear Strength of Conventional Vulcanized Rubber and Thermoplastic Elastomers

ASTM D1037 (2012) Evaluating Properties of Wood-Base Fiber and Particle Panel Materials

ASTM D1149 (2007; R 2012) Standard Test Method for Rubber Deterioration - Surface Ozone Cracking in a Chamber

ASTM D2394 (2017) Standard Test Methods for Simulated Service Testing of Wood and Wood-Base Finish Flooring

ASTM D3273 (2016) Standard Test Method for Resistance to Growth of Mold on the Surface of Interior Coatings in an Environmental Chamber

ASTM D5420 (2016) Standard Test Method for Impact Resistance of Flat, Rigid Plastic Specimen by Means of a Strike Impacted by a Falling Weight (Gardner Impact)

ASTM E84 (2020) Standard Test Method for Surface Burning Characteristics of Building Materials

ASTM E695 (2003; R 2015; E 2015) Measuring Relative Resistance of Wall, Floor, and Roof Construction to Impact Loading

CALIFORNIA DEPARTMENT OF PUBLIC HEALTH (CDPH)

CDPH SECTION 01350 (2010; Version 1.1) Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources using Environmental Chambers

FM GLOBAL (FM)

FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/

SECTION 09 29 00 Page 2

GREEN SEAL (GS)

GS-36 (2013) Adhesives for Commercial Use

GYPSUM ASSOCIATION (GA)

GA 214 (2010) Recommended Levels of Gypsum Board Finish

GA 216 (2010) Application and Finishing of Gypsum Panel Products

GA 600 (2009) Fire Resistance Design Manual

SCIENTIFIC CERTIFICATION SYSTEMS (SCS)

SCS SCS Global Services (SCS) Indoor Advantage

SOUTH COAST AIR QUALITY MANAGEMENT DISTRICT (SCAQMD)

SCAQMD Rule 1168 (2017) Adhesive and Sealant Applications

UNDERWRITERS LABORATORIES (UL)

UL 2818 (2013) GREENGUARD Certification Program For Chemical Emissions For Building Materials, Finishes And Furnishings

UL Fire Resistance (2014) Fire Resistance Directory

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 .00 06 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-03 Product Data

Cementitious Backer Units

Glass Mat Water-Resistant Gypsum Tile Backing Board

Abuse Resistant Gypsum Board

Acoustically enhanced gypsum board

Accessories

Submit for each type of gypsum board and for cementitious backer units.

Gypsum Board

Recycled Content for Gypsum Board ; S

SECTION 09 29 00 Page 3

Recycled Content for Paper Facing and Gypsum Cores ; S

VOC Content of Joint Compound ; S

SD-07 Certificates

Asbestos Free Materials

Certify that gypsum board types, gypsum backing board types, cementitious backer units, and joint treating materials do not contain asbestos.

Indoor Air Quality for Gypsum Board ; S

Indoor Air Quality for Non-aerosol Adhesives ; S

Indoor Air Quality for Aerosol Adhesives ; S

1.3 CERTIFICATIONS

1.3.1 Indoor Air Quality Certifications

Submit required indoor air quality certifications in one submittal package.

Provide current certification from certification body.

1.3.1.1 Ceiling and Wall Systems

Provide products certified to meet indoor air quality emissions requirements of CDPH Section 01350. Give preference to certification by UL 2818 (Greenguard) Gold, SCS Global Services Indoor Advantage Gold or provide certification or validation by other third-party program that products meet the requirements of…

This is the start of the file's text. The full file is on GovTribe.