Attachment 1 - SOW Containment SCBA Fill Station.pdf

PDF 374 KB Posted

Attached to
Humanitarian Assistance Program (HAP) Federal contract opportunity
Solicitation number
W912CL-23-R-0450
Issued by
Department of the Army Materiel Command Army Contracting Command

View the file

Other files for this federal contract opportunity

Other files attached to Humanitarian Assistance Program (HAP), newest first.
File Type Posted
conform copy_solicitation_W912CL23R0450_HAP_06 Jul 2023.pdf PDF
HAP TORFP Containment SCBA Fill StationJun23_rev3.pdf PDF
HAP TORFP Containment SCBA Fill StationJun23_rev2.pdf PDF
Attachment 2 - Volume 4.xlsx XLSX spreadsheet
Amendment 3_HAP FY23 Solicitation_23 Jun 2023.pdf PDF
QA for Solicitation HAP FY23_22 June 2023_rev1.pdf PDF
QA for Solicitation HAP FY23_22 June 2023.pdf PDF
QA for Solicitation HAP FY23_21 June 2023.pdf PDF
Attachment 1 - SOW Containment SCBA Fill Station_rev1.pdf PDF
conform copy_solicitation_W912CL23R0450_HAP_20 Jun 2023.pdf PDF
HAP TORFP Containment SCBA Fill StationJun23_rev1.pdf PDF
Amendment 2_HAP FY23 Solicitation_16 Jun2023.pdf PDF
HAP TORFP Containment SCBA Fill StationJun23.pdf PDF
Attachment 2 -HAP IDIQ- Pricing Model.xlsx XLSX spreadsheet
QA for Solicitation HAP FY23_19 April 2023_rev1.pdf PDF
QA for Solicitation HAP FY23_26 May 2023.pdf PDF
QA for Solicitation HAP FY23_31 May 2023.pdf PDF
QA for Solicitation HAP FY23_17 May 2023.pdf PDF
QA for Solicitation HAP FY23_09 May 2023.pdf PDF
QA for Solicitation HAP FY23_02 May 2023.pdf PDF
QA for Solicitation HAP FY23_03 May 2023.pdf PDF
QA for Solicitation HAP FY23_28 April 2023.pdf PDF
QA for Solicitation HAP FY23_19 April 2023_Part 2.pdf PDF
Copy of QA for Solicitation HAP FY23_20 April 2023_Part 3.xlsx XLSX spreadsheet
QA for Solicitation HAP FY23_19 April 2023_Part 1.pdf PDF
Copy of QA for Solicitation HAP FY23_20 April 2023_Part 2.xlsx XLSX spreadsheet
QA for Solicitation HAP FY23_21 April 2023_Part 2.pdf PDF
QA for Solicitation HAP FY23_26 April 2023.pdf PDF
QA for Solicitation HAP FY23_21 April 2023_Part 1.pdf PDF
Copy of QA for Solicitation HAP FY23_20 April 2023_Part 1.xlsx XLSX spreadsheet
QA for Solicitation HAP FY23_14 April 2023 (2).pdf PDF
QA for Solicitation HAP FY23_18 April 2023 (2).pdf PDF
Amendment_HAP FY23 Solicitation_12 Apr 2023.pdf PDF
Attachment 1 -SOW Containment SCBA Fill Station.pdf PDF
HAP TORFP Containment SCBA Fill StationApr23.pdf PDF
Copy of Attachment 2 -HAP IDIQ- Pricing Model.xlsx XLSX spreadsheet
Amendment_HAP FY23 Solicitation_11 Apr 2023_rev1.pdf PDF
QA for Solicitation HAP FY23_10 April 2023.pdf PDF
FinalRFP_W912CL23R0450_HAP_17Mar2023.pdf PDF
Show all 39

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Containment SCBA Fill Station

U.S. Southern Command 31 May 2023

PART 1

General Information

1. GENERAL: This is a non-personal services contract under which the personnel rendering the services are not subject, either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees. The United States (U.S.) Government shall not exercise any supervision or control over the Contractor’s employees performing the tasks herein. Such contract employees shall be accountable solely to the Contractor who, in turn shall be responsible to the U.S. Government.

1.1 SCOPE OF WORK: Under this contract, the Contractor shall furnish all labor, transportation, equipment, materials, and any other items and services necessary to provide four (4) SCBA FILLING SYSTEMS as defined in this SOW except for those items specified as government furnished property (GFP) and government furnished services (GFS). The contractor shall perform to the standards in this contract. This Statement of Work (SOW) sets forth the minimum requirements for procuring four Self Contained Breathing Apparatus (SCBA) Filling Stations that will be distributed throughout different Firefighting Stations in the country and will serve to recharge the oxygen tanks that the firefighters use in the process of completing their mission.

1.2 Background: The United States Southern Command (SOUTHCOM) conducts Humanitarian Assistance activities to directly relieve or reduce human suffering, disease, hunger or privation or to increase PN capacity to provide essential human services to vulnerable populations in partner nations in the Caribbean, Central and South America.

These SCBA filling stations are vital to the firefighters. Currently there are no firefighter owned recharge stations in country that can support their mission. This donation will greatly enhance their survivability and capabilities. El Salvador is prone to many natural disasters, earthquakes being one of them; in the event of an earthquake, the secondary means of destruction is always fires, this project will contribute to enhance and better prepare the firefighters for any disaster that may arise, especially from the threat of earthquakes.

1.3 Objectives: This donation will help the govenrment of El Salvador provide essential humanitarian services, including the ability to prepare for, reduce the risk of, mitigate the effects of, and respond to disasters.

1.4 Required Delivery: Contractor shall provide non-personal services and provide four (4) SCBA FILLING SYSTEMS that each Include:5500 psi compressor, 6000psi cascade storage system and anti-explosion filling station. Each unit must be able to fil 2 SCBA cylinders simultaneously with “breathing air”. Product requested must be equal or similar to Bauer CFS 5.5-2-S. Voltage for El Salvador is 120V/60Hz.

1.5 Period of Performance: The work shall begin after the Contractor receives the award, and the project shall be completed in 90 calendar days after the Notice to Proceed or less from receipt of contract award.

1.6 General Information:

1.6.1 Quality Control (QC) N/A.

1.6.1.1 N/A.

1.6.1.3 Inspection System: N/A.

1.6.1.4 Deficiency Prevention: N/A.

Ham, Christopher A CIV USARMY ACC (USA) Make sure to change the date March has come and gone….

Fernandez, Hector CIV SOUTHCOM SCJ7/9 (USA) Changed to today's date.

U.S. Southern Command

1.6.1.5 Inspection Files: N/A.

1.6.1.6 Complaints: N/A.

1.6.1.7 Operations Security (OPSEC) SOP/Plan Requirements: N/A.

1.6.2 Quality Assurance (QA): The government shall evaluate the contractor’s performance under this contract in accordance with (IAW) the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed IAW the performance standards and contract quality requirements are met. Contract quality requirements” means the technical requirements in the contract relating to the quality of the product or service and those contract clauses prescribing inspection, and other quality controls incumbent on the contractor, to ensure the product or service conforms to the contractual requirements. It defines how the performance standards will be applied, the frequency of surveillance, the performance threshold, and deductions, if applicable.

1.6.3 Recognized Holidays:

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day

1.6.3.1 El Salvador Recognized Holidays: The Contractor shall follow the same holiday schedule as the US Embassy, San Salvador. The contractor shall perform services on holidays as required.

U.S. Southern Command

1.6.4 Hours of Operation: The contractor is responsible for conducting business between the hours of 8:00 AM to 5:00 PM Monday through Friday, except Federal holidays or when the facility is closed due to local or national emergencies, administrative closings, or similar government directed facility closings.

1.6.5 Place of Performance: The work to be performed under this contract will be performed at:

1- (HQ) Estación Central: Pasaje Galan N° 552 CALLE FRANCISCO MENENDEZ, BARRIO SANTA

ANITA, SAN SALVADOR;

2- Estación San Vicente: FINAL 15 AVENIDA SUR, BARRIO CONCEPCIÓN, PLANTEL DEL MOP

3- Estación San Miguel: KM. 136 CARRETERA PANAMERICANA AL NORTE HOSPITAL MILITAR

4- Estación Santa Ana: 13 CALLE ORIENTE Y 3RA. AVENIDA SUR, FRENTE A LA SEGUNDA

BRIGADA DE INFANTERIA

1.6.6 Type of Contract:

1.6.7 Access and General Protection Policy and Procedures:

1.6.7.1 FPCON: N/A.

1.6.7.2 Physical Security: The contractor shall be responsible for safeguarding all equipment, information, and property provided for contractor use.

1.6.7.3 Escorts: N/A

1.6.7.4 Personnel Security Clearance Requirements: N/A.

1.6.7.5 Background Checks: N/A.

1.6.7.5.1 Background Check Notification Requirements: N/A.

1.6.7.6.1 Contractor Common Access Card (CAC) Eligible Requirements: N/A.

1.6.7.6.1.1 Federal Installation/Facility Access: N/A.

1.6.7.6.2. Contractor Non CAC Eligible Requirements for DOD Facility and Installation Access: N/A.

1.6.7.7 Employment Eligibility: The Contractor shall ensure that all Contractor employees and sub-contractor employees performing services under this contract in the U.S. or its territories have been pre-screened for employment eligibility using the E-verify Program on the Department of Homeland Security website http://www.uscis.gov/e-verify. Personnel that have not met the employment eligibility requirement on this website are not authorized to perform services under this contract. Verification of the eligibility check will be made available to the KO or COR upon request. This requirement is not in lieu of and does not relieve the Contractor from the I-9 Employment Eligibility Verification Forms for employment of personnel.

1.6.7.8 Access to Government Information Systems: N/A.

1.6.7.9 Key Control: N/A.

1.6.7.10 Lock Combinations: N/A.

http://www.uscis.gov/e-verify

U.S. Southern Command

1.6.8 Post Award Conference/Contract Periodic Progress Meetings: N/A.

1.6.9 Contracting Officer Representative (COR): The (COR) will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: ensure the Contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, specifications; monitor Contractor's performance and notifies both the KO and Contractor of any deficiencies; coordinate availability of government furnished property; and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

1.6.10 Key Personnel: The following personnel are considered key personnel by the government:

Contracting Officer, Contract Specialist, COR, Contractor.

1.6.10.1 The Contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate, who shall act for the Contractor when the manager is absent, shall be designated in writing to the Contracting Officer. The Contract Manager and alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The Contract Manager or alternate shall be available between the hours of operation in section

1.6.4 of this document.

1.6.10.2 Qualifications for all Key Personnel: Certified in the installation and trining of requested equipment.

1.6.11 Special Qualifications or Certifications: N/A

1.6.11 Special Qualifications: N/A

1.6.11.1 IA/IT Training Certification: N/A

1.6.12 Identification of Contractor Employees: N/A

1.6.12.1 Badging of Contractor Employees: N/A

1.6.12.2 Uniform: N/A

1.6.13 Contractor Travel: Contractor shall be required to travel to El Salvador during the performance of this contract to attend installation, and training. Contractor may be required to travel to off-site training locations and to ship training aids to these locations in support of this SOW. Contractor will be authorized travel expenses consistent with the substantive provisions of the Joint Travel Regulation (JTR) and the limitation of funds specified in this contract. All travel requires Government approval/authorization and notification to the COR 14 days prior to travel. The Government anticipates 1 trip will be required to support this contract.

1.6.13.1 N/A

1.6.14 Other Direct Costs (ODC): N/A

U.S. Southern Command

1.6.15 Data Rights N/A

1.6.16. Non-Disclosure Requirements: N/A

1.6.16.1 Non-Disclosure Statements: N/A

1.6.16.2 Advertisement and Social Media: The Contractor shall NOT post information to public website or social media locations, personal or professional, that in any way disclose names, locations, hotel data, participants, discussions, pictures, etc. before, during or after the contract period of performance without the express consent of the Government. The use of propaganda violates DOD Commercial Use of Imagery Guidelines stated at (http://www.defenseimagery.mil/products/DODimagery/commercialuse.html). The Contractor shall not cite any information (e.g., contract information, pictures, locations, etc.) obtained through this contract on any marketing tools to include its company website.

1.6.16.3 INFORMATION ASSURANCE: At no time will the Contractor or associated sub-contractor employees transmit government documents or information over using methods that do not meet the security requirements specified in the National Institute of Standards and Technology (NIST) Special Publication (SP) 800-171, "Protecting Controlled Unclassified Information in Nonfederal Information Systems and Organizations" such as personal electronic mail accounts, public digital data storage sites (cloud storage), social media platforms or instant messaging. Approved government sites such as U.S. Army Aviation and Missile Research Development and Engineering Center (ARMDEC) Safe Exchange at https://safe.amrdec.army.mil/SAFE/About.aspx, or All Partners Access Network (APAN) at https://community.apan.org/, or other transmission means determined by the government must be used

1.6.17 Organizational Conflict of Interest (OCI) Contractor and subcontractor personnel performing work under this contract may receive, have access to, or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO and in the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.

(b) Mitigation plans. The Contractor shall review its OCI mitigation procedures to avoid any potential OCI created by performance under this contract. The Contractor shall submit the reviewed OCI mitigation plan to the Contracting Officer no later than thirty (30) days after award. The [insert RCO/location here] reserves the right to reject a mitigation plan, if in the opinion of the Contracting Officer, such a plan is not in the best interests of the [insert RCO/location here]or the Army. Additionally, after award, the [insert RCO/location here] will review OCI mitigation plans, as needed, in the event of changes in the vendor community due to mergers, consolidations, or any unanticipated circumstances that may create an unacceptable organizational conflict of interest.

(c) Potential Organizational Conflict of Interest. The following provides examples of situations where mitigation plans may or may not be required. These examples are not intended to be all inclusive.

(1) Unequal access to information. Access to "nonpublic information" as part of the performance of an Army contract could provide the Contractor a competitive advantage in a later competition for another Army contract. Such an advantage could easily be perceived as unfair by a competing vendor who is not http://www.defenseimagery.mil/products/dodimagery/commercialuse.html

U.S. Southern Command given similar access to the relevant information. If the requirements of the Army procurement anticipate the successful vendor may have access to nonpublic information, the successful vendor should be required to submit and negotiate an acceptable mitigation plan. Alternatively, the "nonpublic information" may be provided to all vendors.

(2) Biased ground rules. A Contractor in the course of performance of an Army contract has in some fashion established important "ground rules" for another Army contract, where the same Contractor may be a competitor. For example, a Contractor may have drafted the statement of work, specifications, or evaluation criteria of a future Army procurement. The primary concern of the Army in this case is that a Contractor so situated could slant key aspects of procurement in its own favor, to the unfair disadvantage of competing vendors. If the requirements of the Army procurement anticipate the Contractor may have been in a position to establish important ground rules, including but not limited to those described herein, the Contractor should be required to submit and negotiate an acceptable mitigation plan.

(3) Impaired objectivity. A Contractor in the course of performance of an Army contract is placed in a situation of providing assessment and evaluation findings over itself, or another business division, or subsidiary of the same corporation, or other entity with which it has a significant financial relationship.

The concern in this case is that the Contractor's ability to render impartial advice to the Army could appear to be undermined by the Contractor's financial or other business relationship to the entity whose work product is being assessed or evaluated. In these situations, a "walling off" of lines of communication may well be insufficient to remove the perception that the objectivity of the Contractor has been tainted. If the requirements of the Army procurement indicate that the Contractor may be in a position to provide evaluations and assessments of itself or corporate siblings, or other entity with which it has a significant financial relationship, the affected Contractor should provide a mitigation plan that includes recusal by the vendor from the affected contract work. Such recusal might include divestiture of the work to a third party vendor.

(d) The Contractor shall provide information which concisely describes all relevant facts concerning any past, present, or currently planned interest (financial, contractual, organizational, or otherwise), relating to the work to be performed and bearing on whether the offeror or Contractor has a possible OCI.

(e) If the Contractor does not disclose any relevant facts concerning an OCI, the Contractor, by signing the contract, warrants that to its best knowledge and belief no such facts exist relevant to possible OCI.

(f) Remedies for nondisclosure. The following are possible remedies should a Contractor refuse to disclose, or misrepresent, any information regarding a potential OCI:

(1) Refusal to provide adequate information may result in disqualification for award.

(2) Termination of the contract, if the nondisclosure or misrepresentation is discovered after award.

(3) Disqualification from subsequent SOUTHCOM HAP contracts.

(4) Other remedial action as may be permitted or provided by law or in the resulting contract.

1.6.18 Phase-in/Phase-Out (PIPO) Period: N/A

1.6.19 General Training Requirements:

1.6.19.1 Anti-Terrorism (AT) Level I Training : N/A

1.6.19.2 OPSEC Awareness: N/A

1.6.19.3 Information Assurance (IA) Training: N/A

U.S. Southern Command

1.6.19.4 Information Assurance (IA)/Information Technology (IT) Training: N/A

1.6.19.5 Threat Awareness Reporting Program (TARP Training): N/A

1.6.19.6 iWATCH Training: N/A

1.6.19.7 OPSEC Training: N/A

1.6.20 Overseas Training Requirements:

1.6.20.1 Antiterrorism (AT) Awareness Training for Contractor Personnel Traveling: N/A

1.6.20.2 SERE Training: N/A

1.6.21 Foreign (OCONUS) Requirements: All U.S. citizen or resident, and TCN contractor personnel must comply with the training requirements listed in the Foreign Clearance Guide (FCG). Verification of the training shall be made available to the COR or KO upon request. Additionally, they must receive personal security training that includes at a minimum:

(a) Safety and security issues facing employees within the USSOUTHCOM AOR,

(b) Identifies safety and security contingency planning activities, and

(c) Identifies ways to utilize safety and security personnel and other resources appropriately.

1.6.21.1 Theater and Country Clearance Requirements: Contractor shall ensure all U.S. citizen or U.S.

resident Contractor employees and sub-contractor employees performing services under this who are traveling in the USSOUTHCOM AOR follow the requirements identified in the electronic Foreign Clearance Guide (FCG) at https://www.fcg.pentagon.mil/fcg.cfm and must have all necessary passports, visas, and other documents required to enter, exit, or work in the USSOUTHCOM AOR; must have the appropriate DOD identity credential(s); must have the appropriate special area, country, and theater clearance as required in DOD Directive 4500.54E. Contractor personnel shall return all U.S. Government issued identification, to include the Common Access Card, to appropriate U.S. Government authorities within 5 days of the end of their travel or contractual duties.

1.6.21.2 Vetting: The Contractor company and all associated sub-contractor companies, must have been vetted by the US Embassy in the country which the contract will be performed. For the purposes of this contract, the company is considered vetted if the company is located in the country which the contract will be performed unless the company has been previously barred from performing services for the Government. If during a previous vetting process the company was barred from performing service for the Government, then that is grounds for termination of the contract. If the company is located outside of the country which the contract will be performed, the company must be vetted by the US Embassy in the country of performance. Vetting will coordinated through the US Embassy's DOD Security Cooperation Office (SCO) in the country of performance. If during any previous vetting process in other countries, the company is found to be barred from performing services for the Government; this finding is grounds for termination of the contract.

1.6.21.3 Installation Access to DOD Facility or Host Nation Installation: N/A

1.6.21.4 Host Nation Installation Access with No DOD Facility: Contractor and all associated subcontractor employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures. The employee performing services under this contract shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services, Security Office or the host nation equivalent.

https://www.fcg.pentagon.mil/fcg.cfm

U.S. Southern Command

1.6.21.5 Deoxyribonucleic Acid (DNA) Samples N/A

1.6.21.6 Medical Travel Requirement: Contractor shall ensure that all Contractor employees and subcontractor employees are medically, dentally, and psychologically fit for performance of their duties.

All U.S. citizen and third country national (TCN) Contractor and subcontractor personnel must meet the medical screening requirements established by the USSOUTHCOM Commander in the Medical Suitability Screening Regulation (SC Reg 40-501), as well as the requirements identified in FORCE HEALTH PROTECTION (FHP) GUIDANCE FOR DEPLOYMENT in the USSOUTHCOM AOR or their successors and follow immunization and health protection guidelines outlined therein. All immunizations must be obtained prior to traveling to the USSOUTHCOM AOR. U.S. citizen and TCN Contractor and subcontractor personnel traveling from a country outside of the USSOUTHCOM AOR must travel into the USSOUTHCOM AOR with a current copy of the Public Health Service Form 791, “International Certificate of Vaccination”. In addition, U.S. citizen and TCN Contractor and subcontractor personnel traveling to the USSOUTHCOM AOR are required to be beneficiaries of a medical evacuation plan and service through an insurance plan provided by their employer or paid for individually.

1.6.22 Synchronized Pre-deployment and Operational Tracker (SPOT): Upon award of this contract, or employment of new personnel, the Contractor will enter Contractor employees and subcontractor employees performing services under this contract into the SPOT database who meet one of the following conditions:

(1) All U.S. citizen and resident, and third country national (TCN) personnel who travel into the USSOUTHCOM AOR for periods of performance anticipated to exceed 30 consecutive days.

(2) TCN, host nation (HN), or local national (LN) personnel who reside with or work in the immediate vicinity of U.S. Armed Forces and/or DOD Civilian personnel for periods of performance anticipated to exceed 30 consecutive days.

(3) Private security Contractors and contingency Contractor personnel authorized to carry weapons regardless of proximity to U.S. Armed Forces or DOD Civilian personnel and regardless of the length of the anticipated period of performance.

(4) Contractor and subcontractor personnel with a place of performance in the continental United States, including the USSOUTHCOM Headquarters and Joint Interagency Task Force-South (JIATF-S) Headquarters, that may, within the terms of the contract, deploy to the USSOUTHCOM AOR for periods anticipated to exceed 30 consecutive days.

1.6.22.1 The COR or KO will approve all employees in the SPOT database and a Letter of Authorization (LOA) is generated to the Contractor on each employee. The signed LOA is required prior to travel to, from, or within the USSOUTHCOM AOR. The LOA will identify any additional authorizations, privileges, or Government support to which Contractor personnel are entitled under this contract. The LOA will be regenerated by the Contractor upon expiration of the LOA. Changes to the status of individual personnel relating to their in-theater arrival date and their duty location, to include closing out the trip with their proper status (e.g., mission complete, wounded, ect.) shall be annotated within the SPOT database in accordance with the timeliness established in the SPOT business rules. Information and standards for the SPOT system is posted on the U.S. Government Foreign Clearance Guide website at https://www.fcg.pentagon.mil/fcg.cfm for the country of employment. Access to SPOT is https://spot.dmdc.mil.

1.6.23 Licenses and Permits:

1.6.23.1 Contractor Licenses and Permits. The Contractor shall, at no additional cost to the U.S.

Government, obtain all licenses and permits required for performance of work. Contractor shall comply with all applicable national, regional, and local Local laws, rules, and regulations. The Contractor shall submit proper documentation and evidence satisfactory to the KO or the COR demonstrating compliance with this requirement when directed by the KO or COR.

https://spot.dmdc.mil/

U.S. Southern Command

1.6.23.2 Sub-contractor Licenses and Permits. The Contractor shall inform the COR and KO in writing that all sub-contractors and others performing work. The Contractor shall submit a copy of the licenses and permits (if applies) to the KO and COR demonstrating compliance with this requirement when directed by the KO and/or COR.

1.6.24 Environmental Protection:

1.6.24.1 Pollution and Abatement Control. In order to present and provide for abatement and control of any environmental pollution arising from the activities in the performance of this contract, the Contractor shall comply with all applicable pollution control and abatement policies, and all applicable provisions of the Local codes, regulations, and laws.

1.6.24.2 Environmental Protection. Environmental protection action required by this section shall consist of furnishing all labor, materials, and equipment and performing all work required for the abatement and prevention of pollution during and as the result of construction operations under this contract. For the purpose of this specification, environmental pollution is defined as the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances; detrimentally impact on biological species and/or their habitat; or degrade the aesthetic and recreational value of the area.

1.6.24.3 Spills and Disposal. The Contractor shall not pollute storm or sewer lines; or swales with fuels, oils, bitumen, calcium chloride, acid, construction wastes, or other harmful materials. It is the responsibility of the Contractor to investigate and comply with all applicable Local laws concerning pollution of river and streams. All work under this contract shall be performed in such a manner that objectionable conditions shall not be created in streams through or adjacent to the project areas.

1.6.24.4 Waste Material. Waste material is defined as any material for which no use or reuse is intended and which is to be discarded. Disposal of hazardous waste, containers or components thereof, shall be in a hazardous waste disposal site only and no other location shall be utilized for such disposal. U.S.

Environmental Protection Agency (EPA) defined hazardous waste as a waste with properties that make it dangerous or capable of having a harmful effect on human health or the environment. Hazardous waste is generated from many sources, ranging from industrial manufacturing process wastes to batteries and may come in many forms, including liquids, solids gases, and sludges. Only hazardous waste sites which are permitted by the EPA, and/or the local government shall be utilized for such disposal actions. Contractor shall coordinate with local environmental agencies for disposal/storage activities. The Contractor shall maintain all required documentation related to hazardous material use and waste disposal in accordance with the Government of Belize regulations and requirements.

1.6.25 Personnel Safety: The Contractor shall ensure the safety of their personnel in accordance with Local law. The Contractor shall immediately correct all safety deficiencies upon notification of such deficiencies by the KO/COR and shall notify the KO/COR of the corrective action taken. The Contractor shall be responsible for the safety of their workers and all visitors at each work site; and ensure that all personnel are wearing appropriate safety gear at all times (i.e. safety glasses, helmet, harness, gloves, and safety shoes).

1.6.26 Unforeseen Conditions: The Contractor shall conduct aerial, surface, underground or embedded interference survey to avoid damage to pipes, boxes, cables, utility poles, hoses, wells or other elements in the work area. If a potential interference is found, the Contractor shall promptly give written notice to the KO/COR in accordance with FAR Clause 52.236-2, and prepare information for possible alternatives.

U.S. Southern Command

PART 2

DEFINITIONS & ACRONYMS

2. DEFINITIONS AND ACRONYMS:

2.1. Definitions

2.1.1 Area of Responsibility. The U.S. Southern Command (USSOUTHCOM) area of responsibility (AOR) includes the geographic areas of Antigua and Barbuda, Argentina, Aruba, Barbados, Belize, Bolivia, Brazil, British Virgin Islands, Cayman Islands, Chile, Colombia, Costa Rica, Cuba, Curacao, Dominica, Dominican Republic, Ecuador, El Salvador, Falkland Islands, French Guiana, Grenada, Guadeloupe, Guatemala, Guyana, Haiti, Honduras, Jamaica, Martinique, Mayotte, Montserrat, Nicaragua, Panama, Paraguay, Peru, Saint Barthélemy, Saint Martin, Saint Kitts and Nevis, Saint Lucia, Saint Vincent and the Grenadines, Saint Maarten, Suriname, Trinidad and Tobago, Turks and Caicos Islands, Uruguay, and Venezuela.

2.1.2. Contractor. The total contractor organization or a separate entity of it; such as an affiliate, division, or plant that performs its own purchasing.

2.1.3. Contracting officer (KO). A person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings.

2.1.4. Contracting officer’s representative (COR). An individual designated and authorized in writing by the contracting officer to perform specific technical or administrative functions.

2.1.5. Defective Service. A service output that does not meet the standard of performance associated with the Statement of Work.

2.1.6. Deliverable. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.

2.1.7. Key Personnel. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the SOW. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.8. Local National. For the purpose of this clause or provision, a local national (LN) is defined as any person who is performing services under a contract and is a resident of any country within the

USSOUTHCOM AOR.

2.1.9. Statement of Work (SOW). A statement of work for performance-based acquisitions that describes the required results in clear, specific, and objective terms with measurable outcomes.

2.1.10. Physical Security. Protection of the perimeter area, government property, and assets that prevent the loss or damage of Government property.

2.1.11. Quality Assurance. The various functions, including inspection, performed by the government to determine whether a Contractor has fulfilled the contract obligations pertaining to quality and quantity.

2.1.12. Quality Assurance Surveillance Plan (QASP). A plan describing how the agency will survey, observe, test, sample, evaluate and document the Contractor’s performance in meeting critical performance standards identified in the contract.

U.S. Southern Command

2.1.13. Quality Control (QC). Tasks performed by the Contractor to improve the quality of the organization’s output.

2.1.14. Shall. Imperative.

2.1.15. Subcontractor. Any supplier, distributor, vendor, or firm that furnishes supplies or services to or for a prime contractor or another subcontractor.

2.1.16. Third Country National. For the purpose of this clause or provision, a third country national (TCN) is defined as any person, regardless of citizenship, who travels into the USSOUTHCOM AOR from outside of the USSOUTHCOM AOR. This includes personnel who are citizens of the country where performance of the contract is being conducted, but reside outside of the USSOUTHCOM AOR. For this purpose, non- DOD contractor personnel are considered traveling under DOD sponsorship.

2.1.17. Work Day. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.18. Work Week. Monday through Friday, unless specified otherwise.

2.2 Acronyms:

AFFSSIR Armed Forces Repository of Specimen Samples ALMS Army Learning Management System ANSI American National Standards Institute AOR Area of Responsibility AR Army Regulation ATCTS Army Training Certification Tracking System AT Anti-Terrorism CAC Common Access Card CFR Code of Federal Regulations CI Counter Intelligence CLIN Contract Line Item Number CMR Contract Manpower Reporting CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative DD Form 254 Department of Defense Contract Security Requirement List DNA Deoxyribonucleic Acid (DNA) DOD Department of Defense DODD Department of Defense Directive DODI Department of Defense Instruction FAR Federal Acquisition Regulation FHP Force Health Protection FCG Foreign Clearance Guide FY Fiscal Year GFE Government Furnished Equipment GFP Government Furnished Property GFS Government Furnished Services IA Information Assurance IAW In Accordance With IT Information Technology JPAS Joint Personnel Adjudication System JTR Joint Travel Regulation KO Contracting Officer LN Local National

U.S. Southern Command

LOA Letter of Authorization NCIC-III National Crime Information Center Interstate Identification Index NIST National Institute of Standards and Technology ODC Other Direct Costs OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs OSHA Occupational Safety and Health Administration OPSEC Operation Security PIPO Phase In/Phase Out PRS Performance Requirements Summary SOW Statement of Work QA Quality Assurance QASP Quality Assurance Surveillance Plan QCP Quality Control Program RA Requiring Activity SOP Standard Operating Procedures SPOT Synchronized Predeployment and Operational Tracker TCN Third Country National TE Technical Exhibit TSDB Terrorist Screening Data Base U.S.C. United States Code USSOUTHCOM United States Southern Command

U.S. Southern Command

PART 3

Government Furnished Equipment (GFE), Government Furnished Property (GFP), and Government

Furnished Services (GFS)

3. GOVERNMENT FURNISHED ITEMS AND SERVICES:

3.1. Services: N/A

3.2 Facilities N/A

3.3 Utilities N/A

3.4 Equipment N/A

3.5 Materials: N/A

U.S. Southern Command

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

4.1 General The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Part 3 of this SOW.

4.2 Facility Security Clearance N/A

4.3. Materials: The Contractor shall., furnish materials, supplies, and equipment necessary to meet the requirements under this SOW.

4.4. Equipment: The Contractor shall provide four (4) SCBA FILLING SYSTEMS that each Include:5500 psi compressor, 6000psi cascade storage system and anti-explosion filling station.

4.7 RESPONSIBILITIES OF CONTRACTOR.

4.7.1 Damage to Persons or Property. The Contractor shall be responsible for all damages to persons or properties at the worksite that occur as a result of the Contractor's own fault or negligence. The Contractor shall take proper safety and health precautions to protect the work sites, the workers, the public, and the property of others.

4.7.2 Responsibility for Work Performed. The Contractor shall be responsible for all materials delivered and work performed until final completion and acceptance of the entire project, except for any completed unit of work which may have been accepted in writing by the COR under the contract.

4.8 CONTRACTOR RECORDS/PROGRESS REPORTS. The Contractor shall certify all completed work and provide progress report to the COR and KO. Report is due 7 days after the contract is awarded.

4.9 CONTRACTOR WORK SCHEDULES. N/A

4.10 REPAIR. The Contractor shall repair any damage to the existing grounds, facilities, or property incurred during the course of construction to its original pre-existing conditions. Refer to section 4.5.1 Damage to Persons or Property for additional info.

4.11 SAFETY. The Contractor shall be responsible for the safety of workers and visitors to the work sites.

The Contractor shall ensure that all personnel wear appropriate safety gear at all times in compliance with all Local Occupational Safety & Health regulations and ensue all local safety regulations are followed at all times. The Contractor shall provide sanitation for workers in accordance with the latest edition of Army Corps of Engineers Safety and Health Manual EM 385-1-1 and Local safety and health laws. Contractor shall comply with safety and health requirements as established by EM 385-1-1. Information about how to obtain electronic and/or hard copies of this manual is located at the following website:

http://www.usace.army.mil/CESO/Pages/EM385-1-1.aspx.

4.11.1 Prohibition on Asbestos and Lead Based Paints. The Contractor shall not use materials containing Asbestos or Lead Based Paints in this construction project. Upon completion of each construction project, the Contractor shall submit two copies of a Certified Letter to the COR stating that no lead based paints or materials containing asbestos were used in this project. One copy of the letter shall be filed with project documents in the Resident Engineer's Office and second copy filed in the COR’s project folder.

U.S. Southern Command

4.12 UTILITIES CONNECTIONS AND EXCAVATIONS

4.12.1 Utility Connections. The U.S. Government will not provide any utility connections. It is the Contractor’s responsibility to provide any generators required to operate its own equipment at its own expense. The Contractor shall be responsible for providing potable water daily at the construction worksite for all employees at Contractor’s own expense. If a water tank truck is planned for this purpose, the Contractor shall be responsible for providing registration information that must be included with the Contractor’s equipment listing.

4.12.2 Excavations. The Contractor shall be responsible for coordinating excavation with local utility companies and shall take every precaution to avoid damage to underground utilities. The Contractor shall be responsible for any damages they incur to the underground utilities and shall repair any construction damages at the worksite at own expense. The Contractor shall be responsible for coordinating the connection of potable water, sewage (if available), and electrical power with local utility companies.

4.13 INTERRUPTION OF UTILITY SERVICES. Any planned interruptions of utility services (electrical power, water, natural gas, etc.) shall be detailed and coordinated by the Contractor. If the outage affects only the facilities in this contract, the request shall be submitted at least three (3) working days before the planned outage. The Contractor shall not interrupt service(s) until written approval has been granted by the Local Public Works or equivalent entity. Requests shall include facility/facilities affected, date of scheduled outage, and duration. Requests for interruption of service(s) will not be approved unless all equipment and materials required for the applicable/ particular phase of work are on the job site.

Interruptions will be granted Monday through Friday for the following times: 7:15 A.M. until 11:00 A.M.

and 12:30 P.M. until 4:00 P.M. If weekend (Saturday and Sunday) outages are required or are preferred, such outages shall be coordinated as specified above.

4.14 Defense Base Act (DBA) Workers' Compensation Insurance. The Contractor shall acquire, by means of an insurance policy or a self-insurance program, workers’ compensation coverage required by the DBA.

This applies to any contractor, either from local country or from any other country. Contractor shall submit a copy of the insurance policy to the KO within 15 days after contract award. For more information to:

http//www.dol.gov/owcp/dlhwc/isdba/htm

U.S. Southern Command

PART 5

SPECIFIC TASKS

5. Specific Tasks: Under this contract, the Contractor shall furnish all labor, transportation, equipment, materials, and any other items and services necessary to Install and provide training for 4 SCBA Filling Systems as defined in this SOW. The contractor shall perform to the standards in this contract. This Statement of Work (SOW) sets forth the minimum requirements for procuring four Self Contained Breathing Apparatus (SCBA) Filling Stations that will be distributed throughout different Firefighting Stations in the country and will serve to recharge the oxygen tanks that the firefighters use in the process of completing their mission.

5.1. Basic Services. GENERAL: The Contractor shall furnish all labor, transportation, equipment, materials necessary tomeet the intent of this requirement.. The contractor shall supply four (4) SCBA FILLING SYSTEMS that each Include: 5500 psi compressor, 6000psi cascade storage system and anti-explosion filling station. Each unit must be able to fill 2 SCBA cylinders simultaneously with “breathing air”. (Voltage for El Salvador is 120V/60Hz). Shipping for all units will directly to Addresses below. These units are available at a local vendor as well. If purchased in country, vendor will ship to all locations.

5.1.1 Delivery and Installation: Will be at 4 locations:

1- (National HQ) Estación Central: Pasaje Galan N° 552 CALLE FRANCISCO MENENDEZ, BARRIO SANTA ANITA, SAN SALVADOR; (Training Location)

2- Estación San Vicente: FINAL 15 AVENIDA SUR, BARRIO CONCEPCIÓN, PLANTEL

DEL MOP

3- Estación San Miguel: KM. 136 CARRETERA PANAMERICANA AL NORTE HOSPITAL

MILITAR

4- Estación Santa Ana: 13 CALLE ORIENTE Y 3RA. AVENIDA SUR, FRENTE A LA

SEGUNDA BRIGADA DE INFANTERIA

5.1.2 Training

Training will only be at one central location. (National Firefighter HQ, San Salvador). Training session shall be conducted by a manufacturer representative or a trainer that is certified on the equipment purchased for this contract requriement. Certified trainer should plan for an 8-hour training session with 10-15 trainees who will be in charge of equipment. Location will be at National Firefighter HQ.

Date and time can be coordinated through U.S. Embassy and SOUTHCOM.

5.1.3 Contractor transportation: Transportation for trainers to installation sites also coordinated with the help of U.S. Embassy.

5.2. Task Heading. Installation and training in the use of 4 Firefighter filling stations to 4 Firefighting Stations at different locations throughout the country of El Salvador. These will serve to recharge the oxygen tanks that the firefighters use in the process of completing their mission.

Need tasking and heading for each broken down sperately for each requirement of this SOW. ( i.e 5.1.1 INSTALLATION , 5.1.2 TRAINING etc..)

Fernandez, Hector CIV SOUTHCOM SCJ7/9 (USA) Complete

Ham, Christopher A CIV USARMY ACC (USA) Why does the Government need to do this? Can't the contractor provide their on transportation.

Fernandez, Hector CIV SOUTHCOM SCJ7/9 (USA) US Embassy will only assist with coordination. Re-worded

Again utilize individual paragraphs to describe required taskings.

U.S. Southern Command

Objective

Standard Performance Threshold (This is the maximum error rate. It could possibly be “Zero deviation from standard”)

Method of

Surveillance

% Deduction from monthly invoice for not meeting Performance

Standards

1. Delivery (Delivery and Installation 5.1.1)

The Contractorshall :

(a) Purhcase all equipment in the U.S.

and ship/deliver to all addresses.

(b) Purhcase all equipment in country and arrange for shipping delivery to all locations with the local vendor.

100% Compliance

100% Inspection, COR

Validation

Installation (Delivery and Installation 5.1.1)

a) Contractor will install equipment at all locations and ensure that all equipment is operational. Locations are: 1- (National HQ) Estación Central:

Pasaje Galan N° 552

CALLE FRANCISCO

MENENDEZ,

BARRIO SANTA

ANITA, SAN

SALVADOR;

(Training Location)

2- Estación San Vicente: FINAL 15

AVENIDA SUR,

BARRIO

CONCEPCIÓN,

PLANTEL DEL MOP

3- Estación San Miguel: KM. 136

CARRETERA

PANAMERICANA

AL NORTE

Zero deviation

100% Inspection by COR at work completion.

Paragraph should be referenced here as well as the appropriate task heading

Fernandez, Hector CIV SOUTHCOM SCJ7/9 (USA) Complete

Ham, Christopher A CIV USARMY ACC (USA) Utilize relevant verbiage as it relates to each SOW paragraph identifying the associated tasking.

Paragraph reference required here as well

U.S. Southern Command

HOSPITAL

MILITAR

4- Estación Santa Ana:

13 CALLE ORIENTE

Y 3RA. AVENIDA

SUR, FRENTE A LA

SEGUNDA

BRIGADA DE

INFANTERIA

Personnel performing the installation will be certified on the equipment.

Training (5.1.2)

a) Training will be at one location (National

HQ).

b) Training session should be conducted in Spanish by manufacturer representative or a trainer that is certified on the equipment.

Certified trainer should plan for an 8-hour training session with 10-15 trainees who will be in charge of equipment.

c) Any training materials provided must be in Spanish.

Zero deviation

100% Inspection by COR at work completion.

5.3. Service Contract Reporting (SCR): N/A

Paragraph reference required as well.

Completed

U.S. Southern Command

PART 6

APPLICABLE PUBLICATIONS

6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)

6.1. The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.

6.1.1 DOD Commercial Use of Imagery Guidelines

6.1.2 AR 190-13, The Army Physical Security Program

6.1.3 Army Directive 2014-05, Policy and Implementation Procedures for CAC Credentialing Access for Uncleared Contractors

6.1.4 DOD 5220.22-M, National Industrial Security Program Operating Manual

6.1.5 Defense Federal Acquisition Regulation Supplement (DFARS)

6.1.6 Joint Travel Regulation (JTR)

6.1.7 AR 735-5, Policies and Procedures for Property Accountability

6.1.8 DODD 8570.01, Information Assurance Training Certification and Workforce Management

6.1.9 DOD 8570.01-M, Information Assurance Workforce Improvement Program

6.1.10 AR 25-2, Information Assurance

6.1.11 DODI 3020.41, Contractor Personnel Authorized to Accompany the U.S. Armed Forces

6.1.12 USSOUTHCOM SC Regulation 40-501, Medical Suitability Screening Regulation

6.1.13 DODI 2000.16 DoD Antiterrorism (AT) Program

6.1.14 https://www.osha.gov/enforcement/directives/cpl-2-254

6.1.15 Standard Interpretations | Occupational Safety and Health Administration (osha.gov) https://www.osha.gov/enforcement/directives/cpl-2-254 https://www.osha.gov/laws-regs/standardinterpretations/standardnumber/1910/1910.134%20-%20Index/result Ham, Christopher A CIV USARMY ACC (USA) Please ensure all applicable regulatory and safety publications associated with this requirement are outlined and included below. ( NIOSH, OSHA, ETC…) SEE LINKS FOR ASSISTANCE PROVIDED IN MY EMAIL. )

Complete

U.S. Southern Command

PART 7

ATTACHMENT/TECHNICAL EXHIBIT LISTING

7. Attachment/Technical Exhibit List:

7.1 Attachment 1 – Deliverables Schedule

Missing portion of the original template, if they are not need you can (RESERVE OR N/A them do not delete from document.

7.2 Attachment 2 – Estimated Workload Data (This document should be made available if historical data exists. See attached example for format.)

7.3 Exhibit A – Diesel Engine Subcomponent Parts List (This is an example)

Check

U.S. Southern Command

ATTACHMENT 1

Deliverables Schedule

Deliverable Frequency # of Copies Medium/Format Submit To Contractor Travel [SOW para. 1.6.13]

Contractor will provide notification of travel to the Government 14 days prior to travel.

1 MS Word or Excel hector.fernandez.civ @us.army.mil

Certifications [SOW para.

1.6.23.1]

Contractor will provide Licenses and Permits that prove proficiency in the installation and operatrion of the requested equipment prior to travel.

1 MS Word or Excel

HECTOR.FERNANDEZ.

CIV@US.ARMY.MIL

Training materials [SOW Para 5.2]

If training materials are used. Please provide copy to gov’t prior to travel.

1 MS Word or Excel

HECTOR.FERNANDEZ.

CIV@US.ARMY.MIL

Ensure that all match as indicated above for 5.1

File details come from the government source that posted it. Updated .