Revised_09_90_00_Amendment_0006.pdf

PDF 85 KB Posted

Attached to
C-17 Refueling Hydrant System Ramp Expansion Federal contract opportunity
Solicitation number
W91242-18-R-0002
Issued by
Department of the Army North Carolina Army National Guard

About this file

Revised 09 90 00 Amendment 0006

View the file

Other files for this federal contract opportunity

Other files attached to C-17 Refueling Hydrant System Ramp Expansion, newest first.
File Type Posted
Questions_and_Answers_96-101__W91242-18-R-0002.pdf PDF
FJRP159073-CG104-Amendment_0007.pdf PDF
FJRP159073-CG103-Amendment_0007.pdf PDF
Questions_and_Answers_78-95__W91242-18-R-0002.pdf PDF
Revised_13_34_19_Amendment_0006.pdf PDF
Revised_08_71_00_Amendment_0006.pdf PDF
Revised_09_97_13.27_Amendment_0006.pdf PDF
FJRP159073-A-201-Amendment_0006.pdf PDF
Amendment_0005_Revised_01_45_00.pdf PDF
Questions_and_Answers_40-77__W91242-18-R-0002.pdf PDF
FJRP159073-M-401-Amd03.pdf PDF
FJRP159073-CU-224-Amd03.pdf PDF
FJRP159073-M-604-Amd03.pdf PDF
Amendment_0003_Exhibit_A_Performance_Relevancy_Questionnaire_Specialized_Experience.pdf PDF
FJRP159073-ES-502-Amd03.pdf PDF
FJRP159073-M-302-Amd03.pdf PDF
FJRP159073-M-513-Amd03.pdf PDF
1.1_Drawings-INDEX_SHEET_(1).pdf PDF
FJRP159073-M-501-Amd03.pdf PDF
01_50_00_Amd03.pdf PDF
FJRP159073-MS504-Amd03.pdf PDF
33_09_53_Amd03.pdf PDF
FJRP159073-GC-003-Amd03.pdf PDF
FJRP159073-M-301-Amd03.pdf PDF
1._Drawings_-COVER_SHEET.pdf PDF
FJRP159073-M-002-Amd03.pdf PDF
32_05_33_Amd03.pdf PDF
FJRP159073-CS-121-Amd03.pdf PDF
Exhibit_G_-_Subcontracting_Plan_Format.pdf PDF
33_52_43.11_Amd03.pdf PDF
FJRP159073-EI-602-Amd03.pdf PDF
FJRP159073-M-502-Amd03.pdf PDF
FJRP159073-E-703-Amd03.pdf PDF
Exhibit_C_Past_Performance_Questionnaire_Package.pdf PDF
FJRP159073-ES-401-Amd03_(1).pdf PDF
03_30_00_Amd03.pdf PDF
Exhibit_B_Subcontractor_Consent_Form.pdf PDF
FJRP159073-EI-501-Amd03.pdf PDF
Questions_and_Answers_1-17__W91242-18-R-0002.pdf PDF
W91242-18-R-0002-0002.pdf PDF
Pre-Proposal_Conference_PPT_Presentation_W91242-18-R-0002_v.pptx PPTX presentation
1.3_Drawings-CIVIL_1_of_4.pdf PDF
Exhibit_C_Past_Performance_Questionnaire_Package.pdf PDF
7_-_VISITOR_REQUEST_WORKSHEET,_2_PGS.pdf PDF
Exhibit_A_Performance_Relevancy_Questionnaire_Specialized_Experience.pdf PDF
6_-_SAP_SINGLE_SOURCE_DETERMINATION,_1_PGS.pdf PDF
1.7_Drawings-MECHANICAL.pdf PDF
8_-_PRE-PROPOSAL_SITE_VISIT_INSTRUCTIONS.pdf PDF
1.9_Drawings-FIRE_DETECTION.pdf PDF
1.2_Drawings-LIFE_SAFETY_PLAN.pdf PDF
Show all 50

C-17 Refueling Hydrant System Ramp Expansion has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

C-17 Type III Fuel System & Ramp Expansion FJRP159073 145th Airlift Wing, North Carolina Air National Guard

Section 09 90 00 Page 1

SECTION 09 90 00

PAINTS AND COATINGS

05/11

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN CONFERENCE OF GOVERNMENTAL INDUSTRIAL HYGIENISTS (ACGIH)

ACGIH 0100 (2015; Suppl 2002-2016) Documentation of the

Threshold Limit Values and Biological Exposure Indices

ASTM INTERNATIONAL (ASTM)

ASTM D235 (2002; R 2012) Mineral Spirits (Petroleum

Spirits) (Hydrocarbon Dry Cleaning Solvent)

ASTM D4263 (1983; R 2012) Indicating Moisture in

Concrete by the Plastic Sheet Method

ASTM D4444 (2013) Use and Calibration of Hand-Held

Moisture Meters

ASTM D523 (2014) Standard Test Method for Specular

Gloss

ASTM D6386 (2016) Standard Practice for Preparation of

Zinc (Hot-Dip Galvanized) Coated Iron and Steel Product and Hardware Surfaces for Painting

ASTM E2129 (2010) Standard Practice for Data Collection for Sustainability Assessment of Building Products

ASTM F1869 (2016) Standard Test Method for Measuring

Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride

MASTER PAINTERS INSTITUTE (MPI)

MPI 101 (Oct 2009) Epoxy Anti-Corrosive Metal Primer

MPI 107 (Oct 2009) Rust Inhibitive Primer (Water-

Based)

MPI 108 (Oct 2009) High Build Epoxy Coating, Low

Gloss

Section 09 90 00 Page 2

MPI 139 (Oct 2009) Interior High Performance Latex, MPI Gloss Level 3

MPI 144 (Oct 2009) Institutional Low Odor / VOC

Interior Latex, MPI Gloss Level 2

MPI 145 (Oct 2009) Institutional Low Odor / VOC

Interior Latex, MPI Gloss Level 3

MPI 163 (Oct 2009) Exterior W.B. Light Industrial

Coating, Semi-Gloss, MPI Gloss Level 5

MPI 23 (Oct 2009) Surface Tolerant Metal Primer

MPI 39 (Oct 2009) Interior Latex-Based Wood Primer

MPI 4 (Oct 2009) Interior/Exterior Latex Block

Filler

MPI 50 (Oct 2009) Interior Latex Primer Sealer

MPI 79 (Oct 2009) Alkyd Anti-Corrosive Metal Primer

MPI 94 (Oct 2009) Exterior Alkyd, Semi-Gloss, MPI

Gloss Level 5

MPI 95 (Oct 2009) Quick Drying Primer for Aluminum

SCIENTIFIC CERTIFICATION SYSTEMS (SCS)

SCS SP-01 (2000) Environmentally Preferable Product

Specification for Architectural and Anti- Corrosive Paints

SOCIETY FOR PROTECTIVE COATINGS (SSPC)

SSPC 7 (2007; E 2004) Brush-Off Blast Cleaning

SSPC PA 1 (2016) Shop, Field, and Maintenance Coating of Metals

SSPC PA Guide 3 (1982; E 1995) A Guide to Safety in Paint

Application

SSPC QP 1 (2012; E 2012) Standard Procedure for

Evaluating Painting Contractors (Field Application to Complex Industrial Structures)

SSPC SP 1 (2015) Solvent Cleaning

SSPC SP 10 (2007) Near-White Blast Cleaning

SSPC SP 12 (2002) Surface Preparation and Cleaning of

Metals by Waterjetting Prior to Recoating

SSPC SP 2 (1982; E 2000; E 2004) Hand Tool Cleaning

Section 09 90 00 Page 3

SSPC SP 3 (1982; E 2004) Power Tool Cleaning

SSPC SP 6 (2007) Commercial Blast Cleaning

SSPC VIS 1 (2002; E 2004) Guide and Reference

Photographs for Steel Surfaces Prepared by Dry Abrasive Blast Cleaning

SSPC VIS 3 (2004) Guide and Reference Photographs for

Steel Surfaces Prepared by Hand and Power Tool Cleaning

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. DEPARTMENT OF DEFENSE (DOD)

MIL-STD-101 (2014; Rev C) Color Code for Pipelines and for Compressed Gas Cylinders

U.S. GENERAL SERVICES ADMINISTRATION (GSA)

FED-STD-313 (2014; Rev E) Material Safety Data, Transportation Data and Disposal Data for Hazardous Materials Furnished to Government Activities

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910.1000 Air Contaminants

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

The current MPI, "Approved Product List" which lists paint by brand, label, product name and product code as of the date of contract award, will be used to determine compliance with the submittal requirements of this specification. The Contractor may choose to use a subsequent MPI "Approved Product List", however, only one list may be used for the entire contract and each coating system is to be from a single manufacturer. All coats on a particular substrate must be from a single manufacturer. No variation from the MPI Approved Products List is acceptable.

Samples of specified materials may be taken and tested for compliance with specification requirements.

In keeping with the intent of Executive Order 13101, "Greening the Government through Waste Prevention, Recycling, and Federal Acquisition", products certified by SCS as meeting SCS SP-01 shall be given preferential consideration over registered products. Products that are registered shall

Section 09 90 00 Page 4 be given preferential consideration over products not carrying any EPP designation.

SD-02 Shop Drawings

Piping identification

Submit color stencil codes

SD-03 Product Data

Local/Regional Materials; S

Submit documentation indicating distance between manufacturing facility and the project site. Indicate distance of raw material origin from the project site. Indicate relative dollar value of local/regional materials to total dollar value of products included in project.

Environmental Data

Materials; S

Submit documentation indicating percentage of post-industrial and post-consumer recycled content per unit of product. Indicate relative dollar value of recycled content products to total dollar value of products included in project.

Coating; G

Manufacturer's Technical Data Sheets; S

Indicate VOC content.

SD-04 Samples

Color; G

Submit manufacturer's samples of paint colors. Cross reference color samples to color scheme as indicated.

SD-07 Certificates

Applicator's qualifications

SD-08 Manufacturer's Instructions

Application instructions

Mixing

Detailed mixing instructions, minimum and maximum application temperature and humidity, potlife, and curing and drying times between coats.

Manufacturer's Material Safety Data Sheets

Section 09 90 00 Page 5

Submit manufacturer's Material Safety Data Sheets for coatings, solvents, and other potentially hazardous materials, as defined in

FED-STD-313.

SD-10 Operation and Maintenance Data

Coatings:; G

Preprinted cleaning and maintenance instructions for all coating systems shall be provided.

SD-11 Closeout Submittals

Local/Regional Materials; S

Documentation relative to local/regional materials.

Materials; S

Documentation relative to recycled content.

Documentation relative to low emitting materials.

1.3 APPLICATOR'S QUALIFICATIONS

Section 09 90 00 Page 6

1.3.1 Contractor Qualification

Submit the name, address, telephone number, FAX number, and e-mail address of the contractor that will be performing all surface preparation and coating application. Submit evidence that key personnel have successfully performed surface preparation and application of coatings on a minimum of three similar projects within the past three years. List information by individual and include the following:

a. Name of individual and proposed position for this work.

b. Information about each previous assignment including:

Position or responsibility

Employer (if other than the Contractor)

Name of facility owner

Mailing address, telephone number, and telex number (if non-US) of facility owner

Name of individual in facility owner's organization who can be contacted as a reference

Location, size and description of structure

Dates work was carried out

Description of work carried out on structure

1.3.1 SSPC QP 1 Certification

All contractors and subcontractors that perform surface preparation or coating application shall be certified by the Society for Protective Coatings (formerly Steel Structures Painting Council) (SSPC) to the requirements of SSPC QP 1 prior to contract award, and shall remain certified while accomplishing any surface preparation or coating application. The painting contractors and painting subcontractors must remain so certified for the duration of the project. If a contractor's or subcontractor's certification expires, the firm will not be allowed to perform any work until the certification is reissued. Requests for extension of time for any delay to the completion of the project due to an inactive certification will not be considered and liquidated damages will apply. Notify the Contracting Officer of any change in contractor certification status.

1.4 QUALITY ASSURANCE

1.4.1 Field Samples and Tests

The Contracting Officer may choose up to two coatings that have been delivered to the site to be tested at no cost to the Government. Take samples of each chosen product as specified in the paragraph "Sampling Procedures." Test each chosen product as specified in the paragraph "Testing Procedure." Products which do not conform, shall be removed from the job site and replaced with new products that conform to the referenced

Section 09 90 00 Page 7 specification. Testing of replacement products that failed initial testing shall be at no cost to the Government.

1.4.1.1 Sampling Procedure

The Contracting Officer will select paint at random from the products that have been delivered to the job site for sample testing. The Contractor shall provide one quart samples of the selected paint materials. The samples shall be taken in the presence of the Contracting Officer, and labeled, identifying each sample. Provide labels in accordance with the paragraph "Packaging, Labeling, and Storage" of this specification.

1.5 REGULATORY REQUIREMENTS

1.5.1 Environmental Protection

In addition to requirements specified elsewhere for environmental protection, provide coating materials that conform to the restrictions of the local Air Pollution Control District and regional jurisdiction. Notify Contracting Officer of any paint specified herein which fails to conform.

1.5.2 Lead Content

Do not use coatings having a lead content over 0.06 percent by weight of nonvolatile content.

1.5.3 Chromate Content

Do not use coatings containing zinc-chromate or strontium-chromate.

1.5.4 Asbestos Content

Materials shall not contain asbestos.

1.5.5 Mercury Content

Materials shall not contain mercury or mercury compounds.

1.5.6 Silica

Abrasive blast media shall not contain free crystalline silica.

1.5.7 Human Carcinogens

Materials shall not contain ACGIH 0100 confirmed human carcinogens (A1) or suspected human carcinogens (A2).

1.6 PACKAGING, LABELING, AND STORAGE

Paints shall be in sealed containers that legibly show the contract specification number, designation name, formula or specification number, batch number, color, quantity, date of manufacture, manufacturer's formulation number, manufacturer's directions including any warnings and special precautions, and name and address of manufacturer. Pigmented paints shall be furnished in containers not larger than 5 gallons. Paints and thinners shall be stored in accordance with the manufacturer's written directions, and as a minimum, stored off the ground, under cover, with

Section 09 90 00 Page 8 sufficient ventilation to prevent the buildup of flammable vapors, and at temperatures between 40 to 95 degrees F. Do not store paint, polyurethane, varnish, or wood stain products with materials that have a high capacity to adsorb VOC emissions, including acoustical ceilings. Do not store paint, polyurethane, varnish, or wood stain products in occupied spaces.

1.7 SAFETY AND HEALTH

Apply coating materials using safety methods and equipment in accordance with the following:

Work shall comply with applicable Federal, State, and local laws and regulations, and with the ACCIDENT PREVENTION PLAN, including the Activity Hazard Analysis as specified in Section 01 35 26 GOVERNMENT SAFETY REQUIREMENTS and in Appendix A of EM 385-1-1. The Activity Hazard Analysis shall include analyses of the potential impact of painting operations on painting personnel and on others involved in and adjacent to the work zone.

1.7.1 Safety Methods Used During Coating Application

Comply with the requirements of SSPC PA Guide 3.

1.7.2 Toxic Materials

To protect personnel from overexposure to toxic materials, conform to the most stringent guidance of:

a. The applicable manufacturer's Material Safety Data Sheets (MSDS) or local regulation.

b. 29 CFR 1910.1000.

c. ACGIH 0100, threshold limit values.

1.8 ENVIRONMENTAL CONDITIONS

Comply, at minimum, with manufacturer recommendations for space ventilation during and after installation.

1.8.1 Coatings

Do not apply coating when air or substrate conditions are:

a. Less than 5 degrees F above dew point;

b. Below 50 degrees F or over 95 degrees F, unless specifically pre-approved by the Contracting Officer and the product manufacturer.

Under no circumstances shall application conditions exceed manufacturer recommendations.

1.8.2 Post-Application

Vacate space for as long as possible after application. Wait a minimum of 48 hours before occupying freshly painted rooms. Maintain one of the following ventilation conditions during the curing period, or for 72 hours after application:

Section 09 90 00 Page 9

a. Supply 100 percent outside air 24 hours a day.

b. Supply airflow at a rate of 6 air changes per hour, when outside temperatures are between 55 degrees F and 85 degrees F and humidity is between 30 percent and 60 percent.

c. Supply airflow at a rate of 1.5 air changes per hour, when outside air conditions are not within the range stipulated above.

1.9 SUSTAINABLE DESIGN REQUIREMENTS

1.9.1 Environmental Data

Submit Table 1 of ASTM E2129 for products.

1.10 SCHEDULING

Allow paint, polyurethane, varnish, and wood stain installations to cure prior to the installation of materials that adsorb VOCs.

1.11 COLOR SELECTION

Colors of finish coats shall be as indicated or specified. Where not indicated or specified, colors shall be selected by the Contracting Officer.

Manufacturers' names and color identification are used for the purpose of color identification only. Named products are acceptable for use only if they conform to specified requirements. Products of other manufacturers are acceptable if the colors approximate colors indicated and the product conforms to specified requirements.

Tint each coat progressively darker to enable confirmation of the number of coats.

Color, texture, and pattern of wall coating systems shall be as indicated.

1.12 LOCATION AND SURFACE TYPE TO BE PAINTED

1.12.1 Painting Included

Where a space or surface is indicated to be painted, include the following unless indicated otherwise.

a. Surfaces behind portable objects and surface mounted articles readily detachable by removal of fasteners, such as screws and bolts.

b. New factory finished surfaces that require identification or color coding and factory finished surfaces that are damaged during performance of the work.

c. Existing coated surfaces that are damaged during performance of the work.

1.12.1.1 Exterior Painting

Includes new surfaces of the building and appurtenances. Also included are existing coated surfaces made bare by cleaning operations.

Section 09 90 00 Page 10

1.12.1.2 Interior Painting

Includes new surfaces of the building and appurtenances as indicated. Where a space or surface is indicated to be painted, include the following items, unless indicated otherwise.

a. Exposed columns, girders, beams, joists, and metal deck; and

b. Other contiguous surfaces.

1.12.2 Painting Excluded

Do not paint the following unless indicated otherwise.

a. Surfaces concealed and made inaccessible by panelboards, fixed ductwork, machinery, and equipment fixed in place.

b. Surfaces in concealed spaces. Concealed spaces are defined as enclosed spaces above suspended ceilings, furred spaces, attic spaces, crawl spaces, elevator shafts and chases.

c. Steel to be embedded in concrete.

d. Copper, stainless steel, aluminum, brass, and lead except existing coated surfaces.

e. Hardware, fittings, and other factory finished items.

1.12.3 Mechanical and Electrical Painting

Includes field coating of interior new surfaces.

a. Where a space or surface is indicated to be painted, include the following items unless indicated otherwise.

(1) Exposed piping, conduit, and ductwork;

(2) Supports, hangers, air grilles, and registers;

(3) Miscellaneous metalwork and insulation coverings.

b. Do not paint the following, unless indicated otherwise:

(1) New zinc-coated, aluminum, and copper surfaces under insulation.

(2) New aluminum jacket on piping.

(3) New interior ferrous piping under insulation.

1.12.4 Definitions and Abbreviations

1.12.4.1 Batch Quality Conformance Testing

Batch quality conformance testing determines that the product provided is the same as the product qualified to the appropriate product specification.

This testing shall only be accomplished by MPI testing lab.

Section 09 90 00 Page 11

1.12.4.2 Coating

A film or thin layer applied to a base material called a substrate. A coating may be a metal, alloy, paint, or solid/liquid suspensions on various substrates (metals, plastics, wood, paper, leather, cloth, etc.). They may be applied by electrolysis, vapor deposition, vacuum, or mechanical means such as brushing, spraying, calendaring, and roller coating. A coating may be applied for aesthetic or protective purposes or both. The term "coating" as used herein includes emulsions, enamels, stains, varnishes, sealers, epoxies, and other coatings, whether used as primer, intermediate, or finish coat. The terms paint and coating are used interchangeably.

1.12.4.3 DFT or dft

Dry film thickness, the film thickness of the fully cured, dry paint or coating.

1.12.4.4 DSD

Degree of Surface Degradation, the MPI system of defining degree of surface degradation. Five (5) levels are generically defined under the Assessment sections in the MPI Maintenance Repainting Manual.

1.12.4.5 EPP

Environmentally Preferred Products, a standard for determining environmental preferability in support of Executive Order 13101.

1.12.4.6 EXT

MPI short term designation for an exterior coating system.

1.12.4.7 INT

MPI short term designation for an interior coating system.

1.12.4.8 micron / microns

The metric measurement for 0.001 mm or one/one-thousandth of a millimeter.

1.12.4.9 mil / mils

The English measurement for 0.001 in or one/one-thousandth of an inch, equal to 25.4 microns or 0.0254 mm.

1.12.4.10 mm

The metric measurement for millimeter, 0.001 meter or one/one-thousandth of a meter.

1.12.4.11 MPI Gloss Levels

MPI system of defining gloss. Seven (7) gloss levels (G1 to G7) are generically defined under the Evaluation sections of the MPI Manuals.

Traditionally, Flat refers to G1/G2, Eggshell refers to G3, Semigloss refers to G5, and Gloss refers to G6.

Section 09 90 00 Page 12

Gloss levels are defined by MPI as follows:

Gloss Description Units Units Level at 60 degrees at 85 degrees

G1 Matte or Flat 0 to 5 10 max G2 Velvet 0 to 10 10 to 35 G3 Eggshell 10 to 25 10 to 35 G4 Satin 20 to 35 35 min G5 Semi-Gloss 35 to 70 G6 Gloss 70 to 85 G7 High Gloss

Gloss is tested in accordance with ASTM D523. Historically, the Government has used Flat (G1 / G2), Eggshell (G3), Semi-Gloss (G5), and Gloss (G6).

1.12.4.12 MPI System Number

The MPI coating system number in each Division found in either the MPI Architectural Painting Specification Manual or the Maintenance Repainting Manual and defined as an exterior (EXT/REX) or interior system (INT/RIN).

The Division number follows the CSI Master Format.

1.12.4.13 Paint

See Coating definition.

1.12.4.14 REX

MPI short term designation for an exterior coating system used in repainting projects or over existing coating systems.

1.12.4.15 RIN

MPI short term designation for an interior coating system used in repainting projects or over existing coating systems.

PART 2 PRODUCTS

2.1 MATERIALS

Conform to the coating specifications and standards referenced in PART 3.

Submit manufacturer's technical data sheets for specified coatings and solvents. Minimum 20 percent post-consumer recycled content for the light-colored paints and primers. Minimum 50 percent post-consumer recycled content for dark-colored paints and primers. Comply with applicable regulations regarding toxic and hazardous materials.

PART 3 EXECUTION

3.1 PROTECTION OF AREAS AND SPACES NOT TO BE PAINTED

Prior to surface preparation and coating applications, remove, mask, or otherwise protect, hardware, hardware accessories, machined surfaces, radiator covers, plates, lighting fixtures, public and private property, and other such items not to be coated that are in contact with surfaces to be coated. Following completion of painting, workmen skilled in the trades

Section 09 90 00 Page 13 involved shall reinstall removed items. Restore surfaces contaminated by coating materials, to original condition and repair damaged items.

3.2 SURFACE PREPARATION

Remove dirt, splinters, loose particles, grease, oil, disintegrated coatings, and other foreign matter and substances deleterious to coating performance as specified for each substrate before application of paint or surface treatments. Oil and grease shall be removed prior to mechanical cleaning. Cleaning shall be programmed so that dust and other contaminants will not fall on wet, newly painted surfaces. Exposed ferrous metals such as nail heads on or in contact with surfaces to be painted with water-thinned paints, shall be spot-primed with a suitable corrosion-inhibitive primer capable of preventing flash rusting and compatible with the coating specified for the adjacent areas. Comply with the application instructions of the paint manufacturer.

3.3 PREPARATION OF METAL SURFACES

3.3.1 New Ferrous Surfaces

a. Ferrous Surfaces including Shop-coated Surfaces and Small Areas That Contain Rust, Mill Scale and Other Foreign Substances: Solvent clean or detergent wash in accordance with SSPC SP 1 to remove oil and grease. Where shop coat is missing or damaged, clean according to SSPC SP 2, SSPC SP 3, SSPC SP 6, or SSPC SP 10. Brush-off blast remaining surface in accordance with SSPC 7. Shop-coated ferrous surfaces shall be protected from corrosion by treating and touching up corroded areas immediately upon detection.

b. Surfaces With More Than 20 Percent Rust, Mill Scale, and Other Foreign

Substances: Clean entire surface in accordance with SSPC SP 6/SSPC SP

12 WJ-3.

3.3.2 Final Ferrous Surface Condition

For tool cleaned surfaces, the requirements are stated in SSPC SP 2 and SSPC SP 3. As a visual reference, cleaned surfaces shall be similar to photographs in SSPC VIS 3.

For abrasive blast cleaned surfaces, the requirements are stated in SSPC 7, SSPC SP 6, and SSPC SP 10. As a visual reference, cleaned surfaces shall be similar to photographs in SSPC VIS 1.

3.3.3 Galvanized Surfaces

a. New Galvanized Surfaces With Only Dirt and Zinc Oxidation Products:

Clean with solvent, steam, or non-alkaline detergent solution in accordance with SSPC SP 1. If the galvanized metal has been passivated or stabilized, the coating shall be completely removed by brush-off abrasive blast. New galvanized steel to be coated shall not be "passivated" or "stabilized" If the absence of hexavalent stain inhibitors is not documented, test as described in ASTM D6386, Appendix X2, and remove by one of the methods described therein.

3.3.4 Non-Ferrous Metallic Surfaces

Section 09 90 00 Page 14

Aluminum and aluminum-alloy, lead, copper, and other nonferrous metal surfaces.

Surface Cleaning: Solvent clean in accordance with SSPC SP 1 and wash with mild non-alkaline detergent to remove dirt and water soluble contaminants.

3.3.5 Terne-Coated Metal Surfaces

Solvent clean surfaces with mineral spirits, ASTM D235. Wipe dry with clean, dry cloths.

3.4 PREPARATION OF CONCRETE AND CEMENTITIOUS SURFACE

3.4.1 Concrete and Masonry

a. Curing: Concrete and masonry surfaces shall be allowed to cure at least 30 days before painting, except concrete slab on grade, which shall be allowed to cure 90 days before painting.

b. Surface Cleaning: Remove the following deleterious substances.

(1) Dirt, Chalking, Grease, and Oil: Wash new surfaces with a solution composed of 1/2 cup trisodium phosphate, 1/4 cup household detergent, and 4 quarts of warm water. Then rinse thoroughly with fresh water. For large areas, water blasting may be used.

(2) Fungus and Mold: Wash new surfaces with a solution composed of 1/2 cup trisodium phosphate, 1/4 cup household detergent, 1 quart 5 percent sodium hypochlorite solution and 3 quarts of warm water.

Rinse thoroughly with fresh water.

(3) Paint and Loose Particles: Remove by wire brushing.

(4) Efflorescence: Remove by scraping or wire brushing followed by washing with a 5 to 10 percent by weight aqueous solution of hydrochloric (muriatic) acid. Do not allow acid to remain on the surface for more than five minutes before rinsing with fresh water.

Do not acid clean more than 4 square feet of surface, per workman, at one time.

c. Cosmetic Repair of Minor Defects: Repair or fill mortar joints and minor defects, including but not limited to spalls, in accordance with manufacturer's recommendations and prior to coating application.

d. Allowable Moisture Content: Latex coatings may be applied to damp surfaces, but not to surfaces with droplets of water. Do not apply epoxies to damp vertical surfaces as determined by ASTM D4263 or horizontal surfaces that exceed 3 lbs of moisture per 1,000 square feet in 24 hours as determined by ASTM F1869. In all cases follow manufacturers recommendations. Allow surfaces to cure a minimum of 30 days before painting.

3.4.2 Gypsum Board

a. Surface Cleaning: Gypsum board shall be dry. Remove loose dirt and dust by brushing with a soft brush, rubbing with a dry cloth, or

Section 09 90 00 Page 15 vacuum-cleaning prior to application of the first coat material. A damp cloth or sponge may be used if paint will be water-based.

b. Repair of Minor Defects: Prior to painting, repair joints, cracks, holes, surface irregularities, and other minor defects with patching plaster or spackling compound and sand smooth.

c. Allowable Moisture Content: Latex coatings may be applied to damp surfaces, but not surfaces with droplets of water. Do not apply epoxies to damp surfaces as determined by ASTM D4263.

3.5 PREPARATION OF PLYWOOD SURFACES

3.5.1 New Plywood Surfaces, Except Floors:

a. Wood surfaces shall be cleaned of foreign matter.

Surface Cleaning: Surfaces shall be free from dust and other deleterious substances and in a condition approved by the Contracting Officer prior to receiving paint or other finish. Do not use water to clean uncoated wood.

b. Moisture content of the wood shall not exceed 12 percent as measured by a moisture meter in accordance with ASTM D4444, Method A, unless otherwise authorized.

c. Wood surfaces adjacent to surfaces to receive water-thinned paints shall be primed and/or touched up before applying water-thinned paints.

d. Cracks and Nailheads: Set and putty stop nailheads and putty cracks after the prime coat has dried.

e. Cosmetic Repair of Minor Defects:

(1) Knots and Resinous Wood: Prior to application of coating, cover knots and stains with two or more coats of 3-pound-cut shellac varnish, plasticized with 5 ounces of castor oil per gallon.

Scrape away existing coatings from knotty areas, and sand before treating. Prime before applying any putty over shellacked area.

(2) Open Joints and Other Openings: Fill with whiting putty, linseed oil putty. Sand smooth after putty has dried.

(3) Checking: Where checking of the wood is present, sand the surface, wipe and apply a coat of pigmented orange shellac. Allow to dry before paint is applied.

3.6 APPLICATION

3.6.1 Coating Application

Painting practices shall comply with applicable federal, state and local laws enacted to insure compliance with Federal Clean Air Standards. Apply coating materials in accordance with SSPC PA 1. SSPC PA 1 methods are applicable to all substrates, except as modified herein.

At the time of application, paint shall show no signs of deterioration.

Uniform suspension of pigments shall be maintained during application.

Section 09 90 00 Page 16

Unless otherwise specified or recommended by the paint manufacturer, paint may be applied by brush, roller, or spray. Use trigger operated spray nozzles for water hoses. Rollers for applying paints and enamels shall be of a type designed for the coating to be applied and the surface to be coated. Wear protective clothing and respirators when applying oil-based paints or using spray equipment with any paints.

Paints, except water-thinned types, shall be applied only to surfaces that are completely free of moisture as determined by sight or touch.

Thoroughly work coating materials into joints, crevices, and open spaces.

Special attention shall be given to insure that all edges, corners, crevices, welds, and rivets receive a film thickness equal to that of adjacent painted surfaces.

Each coat of paint shall be applied so dry film shall be of uniform thickness and free from runs, drops, ridges, waves, pinholes or other voids, laps, brush marks, and variations in color, texture, and finish. Hiding shall be complete.

Touch up damaged coatings before applying subsequent coats. Interior areas shall be broom clean and dust free before and during the application of coating material.

a. Drying Time: Allow time between coats, as recommended by the coating manufacturer, to permit thorough drying, but not to present topcoat adhesion problems. Provide each coat in specified condition to receive next coat.

b. Primers, and Intermediate Coats: Do not allow primers or intermediate coats to dry more than 30 days, or longer than recommended by manufacturer, before applying subsequent coats. Follow manufacturer's recommendations for surface preparation if primers or intermediate coats are allowed to dry longer than recommended by manufacturers of subsequent coatings. Each coat shall cover surface of preceding coat or surface completely, and there shall be a visually perceptible difference in shades of successive coats.

c. Finished Surfaces: Provide finished surfaces free from runs, drops, ridges, waves, laps, brush marks, and variations in colors.

d. Thermosetting Paints: Topcoats over thermosetting paints (epoxies and urethanes) should be applied within the overcoating window recommended by the manufacturer.

3.6.2 Mixing and Thinning of Paints

Reduce paints to proper consistency by adding fresh paint, except when thinning is mandatory to suit surface, temperature, weather conditions, application methods, or for the type of paint being used. Obtain written permission from the Contracting Officer to use thinners. The written permission shall include quantities and types of thinners to use.

When thinning is allowed, paints shall be thinned immediately prior to application with not more than 1 pint of suitable thinner per gallon. The use of thinner shall not relieve the Contractor from obtaining complete

Section 09 90 00 Page 17 hiding, full film thickness, or required gloss. Thinning shall not cause the paint to exceed limits on volatile organic compounds. Paints of different manufacturers shall not be mixed.

3.6.3 Two-Component Systems

Two-component systems shall be mixed in accordance with manufacturer's instructions. Any thinning of the first coat to ensure proper penetration and sealing shall be as recommended by the manufacturer for each type of substrate.

3.6.4 Coating Systems

a. Systems by Substrates: Apply coatings that conform to the respective specifications listed in the following Tables:

Table

Division 5. Exterior Metal, Ferrous and Non-Ferrous Paint Table

Division 4. Interior Concrete Masonry Units Paint Table Division 5. Interior Metal, Ferrous and Non-Ferrous Paint Table Division 6. Interior Wood Paint Table Division 9: Interior Gypsum Board Paint Table

b. Minimum Dry Film Thickness (DFT): Apply paints, primers, varnishes, enamels, undercoats, and other coatings to a minimum dry film thickness of 1.5 mil each coat unless specified otherwise in the Tables. Coating thickness where specified, refers to the minimum dry film thickness.

c. Coatings for Surfaces Not Specified Otherwise: Coat surfaces which have not been specified, the same as surfaces having similar conditions of exposure.

3.7 COATING SYSTEMS FOR METAL

Apply coatings of Tables in Division 5 for Exterior and Interior. Refer to section 09 96 00 HIGH-PERFORMANCE COATINGS for exterior metal coatings at concrete vaults and pits.

a. Apply specified ferrous metal primer on the same day that surface is cleaned, to surfaces that meet all specified surface preparation requirements at time of application.

b. Inaccessible Surfaces: Prior to erection, use one coat of specified primer on metal surfaces that will be inaccessible after erection.

c. Shop-primed Surfaces: Touch up exposed substrates and damaged coatings to protect from rusting prior to applying field primer.

d. Surface Previously Coated with Epoxy or Urethane: Apply MPI 101, 1.5 mils DFT immediately prior to application of epoxy or urethane coatings.

e. Pipes and Tubing: The semitransparent film applied to some pipes and tubing at the mill is not to be considered a shop coat, but shall be

Section 09 90 00 Page 18 overcoated with the specified ferrous-metal primer prior to application of finish coats.

f. Exposed Nails, Screws, Fasteners, and Miscellaneous Ferrous Surfaces.

On surfaces to be coated with water thinned coatings, spot prime exposed nails and other ferrous metal with latex primer MPI 107.

3.8 COATING SYSTEMS FOR CONCRETE AND CEMENTITIOUS SUBSTRATES

Apply coatings of Tables in Division 4 and 9 for Interior. Refer to section 09 96 00 HIGH-PERFORMANCE COATINGS for exterior concrete.

3.9 COATING SYSTEMS FOR PLYWOOD

a. Apply coatings of Tables in Division 6 for Interior.

3.10 PIPING IDENTIFICATION

Piping Identification, Including Surfaces In Concealed Spaces: Provide in accordance with MIL-STD-101. Place stenciling in clearly visible locations.

On piping not covered by MIL-STD-101, stencil approved names or code letters, in letters a minimum of 1/2 inch high for piping and a minimum of 2 inches high elsewhere. Stencil arrow-shaped markings on piping to indicate direction of flow using black stencil paint.

3.11 INSPECTION AND ACCEPTANCE

In addition to meeting previously specified requirements, demonstrate mobility of moving components, including swinging and sliding doors, cabinets, and windows with operable sash, for inspection by the Contracting Officer. Perform this demonstration after appropriate curing and drying times of coatings have elapsed and prior to invoicing for final payment.

3.12 WASTE MANAGEMENT

As specified in the Waste Management Plan and as follows. Do not use kerosene or any such organic solvents to clean up water based paints.

Properly dispose of paints or solvents in designated containers. Close and seal partially used containers of paint to maintain quality as necessary for reuse. Store in protected, well-ventilated, fire-safe area at moderate temperature. Place materials defined as hazardous or toxic waste in designated containers. Set aside extra paint for future color matches or reuse by the Government. Where local options exist for leftover paint recycling, collect all waste paint by type and provide for delivery to recycling or collection facility for reuse by local organizations.

3.13 PAINT TABLES

All DFT's are minimum values. Acceptable products are listed in the MPI Green Approved Products List, available at http://www.specifygreen.com/APL/ProductIdxByMPInum.asp.

3.13.1 EXTERIOR PAINT TABLES

DIVISION 5: EXTERIOR METAL, FERROUS AND NON-FERROUS PAINT TABLE

STEEL / FERROUS SURFACES

http://www.specifygreen.com/APL/ProductIdxByMPInum.asp

Section 09 90 00 Page 19

A. New Steel that has been hand or power tool cleaned to SSPC SP 2 or

SSPC SP 3

1. Alkyd New; MPI EXT 5.1Q-G5 (Semigloss) Existing; MPI REX 5.1D-G5 Primer: Intermediate: Topcoat:

MPI 23 MPI 94 MPI 94

System DFT: 5.25 mils

B. New Steel that has been blast-cleaned to SSPC SP 6:

1. Alkyd New; MPI EXT 5.1D-G5 (Semigloss) / Existing; MPI REX 5.1D-G5 Primer: Intermediate: Topcoat:

MPI 79 MPI 94 MPI 94

System DFT: 5.25 mils

C. New steel blast cleaned to SSPC SP 10:

1. Waterborne Light Industrial MPI EXT 5.1R-G5 (Semigloss) Primer: Intermediate: Topcoat:

MPI 101 MPI 108 MPI 163

System DFT: 8.5 mils

EXTERIOR GALVANIZED SURFACES

D. New Galvanized surfaces:

1. Epoxy Primer / Waterborne Light Industrial Coating MPI EXT 5.3K-G5 (Semigloss) Primer: Intermediate: Topcoat:

MPI 101 MPI 163 MPI 163

System DFT: 5 mils

EXTERIOR SURFACES, OTHER METALS (NON-FERROUS)

E. Aluminum, aluminum alloy and other miscellaneous non-ferrous metal items not otherwise specified except hot metal surfaces, roof surfaces, and new prefinished equipment. Match surrounding finish:

1. Alkyd

MPI EXT 5.4F-G5 (Semigloss) Primer: Intermediate: Topcoat:

MPI 95 MPI 94 MPI 94

System DFT: 5 mils

F. Surfaces adjacent to painted surfaces; Mechanical, Electrical, and miscellaneous metal items not otherwise specified except floors, hot metal surfaces, and new prefinished equipment. Match surrounding finish:

1. Alkyd

MPI EXT 5.1D-G5 (Semigloss) Primer: Intermediate: Topcoat:

Section 09 90 00 Page 20

MPI 79 MPI 94 MPI 94

System DFT: 5.25 mils

3.13.2 INTERIOR PAINT TABLES

DIVISION 4: INTERIOR CONCRETE MASONRY UNITS PAINT TABLE

A. New Concrete masonry:

1. Institutional Low Odor / Low VOC Latex

New; MPI INT 4.2E-G3 (Eggshell) Filler Primer: Intermediate: Topcoat:

MPI 4 N/A MPI 145 MPI 145

System DFT: 4 mils

DIVISION 5: INTERIOR METAL, FERROUS AND NON-FERROUS PAINT TABLE

INTERIOR STEEL / FERROUS SURFACES

A. Metal, Mechanical, Electrical, Surfaces adjacent to painted surfaces (Match surrounding finish), and miscellaneous metal items not otherwise specified except floors, hot metal surfaces, and new prefinished equipment:

1. High Performance Architectural Latex

MPI INT 5.1R-G3 (Eggshell) Primer: Intermediate: Topcoat:

MPI 79 MPI 139 MPI 139

System DFT: 5 mils

B. Miscellaneous non-ferrous metal items not otherwise specified except floors, hot metal surfaces, and new prefinished equipment. Match surrounding finish:

1. High Performance Architectural Latex

MPI INT 5.4F-G3 (Eggshell) Primer: Intermediate: Topcoat:

MPI 95 MPI 139 MPI 139

System DFT: 5 mils

DIVISION 6: INTERIOR WOOD PAINT TABLE

A. New plywood not otherwise specified:

1. High Performance Architectural Latex MPI INT 6.4S-G3 (Eggshell) Primer: Intermediate: Topcoat:

MPI 39 MPI 139 MPI 139

System DFT: 4.5 mils

DIVISION 9: INTERIOR PLASTER, GYPSUM BOARD, TEXTURED SURFACES PAINT

TABLE

A. New Wallboard not otherwise specified:

Section 09 90 00 Page 21

1. Institutional Low Odor / Low VOC Latex New; MPI INT 9.2M-G2 (Flat) / Existing; MPI RIN 9.2M-G2 (Flat) Primer: Intermediate: Topcoat:

MPI 50 MPI 144 MPI 144

System DFT: 4 mils

New; MPI INT 9.2M-G3 (Eggshell) / Existing; MPI RIN 9.2M-G3 (Eggshell) Primer: Intermediate: Topcoat:

MPI 50 MPI 145 MPI 145

System DFT: 4 mils

-- End of Section --

PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 APPLICATOR'S QUALIFICATIONS
1.3.1 Contractor Qualification
Submit the name, address, telephone number, FAX number, and e-mail address of the contractor that will be performing all surface preparation and coating application. Submit evidence that key personnel have successfully performed surface preparation an...
a. Name of individual and proposed position for this work.
b. Information about each previous assignment including:
Position or responsibility
Employer (if other than the Contractor)
Name of facility owner
Mailing address, telephone number, and telex number (if non-US) of
facility owner
Name of individual in facility owner's organization who can be
contacted as a reference
Location, size and description of structure
Dates work was carried out
Description of work carried out on structure
1.3.1 SSPC QP 1 Certification
1.4 QUALITY ASSURANCE
1.4.1 Field Samples and Tests
1.4.1.1 Sampling Procedure
1.5 REGULATORY REQUIREMENTS
1.5.1 Environmental Protection
1.5.2 Lead Content
1.5.3 Chromate Content
1.5.4 Asbestos Content
1.5.5 Mercury Content
1.5.6 Silica
1.5.7 Human Carcinogens
1.6 PACKAGING, LABELING, AND STORAGE
1.7 SAFETY AND HEALTH
1.7.1 Safety Methods Used During Coating Application
1.7.2 Toxic Materials
1.8 ENVIRONMENTAL CONDITIONS
1.8.1 Coatings
1.8.2 Post-Application
1.9 SUSTAINABLE DESIGN REQUIREMENTS
1.9.1 Environmental Data
1.10 SCHEDULING
1.11 COLOR SELECTION
1.12 LOCATION AND SURFACE TYPE TO BE PAINTED
1.12.1 Painting Included
1.12.1.1 Exterior Painting
1.12.1.2 Interior Painting
1.12.2 Painting Excluded
1.12.3 Mechanical and Electrical Painting
1.12.4 Definitions and Abbreviations
1.12.4.1 Batch Quality Conformance Testing
1.12.4.2 Coating
1.12.4.3 DFT or dft
1.12.4.4 DSD
1.12.4.5 EPP
1.12.4.6 EXT
1.12.4.7 INT
1.12.4.8 micron / microns
1.12.4.9 mil / mils
1.12.4.10 mm
1.12.4.11 MPI Gloss Levels
1.12.4.12 MPI System Number
1.12.4.13 Paint
1.12.4.14 REX
1.12.4.15 RIN
PART 2 PRODUCTS
2.1 MATERIALS
PART 3 EXECUTION
3.1 PROTECTION OF AREAS AND SPACES NOT TO BE PAINTED
3.2 SURFACE PREPARATION
3.3 PREPARATION OF METAL SURFACES
3.3.1 New Ferrous Surfaces
3.3.2 Final Ferrous Surface Condition
3.3.3 Galvanized Surfaces
3.3.4 Non-Ferrous Metallic Surfaces
3.3.5 Terne-Coated Metal Surfaces
3.4 PREPARATION OF CONCRETE AND CEMENTITIOUS SURFACE
3.4.1 Concrete and Masonry
3.4.2 Gypsum Board
3.5 PREPARATION OF PLYWOOD SURFACES
3.5.1 New Plywood Surfaces, Except Floors:
3.6 APPLICATION
3.6.1 Coating Application
3.6.2 Mixing and Thinning of Paints
3.6.3 Two-Component Systems
3.6.4 Coating Systems
3.7 COATING SYSTEMS FOR METAL
3.8 COATING SYSTEMS FOR CONCRETE AND CEMENTITIOUS SUBSTRATES
3.9 COATING SYSTEMS FOR PLYWOOD
3.10 PIPING IDENTIFICATION
3.11 INSPECTION AND ACCEPTANCE
3.12 WASTE MANAGEMENT
3.13 PAINT TABLES
3.13.1 EXTERIOR PAINT TABLES
3.13.2 INTERIOR PAINT TABLES

File details come from the government source that posted it.