NCARNG_Wilmington_RC_Addendum_1_Drawings_20170817_Part_2.pdf
PDF 8 MB Posted
- Attached to
- Wilmington Readiness Center
- Solicitation number
- W91242-17-B-0005
About this file
Updated Drawings Part 2 08/17/2017
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
D
C
B
A
2 3 4 5
C p w w o r k i n g g b n a g o l l i n g s j e d
N
C A
R N
G
C I V
I L
S
T O
R M
D
E T
A I L
S d w g
A
M
BID FINAL SUBMITTAL
Designed:
Drawn :
Checked:
Drawing No.:
Date:
Drawing Title:
Scales:
Key Plan:
P R
O J E
T
N
O
W I L M
I N
G T
O N
N
O R
T H
A R
O L I N
A
N A
T I O
N A
L
G
U A
R D
R
E A
D I N
E S
S
C
E N
T E
R
N O
R T
H
C
A R
O L
I N
A
A
R M
Y
N
A T
I O
N A
L
G
U A
R D
03 APRIL 2017
DATEREV DESCRIPTION
501 North Broadway, Saint Louis, Missouri 63102
DISCLAIMER
ATTACHMENT OF THIS SEAL TO THIS DOCUMENT IS MADE ONLY
FOR THE PURPOSE OF AUTHENTICATING THIS DOCUMENT.
RESPONSIBILITY FOR ALL OTHER DOCUMENTS RELATING TO
THIS PROJECT IS DISCLAIMED
REGISTRATION NUMBER:
NC Engineering Firm License No. F-0287
NC Architectural Firm No. 50757
CS711
STORM DRAINAGE
DETAILS
JEG
JEG
TJW
TOP ELEVATION OF STORMWATER
FRONT VIEW
1.0
VARIES
0.75' MIN
EXISTING SLOPES
#5 WASHED STONE
KEYED RIP RAP
STONE
SIDE VIEW
CLASS B RIP-RAP
#5 WASHED
1.0'
0.5'-1'
2 MAX.
STEP SEQUENCE
EXISTING GROUND
1.5'
MAINTENANCE:
INSPECT CHECK DAMS AND CHANNELS DAILY AND REPAIR, AS NECESSARY FOLLOWING EVERY
RAINFALL EVENT OF GREATER THAN 1/2" WITHIN A 24HR PERIOD. CLEAN OUT SEDIMENT, STRAW, LIMBS, OR OTHER DEBRIS THAT COULD CLOG THE CHANNEL WHEN NEEDED.
ANTICIPATE SUBMERGENCE AND DEPOSITION ABOVE THE CHECK DAM AND EROSION FROM HIGH
FLOWS AROUND THE EDGES OF THE DAM. CORRECT ALL DAMAGE IMMEDIATELY. IF SIGNIFICANT EROSION OCCURS BETWEEN DAMS, ADDITIONAL MEASURES CAN BE TAKEN SUCH AS, INSTALLING A PROTECTIVE RIPRAP LINER IN THAT PORTION OF THE CHANNEL (PRACTICE 6.31, RIPRAP-LINE AND
PAVED CHANNELS).
REMOVE SEDIMENT ACCUMULATED BEHIND THE DAMS AS NEEDED TO PREVENT DAMAGE TO
CHANNEL VEGETATION, ALLOW THE CHANNEL TO DRAIN THROUGH THE STONE CHECK DAM, AND
PREVENT LARGE FLOWS FROM CARRYING SEDIMENT OVER THE DAM. ADD STONES TO DAMS AS
NEEDED TO MAINTAIN DESIGN HEIGHT AND CROSS SECTION.
NOTE: REMOVE SEDIMENT ACCUMULATION
FROM BEHIND CHECK DAMS TO PREVENT
DAMAGE TO CHANNEL VEGETATION. FLOW
SHOULD BE MAINTAINED THROUGH THE DAM.
CONSTRUCTION SPECIFICATIONS
1. PLACE STONE TO THE LINES AND DIMENSIONS SHOWN IN THE PLAN ON A FILTER FABRIC FOUNDATION.
2. KEEP THE CENTER STONE SECTION AT LEAST 9 INCHES BELOW NATURAL GROUND LEVEL WHERE THE
DAM ABUTS THE CHANNEL BANKS.
3. EXTEND STONE AT LEAST 1.5 FEET BEYOND THE DITCH BANK TO KEEP WATER FROM CUTTING AROUND
THE ENDS OF THE CHECK DAM.
4. SET SPACING BETWEEN DAMS TO ASSURE THAT THE ELEVATION AT THE TOP OF THE LOWER DAM IS THE
SAME AS THE TOE ELEVATION OF THE UPPER DAM.
5. PROTECT THE CHANNEL AFTER THE LOWEST CHECK DAM FROM HEAVY FLOW THAT COULD CAUSE
EROSION.
6. MAKE SURE THAT THE CHANNEL REACH ABOVE THE MOST UPSTREAM DAM IS STABLE.
7. ENSURE THAT OTHER AREAS OF THE CHANNEL, SUCH AS CULVERT ENTRANCES BELOW THE CHECK
DAMS, ARE NOT SUBJECT TO DAMAGE OR BLOCKAGE FROM DISPLACED STONES.
FILTER FABRIC
FILTER FABRIC
1.0'
NCDEQ COMMENTS1 07/18/17
PERMIT SUBMITTAL
2' MIN.
PLAN VIEW
CROSS SECTION
POSITIVE GRADE 5.0% MAX.
-STABILIZE DIVERSION DITCH WITH TEMPORARY
SEEDING AND EROSION CONTROL NETTING (DOUBLE
STRAW MATT > 0.85 #/SF SHEAR STRENGTH).
STEEP CUT OR
FILL SLOPE
2:1 SLOPE (MAX)
COMPACTED
2' MIN.
18"
UPSLOPE TOE
SIDE SLOPES
2:1 (MAX)
STEEP CUT OR FILL SLOPE
2' MIN.
CONSTRUCTION SPECIFICATIONS
1. REMOVE AND PROPERLY DISPOSE OF ALL TREES, BRUSH, STUMPS, AND OTHER OBJECTIONABLE MATERIAL.
2. ENSURE THAT THE MINIMUM CONSTRUCTED CROSS SECTION MEETS ALL DESIGN REQUIREMENTS.
3. ENSURE THAT THE TOP OF THE DIKE IS NOT LOWER AT ANY POINT THAN THE DESIGN ELEVATION PLUS THE SPECIFIED SETTLEMENT.
4. PROVIDE SUFFICIENT ROOM AROUND DIVERSIONS TO PERMIT MACHINE RE-GRADING AND CLEANOUT.
5. VEGETATE THE RIDGE AND CHANNEL IMMEDIATELY AFTER CONSTRUCTION, UNLESS IT WILL REMAIN IN PLACE LESS THAN 30
WORKING DAYS.
GENERAL NOTES:
1. DIVERSION TO BE USED TO CONVEY SEDIMENT LADEN WATER INTO AN APPROVED EROSION AND SEDIMENT CONTROL BMP.
2. IMMEDIATELY LINE AND STABILIZE BEFORE ANY DOWNSLOPE GRADING BEGINS (STABILIZATION MUST OCCUR BEFORE ISSUANCE OF
A CERTIFICATE OF COMPLIANCE). STABILIZATION METHOD IS BASED ON VELOCITY OF DRAINAGE.
3. DIVERSIONS SHOULD ONLY BE USED FOR DRAINAGE AREAS 5 ACRES OR LESS.
4. MINIMUM LONGITUDINAL SLOPE OF DIVERSION SHALL BE 0.3%.
5. DEPTHS SHOWN SHALL BE FINAL AFTER SETTLEMENT. CONTRACTOR SHALL BE RESPONSIBLE FOR ADJUSTING DITCHES IN FIELD TO
MEET DESIGN CRITERIA IF SETTLEMENT OCCURS.
6. REFER TO SKIMMER BASIN DETAIL FOR DIVERSION DITCH/SKIMMER BASIN ENTRANCE.
MAINTENANCE:
INSPECT TEMPORARY DIVERSIONS DAILY AND REPAIR, AS NECESSARY AND FOLLOWING EVERY RAINFALL EVENT OF GREATER THAN 1/2" WITHIN A 24HR PERIOD. IMMEDIATELY REMOVE SEDIMENT FROM THE FLOW AREA AND REPAIR THE DIVERSION RIDGE. CAREFULLY CHECK OUTLETS AND MAKE TIMELY REPAIRS AS NEEDED. WHEN THE AREA PROTECTED IS PERMANENTLY STABILIZED, REMOVE THE RIDGE AND THE CHANNEL TO BLEND WITH THE NATURAL GROUND LEVEL AND APPROPRIATELY STABILIZE IT.
CS600
DIVERSION DITCH WITH ROCK CHECK DAMS DETAIL
NOT TO SCALE
PERMIT SUBMITTAL
File details come from the government source that posted it. Updated .