Bid Final Submittal Specifications Volume 2 of 2 03 April 2017
Prepared by:
NATIONAL GUARD READINESS CENTER
WILMINGTON, NORTH CAROLINA
National Guard Bureau Project No. 85498371301
North Carolina Army National Guard
National Guard Readiness Center Wilmington, North Carolina Bid Final Submittal 03 April 2017
DIVISION 01 – GENERAL REQUIREMENTS
000104 Seals Page
010000 General Requirements
011000 Summary
012200 Unit Prices
012300 Additive Bid Items (ABI)
012500 Substitution Procedures
012600 Contract Modification Procedures
013100 Project Management and Coordination
013200 Construction Progress Documentation
013233 Photographic Documentation
013300 Submittal Procedures
014000 Quality Requirements
014200 References
014536 Statement of Special Inspections
014537 Schedule of Special Inspections
015000 Temporary Facilities and Controls
015639 Temporary Tree and Plant Protection
016000 Product Requirements
017300 Execution
017419 Construction Waste Management and Disposal
017700 Closeout Procedures
017823 Operation and Maintenance Data
017839 Project Record Documents
017900 Demonstration and Training
018113.13 Sustainable Design Requirements – LEED 2009 for
New Construction and Major Renovations
019113 General Commissioning Requirements
DIVISION 02 – EXISTING CONDITIONS
024116 Structure Demolition 024117 Asbestos and Regulated Material Removal 024117b Asbestos Survey Wilmington Dec 2007 Attachment 023132 Geotechnical Data 023132b Subsurface Exploration and Geotechnical Analysis
TOC PAGE NO. i
Bid Final Submittal 03 April 2017
DIVISION 03 – CONCRETE
033000 Cast-In-Place Concrete
033543 Polished Concrete Finishing
DIVISION 04 – MASONRY
042000 Unit Masonry
047200 Cast Stone Masonry
DIVISION 05 – METALS
051200 Structural Steel Framing
052100 Steel Joist Framing
053100 Steel Decking
054000 Cold-Formed Metal Framing
055000 Metal Fabrications
055015 Aluminum Ladders
055113 Metal Pan Stairs
055213 Pipe and Tube Railings
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
061053 Miscellaneous Rough Carpentry
061600 Sheathing
064116 Plastic-Laminate-Faced Architectural Cabinets
066400 Plastic Paneling
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
071326 Self-Adhering Sheet Waterproofing
072100 Thermal Insulation
072119 Foamed-In-Place Insulation
072413 Polymer-Based Exterior Finish System (EFS)
072726 Fluid-Applied Membrane Air Barriers
074113.19 Batten-Seam Metal Roof Panels
074213.13 Formed Metal Wall Panels
074213.23 Metal Composite Material Wall Panels
074293 Soffit Panels
TOC PAGE NO. ii
Bid Final Submittal 03 April 2017
075419 Polyvinyl Chloride (PVC) Roofing
076200 Sheet Metal Flashing and Trim
077100 Roof Specialties
077200 Roof Accessories
077210 Rooftop Fall Arrest System
078100 Applied Fireproofing
078123 Intumescent Fireproofing
078413 Penetration Firestopping
078446 Fire-Resistive Joint Systems
079100 Preformed Foam Joint Seals
079200 Joint Sealants
079219 Acoustical Joint Sealants
DIVISION 08 – OPENINGS
081113 Hollow Metal Doors and Frames
081416 Flush Wood Doors
083113 Access Doors and Frames
083323 Overhead Coiling Doors
083459 Vault Doors and Day Gates
084113 Aluminum-Framed Entrances and Storefronts
084413 Glazed Aluminum Curtain Walls
087100 Door Hardware
087113 Automatic Door Operators
088000 Glazing
088300 Mirrors
089119 Fixed Louvers
089500 Blast Resistance
DIVISION 09 – FINISHES
092116.23 Gypsum Board Shaft Wall Assemblies
092216 Non-Structural Metal Framing
092900 Gypsum Board
093013 Ceramic Tiling
095000 Channeled Wood Panel Ceilings
TOC PAGE NO. iii
Bid Final Submittal 03 April 2017
095010 Wood Panel Ceilings
095113 Acoustical Panel Ceilings
096513 Resilient Base and Accessories
096519 Resilient Tile Flooring
096536 Static-Control Resilient Flooring
096566 Resilient Athletic Flooring
096623 Resinous Matrix Terrazzo Flooring
096723 Resinous Flooring
096813 Tile Carpeting
097230 Dry Erase Wallcovering
097714 Wood Veneer Wall Panels
097715 Wood Veneer Wall Panels
098433 Sound-Absorbing Wall Units
099113 Exterior Painting
099123 Interior Painting
099646 Intumescent Painting
099800 Coatings For CMU Veneer
DIVISION 10 – SPECIALTIES
101100 Visual Display Units
101419 Dimensional Letter Signage
101423.16 Room-Identification Panel Signs
102113.19 Plastic Toilet Compartments
102213 Wire Mesh Partitions
102239 Folding Panel Partitions
102600 Wall and Door Protection
102800 Toilet, Bath, and Laundry Accessories
104313 Defibrillator Cabinets and Defibrillators
104413 Fire Protection Cabinets
104416 Fire Extinguishers
105113 Metal Lockers
105613 Metal Storage Shelving
107516 Ground-Set Flagpoles
109160 Ventilated Wire Shelving
TOC PAGE NO. iv
Bid Final Submittal 03 April 2017
109900 Miscellaneous Items
DIVISION 11 – EQUIPMENT
114000 Food Service Equipment
115213 Projection Screens
DIVISION 12 – FURNISHINGS
122413 Roller Window Shades
123661.16 Solid Surfacing Countertops
124813 Entrance Floor Mats and Frames
DIVISION 13 – SPECIAL CONSTRUCTION
133423.10 Fabricated Storage Building
DIVISION 14 - CONVEYING EQUIPMENT
142100 Electric Traction Elevators
DIVISION 21 - FIRE SUPPRESSION
210517 Sleeves and Sleeve Seals for Fire-Suppression Piping
210518 Escutcheons for Fire-Suppression Piping
210548 Vibration and Seismic Controls for Fire-Suppression Piping and Equipment
211119 Fire Department Connections
211313 Wet Pipe Sprinkler Systems
213113 Electric Drive, Centrifugal Fire Pumps
213413 Pressure-Maintenance Pumps
DIVISION 22 – PLUMBING
220513 Common Motor Requirements for Plumbing Equipment
220517 Sleeves and Sleeve Seals for Plumbing Piping
220518 Escutcheons for Plumbing Piping
220519 Meters and Gages for Plumbing Piping
220523.12 Ball Valves for Plumbing Piping
220523.13 Butterfly Valves for Plumbing Piping
220523.14 Check Valves for Plumbing Piping
TOC PAGE NO. v
Bid Final Submittal 03 April 2017
220529 Hangers and Supports for Plumbing Piping and Equipment
220548 Vibration Controls for Plumbing Piping and Equipment
220553 Identification for Plumbing Piping and Equipment
220719 Plumbing Piping Insulation
220800 Commissioning of Plumbing Systems
221116 Domestic Water Piping
221119 Domestic Water Piping Specialties
221123.21 Inline, Domestic-Water Pumps
221316 Sanitary Waste and Vent Piping
221319 Sanitary Waste Piping Specialties
221319.13 Sanitary Drains
221323 Sanitary Waste Interceptors
221429 Sump Pumps
221513 General-Service Compressed-Air Piping
221519 General-Service Packaged Air Compressors and Receivers
223300 Electric, Domestic-Water Heaters
224213.13 Commercial Water Closets
224213.16 Commercial Urinals
224216.13 Commercial Lavatories
224216.16 Commercial Sinks
224223 Commercial Showers
224500 Emergency Plumbing Fixtures
224713 Drinking Fountains
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
230511 HVAC Electrical Provisions
230513 Common Motor Requirements for HVAC Equipment
230517 Sleeves and Sleeve Seals for HVAC Piping
230518 Escutcheons for HVAC Piping
230529 Hangers and Supports for HVAC Piping and Equipment
230548 Vibration Controls
230553 Identification for HVAC Piping and Equipment
230593 Testing, Adjusting, and Balancing for HVAC
TOC PAGE NO. vi
Bid Final Submittal 03 April 2017
230713 Duct Insulation
230719 HVAC Piping Insulation
230800 HVAC Systems Commissioning Requirements
230923 Direct Digital Control (DDC) System for HVAC
230923.12 Control Dampers
230923.19 Moisture Instruments
230923.27 Temperature Instruments
232113 Hydronic Piping
232300 Refrigerant Piping
232300.0011 Overhead Vehicle Tailpipe Exhaust Removal System(s)
233113 Metal Ducts
233300 Air Duct Accessories
233346 Flexible Ducts
233416 Centrifugal HVAC Fans
233371.13 Air Diffusers
233713.23 Registers and Grilles
233723 HVAC Gravity Ventilators
236200 Packaged Compressor and Condenser Units
237223 Air-to-Air Energy Recovery Equipment
237433 Dedicated Outdoor-Air Units
238126 Split-System Air Conditioners
238219 Fan Coil Units
238239.19 Wall, Ceiling and Duct Unit Heaters
238416.16 Indoor, Mechanical Dehumidification Units
DIVISION 26 – ELECTRICAL
260519 Low-Voltage Electrical Power Conductors and Cables
260526 Grounding and Bonding for Electrical Systems
260529 Hangers and Supports for Electrical Systems
260533 Raceways and Boxes for Electrical Systems
260543 Underground Ducts and Race Ways for Electrical Systems
260544 Sleeves and Sleeve Seals for Electrical Raceways and Cabling
260553 Identification for Electrical Systems
TOC PAGE NO. vii
National Guard Readiness Center Jacobs Project No. F6W72100
Bid Final Submittal 03 April 2017
260573.13 Short-Circuit Studies
260573.16 Coordination Studies
260573.19 Arc-Flash Hazard Analysis
260800 Commissioning of Electrical Systems
260923 Lighting Control Devices
260943.23 Relay-Based Lighting Controls
262213 Low-Voltage Distribution Transformers
262413 Switchboards
262416 Panelboards
262726 Wiring Devices 262813 Fuses
262816 Enclosed Switches and Circuit Breakers
262913.03 Manual and Magnetic Motor Controllers
262933 Controllers For Fire-Pump Drivers
263213.13 Diesel Emergency Engine Generators
263323.11 Central Battery Equipment for Emergency Lighting
263600 Transfer Switches
264113 Lightning Protection For Structures
264313 Surge Protection For Low-Voltage Electrical Power Circuits
265119 LED Interior Lighting
265213 Emergency and Exit Lighting
265619 LED Exterior Lighting
DIVISION 27 – COMMUNICATIONS
270526 Grounding and Bonding for Communications Systems
270528 Pathways for Communications Systems
270529 Hangers and Supports for Communications Systems
270536 Cable Trays for Communication Systems
270543 Underground Pathways and Structures for Communication Systems
270544 Sleeves and Sleeve Seals for Communications
Pathways and Cabling
270548.16 Seismic Controls for Communications Systems
270553 Identification for Communications Systems
271100 Communications Equipment Room Fittings
TOC PAGE NO. viii
National Guard Readiness Center Jacobs Project No. F6W72100
Bid Final Submittal 03 April 2017
271116 Communications Racks, Frames and Enclosures
271313 Communications Copper Backbone Cabling
271323 Communications Optical Fiber Backbone Cabling
271513 Communications Copper Horizontal Cabling
275116 Public Address Systems
DIVISION 28 – Electronic Safety and Security
283111 Digital, Addressable Fire-Alarm and Mass Notification System
DIVISION 31 – Earthwork
311000 Site Clearing
312000 Earth Moving
312500 Erosion Control
313116 Termite Control
DIVISION 32 – Exterior Improvements
321123 Dense Graded Base
321216 Asphalt Pavement
321313 Portland Cement Concrete Paving
321373 Concrete Paving Joint Sealants
321713 Parking Bumpers
321723 Pavement Markings (For Building Interior)
323113 Fencing and Gates
329113 Soil Preparation
329119 Landscape Finish Grading
329200 Turf and Grasses
329300 Plants
DIVISION 33 – Utilities
330500 Common Work Results for Utilities
331100 Water Distribution
333100 Sanitary Sewer Systems
334100 Storm Utility Drainage Piping
TOC PAGE NO. ix
Bid Final Submittal 03 April 2017
SECTION 210517 - SLEEVES AND SLEEVE SEALS FOR FIRE-SUPPRESSION PIPING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Sleeves.
2. Sleeve-seal systems.
3. Sleeve-seal fittings.
4. Grout.
5. Silicone sealants.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
1.4 INFORMATIONAL SUBMITTALS
A. Field quality-control reports.
PART 2 - PRODUCTS
2.1 SLEEVES
A. Cast-Iron Pipe Sleeves: Cast or fabricated of cast or ductile iron and equivalent to ductile-iron pressure pipe, with plain ends and integral waterstop.
2.2 SLEEVE-SEAL SYSTEMS
A. Description:
1. Modular sealing-element unit, designed for field assembly, for filling annular space between piping and sleeve.
2. Designed to form a hydrostatic seal of 20 psig minimum.
SLEEVES AND SLEEVE SEALS FOR FIRE-SUPPRESSION PIPING 210517 - 1
3. Sealing Elements: EPDM-rubber interlocking links shaped to fit surface of pipe.
Include type and number required for pipe material and size.
4. Connecting Bolts and Nuts: Carbon steel, with corrosion-resistant coating, ASTM B 633 of length required to secure pressure plates to sealing elements.
2.3 SLEEVE-SEAL FITTINGS
A. Description: Manufactured plastic, sleeve-type, waterstop assembly made for imbedding in concrete slab or wall.
B. Plastic or rubber waterstop collar with center opening to match piping OD.
2.4 GROUT
A. Description: Nonshrink, for interior and exterior sealing openings in non-fire-rated walls or floors.
B. Standard: ASTM C 1107/C 1107M, Grade B, post-hardening and volume-adjusting, dry, hydraulic-cement grout.
C. Design Mix: 5000-psi, 28-day compressive strength.
D. Packaging: Premixed and factory packaged.
2.5 SILICONE SEALANTS
A. Silicone, S, NS, 25, NT: Single-component, nonsag, plus 25 percent and minus 25 percent movement capability, nontraffic-use, neutral-curing silicone joint sealant, ASTM C 920, Type S, Grade NS, Class 25, Use NT.
PART 3 - EXECUTION
3.1 SLEEVE INSTALLATION
A. Install sleeves for piping passing through penetrations in floors, partitions, roofs, and walls.
B. For sleeves that will have sleeve-seal system installed, select sleeves of size large enough to provide 2-inch annular clear space between piping and concrete slabs and walls.
1. Sleeves are not required for core-drilled holes.
C. Install sleeves in concrete floors, concrete roof slabs, and concrete walls as new slabs and walls are constructed.
SLEEVES AND SLEEVE SEALS FOR FIRE-SUPPRESSION PIPING 210517 - 2
1. Permanent sleeves are not required for holes in slabs formed by molded-PE or - PP sleeves.
2. Cut sleeves to length for mounting flush with both surfaces.
a. Exception: Extend sleeves installed in floors of mechanical equipment areas or other wet areas 2 inches above finished floor level.
3. Using grout or silicone sealant, seal space outside of sleeves in slabs and walls without sleeve-seal system.
D. Install sleeves for pipes passing through interior partitions.
1. Cut sleeves to length for mounting flush with both surfaces.
2. Install sleeves that are large enough to provide 1/4-inch (6.4-mm) annular clear space between sleeve and pipe or pipe insulation.
3. Seal annular space between sleeve and piping or piping insulation; use joint sealants appropriate for size, depth, and location of joint.
E. Fire-Resistance-Rated Penetrations, Horizontal Assembly Penetrations, and Smoke Barrier Penetrations: Maintain indicated fire or smoke rating of walls, partitions, ceilings, and floors at pipe penetrations. Seal pipe penetrations with fire- and smoke-stop materials. Comply with requirements for firestopping and fill materials specified in Section 078413 "Penetration Firestopping."
3.2 SLEEVE-SEAL-SYSTEM INSTALLATION
A. Install sleeve-seal systems in sleeves in exterior concrete walls and slabs-on-grade at service piping entries into building.
B. Select type, size, and number of sealing elements required for piping material and size and for sleeve ID or hole size. Position piping in center of sleeve. Center piping in penetration, assemble sleeve-seal system components, and install in annular space between piping and sleeve. Tighten bolts against pressure plates that cause sealing elements to expand and make a watertight seal.
3.3 SLEEVE-SEAL-FITTING INSTALLATION
A. Install sleeve-seal fittings in new walls and slabs as they are constructed.
B. Assemble fitting components of length to be flush with both surfaces of concrete slabs and walls. Position waterstop flange to be centered in concrete slab or wall.
C. Secure nailing flanges to concrete forms.
D. Use grout or silicone sealant, to seal the space around outside of sleeve-seal fittings.
SLEEVES AND SLEEVE SEALS FOR FIRE-SUPPRESSION PIPING 210517 - 3
Bid Final Submittal 03 April 2017
3.4 FIELD QUALITY CONTROL
A. Perform the following tests and inspections:
1. Leak Test: After allowing for a full cure, test sleeves and sleeve seals for leaks.
Repair leaks and retest until no leaks exist.
B. Sleeves and sleeve seals will be considered defective if they do not pass tests and inspections.
C. Prepare test and inspection reports.
3.5 SLEEVE AND SLEEVE-SEAL SCHEDULE
A. Use sleeves and sleeve seals for the following piping-penetration applications:
1. Exterior Concrete Walls above Grade:
a. Piping Smaller Than NPS 6 : Steel pipe sleeves.
b. Piping NPS 6 and Larger: Steel pipe sleeves.
2. Concrete Slabs-on-Grade:
a. Piping Smaller Than NPS 6: Steel pipe sleeves with sleeve-seal system.
1) Select sleeve size to allow for 2-inch annular clear space between piping and sleeve for installing sleeve-seal system.
b. Piping NPS 6 and Larger: Steel pipe sleeves with sleeve-seal system.
1) Select sleeve size to allow for 2-inch annular clear space between piping and sleeve for installing sleeve-seal system.
3. Concrete Slabs above Grade:
a. Piping Smaller Than NPS 6 : Steel pipe sleeves.
b. Piping NPS 6 and Larger: Steel pipe sleeves.
4. Interior Partitions:
a. Piping Smaller Than NPS 6: Steel pipe sleeves.
b. Piping NPS 6 and Larger: Galvanized-steel sheet sleeves.
END OF SECTION 210517
SLEEVES AND SLEEVE SEALS FOR FIRE-SUPPRESSION PIPING 210517 - 4
SECTION 210518 - ESCUTCHEONS FOR FIRE-SUPPRESSION PIPING
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Escutcheons.
2. Floor plates.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
PART 2 - PRODUCTS
2.1 ESCUTCHEONS
A. One-Piece, Cast-Brass Type: With polished, chrome-plated finish and setscrew fastener.
2.2 FLOOR PLATES
A. Split Floor Plates: Steel with concealed hinge.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install escutcheons for piping penetrations of walls, ceilings, and finished floors.
B. Install escutcheons with ID to closely fit around pipe, tube, and insulation of piping and with OD that completely covers opening.
ESCUTCHEONS FOR FIRE-SUPPRESSION PIPING 210518 - 1
Bid Final Submittal 03 April 2017
1. Escutcheons for New Piping:
a. Piping with Fitting or Sleeve Protruding from Wall: One-piece, deep pattern.
b. Bare Piping at Wall and Floor Penetrations in Finished Spaces: One-piece cast brass with polished, chrome-plated finish.
c. Bare Piping at Ceiling Penetrations in Finished Spaces: One-piece cast brass with polished, chrome-plated finish.
d. Bare Piping in Unfinished Service Spaces:
e. Bare Piping in Unfinished Service Spaces: One-piece cast brass with rough-brass finish.
f. Bare Piping in Equipment Rooms: One-piece cast brass with rough-brass finish.
C. Install floor plates for piping penetrations of equipment-room floors.
D. Install floor plates with ID to closely fit around pipe, tube, and insulation of piping and with OD that completely covers opening.
1. New Piping One-piece, floor plate.
2. Existing Piping: Split floor plate.
3.2 FIELD QUALITY CONTROL
A. Using new materials, replace broken and damaged escutcheons and floor plates.
END OF SECTION 210518
ESCUTCHEONS FOR FIRE-SUPPRESSION PIPING 210518 - 2
SECTION 210548 - VIBRATION AND SEISMIC CONTROLS FOR FIRE-SUPPRESSION
PIPING AND EQUIPMENT
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Elastomeric isolation pads.
2. Elastomeric isolation mounts.
3. Restrained elastomeric isolation mounts.
4. Pipe-riser resilient supports.
5. Resilient pipe guides.
6. Elastomeric hangers.
7. Snubbers.
8. Restraint channel bracings.
9. Seismic-restraint accessories.
10. Mechanical anchor bolts.
11. Adhesive anchor bolts.
B. Related Requirements:
1. Section 220548 "Vibration and Seismic Controls for Plumbing Piping and Equipment" for devices for plumbing equipment and systems.
2. Section 230548 "Vibration and Seismic Controls for HVAC" for devices for HVAC equipment and systems.
1.3 DEFINITIONS
A. IBC: International Building Code.
B. ICC-ES: ICC-Evaluation Service.
C. OSHPD: Office of Statewide Health Planning & Development (for the State of California).
VIBRATION AND SEISMIC CONTROLS FOR FIRE-SUPPRESSION
210548 - 1
Bid Final Submittal 03 April 2017
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include rated load, rated deflection, and overload capacity for each vibration isolation device.
2. Illustrate and indicate style, material, strength, fastening provision, and finish for each type and size of vibration isolation device and seismic-restraint component required.
a. Tabulate types and sizes of seismic restraints, complete with report numbers and rated strength in tension and shear as evaluated by an agency acceptable to authorities having jurisdiction.
b. Annotate to indicate application of each product submitted and compliance with requirements.
3. Interlocking Snubbers: Include ratings for horizontal, vertical, and combined loads.
B. Delegated-Design Submittal: For each vibration isolation and seismic-restraint device.
1. Include design calculations and details for selecting vibration isolators and seismic restraints complying with performance requirements, design criteria, and analysis data signed and sealed by the qualified professional engineer responsible for their preparation.
2. Design Calculations: Calculate static and dynamic loading due to equipment weight and operation, due to seismic forces required to select vibration isolators, and due to seismic restraints.
3. Riser Supports: Include riser diagrams and calculations showing anticipated expansion and contraction at each support point, initial and final loads on building structure, spring deflection changes, and seismic loads. Include certification that riser system was examined for excessive stress and that none exists.
4. Seismic-Restraint Details:
a. Design Analysis: To support selection and arrangement of seismic restraints. Include calculations of combined tensile and shear loads.
b. Details: Indicate fabrication and arrangement. Detail attachments of restraints to the restrained items and to the structure. Show attachment locations, methods, and spacings. Identify components, list their strengths, and indicate directions and values of forces transmitted to the structure during seismic events. Indicate association with vibration isolation devices.
c. Coordinate seismic-restraint and vibration isolation details with wind-restraint details required for equipment mounted outdoors. Comply with requirements in other Sections for equipment mounted outdoors.
d. Preapproval and Evaluation Documentation: By an agency acceptable to authorities having jurisdiction, showing maximum ratings of restraint items and the basis for approval (tests or calculations).
VIBRATION AND SEISMIC CONTROLS FOR FIRE-SUPPRESSION
210548 - 2
Bid Final Submittal 03 April 2017
1.5 INFORMATIONAL SUBMITTALS
A. Coordination Drawings: Show coordination of vibration isolation device installation and seismic bracing for fire-suppression piping and equipment with other systems and equipment in the vicinity, including other supports and restraints, if any.
B. Qualification Data: For professional engineer and testing agency.
C. Welding certificates.
D. Field quality-control reports.
1.6 QUALITY ASSURANCE
A. Testing Agency Qualifications: An independent agency, with the experience and capability to conduct the testing indicated, that is an NRTL as defined by OSHA in 29 CFR 1910.7 and that is acceptable to authorities having jurisdiction.
B. Comply with seismic-restraint requirements in the IBC unless requirements in this Section are more stringent.
C. Welding Qualifications: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding Code - Steel."
D. Seismic-restraint devices shall have horizontal and vertical load testing and analysis and shall bear anchorage preapproval OPA number from OSHPD, preapproval by ICC- ES, or preapproval by another agency acceptable to authorities having jurisdiction, showing maximum seismic-restraint ratings. Ratings based on independent testing are preferred to ratings based on calculations. If preapproved ratings are unavailable, submittals based on independent testing are preferred. Calculations (including combining shear and tensile loads) to support seismic-restraint designs must be signed and sealed by a qualified professional engineer.
PART 2 - PRODUCTS
2.1 ELASTOMERIC ISOLATION PADS
A. Elastomeric Isolation Pads:.
1. Fabrication: Single or multiple layers of sufficient durometer stiffness for uniform loading over pad area.
2. Size: Factory or field cut to match requirements of supported equipment.
3. Pad Material: Oil and water resistant with elastomeric properties.
4. Surface Pattern: Smooth Ribbed Waffle pattern.
5. Infused nonwoven cotton or synthetic fibers.
6. Load-bearing metal plates adhered to pads.
7. Sandwich-Core Material: Resilient and elastomeric.
a. Surface Pattern: Smooth Ribbed Waffle pattern.
VIBRATION AND SEISMIC CONTROLS FOR FIRE-SUPPRESSION
210548 - 3
b. Infused nonwoven cotton or synthetic fibers.
2.2 ELASTOMERIC ISOLATION MOUNTS
A. Double-Deflection, Elastomeric Isolation Mounts:
1. Mounting Plates:
a. Top Plate: Encapsulated steel load transfer top plates, factory drilled and threaded with threaded studs or bolts.
b. Baseplate: Encapsulated steel bottom plates with holes provided for anchoring to support structure.
2. Elastomeric Material: Molded, oil-resistant rubber, neoprene, or other elastomeric material.
2.3 RESTRAINED ELASTOMERIC ISOLATION MOUNTS
A. Restrained Elastomeric Isolation Mounts:
1. Description: All-directional isolator with seismic restraints containing two separate and opposing elastomeric elements that prevent central threaded element and attachment hardware from contacting the housing during normal operation.
a. Housing: Cast-ductile iron or welded steel.
b. Elastomeric Material: Molded, oil-resistant rubber, neoprene or other elastomeric material.
2.4 PIPE-RISER RESILIENT SUPPORT
A. Description: All-directional, acoustical pipe anchor consisting of two steel tubes separated by a minimum 1/2-inch- (13-mm-) thick neoprene.
1. Vertical-Limit Stops: Steel and neoprene vertical-limit stops arranged to prevent vertical travel in both directions.
2. Maximum Load Per Support: 500 psig (3.45 MPa) on isolation material providing equal isolation in all directions.
2.5 RESILIENT PIPE GUIDES
A. Description: Telescopic arrangement of two steel tubes or post-and-sleeve arrangement separated by a minimum 1/2-inch- (13-mm-) thick neoprene.
1. Factory-Set Height Guide with Shear Pin: Shear pin shall be removable and reinsertable to allow for selection of pipe movement. Guides shall be capable of motion to meet location requirements.
VIBRATION AND SEISMIC CONTROLS FOR FIRE-SUPPRESSION
210548 - 4
Bid Final Submittal 03 April 2017
2.6 ELASTOMERIC HANGERS
A. Elastomeric Mount in a Steel Frame with Upper and Lower Steel Hanger Rods:.
1. Frame: Steel, fabricated with a connection for an upper threaded hanger rod and an opening on the underside to allow for a maximum of 30 degrees of angular lower hanger-rod misalignment without binding or reducing isolation efficiency.
2. Dampening Element: Molded, oil-resistant rubber, neoprene, or other elastomeric material with a projecting bushing for the underside opening preventing steel to steel contact.
2.7 SNUBBERS
A. Description: Factory fabricated using welded structural-steel shapes and plates, anchor bolts, and replaceable resilient isolation washers and bushings.
1. Anchor bolts for attaching to concrete shall be seismic-rated, drill-in, and stud-wedge or female-wedge type.
2. Resilient Isolation Washers and Bushings: Oil- and water-resistant neoprene.
3. Maximum 1/4-inch (6-mm) air gap, and minimum 1/4-inch- (6-mm-) thick resilient cushion.
2.8 RESTRAINT CHANNEL BRACINGS
A. Description: MFMA-4, shop- or field-fabricated bracing assembly made of slotted steel channels with accessories for attachment to braced component at one end and to building structure at the other end and other matching components and with corrosion-resistant coating; rated in tension, compression, and torsion forces.
2.9 SEISMIC-RESTRAINT ACCESSORIES
A. Hanger-Rod Stiffener: Steel tube or steel slotted-support-system sleeve with internally bolted connections. Reinforcing steel angle clamped to hanger rod.
B. Hinged and Swivel Brace Attachments: Multifunctional steel connectors for attaching hangers to rigid channel bracings.
C. Bushings for Floor-Mounted Equipment Anchor Bolts: Neoprene bushings designed for rigid equipment mountings, and matched to type and size of anchor bolts and studs.
D. Bushing Assemblies for Wall-Mounted Equipment Anchorage: Assemblies of neoprene elements and steel sleeves designed for rigid equipment mountings, and matched to type and size of attachment devices used.
E. Resilient Isolation Washers and Bushings: One-piece, molded, oil- and water-resistant neoprene, with a flat washer face.
VIBRATION AND SEISMIC CONTROLS FOR FIRE-SUPPRESSION
210548 - 5
Bid Final Submittal 03 April 2017
2.10 MECHANICAL ANCHOR BOLTS
A. Mechanical Anchor Bolts: Drilled-in and stud-wedge or female-wedge type in zinc-coated steel for interior applications and stainless steel for exterior applications. Select anchor bolts with strength required for anchor and as tested according to ASTM E 488.
2.11 ADHESIVE ANCHOR BOLTS
A. Adhesive Anchor Bolts: Drilled-in and capsule anchor system containing PVC or urethane methacrylate-based resin and accelerator, or injected polymer or hybrid mortar adhesive. Provide anchor bolts and hardware with zinc-coated steel for interior applications and stainless steel for exterior applications. Select anchor bolts with strength required for anchor and as tested according to ASTM E 488.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and equipment to receive vibration isolation and seismic-control devices for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.
B. Examine roughing-in of reinforcement and cast-in-place anchors to verify actual locations before installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 APPLICATIONS
A. Multiple Pipe Supports: Secure pipes to trapeze member with clamps approved for application by an agency acceptable to authorities having jurisdiction.
B. Hanger-Rod Stiffeners: Install hanger-rod stiffeners where indicated or scheduled on Drawings to receive them and where required to prevent buckling of hanger rods due to seismic forces.
C. Strength of Support and Seismic-Restraint Assemblies: Where not indicated, select sizes of components so strength is adequate to carry present and future static and seismic loads within specified loading limits.
3.3 VIBRATION CONTROL AND SEISMIC-RESTRAINT DEVICE INSTALLATION
A. Coordinate the location of embedded connection hardware with supported equipment attachment and mounting points and with requirements for concrete reinforcement and formwork specified in Section 033000 "Cast-in-Place Concrete."
VIBRATION AND SEISMIC CONTROLS FOR FIRE-SUPPRESSION
210548 - 6
B. Installation of vibration isolators must not cause any change of position of equipment, piping, or ductwork resulting in stresses or misalignment.
C. Comply with requirements in Section 077200 "Roof Accessories" for installation of equipment supports and roof penetrations.
D. Equipment Restraints:
1. Install seismic snubbers on fire-suppression equipment mounted on vibration isolators. Locate snubbers as close as possible to vibration isolators and bolt to equipment base and supporting structure.
2. Install resilient bolt isolation washers on equipment anchor bolts where clearance between anchor and adjacent surface exceeds 0.125 inch (3.2 mm).
3. Install seismic-restraint devices using methods approved by an agency acceptable to authorities having jurisdiction that provides required submittals for component.
E. Piping Restraints:
1. Comply with requirements in MSS SP-127.
2. Space lateral supports a maximum of 40 feet (12 m) o.c., and longitudinal supports a maximum of 80 feet (24 m) o.c.
3. Brace a change of direction longer than 12 feet (3.7 m).
F. Install seismic-restraint devices using methods approved by an agency acceptable to authorities having jurisdiction that provides required submittals for component.
G. Install bushing assemblies for anchor bolts for floor-mounted equipment, arranged to provide resilient media between anchor bolt and mounting hole in concrete base.
H. Install bushing assemblies for mounting bolts for wall-mounted equipment, arranged to provide resilient media where equipment or equipment-mounting channels are attached to wall.
I. Attachment to Structure: If specific attachment is not indicated, anchor bracing to structure at flanges of beams, at upper truss chords of bar joists, or at concrete members.
J. Drilled-in Anchors:
1. Identify position of reinforcing steel and other embedded items prior to drilling holes for anchors. Do not damage existing reinforcing or embedded items during coring or drilling. Notify the structural engineer if reinforcing steel or other embedded items are encountered during drilling. Locate and avoid prestressed tendons, electrical and telecommunications conduit, and gas lines.
2. Do not drill holes in concrete or masonry until concrete, mortar, or grout has achieved full design strength.
3. Wedge Anchors: Protect threads from damage during anchor installation. Heavy-duty sleeve anchors shall be installed with sleeve fully engaged in the structural element to which anchor is to be fastened.
VIBRATION AND SEISMIC CONTROLS FOR FIRE-SUPPRESSION
210548 - 7
4. Adhesive Anchors: Clean holes to remove loose material and drilling dust prior to installation of adhesive. Place adhesive in holes proceeding from the bottom of the hole and progressing toward the surface in such a manner as to avoid introduction of air pockets in the adhesive.
5. Set anchors to manufacturer's recommended torque, using a torque wrench.
6. Install zinc-coated steel anchors for interior and stainless-steel anchors for exterior applications.
3.4 ACCOMMODATION OF DIFFERENTIAL SEISMIC MOTION
A. Install flexible connections in piping where they cross seismic joints, where adjacent sections or branches are supported by different structural elements, and where the connections terminate with connection to equipment that is anchored to a different structural element from the one supporting the connections as they approach equipment. Comply with requirements in "Section 211313 "Wet-Pipe Sprinkler Systems," for piping flexible connections.
3.5 FIELD QUALITY CONTROL
A. Testing Agency: Engage a qualified testing agency to perform tests and inspections.
B. Perform tests and inspections.
C. Tests and Inspections:
1. Provide evidence of recent calibration of test equipment by a testing agency acceptable to authorities having jurisdiction.
2. Schedule test with Owner, through Architect, before connecting anchorage device to restrained component (unless postconnection testing has been approved), and with at least seven days' advance notice.
3. Obtain Architect's approval before transmitting test loads to structure. Provide temporary load-spreading members.
4. Test at least four of each type and size of installed anchors and fasteners selected by Architect.
5. Test to 90 percent of rated proof load of device.
6. Measure isolator restraint clearance.
7. Measure isolator deflection.
8. Verify snubber minimum clearances.
D. Remove and replace malfunctioning units and retest as specified above.
E. Prepare test and inspection reports.
END OF SECTION 210548
VIBRATION AND SEISMIC CONTROLS FOR FIRE-SUPPRESSION
210548 - 8
SECTION 211119 – FIRE DEPARTMENT CONNECTIONS
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Exposed-type fire-department connections.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for each fire-department connection.
PART 2 - PRODUCTS
2.1 EXPOSED-TYPE FIRE-DEPARTMENT CONNECTION
A. Standard: UL 405.
B. Type: Exposed, projecting, for wall mounting.
C. Pressure Rating: 175 psig minimum.
D. Body Material: Corrosion-resistant metal.
E. Inlet: 5 inch brass with a 30 degree down elbow storz connection matching local fire-department sizes. Include extension pipe nipples, brass lugged swivel connections, and check devices or clappers.
F. Caps: Brass, lugged type, with gasket and chain.
G. Escutcheon Plate: Round, brass, wall type.
H. Outlet: Back, with pipe threads.
FIRE DEPARTMENT CONNECTIONS 211119 - 1
I. Number of Inlets: One.
J. Escutcheon Plate Marking: Similar to "AUTO SPKR."
K. Finish: Rough brass or bronze.
L. Outlet Size: NPS 6.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of fire-department connections.
B. Examine roughing-in for fire-suppression standpipe system to verify actual locations of piping connections before fire-department connection installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Install wall-type fire-department connections.
B. Install six protective pipe bollards around each fire-department connection. Comply with requirements for bollards in Section 055000 "Metal Fabrications."
C. Install automatic (ball-drip) drain valve at each check valve for fire-department connection.
END OF SECTION 211119
FIRE DEPARTMENT CONNECTIONS 211119 - 2
SECTION 211313 - WET-PIPE SPRINKLER SYSTEMS
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Pipes, fittings, and specialties.
2. Cover system for sprinkler piping.
3. Specialty valves.
4. Sprinklers.
5. Alarm devices.
6. Manual control stations.
7. Control panels.
8. Pressure gages.
B. Related Requirements:
1. Section 211119 "Fire Department Connections" for exposed-, flush-, and yard-type fire department connections.
1.3 DEFINITIONS
A. Standard-Pressure Sprinkler Piping: Wet-pipe sprinkler system piping designed to operate at working pressure of 175-psig maximum.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include rated capacities, operating characteristics, electrical characteristics, and furnished specialties and accessories.
B. Shop Drawings: For wet-pipe sprinkler systems.
1. Include plans, elevations, sections, and attachment details.
2. Include diagrams for power, signal, and control wiring.
WET-PIPE SPRINKLER SYSTEMS 211313 - 1
Bid Final Submittal 03 April 2017
C. Delegated-Design Submittal: For wet-pipe sprinkler systems indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.
1.5 INFORMATIONAL SUBMITTALS
A. Coordination Drawings: Sprinkler systems, drawn to scale, on which the following items are shown and coordinated with each other, using input from installers of the items involved:
1. Domestic water piping.
2. Compressed air piping.
3. HVAC hydronic piping.
4. Items penetrating finished ceiling include the following:
a. Lighting fixtures.
b. Air outlets and inlets.
B. Qualification Data: For qualified Installer and professional engineer.
C. Design Data:
1. Approved Sprinkler Piping Drawings: Working plans, prepared according to NFPA 13, that have been approved by authorities having jurisdiction, including hydraulic calculations if applicable.
D. Welding certificates.
E. Field Test Reports:
1. Indicate and interpret test results for compliance with performance requirements and as described in NFPA 13. Include "Contractor's Material and Test Certificate for Aboveground Piping."
2. Fire-hydrant flow test report.
F. Field quality-control reports.
1.6 CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data: For wet-pipe sprinkler systems and specialties to include in emergency, operation, and maintenance manuals.
1.7 MAINTENANCE MATERIAL SUBMITTALS
A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.
WET-PIPE SPRINKLER SYSTEMS 211313 - 2
1. Sprinkler Cabinets: Finished, wall-mounted, steel cabinet with hinged cover, and with space for minimum of six spare sprinklers plus sprinkler wrench. Include number of sprinklers required by NFPA 13 and sprinkler wrench. Include separate cabinet with sprinklers and wrench for each type of sprinkler used on Project.
1.8 QUALITY ASSURANCE
A. Installer Qualifications:
1. Installer's responsibilities include designing, fabricating, and installing sprinkler systems and providing professional engineering services needed to assume engineering responsibility. Base calculations on results of fire-hydrant flow test.
a. Engineering Responsibility: Preparation of working plans, calculations, and field test reports by a qualified professional engineer.
B. Welding Qualifications: Qualify procedures and operators according to 2010 ASME Boiler and Pressure Vessel Code.
1.9 FIELD CONDITIONS
A. Interruption of Existing Sprinkler Service: Do not interrupt sprinkler service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary sprinkler service according to requirements indicated:
1. Notify Owner no fewer than two days in advance of proposed interruption of sprinkler service.
2. Do not proceed with interruption of sprinkler service without Owner's written permission.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Sprinkler system equipment, specialties, accessories, installation, and testing shall comply with the following:
1. NFPA 13.
B. Standard-Pressure Piping System Component: Listed for 175-psig minimum working pressure.
C. Delegated Design: Engage a qualified professional engineer, as defined in Section 014000 "Quality Requirements," to design wet-pipe sprinkler systems.
WET-PIPE SPRINKLER SYSTEMS 211313 - 3
1. Available fire-hydrant flow test records indicate the following conditions:
a. Date: 21 July 2015.
b. Performed by: New Hanover County Department of Fire Services.
c. Location of Residual Fire Hydrant R: Control Tower Rd & Kerr Ave.
d. Location of Flow Fire Hydrant F: Control Tower Rd.
e. Static Pressure at Residual Fire Hydrant R: 70 psig.
f. Measured Flow at Flow Fire Hydrant F: 904 gpm.
g. Residual Pressure at Residual Fire Hydrant R: 53 psig.
2. Sprinkler system design shall be approved by authorities having jurisdiction.
a. Margin of Safety for Available Water Flow and Pressure: 10 percent, including losses through water-service piping, valves, and backflow preventers.
b. Sprinkler Occupancy Hazard Classifications:
1) General Purpose Training Bay, Assembly Hall, Vault, Storage, Unit Storage, Unheated Storage, Vault, Telecom, Electrical, Mechanical, Kitchen, Pump Riser, Mail Room, Auditorium: Ordinary Hazard.
2) Office, Administrative and Public Areas: Light Hazard.
3) Hazardous Waste Storage: Extra Hazard.
3. Minimum Density for Automatic-Sprinkler Piping Design:
a. Light-Hazard Occupancy: 0.10 gpm over 1500-sq. ft.
b. Ordinary-Hazard Occupancy: 0. 2 gpm over 2500-sq. ft.
c. Extra-Hazard Occupancy: 0.30 gpm over 2500-sq. ft.
4. Maximum Protection Area per Sprinkler: According to UL listing.
5. Maximum Protection Area per Sprinkler:
a. Office Spaces: 225 sq. ft.
b. Storage Areas: 130 sq. ft.
c. Mechanical Equipment Rooms: 130 sq. ft.
d. Electrical Equipment Rooms: 130 sq. ft.
e. Hazardous Storage: 100 sq. ft.
f. Other Areas: According to NFPA 13 recommendations unless otherwise indicated.
D. Seismic Performance: Sprinkler piping shall withstand the effects of earthquake motions determined according to NFPA 13 and ASCE/SEI 7.
2.2 STEEL PIPE AND FITTINGS
A. Standard-Weight, Galvanized and Black-Steel Pipe: ASTM A 53 /A 53M, Type F, Grade A, with furnace butt-welds. Electric-resistance-welded steel pipe is not permitted.
WET-PIPE SPRINKLER SYSTEMS 211313 - 4
B. Galvanized and Black-Steel Pipe Nipples: ASTM A 733, made of ASTM A 53 /A 53M, standard-weight, seamless steel pipe with threaded ends.
C. Galvanized and Uncoated-Steel Couplings: ASTM A 865/A 865M, threaded.
D. Galvanized and Uncoated, Gray-Iron Threaded Fittings: ASME B16.4, Class 125, standard pattern.
E. Malleable- or Ductile-Iron Unions: UL 860.
F. Cast-Iron Flanges: ASME 16.1, Class 125.
G. Steel Flanges and Flanged Fittings: ASME B16.5, Class 150.
1. Pipe-Flange Gasket Materials: AWWA C110, rubber, flat face, 1/8 inch thick, ASME B16.21, nonmetallic and asbestos free or EPDM rubber gasket].
a. Class 125 and Class 250, Cast-Iron, Flat-Face Flanges: Full-face gaskets.
b. Class 150 and Class 300, Ductile-Iron or -Steel, Raised-Face Flanges:
Ring-type gaskets.
2. Metal, Pipe-Flange Bolts and Nuts: Carbon steel unless otherwise indicated.
H. Steel Welding Fittings: ASTM A 234/A 234M and ASME B16.9.
1. Welding Filler Metals: Comply with AWS D10.12M/D10.12 for welding materials appropriate for wall thickness and chemical analysis of steel pipe being welded.
I. Grooved-Joint, Steel-Pipe Appurtenances:
1. Pressure Rating: 175-psig minimum.
2. Grooved-End Fittings for Steel Piping: ASTM A 47/A 47M, malleable-iron casting or ASTM A 536, ductile-iron casting, with dimensions matching steel pipe.
3. Grooved-End-Pipe Couplings for Steel Piping: AWWA C606 and UL 213 rigid pattern, unless otherwise indicated, for steel-pipe dimensions. Include ferrous housing sections, EPDM-rubber gasket, and bolts and nuts.
J. Steel Pressure-Seal Fittings: UL 213, FM Global-approved, 175-psig pressure rating with steel housing, rubber O-rings, and pipe stop; for use with fitting manufacturers' pressure-seal tools.
2.3 SPECIALTY VALVES
A. Listed in UL's "Fire Protection Equipment Directory" or FM Global's "Approval Guide."
B. Pressure Rating:
1. Standard-Pressure Piping Specialty Valves: 175-psig minimum.
C. Body Material: Cast or ductile iron.
WET-PIPE SPRINKLER SYSTEMS 211313 - 5
Bid Final Submittal 03 April 2017
D. Size: Same as connected piping.
E. End Connections: Flanged or grooved.
F. Alarm Valves:
1. Standard: UL 193.
2. Design: For horizontal or vertical installation.
3. Include trim sets for bypass, drain, electrical sprinkler alarm switch, pressure gages, retarding chamber, and fill-line attachment with strainer.
4. Drip Cup Assembly: Pipe drain without valves and separate from main drain piping.
5. Drip Cup Assembly: Pipe drain with check valve to main drain piping.
6. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.
G. Automatic (Ball Drip) Drain Valves:
1. Standard: UL 1726.
2. Pressure Rating: 175-psig minimum.
3. Type: Automatic draining, ball check.
4. Size: NPS 3/4.
5. End Connections: Threaded.
2.4 SPRINKLER PIPING SPECIALTIES
A. Branch Outlet Fittings:
1. Standard: UL 213.
2. Pressure Rating: 175-psig minimum.
3. Body Material: Ductile-iron housing with EPDM seals and bolts and nuts.
4. Type: Cross fittings.
5. Configurations: Ductile-iron housing with branch outlets.
6. Size: Of dimension to fit onto sprinkler main and with outlet connections as required to match connected branch piping.
7. Branch Outlets: Grooved, plain-end pipe, or threaded.
B. Flow Detection and Test Assemblies:
1.
2. Standard: UL's "Fire Protection Equipment Directory" or FM Global's "Approval
Guide."
3. Pressure Rating: 175-psig minimum.
4. Body Material: Cast- or ductile-iron housing with orifice, sight glass, and integral test valve.
5. Size: Same as connected piping.
6. Inlet and Outlet: Threaded or grooved.
C. Branch Line Testers:
1. Standard: UL 199.
2. Pressure Rating: 175 psig.
WET-PIPE SPRINKLER SYSTEMS 211313 - 6
3. Body Material: Brass.
4. Size: Same as connected piping.
5. Inlet: Threaded.
6. Drain Outlet: Threaded and capped.
7. Branch Outlet: Threaded, for sprinkler.
D. Sprinkler Inspector's Test Fittings:
1.
2. Standard: UL's "Fire Protection Equipment Directory" or FM Global's "Approval
Guide."
3. Pressure Rating: 175-psig minimum.
4. Body Material: Cast- or ductile-iron housing with sight glass.
5. Size: Same as connected piping.
6. Inlet and Outlet: Threaded.
E. Flexible Sprinkler Hose Fittings:
1. Not permitted.
2.5 SPRINKLERS
A. Listed in UL's "Fire Protection Equipment Directory" or FM Global's "Approval Guide."
B. Pressure Rating for Residential Sprinklers: 175-psig maximum.
C. Pressure Rating for Automatic Sprinklers: 175-psig minimum.
D. Automatic Sprinklers with Heat-Responsive Element:
1.
2. Nonresidential Applications: UL 199.
3. Characteristics: Nominal 1/2-inch orifice with Discharge Coefficient K of 5.6, and for "Ordinary" temperature classification rating unless otherwise indicated or required by application.
E. Sprinkler Finishes: Chrome plated, bronze and painted.
F. Special Coatings: Wax and corrosion-resistant paint.
G. Sprinkler Escutcheons: Materials, types, and finishes for the following sprinkler mounting applications. Escutcheons for concealed, flush, and recessed-type sprinklers are specified with sprinklers.
1. Ceiling Mounting: Chrome-plated steel or white finish, one piece, flat.
2. Sidewall Mounting: Chrome-plated steel or white finish, one piece, flat.
H. Sprinkler Guards:
1. Standard: UL 199.
2. Type: Wire cage with fastening device for attaching to sprinkler.
WET-PIPE SPRINKLER SYSTEMS 211313 - 7
http://www.specagent.com/LookUp/?ulid=1472&mf=04&src=wd
Bid Final Submittal 03 April 2017
2.6 ALARM DEVICES
A. Alarm-device types shall match piping and equipment connections.
B. Electrically Operated Alarm Bell:
1. Standard: UL 464.
2. Type: Vibrating, metal alarm bell.
3. Size: 10-inch diameter.
4. Finish: Red-enamel factory finish, suitable for outdoor use.
5. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.
C. Water-Flow Indicators:
1. Standard: UL 346.
2. Water-Flow Detector: Electrically supervised.
3. Components: Two single-pole, double-throw circuit switches for isolated alarm and auxiliary contacts, 7 A, 125-V ac…