Bid Final Submittal Specifications Volume 1 of 2 03 April 2017
Prepared by:
NATIONAL GUARD READINESS CENTER
WILMINGTON, NORTH CAROLINA
National Guard Bureau Project No. 85498371301
North Carolina Army National Guard
National Guard Readiness Center Wilmington, North Carolina Bid Final Submittal 03 April 2017
DIVISION 01 – GENERAL REQUIREMENTS
000104 Seals Page
010000 General Requirements
011000 Summary
012200 Unit Prices
012300 Additive Bid Items (ABI)
012500 Substitution Procedures
012600 Contract Modification Procedures
013100 Project Management and Coordination
013200 Construction Progress Documentation
013233 Photographic Documentation
013300 Submittal Procedures
014000 Quality Requirements
014200 References
014536 Statement of Special Inspections
014537 Schedule of Special Inspections
015000 Temporary Facilities and Controls
015639 Temporary Tree and Plant Protection
016000 Product Requirements
017300 Execution
017419 Construction Waste Management and Disposal
017700 Closeout Procedures
017823 Operation and Maintenance Data
017839 Project Record Documents
017900 Demonstration and Training
018113.13 Sustainable Design Requirements – LEED 2009 for
New Construction and Major Renovations
019113 General Commissioning Requirements
DIVISION 02 – EXISTING CONDITIONS
024116 Structure Demolition 024117 Asbestos and Regulated Material Removal 024117b Asbestos Survey Wilmington Dec 2007 Attachment 023132 Geotechnical Data 023132b Subsurface Exploration and Geotechnical Analysis
TOC PAGE NO. i
Bid Final Submittal 03 April 2017
DIVISION 03 – CONCRETE
033000 Cast-In-Place Concrete
033543 Polished Concrete Finishing
DIVISION 04 – MASONRY
042000 Unit Masonry
047200 Cast Stone Masonry
DIVISION 05 – METALS
051200 Structural Steel Framing
052100 Steel Joist Framing
053100 Steel Decking
054000 Cold-Formed Metal Framing
055000 Metal Fabrications
055015 Aluminum Ladders
055113 Metal Pan Stairs
055213 Pipe and Tube Railings
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
061053 Miscellaneous Rough Carpentry
061600 Sheathing
064116 Plastic-Laminate-Faced Architectural Cabinets
066400 Plastic Paneling
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
071326 Self-Adhering Sheet Waterproofing
072100 Thermal Insulation
072119 Foamed-In-Place Insulation
072413 Polymer-Based Exterior Finish System (EFS)
072726 Fluid-Applied Membrane Air Barriers
074113.19 Batten-Seam Metal Roof Panels
074213.13 Formed Metal Wall Panels
074213.23 Metal Composite Material Wall Panels
074293 Soffit Panels
TOC PAGE NO. ii
Bid Final Submittal 03 April 2017
075419 Polyvinyl Chloride (PVC) Roofing
076200 Sheet Metal Flashing and Trim
077100 Roof Specialties
077200 Roof Accessories
077210 Rooftop Fall Arrest System
078100 Applied Fireproofing
078123 Intumescent Fireproofing
078413 Penetration Firestopping
078446 Fire-Resistive Joint Systems
079100 Preformed Foam Joint Seals
079200 Joint Sealants
079219 Acoustical Joint Sealants
DIVISION 08 – OPENINGS
081113 Hollow Metal Doors and Frames
081416 Flush Wood Doors
083113 Access Doors and Frames
083323 Overhead Coiling Doors
083459 Vault Doors and Day Gates
084113 Aluminum-Framed Entrances and Storefronts
084413 Glazed Aluminum Curtain Walls
087100 Door Hardware
087113 Automatic Door Operators
088000 Glazing
088300 Mirrors
089119 Fixed Louvers
089500 Blast Resistance
DIVISION 09 – FINISHES
092116.23 Gypsum Board Shaft Wall Assemblies
092216 Non-Structural Metal Framing
092900 Gypsum Board
093013 Ceramic Tiling
095000 Channeled Wood Panel Ceilings
TOC PAGE NO. iii
Bid Final Submittal 03 April 2017
095010 Wood Panel Ceilings
095113 Acoustical Panel Ceilings
096513 Resilient Base and Accessories
096519 Resilient Tile Flooring
096536 Static-Control Resilient Flooring
096566 Resilient Athletic Flooring
096623 Resinous Matrix Terrazzo Flooring
096723 Resinous Flooring
096813 Tile Carpeting
097230 Dry Erase Wallcovering
097714 Wood Veneer Wall Panels
097715 Wood Veneer Wall Panels
098433 Sound-Absorbing Wall Units
099113 Exterior Painting
099123 Interior Painting
099646 Intumescent Painting
099800 Coatings For CMU Veneer
DIVISION 10 – SPECIALTIES
101100 Visual Display Units
101419 Dimensional Letter Signage
101423.16 Room-Identification Panel Signs
102113.19 Plastic Toilet Compartments
102213 Wire Mesh Partitions
102239 Folding Panel Partitions
102600 Wall and Door Protection
102800 Toilet, Bath, and Laundry Accessories
104313 Defibrillator Cabinets and Defibrillators
104413 Fire Protection Cabinets
104416 Fire Extinguishers
105113 Metal Lockers
105613 Metal Storage Shelving
107516 Ground-Set Flagpoles
109160 Ventilated Wire Shelving
TOC PAGE NO. iv
Bid Final Submittal 03 April 2017
109900 Miscellaneous Items
DIVISION 11 – EQUIPMENT
114000 Food Service Equipment
115213 Projection Screens
DIVISION 12 – FURNISHINGS
122413 Roller Window Shades
123661.16 Solid Surfacing Countertops
124813 Entrance Floor Mats and Frames
DIVISION 13 – SPECIAL CONSTRUCTION
133423.10 Fabricated Storage Building
DIVISION 14 - CONVEYING EQUIPMENT
142100 Electric Traction Elevators
DIVISION 21 - FIRE SUPPRESSION
210517 Sleeves and Sleeve Seals for Fire-Suppression Piping
210518 Escutcheons for Fire-Suppression Piping
210548 Vibration and Seismic Controls for Fire-Suppression Piping and Equipment
211119 Fire Department Connections
211313 Wet Pipe Sprinkler Systems
213113 Electric Drive, Centrifugal Fire Pumps
213413 Pressure-Maintenance Pumps
DIVISION 22 – PLUMBING
220513 Common Motor Requirements for Plumbing Equipment
220517 Sleeves and Sleeve Seals for Plumbing Piping
220518 Escutcheons for Plumbing Piping
220519 Meters and Gages for Plumbing Piping
220523.12 Ball Valves for Plumbing Piping
220523.13 Butterfly Valves for Plumbing Piping
220523.14 Check Valves for Plumbing Piping
TOC PAGE NO. v
Bid Final Submittal 03 April 2017
220529 Hangers and Supports for Plumbing Piping and Equipment
220548 Vibration Controls for Plumbing Piping and Equipment
220553 Identification for Plumbing Piping and Equipment
220719 Plumbing Piping Insulation
220800 Commissioning of Plumbing Systems
221116 Domestic Water Piping
221119 Domestic Water Piping Specialties
221123.21 Inline, Domestic-Water Pumps
221316 Sanitary Waste and Vent Piping
221319 Sanitary Waste Piping Specialties
221319.13 Sanitary Drains
221323 Sanitary Waste Interceptors
221429 Sump Pumps
221513 General-Service Compressed-Air Piping
221519 General-Service Packaged Air Compressors and Receivers
223300 Electric, Domestic-Water Heaters
224213.13 Commercial Water Closets
224213.16 Commercial Urinals
224216.13 Commercial Lavatories
224216.16 Commercial Sinks
224223 Commercial Showers
224500 Emergency Plumbing Fixtures
224713 Drinking Fountains
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
230511 HVAC Electrical Provisions
230513 Common Motor Requirements for HVAC Equipment
230517 Sleeves and Sleeve Seals for HVAC Piping
230518 Escutcheons for HVAC Piping
230529 Hangers and Supports for HVAC Piping and Equipment
230548 Vibration Controls
230553 Identification for HVAC Piping and Equipment
230593 Testing, Adjusting, and Balancing for HVAC
TOC PAGE NO. vi
Bid Final Submittal 03 April 2017
230713 Duct Insulation
230719 HVAC Piping Insulation
230800 HVAC Systems Commissioning Requirements
230923 Direct Digital Control (DDC) System for HVAC
230923.12 Control Dampers
230923.19 Moisture Instruments
230923.27 Temperature Instruments
232113 Hydronic Piping
232300 Refrigerant Piping
232300.0011 Overhead Vehicle Tailpipe Exhaust Removal System(s)
233113 Metal Ducts
233300 Air Duct Accessories
233346 Flexible Ducts
233416 Centrifugal HVAC Fans
233371.13 Air Diffusers
233713.23 Registers and Grilles
233723 HVAC Gravity Ventilators
236200 Packaged Compressor and Condenser Units
237223 Air-to-Air Energy Recovery Equipment
237433 Dedicated Outdoor-Air Units
238126 Split-System Air Conditioners
238219 Fan Coil Units
238239.19 Wall, Ceiling and Duct Unit Heaters
238416.16 Indoor, Mechanical Dehumidification Units
DIVISION 26 – ELECTRICAL
260519 Low-Voltage Electrical Power Conductors and Cables
260526 Grounding and Bonding for Electrical Systems
260529 Hangers and Supports for Electrical Systems
260533 Raceways and Boxes for Electrical Systems
260543 Underground Ducts and Race Ways for Electrical Systems
260544 Sleeves and Sleeve Seals for Electrical Raceways and Cabling
260553 Identification for Electrical Systems
TOC PAGE NO. vii
National Guard Readiness Center Jacobs Project No. F6W72100
Bid Final Submittal 03 April 2017
260573.13 Short-Circuit Studies
260573.16 Coordination Studies
260573.19 Arc-Flash Hazard Analysis
260800 Commissioning of Electrical Systems
260923 Lighting Control Devices
260943.23 Relay-Based Lighting Controls
262213 Low-Voltage Distribution Transformers
262413 Switchboards
262416 Panelboards
262726 Wiring Devices 262813 Fuses
262816 Enclosed Switches and Circuit Breakers
262913.03 Manual and Magnetic Motor Controllers
262933 Controllers For Fire-Pump Drivers
263213.13 Diesel Emergency Engine Generators
263323.11 Central Battery Equipment for Emergency Lighting
263600 Transfer Switches
264113 Lightning Protection For Structures
264313 Surge Protection For Low-Voltage Electrical Power Circuits
265119 LED Interior Lighting
265213 Emergency and Exit Lighting
265619 LED Exterior Lighting
DIVISION 27 – COMMUNICATIONS
270526 Grounding and Bonding for Communications Systems
270528 Pathways for Communications Systems
270529 Hangers and Supports for Communications Systems
270536 Cable Trays for Communication Systems
270543 Underground Pathways and Structures for Communication Systems
270544 Sleeves and Sleeve Seals for Communications
Pathways and Cabling
270548.16 Seismic Controls for Communications Systems
270553 Identification for Communications Systems
271100 Communications Equipment Room Fittings
TOC PAGE NO. viii
National Guard Readiness Center Jacobs Project No. F6W72100
Bid Final Submittal 03 April 2017
271116 Communications Racks, Frames and Enclosures
271313 Communications Copper Backbone Cabling
271323 Communications Optical Fiber Backbone Cabling
271513 Communications Copper Horizontal Cabling
275116 Public Address Systems
DIVISION 28 – Electronic Safety and Security
283111 Digital, Addressable Fire-Alarm and Mass Notification System
DIVISION 31 – Earthwork
311000 Site Clearing
312000 Earth Moving
312500 Erosion Control
313116 Termite Control
DIVISION 32 – Exterior Improvements
321123 Dense Graded Base
321216 Asphalt Pavement
321313 Portland Cement Concrete Paving
321373 Concrete Paving Joint Sealants
321713 Parking Bumpers
321723 Pavement Markings (For Building Interior)
323113 Fencing and Gates
329113 Soil Preparation
329119 Landscape Finish Grading
329200 Turf and Grasses
329300 Plants
DIVISION 33 – Utilities
330500 Common Work Results for Utilities
331100 Water Distribution
333100 Sanitary Sewer Systems
334100 Storm Utility Drainage Piping
TOC PAGE NO. ix
Bid Final Submittal 03 April 2017
SEALS PAGE 000107 - 1
DOCUMENT 000107 - SEALS PAGE
1.1 DESIGN PROFESSIONALS OF RECORD
A. Architect:
1. Daniel E. Flippen
2. 7861
B. Civil Engineer:
1. Jamie E. Gollings
2. 034090
C. Landscape Architect:
1. Jamie E. Gollings
2. 034090
D. Structural Engineer:
1. Brian J. Horstmann
2. 044707
E. Fire-Protection Engineer:
1. Jeffery L. McLaughlin
2. 043641 dimartj Snapshot dimartj Snapshot dimartj Snapshot
Bid Final Submittal 03 April 2017
SEALS PAGE 000107 - 2
F. Plumbing Engineer:
1. Craig A. Crader
2. 034090
G. HVAC Engineer:
1. Craig A. Crader
2. 034090
H. Electrical Engineer:
1. Richard B. Kurzawa
2. 037131
I. Telecommunications & Security Engineer:
1. Scott L. Hansberry
2. 182996R
END OF DOCUMENT 000107
dimartj Snapshot dimartj Snapshot dimartj Snapshot
Bid Final Submittal 03 April 2017
SECTION 010000 - GENERAL REQUIREMENTS
PART 1 - GENERAL
1.1 SCOPE
A. General: This section provides general requirements complimenting those specified in Division 1 and the Contract Documents. The CONTRACTOR shall follow the require-ments described within this section in addition to those included in other related sec-tions. Discrepancies between the related sections shall be controlled as described herein.
B. Project provides for furnishing all plant, labor, material, equipment and appliances to construct the building as described herein and shown on the construction Drawings.
C. The CONTRACTOR will be held responsible for all requirements described in the Contract Documents. All work, including that of subcontractors, shall be completed in accordance with the Contract Documents. Failure to be familiar with the requirements of the Contract will not relieve the CONTRACTOR of responsibility to comply.
D. The organization of the Specifications into divisions, sections, and articles, and the arrangement of the Drawings shall not control the CONTRACTOR in dividing the work among subcontractors or in establishing the extent of the work to be performed by any trade.
E. Superintendence by the CONTRACTOR: At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the work a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.
1.2 WORK SCHEDULING
A. Normal base work hours for the CONTRACTOR will be between the hours of 7:00 am through 5:00 pm, excluding Saturdays, Sundays, and Federal Holidays. The normal work hours for National Guard personnel are 7:00 am to 5:00 pm, Monday through Friday. If the CONTRACTOR desires to work during periods other than above, CONTRACTOR must notify the CONTRACTING OFFICER 5 working days in advance of CONTRACTOR’s intention to work during other periods to allow assignment of additional inspection forces and for notification of fire, security and safety. When the CONTRACTING OFFICER determines that they are reasonably available, CONTRACTING OFFICER may authorize the CONTRACTOR to perform work during periods other than normal duty hours/days. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the CONTRACTOR, the actual cost of the inspection, at overtime rates, will be charged to the CONTRACTOR and will be deducted from the final payment of the Contract amount.
B. The following Federal legal Holidays are observed by this base:
GENERAL REQUIREMENTS 010000 – 1
1. New Year’s Day 1 January
2. Martin Luther’s King’s Birthday Third Monday of January
3. President’s Day Third Monday of February
4. Memorial Day Last Monday of May
5. Independence Day 4 July
6. Labor Day First Monday in September
7. Columbus Day Second Monday in October
8. Veteran’s Day 11 November
9. Thanksgiving Day Fourth Thursday in November
10. Christmas Day 25 December
C. NOTE: Any of the above holidays falling on a Saturday will be observed the preceding Friday, holidays falling on a Sunday will be observed on the following Monday.
D. Prior to commencing work on the job initially, resumption of work after prolonged interruption (7 calendar days or more) commencement of any warranty work, and upon completion of warranty work, the CONTRACTOR must notify the CONTRACTING OFFICER or the CONTRACTING OFFICER Representative (COTR). When relocating to new sites, returning to sites for follow-up work on a phased work plan, notification to the COTR is sufficient. Notification should be by personal contact; however, advance notification may be by telephone, or in writing, and should be accomplished sufficiently in advance to allow scheduling of inspection forces. The above precautions are to ensure construction inspection and recording of work proceedings.
1.3 UNAUTHORIZED PERSONNEL
A. The CONTRACTOR shall inform all personnel (including subcontractor and visiting supplier personnel) that access to areas outside of the immediate work area excluding, direct haul and access routes, Contracting and Civil Engineering offices and point of supply and storage, is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.
1.4 INSPECTION OF SITE
A. The CONTRACTOR shall be responsible for the complete coordination and proper relation of the work of all trades. Reference Contract Clauses FAR 52.236-3, “Site Investigation and Conditions Affecting the Work,” and FAR 52.236-8, “Other Contracts.”
B. It is recommended that prospective offerors visit the premises and thoroughly familiarize themselves with the details of the work and working conditions. It is the responsibility of all offerors to have compared the premises and the site with the Specifications and Drawings, and to have satisfied themselves as to all conditions of the premises, the existing obstructions, the actual elevations, and any other conditions affecting the execution and completion of the work prior to submission of the Proposal.
Reference Contract Clause FAR 52.236-3, “Site Investigation and Conditions Affecting the Work.”
GENERAL REQUIREMENTS 010000 – 2
C. No allowances or extra construction on behalf of any CONTRACTOR will be permitted subsequently by reason of error or oversight on the part of the subcontractor, or on account of interferences by the activities of the CONTRACTING OFFICER or others.
Reference Contract Clause FAR 52.236-3, “Site Investigation and Conditions Affecting the Work.”
1.5 CORRELATION OF DRAWINGS, SPECIFICATIONS AND CONTRACTS
A. The Specifications, Contract and the accompanying Drawings are intended to describe and provide for a complete, new and usable facility. They are intended to be cooperative and what is called for by one shall be as binding as if called for by all. The CONTRACTOR will understand that the work herein described shall be complete in every detail, not withstanding every item necessarily involved is not particularly mentioned, and the CONTRACTOR shall be responsible to provide all labor and material for the entire completion of the work intended. Should any error or inconsistency appear in the Drawings or Specifications, the CONTRACTOR, before proceeding with the work, shall make mention of same to the CONTRACTING OFFICER for proper adjustment, and in no case shall the work proceed with uncertainty. Reference Contract Clause DFARS 252.236-7001, “Contract Drawings and Specifications” and FAR 52.236-21 specifications and drawings for construction.
1.6 REPORT OF ERROR AND DISCREPANCIES
A. The CONTRACTOR shall be responsible for any and all discrepancies in work due to failure to obtain dimensions and investigate conditions at the building before fabrication and installation.
B. The CONTRACTOR shall bear all costs in replacing all materials and labor due to not observing the above paragraph and such replaced materials shall meet the approval of the CONTRACTING OFFICER.
C. The CONTRACTOR shall promptly notify the CONTRACTING OFFICER in writing of any discrepancies.
D. Reference Contract clauses FAR 52.236-21, “Specifications and Drawings for Construction.” FAR 52.246-12 “Inspection of Construction,” and DFARS 252.236-7001, “Contract Drawings and Specifications.”
E. Any proposed changes to the specifications by the CONTRACTOR must be submitted in writing to the CONTRACTING OFFICER for approval prior to implementation.
1.7 DIVISION OF WORK
A. The various divisions of the specifications shall not be considered as negotiations of the material and labor involved. The arrangement and order of these divisions have been made for convenience only, and it is not the intent, nor shall it be so construed, a particular trade or subcontractor must perform that work included in any one division.
B. Any item mentioned under any division heading must be supplied even though it is not specified under the heading for the respective work, but is shown on the Drawings. No
GENERAL REQUIREMENTS 010000 – 3
claims for extras arising out of real or alleged error in such arrangement or order of the various divisions will be given consideration.
C. Reference Contract clause FAR 52.236-21, “Specifications and Drawings for Construction.”
D. Any proposed changes to the specifications by the CONTRACTOR must be submitted in writing to the CONTRACTING OFFICER for approval prior to implementation.
1.8 METHOD OF CARRYING ON THE WORK
A. All work under the Contract shall be arranged and carried on in such a manner as to complete work in the least possible time. The CONTRACTOR shall consult with the CONTRACTING OFFICER as to methods or sequence of carrying on the work. A definite program of work shall be arranged before starting. Reference Contract Clause FAR 52.236-15, “Schedules for Construction Contracts.”
B. Activities in the vicinity of this Project may be kept in full or partial operation during construction. The CONTRACTOR shall coordinate with the CONTRACTING OFFICER and schedule construction activities. Reference Contract Clause FAR 52.236-8, “Other Contracts.”
1.9 STANDARDS OF MANUFACTURE
A. All recognized regulatory/code standards shall be the latest published edition prior to the date of release for bid/proposal of the Contract Documents.
B. For purpose of establishing the standard of construction and the requirements to be met in the work of all divisions, the Drawings and these Specifications are based on the use of products hereinafter specified, adapted to the installation as required to meet the condition.
C. Where brand names are shown, these names are intended to describe a quality of product, and in no way are intended to limit products of equal quality. Therefore, products of other manufacturers may be employed for this work provided they are approved as equivalent materials and construction and equally adaptable to the conditions as approved by the CONTRACTING OFFICER. Reference Contract Clause FAR 52.236-5, “Materials and Workmanship.”
1.10 MEANING OF APPROVED, DIRECTED, ETC.
A. “Approved,” “Directed,” “Required,” “Applicable,” or words of like or similar effect, when used in the Specifications shall be interpreted to mean “Approved By,” “Directed By,” etc., the CONTRACTING OFFICER unless otherwise specifically stipulated.
1.11 MISPLACED MATERIALS
A. Any material that is deposited elsewhere than areas designated as approved by the CONTRACTING OFFICER shall be rehandled and deposited where directed. No
GENERAL REQUIREMENTS 010000 – 4
payment will be made for rehandling such material. The CONTRACTING OFFICER will notify CONTRACTOR of any noncompliance with the foregoing provisions.
1.12 COMPLIANCE WITH CODES AND REGULATIONS
A. All work shall be done in accordance with the applicable codes and/or ordinances in force at the time of construction. It is the CONTRACTOR’s responsibility to ensure that where EPA, DEQ or other such regulations control the removal, handling, installation or disposal of materials, they shall be strictly adhered to whether or not specifically referenced in the construction documents.
B. CONTRACTOR shall have data sheets available at the site on any materials used to comply with OSHA and EPA. Reference Contract Clause FAR 52.223.3, “Hazardous Material Identification and Material Safety Data.”
1.13 MATERIAL TESTING BY NATIONAL LABORATORIES
A. Electrical materials and equipment shall be new and bear the UL label or be listed in UL Electrical Construction Materials Directory or Electrical Appliance and Utilization Equipment Directory, wherever standards have been established by the agency.
B. The CONTRACTOR shall submit proof that the material or equipment, which the CONTRACTOR proposes to furnish under this Specification, conforms to the standards of Underwriters’ Laboratories. The label of Underwriters Laboratories (UL) shall be accepted as conforming to this requirement.
C. In lieu of the label, the CONTRACTOR may submit a written certification from any recognized testing agency, adequately equipped and competent to perform such services, that the material or equipment has been tested and conforms to the standards, including the methods of testing used.
1.14 SUBMITTALS
A. Shop Drawings and Product Data: The CONTRACTOR shall furnish submittals in the form of manufacturer’s brochures, pamphlets, or written specifications on all items to be installed unless specifically directed otherwise by these Specifications or by the CONTRACTING OFFICER. Reference Contract Clause FAR 52.236-5, “Material and Workmanship,” 52.225-9, “Buy American Act-Construction Materials,” FAR 52.223-3, “Hazardous Material Identification and Material Safety Data,” and DFAR 252.227-7033, “Rights in Shop Drawings.” Submittals shall clearly identify performance criteria requested.
B. Approval of Materials: Prior to the purchase of material, the CONTRACTOR shall submit to the CONTRACTING OFFICER, for material approval/ disapproval, brochures and technical literature covering, in detail, the materials the CONTRACTOR proposes to supply. This shall include the specific catalog and model specification number designations. Submittals shall demonstrate that the item conforms to all of the requirements. No unapproved or disapproved materials shall be used. Submittals shall be made for the items listed on013300 Submittals Report.
GENERAL REQUIREMENTS 010000 – 5
1.15 CONSTRUCTION SCHEDULING, WORK PROGRESS AND PREPARATION OF
PROGRESS SCHEDULES AND REPORTS
A. The CONTRACTOR shall prepare a work progress schedule in Microsoft Project, latest version, or acceptable substitute format. These schedules are to be submitted to the CONTRACTING OFFICER for approval, in the number of copies as directed, prior to start of construction. The schedule will show the order in which the contractor proposes to perform the work, the dates on which the CONTRACTOR contemplates starting and completing the various divisions and salient features of the work. Reference Contract Clause FAR 52.236-15, “Schedules for Construction Contracts.” The work shall be scheduled so that upon the start of construction, work progresses in a continuous and diligent manner. A schedule that does not reflect steady and reasonable progress throughout the construction period will be rejected. The schedule shall include a line item for rough inspections by GOVERNMENT personnel as outlined in the various sections of the Specifications or on the Drawings. A rough inspection is required on all installed systems prior to sealing off or closing in a wall, pipe chase, suspended ceiling system etc. These systems include by not limited to: domestic and heating water lines, communication and electric runs, all insulation material to be covered by other material (GWB, wood panel etc), duct runs, ceiling suspension systems, raised flooring, fire detection/protection/suppression systems etc. A second or finish inspection will be conducted after these systems are “hidden” to ensure the quality of the finished product. The finish inspection does not constitute the final Project inspection accomplished at Project completion. The CONTRACTOR shall request these inspections, through the CONTRACTING OFFICER at least 5 workdays prior to the desired inspection date.
B. A weekly meeting may be held between the CONTRACTOR, COTR and CONTRACTING OFFICER, to discuss work progress, problems and potential change orders. The CONTRACTOR shall attend these meetings at no additional cost to the GOVERNMENT. Prior to specific work elements of a project, the CONTRACTOR shall confer with the COTR and agree on a sequence of procedures and means of access to premise; space for storage of materials and equipment; delivery of materials and use of approaches, use of corridors, stairways and similar means of passage. Weekly progress reports are to be submitted to both the CONTRACTING OFFICER and the CONTRACTING OFFICER’s Representative (COTR) covering the period from notice to proceed through final inspection. If there are possible deviations from the original plan, those are to be noted and approved by the CONTRACTING OFFICER before work changes are implemented. Reference Contract Clause FAR 52.236-15, “Schedules for Construction Contracts.”
1.16 SAFETY ASSURANCE
A. Compliance with Regulations. All work including the handling of hazardous materials shall comply with the applicable requirements of 29 CFR 1910/1926. All work shall comply with applicable state and municipal safety and health requirements. Where there is a conflict between applicable regulations, the most stringent shall apply.
B. CONTRACTOR Responsibility. The CONTRACTOR shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of work. The GOVERNMENT shall not be
GENERAL REQUIREMENTS 010000 – 6
held liable for any action on the part of the CONTRACTOR, the CONTRACTOR’s employees or subcontractor, which results in illness, injury or death.
C. Where an employee can fall more than 6 feet, a fall protection system must be used;
29 CFR 1926.500 stipulates where this occurs and the different types of fall arrest systems.
D. All references to protection of the site and adjacent buildings when trenching, shall include protection of all employees also.
E. Inspections, Tests and Reports. The required inspections, tests and reports made by the CONTRACTOR, subcontractor, specially trained technicians, equipment manufacturers and other as required, shall be at the CONTRACTOR’s expense.
F. Materials and Equipment. Special facilities, devices, equipment, clothing and similar items used by the CONTRACTOR in the execution of work shall comply with applicable regulations.
G. Health and Safety Plan: Prior to commencing on-site work, Contractor must submit an Occupational Safety and Health Administration (OSHA) Emergency Action Plan (EAP) to Contracting Officer to demonstrate compliance by Contractor and subcontractors with applicable OSHA regulations. Prior to commencing on-site work, Contractor must submit a project-specific Project Safety Plan to Contracting Officer. The plan must include, but is not limited to, hazard communications, labeling, emergency response and preparedness and training.
1.17 INSPECTIONS AND TESTS
A. Inspections and tests are for the sole benefit of the GOVERNMENT and shall not relieve the CONTRACTOR of the responsibility of providing quality control measures to ensure that the work strictly complies with the Contract requirements. No inspection or test by the GOVERNMENT shall be construed as constituting or implying acceptance.
Reference Contract Clause FAR 52.246-12, “Inspection of Construction.”
1.18 QUALITY CONTROL/TESTS
A. Where work is specified to be in conformity with Standard Specifications of the American Society for Testing Materials (ASTM), or with Federal Specifications or with specifications of well known recognized technical and trade organizations, but no tests are specifically stipulated in connection herewith, the CONTRACTOR shall furnish and pay for any tests or certifications required by the CONTRACTING OFFICER to show that the proposed materials meet with the applicable requirements.
B. The CONTRACTOR shall submit a written certification from any recognized testing agency, adequately equipped and competent to perform such services, that the material or equipment has been tested and conforms to the standards, including the methods of testing used.
C. Wherever testing or analysis of material is required, such testing unless otherwise noted will be made at the CONTRACTOR’s expense.
GENERAL REQUIREMENTS 010000 – 7
D. Subsequent testing of those materials which fail to meet specifications will be accomplished by the CONTRACTOR at no cost to the GOVERNMENT.
E. CONTRACTOR Quality Control (CQC) Program: The CONTRACTOR shall provide and maintain an effective quality control program in accordance with the Contract.
Within 10 days of the Award of the Contract, the CONTRACTOR shall provide three copies of the Project CQC plan to the CONTRACTING OFFICER. This document, as a minimum, shall include name and address of the independent testing agency and the responsible principal with the firm; a summary of QC tests required by the Specification and to be provided by the testing agency; and typical daily reports forms to be used for this Project. The plan shall also indicate organizational procedures to immediately notify the CONTRACTING OFFICER or COTR of test results in noncompliance with the Specification and recommendations on correction. The testing agency must be an independent company and not owned or partially owned by the CONTRACTOR or any relation or employee of the CONTRACTOR.
F. Samples used for testing shall be selected as specified for the various tests elsewhere in the Specifications but in every case the method of selecting samples and the location for selection shall be as approved by the CONTRACTING OFFICER.
G. Tests shall be made in accordance with the specified testing procedures and/or methods and otherwise as required to provide compliance with all Contract requirements. Tests shall be made by independent, commercial testing laboratories approved in writing by the CONTRACTING OFFICER.
H. Results of all tests shall be recorded on certified test reports of the commercial testing laboratories. Reports shall include a statement that the materials tested do or do not meet the requirements of the Contract Specifications. Six copies of all reports shall be forwarded directly to the CONTRACTING OFFICER for approval within 5 days of the actual performance of the test. The testing agency shall immediately notify (verbally) the CONTRACTING OFFICER of any tests, which indicate failure to meet the Contract requirements.
I. Any item, for which test reports show failure to meet all Contract requirements shall be retested as often as required to show full compliance with Contract requirements, at the CONTRACTOR’s expense.
J. CONTRACTOR will provide an emergencies plan, with names of personnel to accomplish the repairs in the event of utility and/or communications emergencies.
1.19 KEYS
A. The CONTRACTOR shall be responsible for any GOVERNMENT-owned keys that have been issued to the CONTRACTOR for access to facilities or areas pertinent to this Contract.
B. Upon completion of the work in an area, or upon request of the CONTRACTING OFFICER, the key or keys relevant to the area shall be returned immediately. Keys shall be returned prior to final task order payments.
GENERAL REQUIREMENTS 010000 – 8
C. Should the CONTRACTOR Lose a Key: The CONTRACTOR shall notify the CONTRACTING OFFICER, immediately and in writing, but not later than 1 working day after the CONTRACTOR is aware of the loss. Should the key not be found before final acceptance, the final Contract payment shall be reduced by the replacement cost for each key not returned and, if required by the CONTRACTING OFFICER, any re-keying costs and cost of any other damages suffered by the GOVERNMENT.
1.20 WARRANTY
A. In addition to the specific guarantees required by the Specifications for certain portions of the work to be performed under this Contract, the CONTRACTOR shall furnish a written warranty for all of the work to be performed under this Contract, against defects in materials or workmanship for a period of 1 year from the date of final acceptance of the completed work by the GOVERNMENT.
B. All work including workmanship, material, and equipment (other than GOVERNMENT furnished equipment) shall be warranted for the full period of standard manufacturer’s warranty, but in no case shall be warranted for a period of less than 1 year upon notice from the CONTRACTING OFFICER of any failure during this warranty period, the part or parts shall be replaced promptly with new parts by and at the expense of the CONTRACTOR. Whenever the manufacturer of a piece of equipment supplied by the CONTRACTOR customarily provides a warranty covering the equipment, the CONTRACTOR shall promptly turn over such to the CONTRACTING OFFICER.
C. Upon completion, the CONTRACTOR shall provide the CONTRACTING OFFICER with five bound sets O and M Manuals for each piece of installed equipment. Also provide 3 compact disks with complete O and M’s in searchable PDF format.
D. Reference Contract Clause FAR 52.246-12, “Inspection of Construction” and FAR 52.246-21, “Warranty of Construction.”
1.21 CUTTING AND REPAIRING
A. Unless otherwise specified hereinafter, the CONTRACTOR shall do all necessary cutting, drilling, fitting and patching of work and corresponding work that may be required to make several parts come together and fit it to receive, or be received, by work of other trades shown upon, or reasonably implied, by the Drawings and Specifications for the completed Project. Reference Contract Clause FAR 52.246-12, “Inspection of Construction.”
B. The CONTRACTOR shall be held responsible for all cutting, replacement, and repairing of work that is due to faulty workmanship and which is not specifically covered by Specifications for trades which are affected. The CONTRACTOR will also be held responsible for providing, without extra cost to the GOVERNMENT, any small incidental items which are not specifically mentioned in trade specifications, but which are necessary to complete the work in accordance with the Drawings, and under the general understanding that the work, when completed, shall be a finished and workmanlike job. Reference Contract Clause FAR 52.236-5, “Material and Workmanship,” and FAR 52.246-12, “Inspection of Construction.”
GENERAL REQUIREMENTS 010000 – 9
1.22 SITE CLEANUP
A. The CONTRACTOR shall maintain the construction site in as clean and orderly condition daily. All refuse and/or salvage material shall be gathered and disposed of periodically to maintain the site in this condition. Refer to Section 017419, CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL, for requirements on material disposal. All roadways, and roadway areas within the work area, or used by the CONTRACTOR, shall be kept free of construction debris, and associated mud, dirt, sand, or gravel that may be tracked from the construction work area by cleaning daily to assure safe operation of vehicles. The method of cleaning and equipment employed shall be subject to the approval of the CONTRACTING OFFICER. Reference Contract Clause FAR 52.236-12, “Cleaning Up.”
B. Dewatering techniques are a CONTRACTOR’s option; however, the CONTRACTING OFFICER shall approve the method prior to start of work.
C. Following completion of the work, the CONTRACTOR shall clean the entire area from any debris and/or excess of misplaced material due to the CONTRACTOR’s operation and obtain CONTRACTING OFFICER’s approval of this finished work. (Reference Contract Clause FAR 52.246-12, entitled “Inspection of Construction,” and FAR 52.236-12, “Cleaning Up.”)
1.23 LAYOUT AND GRADES
A. All lines and grade work not presently established at the site shall be laid out by the CONTRACTOR in accordance with the Drawings and Specifications. The CONTRACTOR shall maintain all established boundaries and benchmarks and replace as directed any which are destroyed or disturbed. Reference Contract Clause FAR 52.236-17, “Layout of Work.”
B. The CONTRACTOR shall engage a Professional Engineer or Registered Land Surveyor, licensed to practice in the State of North Carolina, to properly establish all locations, grades, elevations, dimensions, joints, etc., necessary to the proper location of all items of work included in this Contract. All such items shall be established in relation to the benchmark and control points noted on the Drawings.
C. Prior to acceptance of the facility and at such times as directed by the CONTRACTING OFFICER, the CONTRACTOR shall thoroughly clean all exposed surfaces of the building where work under this Contract was completed.
D. All protective coatings, except lacquers, shall be removed from finish surfaces and the finish surfaces shall be washed and cleaned. CONTRACTOR shall be held responsible for all damaged materials, and at completion, shall replace, at the CONTRACTOR’s own expense, all such damaged materials.
E. Reference Contract Clause FAR 52.236-12, “Cleaning Up,” and FAR 52.246-12, “Inspection of Construction.”
1.24 REFUSE AND SALVAGE MATERIALS:
GENERAL REQUIREMENTS 010000 – 10
A. Refer to Section 017419, CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL, for instruction regarding the disposal and recycling of onsite materials.
B. All refuse, debris, and construction waste shall be legally disposed of off Post at the CONTRACTOR’s expense. (Reference FAR 52.236-12 “Cleaning Up.”) Accumulations of refuse on the site will not be permitted.
C. All salvage property removed and not reinstalled under this Contract shall be returned to the GOVERNMENT at a place on base designated by the CONTRACTING OFFICER, or properly disposed of when directed by the GOVERNMENT.
D. Nonhazardous solid waste must be diverted to recycling, through appropriate means available to the CONTRACTOR, if such diversion is less than or equal to the equivalent cost of landfill or incineration.
E. Prior to Contract closeout the CONTRACTOR must supply a report, including the following:
1. Amount (in tons) of nonhazardous solid waste, including construction and demolition debris, that is composted, mulched, recycled, reused, donated or otherwise diverted from a disposal facility.
2. Amount (in tons) of solid waste (including construction and demolition debris) transferred to a disposal facility (landfill).
1.25 STORAGE
A. No secure storage space will be provided by the GOVERNMENT. The GOVERNMENT will not be responsible for property belonging to, or under the present control of the CONTRACTOR. The CONTRACTING OFFICER, or COTR, will designate an unsecured, open area for storage of construction equipment and materials during the period covered by this Contract. Reference Contract Clause FAR 52.236-10, “Operations and Storage Areas.” The CONTRACTOR shall protect CONTRACTOR’s materials.
B. The CONTRACTOR shall construct such temporary sheds, as may be required, for the use of workmen and as required for tool cribs and storage of all work under this Contract. Temporary sheds shall be confined to the space assigned by the CONTRACTING OFFICER, or COTR. Sheds shall be of approved construction and wood floors, lighting and heat shall be provided in all parts used by workmen. Exterior of sheds shall be painted, all parts maintained in good condition throughout the life of the Contract, and at completion, all parts shall be removed and the premises cleaned
up. Reference Contract Clauses FAR 52.236-10, “Operations and Storage Areas,” and FAR 52.236-12, “Cleaning Up.”
1.26 TEMPORARY FIELD OFFICES
A. As soon as practicable after award of Contract, and until final completion of the work, CONTRACTOR shall provide, maintain and later remove suitable temporary office(s).
All field offices shall be in good repair, painted on the exterior, provided with adequate
GENERAL REQUIREMENTS 010000 – 11
heating, lighting and maintained in a clean and sanitary condition at all times.
Reference Contract Clause FAR 52.236-10, “Operations and Storage Areas.”
B. The CONTRACTOR shall provide a separate secure trailer from that used by the Contractor with heating and air conditioning. It shall include a safe, securely anchored stairway from each means of egress with hand/guardrails/landings and ABA compliant ramp/landings with hand/guard rails at the main entry. This trailer shall include, as a minimum, two desks, two suitable chairs, access to a phone line and separate high speed internet connection at no additional cost to the GOVERNMENT. Trailer needs to be able to accommodate 12 people at construction meetings.
C. The CONTRACTOR is reminded that smoking in buildings on a GOVERNMENT facility is prohibited. A smoking area for employees, away from the main entrance of a building, must be provided.
1.27 TEMPORARY TOILET FACILITIES
A. The CONTRACTOR shall provide all temporary toilet facilities. The temporary toilet facilities shall meet the requirements of health authorities having jurisdiction and shall be kept clean and in a sanitary condition at all times.
1.28 TELEPHONE AND COMMUNICATIONS SECURITY MONITORING
A. The CONTRACTOR shall provide telephone service at the field office for personal and subcontractor use. Arrangements with the telephone company will be the responsibility of the CONTRACTOR, as well as all charges for installation, services and removal.
B. All communications with DOD organizations are subject to communications security (COMSEC) review. CONTRACTOR personnel will be aware telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. The DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, civilian CONTRACTOR personnel are advised any time they place a call to, or receive a call from, a DoD organization, they are subject to COMSEC procedures. The CONTRACTOR will assume the responsibility for ensuring wide and frequent dissemination of the above information to all employees dealing with DOD information.
1.29 UTILITIES
A. The CONTRACTING OFFICER has determined that GOVERNMENT-operated utilities are not adequate and will not be furnished to the CONTRACTOR. The Contractor shall be responsible for any and all permitting, fees, metering, etc. associated with the construction and acceptance of all utilities until accepted by the GOVERNMENT.
1.30 UTILITY INTERRUPTIONS
A. All utility shutdowns require the prior approval of the CONTRACTING OFFICER.
Request for utility shutdown shall be made in writing at least 4 weeks prior to the expected date of implementation. As soon as actual shutdown date is known, the
GENERAL REQUIREMENTS 010000 – 12
CONTRACTOR shall notify the CONTRACTING OFFICER, in writing, requesting approval at least 8 work days prior to requested shutdown.
B. The CONTRACTOR’s progress schedule shall include preliminary listing of all proposed shutdown dates. Every effort shall be made to make all shutdowns as brief as possible, and as limited in extent as possible.
1.31 PERMITS
A. The Contractor shall be responsible for any and all costs required for permitting associated with the construction and its acceptance.
1.32 COMPRESSED AIR
A. CONTRACTOR shall provide all compressed air used for work under this Contract, including temporary lines and connections. All temporary lines, etc., shall be removed at the completion of the work.
1.33 WEATHER PROTECTION AND TEMPORARY HEATING
A. The CONTRACTOR shall provide and maintain weather protection as may be required to properly protect all parts of the structure from damage during construction.
B. The CONTRACTOR shall be responsible for repairs and maintenance to the heating system or units during the period during progress of building construction and shall deliver same to the GOVERNMENT, at termination of such use, in perfect condition, duct cleaning and replacing all filters will be required even if the permanent HVAC system is not used for temporary heat, but run for Testing and Balancing purposes.
Any temporary heating shall be at the expense of the CONTRACTOR.
1.34 ARCHEOLOGICAL, PALEONTOLOGICAL AND ENDANGERED SPECIES FINDS
A. Any archeological finds (evidence of human occupation) or paleontological finds (evidence of prehistoric plant or animal life) are to be reported to the CONTRACTING OFFICER immediately and continue work in other areas without interruption. Protect native endangered flora and fauna and notify the CONTRACTING OFFICER of any construction activities that might threaten endangered species or their habitats.
1.35 REAL PROPERTY/EQUIPMENT REPORT
A. The CONTRACTOR shall furnish, upon completion of the Project, “Real Property Installed Cost,” form in triplicate, of all equipment installed in the facility, and the installed cost of each item. Furthermore, the listing shall include the location of each item and nameplate data.
B. Typically, the listing shall include: air conditioners, air handling units, condensers, fans, pumps, air compressors, transformers, unit heaters, regulators, direct current power supplies, latrine fixtures, motors, engines, motor or engine-driven equipment, drinking fountains, sinks, water coolers, generators, space heaters, water heaters, refrigerators, freezers, coolers, meters, gas detectors, humidifiers dehumidifier, air purifier, ovens, GENERAL REQUIREMENTS 010000 – 13 power units, fuel tanks, water tanks, elevators, welders, recorders, reels, scales, hydrants, intrusion detection equipment, fire detection and alarm equipment, emergency light sets, emergency eye wash, deluge showers, washers, dryers, dishwashers, bridge cranes, and like items of equipment.
C. Final payment will not be made to the CONTRACTOR until the GOVERNMENT has received and approved the listing. The CONTRACTOR shall use the “Real Property Installed Cost” form provided in the Preconstruction Contractor Guide or given at the Pre-performance Conference.
D. The Contractor shall submit DD Form 1354 allocating total contract amount to specific facilities as directed by the Contracting Officer.
1.36 DAMAGES, REPAIRS
A. All damages by the CONTRACTOR’s operations shall be repaired, or replaced, at the CONTRACTOR’s expense, as directed by the CONTRACTING OFFICER. Any GOVERNMENT property damaged as a result of the work, materials, or operations of the CONTRACTOR shall be restored at no additional expense to the GOVERNMENT.
B. All existing sidewalks, curbs, fencing, and pavement disturbed, broken or removed or otherwise damaged by the CONTRACTOR during performance of the work under this Contract shall be replaced by the CONTRACTOR at the CONTRACTOR’s own expense. Replaced sidewalks, curbs, and pavements shall be smooth, shall blend into the existing work, and shall not present depressions or humps.
C. Reference Contract Clause FAR 52.236-9, “Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements.”
1.37 AS-BUILT DRAWINGS
A. The CONTRACTOR shall keep an accurate record of all deviations from the approved design Drawings and Specifications which may occur in the work as actually constructed, and shall submit to the CONTRACTING OFFICER, at completion of the work, complete information including descriptions, Drawings, dimensions, marked prints, etc., as required for correction of the tracings to the as-built conditions. It is not sufficient to simply reference an addendum or change order.