Phase 2 Attachment 3 Supplemental Contract Requirements.pdf
PDF 141 KB Posted
- Attached to
- West 388th/419th Fighter Wing Apron at Hill AFB
- Solicitation number
- W9123822R0008
About this file
This document outlines requirements for a design-build contract to replace a fighter wing apron at Hill Air Force Base in Utah. The contract will remove and replace the pavement and sunshade shelters on the West portion of the 388th/419th Fighter Wing apron, with the majority of the existing 40-year old pavement identified as needing replacement. The scope of work involves removing the existing 12-inch thick concrete and replacing it with 15-inch thick concrete incorporating a stabilized drainage layer and new subbase materials. It will also dismantle and replace the sunshade shelters, remove and relocate existing crew shacks, and add one additional crew shack. The performance period is 730 calendar days, with liquidated damages of $1,927.18 per day of delay. The applicable wage determination is General Decision No. UT20210083 from SAM.gov.
View the file
Other files
Show 40 more
Latest 50 of 55 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 3
SUPPLEMENTAL CONTRACT REQUIREMENTS
1. Performance Period: Refer to contract section 00700, FAR 52.211-10. The performance period for the work stated above shall be 730 calendar days.
2. Liquidated Damages: Refer to contract section 00700, FAR 52.211-12, Liquidated Damages-Construction. Liquidated damages for this work are $1,927.18 for each day of delay.
3. Authorities: “Only a warranted Contracting Officer (either PCO or ACO) acting within their delegated limits has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer.”
4. Wage Determination: General Decision No. UT20210083, or its most current modification at the time of award is hereby applicable to work performed under this task order.
The most current decision or its modification can be found at:
SAM.gov
6. Time Extensions For Unusually Severe Weather: Refer to FAR 52.249-10, Default (Fixed- Priced Construction). All weather delay will need to be submitted and approved by the Contracting Officer Representative.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK-HILL AFB
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
(22) (19) (15) (07) (04) (03) (01) (02) (02) (05) (15) (22) https://sam.gov/wage-determination/UT20210083/5