Attachment 5 Price Schedule 20220729.pdf
PDF 87 KB Posted
- Attached to
- West 388th/419th Fighter Wing Apron at Hill AFB
- Solicitation number
- W9123822R0008
About this file
This solicitation is for a design-build contract to remove and replace the West portion of the 388th/419th Fighter Wing F-35 Apron at Hill Air Force Base in Utah. The existing sunshade shelters and pavement, which is approximately 40 years old and has exceeded its design life, will be removed and replaced. The awarded contractor will be responsible for performing the complete design and construction documents for a new 15-inch thick Portland cement concrete pavement section incorporating a stabilized drainage layer and new subbase course material. In addition to replacing the parking apron and shoulders, the project includes dismantling and replacing 26 existing sunshade structures with appropriately sized structures, one at each parking position. The contractor will also remove and relocate one existing crew shack and provide one additional crew shack so that each parking row has a crew shack. Upon completion, the apron will be re-marked. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Sacramento.
View the file
Other files
Show 40 more
Latest 50 of 55 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W9123822R0008 Price Schedule Page 1 of 2
W9123822R0008 Attachment 05 - Price Schedule
West 388th Apron Repair - Hill Air Force Base (HAFB), Utah (UT) 29 July 2022
Base Contract Line Item Number (CLIN) 0001: HAFB West 388th Apron Repairs
PRICING
ELEMENT
DESCRIPTION
QTY
UNIT OF
MEASURE
UNIT PRICE
TOTAL PRICE
01 Mobilization and Demobilization 1 Job
02 Demolition 1 Job
Provide and Operate Concrete Batch Plant
1 Job
Install New Portland Cement Concrete Pavement and Markings
1 Job
Demolish Existing Asphalt and Install New Asphalt
34,335 Square Feet
06 Demolish Existing Shade Structures 26 Each
Construct Shade Structure Foundations - Parking Positions 1 - 26
26 Each
Electrical Work from Crew Shacks to Sunshades
1 Job
Electrical Work (installation of the crew shack main electrical panels and electrical distribution from the crew shacks to the main power source)
1 Job
10 Communications 1 Job
Remove and Reinstall Existing Crew Shack
1 Job
12 Provide and Install New Crew Shack 1 Job
CLIN 0001 SUBTOTAL
W9123822R0008 Price Schedule Page 2 of 2
Option CLINs 1001 - 1007
CLIN DESCRIPTION QTY
UNIT OF
MEASURE
UNIT PRICE TOTAL PRICE
1001 Unstable Soil Replacement 4,206 Cubic Yards
1002 Asbestos Pipe Removal 500 Linear Feet
Provide and Install Shade Structures - Parking Positions 1 - 7
Each
Provide and Install Shade Structures - Parking Positions 8 - 13
6 Each
Provide and Install Shade Structures - Parking Positions 14 -20
7 Each
Provide and Install Shade Structures - Parking Positions 21 - 23
3 Each
Provide and Install Shade Structures - Parking Positions 24 - 26
3 Each
OPTION CLIN SUBTOTAL
TOTAL PROPOSED COST (including base and all options)