This specification section outlines temporary construction facilities and controls requirements for the restoration of Building 54 at the Navy Artifact facility. The project involves HVAC work and restoration of high density artifact storage cabinets. The contractor must provide temporary facilities including a bulletin board, signs, fencing, lighting, and security at the site. It specifies requirements for employee parking, identification, and sanitation facilities. The contractor must also maintain traffic control measures and dust control, and remove temporary facilities after completion of the work. The related solicitation is for the restoration work at DLA Building 54 issued by the Army Corps of Engineers Engineering District Norfolk on December 7, 2022 under solicitation number W91236-22-B-2041. Pricing and response dates are not provided.

View the file

Other files for this federal contract opportunity

Other files attached to DLA Building 54 Navy Artifact Restoration, newest first.
File Type Posted
B.01.02_22B2041 Abstract of Offers.pdf PDF
Attch 27 01 45 04.00 50.pdf PDF
W9123622B2041 Amendment 0011.pdf PDF
Amendment 10 Final.pdf PDF
Amendment 9 Final.pdf PDF
W9123622D2041 Amendment 0008.pdf PDF
W9123622B2041 Amendment 0006.pdf PDF
Attch 26 EL101.pdf PDF
Attch 23 M602.pdf PDF
Attch 17 FA101.pdf PDF
Attch 10 AD111.pdf PDF
Attch 1 Project Table of Contents 00 00 00.pdf PDF
22B2041 Amendment 0006.pdf PDF
Attch 25 M805.pdf PDF
Attch 20 MH111.pdf PDF
Attch 12 AD122.pdf PDF
Attch 4 01 45 35.pdf PDF
Attch 3 01 45 35 SI Schedule - 1-28-2022.pdf PDF
Attch 2 01 45 35 Statement of Special Inspections - 1 28 2022.pdf PDF
Attch 24 M801.pdf PDF
Attch 21 MP101.pdf PDF
Attch 18 MD101.pdf PDF
Attch 13 A111.pdf PDF
Attch 8 AD101.pdf PDF
Attch 7 08 33 23.pdf PDF
Attch 22 M601.pdf PDF
Attch 19 MH101.pdf PDF
Attch 16 A601.pdf PDF
Attch 15 A301.pdf PDF
Attch 14 A112.pdf PDF
Attch 11 AD112.pdf PDF
Attch 9 AD102.pdf PDF
Attch 6 03 30 53.pdf PDF
W9123622B2041 Amendment 0005.pdf PDF
22B2041 B54 HVAC Amendment 4.pdf PDF
19 Jan Site visit.pdf PDF
Amendment 0003 Final.pdf PDF
Amendment 0002 Final.pdf PDF
Amendment 0001 Final.pdf PDF
Site Visit 5 January.pdf PDF
A.01.13_0455737 NAO663A B54-HVAC-ARTIFACT-IFB-DRAWINGS.pdf PDF
A.01.13_0455737 NAO663A B54-ARTIFACT-SPECS.pdf PDF
W9123622B2041 IFB.pdf PDF
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DSCR W91236-17-D-0001-0455737

B54 HVAC NAVY ARTIFACT

SECTION 01 50 02.00 50

TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

08/09

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 241 (2013; Errata 2015) Standard for Safeguarding Construction,Alteration, and Demolition Operations

NFPA 70 (2020; ERTA 20-1 2020; ERTA 20-2 2020; TIA

20-1; TIA 20-2; TIA 20-3; TIA 20-4)

National Electrical Code

U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)

MUTCD (2009) Manual on Uniform Traffic Control Devices

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00.00 50

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Construction Site Plan; G

Traffic Control Plan; G

1.3 CONSTRUCTION SITE PLAN

Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.

SECTION 01 50 02.00 50 Page 1

PART 2 PRODUCTS

2.1 TEMPORARY SIGNAGE

2.1.1 Bulletin Board, Project Sign, and Project Safety Sign

Bulletin Board Immediately upon beginning of work, the Contractor shall provide a weatherproof glass-covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the contract, Wage Rate Information poster, and other information approved by the Contracting Officer. The bulletin board shall be located at the project site in a conspicuous place easily accessible to all employees, as approved by the Contracting Officer. Legible copies of the aforementioned data shall be displayed until work is completed. Upon completion of work the bulletin board shall be removed by and remain the property of the Contractor.

2.1.2 Project and Safety Signs

The requirements for the signs, their content, and location shall be provided at a location designated by the Contracting Officer. The signs shall be erected within 15 days after receipt of the Notice to Proceed.

The data required by the safety sign shall be corrected daily, with light colored metallic or non-metallic numerals. Upon completion of the project, the signs shall be removed and disposed of by the Contractor.

2.1.2.1 Project Sign

The project sign shall conform to the requirements as indicated on Attachment No.1, attached hereto.

2.1.2.2 Safety Sign

The safety sign shall conform to the requirements as indicated on Attachment No.1, attached hereto. The data required by the sign shall be corrected daily, with light colored metallic or nonmetallic numerals.

Numerals, including mounting hardware, shall be subject to the approval of the Contracting Officer.

2.2 TEMPORARY TRAFFIC CONTROL

2.2.1 Haul Roads

Construct access and haul roads necessary for proper prosecution of the work under this contract. Construct with suitable grades and widths;

sharp curves, blind corners, and dangerous cross traffic are be avoided.

Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times.

Location, grade, width, and alignment of construction and hauling roads are subject to approval by the Contracting Officer. Lighting must be adequate to assure full and clear visibility for full width of haul road and work areas during any night work operations.

2.2.2 Barricades

Erect and maintain temporary barricades to limit public access to hazardous areas. Whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities

SECTION 01 50 02.00 50 Page 2 or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic barricades will be required. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.

2.2.3 Fencing

Provide fencing along the construction site at all open excavations and tunnels to control access by unauthorized people.

a. The safety fencing must be a high visibility orange colored, high density polyethylene grid or approved equal, a minimum of 48 inches high and maximum mesh size of 2 inches, supported and tightly secured to steel posts located on maximum 10 foot centers, constructed at the approved location. Install fencing to be able to restrain a force of at least 250 pounds against it.

b. In addition, prior to the start of work, enclose those areas at the construction site which are not within the construction fence with a temporary safety fence, including gates and warning signs, to protect the public from construction activities. The safety fence shall match the base standard color (or bright orange where it protects excavated areas), shall be made of high density polyethylene grid or approved equal, a minimum of 42 inches high, supported and tightly secured to steel posts located on minimum 10 foot centers. Remove the fence from the work site upon completion of the contract.

2.3 TEMPORARY WIRING

Provide temporary wiring in accordance with NFPA 241 and NFPA 70 . Include frequent inspection of all equipment and apparatus.

2.4 Temporary Artifact Storage

Cabinets (high density units) will be disassembled and moved by DLA, DCSR and NHHC staff pr i or t o t he st ar t of t hi s cont r act . DLA, DSCR and NHHC st af f wi l l be r esponsi bl e f or r e- i nst al l at i on of t he HD Uni t s t o t he Ar t i f act r oom upon compl et i on of t he cont r act .

PART 3 EXECUTION

3.1 EMPLOYEE PARKING

Contractor employees will park privately owned vehicles in an area designated by the Contracting Officer. This area will not necessarily be within reasonable walking distance of the construction site. Contractor employee parking must not interfere with existing and established parking requirements of the government installation.

3.2 IDENTIFICATION OF EMPLOYEES

The Contractor shall be responsible for furnishing to each employee, and for requiring each employee engaged on the work to display identification as approved and directed by the Contracting Officer. Prescribed identification shall immediately be delivered to the Contracting Officer for cancellation upon release of any employee. When required, the Contractor shall obtain and provide fingerprints of persons employed on the project. Contractor and subcontractor personnel shall wear identifying markings on hard hats clearly identifying the company for whom

SECTION 01 50 02.00 50 Page 3 the employees works.

3.3 TEMPORARY BULLETIN BOARD

Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, as approved by the Contracting Officer.

3.4 AVAILABILITY AND USE OF UTILITY SERVICES

3.4.1 Temporary Utilities

Provide temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.

3.4.2 Payment for Utility Services

a. The Government will make all reasonably required utilities available to the Contractor from existing outlets and supplies, as specified in the contract.

3.4.3 Meters and Temporary Connections

At the Contractors expense and in a manner satisfactory to the Contracting Officer, provide and maintain necessary temporary connections, distribution lines, and meter bases (Government will provide meters) required to measure the amount of each utility used for the purpose of determining charges. Notify the Contracting Officer, in writing, 5 working days before final electrical connection is desired so that a utilities contract can be established. The Government will provide a meter and make the final hot connection after inspection and approval of the Contractor's temporary wiring installation. The Contractor will not make the final electrical connection.

3.4.4 Advance Deposit

An advance deposit for utilities consisting of an estimated month's usage or a minimum of $50.00 will be required. The last monthly bills for the fiscal year will normally be offset by the deposit and adjustments will be billed or returned as appropriate. Services to be rendered for the next fiscal year, beginning 1 October, will require a new deposit.

Notification of the due date for this deposit will be mailed to the Contractor prior to the end of the current fiscal year.

3.4.5 Final Meter Reading

Before completion of the work and final acceptance of the work by the Government, notify the Contracting Officer, in writing, 5 working days before termination is desired. The Government will take a final meter reading, disconnect service, and remove the meters. Then remove all the temporary distribution lines, meter bases, and associated paraphernalia.

Pay all outstanding utility bills before final acceptance of the work by the Government.

3.4.6 Sanitation

a. Provide and maintain within the construction area minimum field-type sanitary facilities approved by the Contracting Officer and periodically empty wastes into a municipal, district, or station

SECTION 01 50 02.00 50 Page 4 sanitary sewage system, or remove waste to a commercial facility.

Obtain approval from the system owner prior to discharge into any municipal, district, or commercial sanitary sewer system. Any penalties and / or fines associated with improper discharge will be the responsibility of the Contractor. Coordinate with the Contracting Officer and follow station regulations and procedures when discharging into the station sanitary sewer system. Maintain these conveniences at all times without nuisance. Include provisions for pest control and elimination of odors. Government toilet facilities will not be available to Contractor's personnel.

3.5 TRAFFIC PROVISIONS

3.5.1 Maintenance of Traffic

a. Conduct operations in a manner that will not close any thoroughfare or interfere in any way with traffic on railways or highways except with written permission of the Contracting Officer at least 15 calendar days prior to the proposed modification date, and provide a Traffic Control Plan detailing the proposed controls to traffic movement for approval. The plan must be in accordance with State and local regulations and the MUTCD, Part VI. Contractor may move oversized and slow-moving vehicles to the worksite provided requirements of the highway authority have been met.

b. Conduct work so as to minimize obstruction of traffic, and maintain traffic on at least half of the roadway width at all times. Obtain approval from the Contracting Officer prior to starting any activity that will obstruct traffic.

c. Provide, erect, and maintain, at contractors expense, lights, barriers, signals, passageways, detours, and other items, that may be required by the Life Safety Signage, overhead protection authority having jurisdiction.

3.5.2 Protection of Traffic

Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment the work, and the erection and maintenance of adequate warning, danger, and direction signs, will be as required by the State and local authorities having jurisdiction. Protect the traveling public from damage to person and property. Minimize the interference with public traffic on roads selected for hauling material to and from the site. Investigate the adequacy of existing roads and their allowable load limit. Contractor is responsible for the repair of any damage to roads caused by construction operations.

3.5.3 Dust Control

Dust control methods and procedures must be approved by the Contracting Officer. Treat dust abatement on access roads with applications of calcium chloride, water sprinklers, or similar methods or treatment.

SECTION 01 50 02.00 50 Page 5

3.6 CONTRACTOR'S TEMPORARY FACILITIES

3.6.1 Safety

Protect the integrity of any installed safety systems or personnel safety devices. If entrance into systems serving safety devices is required, the Contractor must obtain prior approval from the Contracting Officer. If it is temporarily necessary to remove or disable personnel safety devices in order to accomplish contract requirements, provide alternative means of protection prior to removing or disabling any permanently installed safety devices or equipment and obtain approval from the Contracting Officer.

3.6.2 Administrative Field Offices

Provide and maintain Contractor's administrative field office facilities.

The area for the Contractor's administrative field office facilities will not necessarily be within reasonable walking distance of the construction site. The Contractor shall provide transportation between the Contractor's administrative field office facilities and the construction site.

Government office and warehouse facilities will not be available to the Contractor's personnel.

3.6.3 Storage Area

Construct a temporary 6 foot high chain link fence around trailers and materials. Include plastic strip inserts, colored brown, so that visibility through the fence is obstructed. Fence posts may be driven, in lieu of concrete bases, where soil conditions permit. Do not place or store Trailers, materials, or equipment outside the fenced area unless such trailers, materials, or equipment are assigned a separate and distinct storage area by the Contracting Officer away from the vicinity of the construction site but within the installation boundaries. Trailers, equipment, or materials must not be open to public view with the exception of those items which are in support of ongoing work on any given day. Do not stockpile materials outside the fence in preparation for the next day's work. Park mobile equipment, such as tractors, wheeled lifting equipment, cranes, trucks, and like equipment within the fenced area at the end of each work day.

The area for the Contractor's storage area will not necessarily be within reasonable walking distance of the construction site. The Contractor shall provide transportation between the Contractor's storage area and the construction site. One-way travel distance from the storage area to the site of the work is approximately 2.5 miles.

3.6.4 Supplemental Storage Area

Upon Contractor's request, the Contracting Officer will designate another or supplemental area for the Contractor's use and storage of trailers, equipment, and materials. This area may not be in close proximity of the construction site but will be within the installation boundaries. Fencing of materials or equipment will not be required at this site; however, the Contractor is responsible for cleanliness and orderliness of the area used and for the security of any material or equipment stored in this area.

Utilities will not be provided to this area by the Government.

3.6.5 Appearance of Trailers

a. Trailers utilized by the Contractor for administrative or material

SECTION 01 50 02.00 50 Page 6 storage purposes must present a clean and neat exterior appearance and be in a state of good repair. Trailers which, in the opinion of the Contracting Officer, require exterior painting or maintenance will not be allowed on installation property.

3.6.6 Maintenance of Storage Area

a. Keep fencing in a state of good repair and proper alignment. Grassed or unpaved areas, which are not established roadways, will be covered with a layer of gravel as necessary to prevent rutting and the tracking of mud onto paved or established roadways, should the Contractor elect to traverse them with construction equipment or other vehicles; gravel gradation will be at the Contractor's discretion.

Mow and maintain grass located within the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers will be edged or trimmed neatly.

b. Cut grass (or annual weeds) within the construction and storage sites to a maximum 4 inch height at least once a week during the growing season unless the grass area is not visible to the public. Trim the grass around fences at time of grass cutting. Maintain grass or weeds on stockpiled earth as descried above.

3.6.7 Security Provisions

Provide adequate outside security lighting at the Contractor's temporary facilities. The Contractor will be responsible for the security of its own equipment; in addition, the Contractor will notify the appropriate law enforcement agency requesting periodic security checks of the temporary project field office.

3.6.8 Weather Protection of Temporary Facilities and Stored Materials

Take necessary precautions to ensure that roof openings and other critical openings in the building are monitored carefully. Take immediate actions required to seal off such openings when rain or other detrimental weather is imminent, and at the end of each workday. Ensure that the openings are completely sealed off to protect materials and equipment in the building from damage.

3.6.8.1 Building and Site Storm Protection

When a warning of gale force winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.

Precautions must include, but are not limited to, closing openings;

removing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work. Close openings in the work when storms of lesser intensity pose a threat to the work or any nearby Government property.

3.7 FIELD OFFICE

3.7.1 Trailer-Type Mobile Office

The Contractor may, at its option, furnish and maintain a trailer-type mobile office acceptable to the Contracting Officer and providing as a minimum the facilities specified above. Securely anchor the trailer to the ground at all four corners to guard against movement during high winds.

SECTION 01 50 02.00 50 Page 7

3.8 TEMPORARY PROJECT SAFETY FENCING

As soon as practicable, but not later than 15 days after the date established for commencement of work, furnish and erect temporary project safety fencing at the work site. Maintain the safety fencing during the life of the contract and, upon completion and acceptance of the work, will become the property of the Contractor and be removed from the work site.

3.9 CLEANUP

Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store any salvageable materials resulting from demolition activities within the fenced area described above or at the supplemental storage area. Neatly stack stored materials not in trailers, whether new or salvaged.

3.10 RESTORATION OF STORAGE AREA

Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and any other temporary products from the site.

After removal of trailers, materials, and equipment from within the fenced area, remove the fence that will become the property of the Contractor.

Restore areas used by the Contractor for the storage of equipment or material, or other use to the original or better condition. Remove gravel used to traverse grassed areas and restore the area to its original condition, including top soil and seeding as necessary.

-- End of Section --