This amendment modifies solicitation W9123621R2005 for the Air Force Targeting Center Facility project at Joint Base Langley-Eustis. The amendment provides revisions to technical specifications, drawings, and documents related to furniture specifications. Specification revisions include additions to sections on glazing types and shower pans. Revised drawings depict showers, nursing rooms, interior details, door schedules, storefronts, finish plans and erosion control details. The opportunity description indicates the project will construct a new facility for the 25th Air Force to support command and control of targeting and threat analysis. The facility must meet DoD, Air Force and Langley standards and be designed as a permanent structure in compliance with UFC requirements and DoD antiterrorism standards. The scope also includes site work, generators, parking and support facilities.
View the file
Other files for this federal contract opportunity
Show all 50
Air Force Targeting Center, Langley AFB - Solicitation has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation W9123621R2005 Air Force Targeting Center Facility, Joint Base Langley-Eustis, Hampton, VA is hereby amended as follow s:
1. Technical information is revised per questions asked in ProjNet. Please see the continuation page for breakout of technical documents revisions. Documents referenced in this amendment are uploaded to beta.SAM.
Contracting POC: Axel Doody 757-201-7712 Axel.F.Doody@usace.army.mil
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-Dec-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9123621R2005
X 9B. DATED (SEE ITEM 11)
03-Nov-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-Dec-2020
CODE
USACE, NORFOLK DISTRICT OFFICE
CONTRACTING OFFICE
803 FRONT STREET
NORFOLK VA 23510-1011
W91236 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9123621R2005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The following have been added by full text:
AMENDMENT 0006 DETAILS
Description of Change:
A. “Langley Furniture Qty” is uploaded to beta.SAM as an addendum to the “Furniture Specification Package”.
The follows documents are also uploaded to beta.SAM:
B. Specification Revisions:
1. Specs_V1_Revised_00 00 00_TOC
2. Specs_V2_Revised_08 81 00
a. Added notes to paragraph 3.5.b.2 and 3.5.c.2 Glazing Types GL-5 & GL-7
b. Added glazing types to paragraph 3.6 Laminated Glass Schedule GL-6 & GL-8
2. Specs_V3_Revised_22 00 00
a. Added paragraph 2.10 & 2.10.1 Shower Pan
C. Drawing Revisions:
Volume 1
1. Vol.1B_Revised_Sheet A-411, ARCHITECTURAL, ENLARGED PLANS AND ELEVATIONS –
SHOWERS AND NURSING ROOM
2. Vol.1B_Revised_Sheet A-521, DETAILS, INTERIOR- ACOUSTIC & WOOD
3. Vol.1B_Revised_Sheet A-601, ARCHITECTURAL, DOOR SCHEDULE – LEVEL 1
4. Vol.1B_Revised_Sheet A-602, ARCHITECTURAL, DOOR SCHEDULE – LEVEL 2
5. Vol.1B_Revised_Sheet A-607, ARCHITECTURAL, INTERIOR STOREFRONTS – LEVEL 2
6. Vol.1B_Revised_Sheet I-001, INTERIORS, INTERIOR NOTES AND FINISH LEGEND
7. Vol.1B_Revised_Sheet IN101A, INTERIORS, INTERIOR FINISH PLAN - FIRST FLOOR – AREA A
8. Vol.1B_Revised_Sheet IN102C, INTERIORS, INTERIOR FINISH PLAN- SECOND FLOOR-AREA C
Remarks: During the most recent DEQ correspondence, our team realized a few STANDARD Detail links were broken and did not plot. For that reason, we are providing the following sheets:
9. Vol.1A_Revised_Sheet CG-111, EROSION & SEDIMENT CONTROL DETAILS
10. Vol.1A_Revised_Sheet CG-112, EROSION & SEDIMENT CONTROL DETAILS
11. Vol.1A_Revised_Sheet CG-113, EROSION & SEDIMENT CONTROL DETAILS
12. Vol.1A_Revised_Sheet X-002, TRAFFIC DETAILS
Volume 2
N/A
SECTION 00 72 00 - GENERAL CONDITIONS
The following have been modified:
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
PLANS:
1. 2020RTA_AFTC_Vol.1A
2. 2020RTA_AFTC_Vol.1B
3. 2020RTA_AFTC_Vol.2
SPECS:
4. 20201124_RTA_Specs_V1_Div_00-06_Consolidated
5. 20201124_RTA_Specs_V2_Div_07-14_Consolidated
6. 20201124_RTA_Specs_V3_Div_21-25_Consolidated
7. 20201124_RTA_Specs_V4_Div_26-33_Appendix_Consolidated
8. 20190411_Furniture_specification_package_Amendment_2 (1)
9. JBLE-Langley AF TCF - NTCRA ESS Construction Support (20181115) DRAFT
Amendment 0006 revisions:
A. “Langley Furniture Qty” is uploaded to beta.SAM as an addendum to the “Furniture Specification Package”.
The follows documents are also uploaded to beta.SAM:
B. Specification Revisions:
1. Specs_V1_Revised_00 00 00_TOC
2. Specs_V2_Revised_08 81 00
a. Added notes to paragraph 3.5.b.2 and 3.5.c.2 Glazing Types GL-5 & GL-7
b. Added glazing types to paragraph 3.6 Laminated Glass Schedule GL-6 & GL-8
3. Specs_V3_Revised_22 00 00
a. Added paragraph 2.10 & 2.10.1 Shower Pan
C. Drawing Revisions:
Volume 1
1. Vol.1B_Revised_Sheet A-411, ARCHITECTURAL, ENLARGED PLANS AND ELEVATIONS –
SHOWERS AND NURSING ROOM
2. Vol.1B_Revised_Sheet A-521, DETAILS, INTERIOR- ACOUSTIC & WOOD
3. Vol.1B_Revised_Sheet A-601, ARCHITECTURAL, DOOR SCHEDULE – LEVEL 1
4. Vol.1B_Revised_Sheet A-602, ARCHITECTURAL, DOOR SCHEDULE – LEVEL 2
5. Vol.1B_Revised_Sheet A-607, ARCHITECTURAL, INTERIOR STOREFRONTS – LEVEL 2
6. Vol.1B_Revised_Sheet I-001, INTERIORS, INTERIOR NOTES AND FINISH LEGEND
7. Vol.1B_Revised_Sheet IN101A, INTERIORS, INTERIOR FINISH PLAN - FIRST FLOOR – AREA A
8. Vol.1B_Revised_Sheet IN102C, INTERIORS, INTERIOR FINISH PLAN- SECOND FLOOR-AREA C
Remarks: During the most recent DEQ correspondence, our team realized a few STANDARD Detail links were broken and did not plot. For that reason, we are providing the following sheets:
9. Vol.1A_Revised_Sheet CG-111, EROSION & SEDIMENT CONTROL DETAILS
10. Vol.1A_Revised_Sheet CG-112, EROSION & SEDIMENT CONTROL DETAILS
11. Vol.1A_Revised_Sheet CG-113, EROSION & SEDIMENT CONTROL DETAILS
12. Vol.1A_Revised_Sheet X-002, TRAFFIC DETAILS
(End of clause)
(End of Summary of Changes)