This solicitation package includes specifications for renovations to Building 11 at the Defense Supply Center Richmond in Virginia. The solicitation seeks bids for removal and salvage of historic construction materials, including concrete, masonry, metals, doors and windows, equipment, and electrical fixtures. Bidders must submit qualifications demonstrating experience with whole-building recycling and historic material removal. The solicitation requires dust control, protection of existing historic structures, and compliance with environmental regulations for hazardous materials. Salvaged and recycled materials must be stored daily in designated areas. The U.S. Army Corps of Engineers is the contracting agency, and bids must be submitted electronically by the specified due date.

View the file

Other files for this federal contract opportunity

Other files attached to DLA Warehouse 11 Renovation, newest first.
File Type Posted
Warehouse 11 KO Signed Page 1.pdf PDF
Warehouse 11 page 3.pdf PDF
Warehouse 11 page 4.pdf PDF
Warehouse 11 page 2.pdf PDF
ProjNet Responses Amend 7.pdf PDF
20-B-0017 Amendment 7.pdf PDF
20-B-0017 Amendment 6.pdf PDF
AD102.pdf PDF
23 52 43.00 20.pdf PDF
A-501.pdf PDF
08 51 00.pdf PDF
G-001.pdf PDF
AD103.pdf PDF
PD102.pdf PDF
A-133.pdf PDF
09 29 00.pdf PDF
A-134.pdf PDF
A-136.pdf PDF
01 33 29.pdf PDF
01 11 00.05 50.pdf PDF
A-321.pdf PDF
A-311.pdf PDF
01 32 01.00 10.pdf PDF
A-403.pdf PDF
A-401.pdf PDF
PROJECT.pdf PDF
20B0017 Amendment 5.pdf PDF
A-132.pdf PDF
A.01.13 Specs Table of Contents.pdf PDF
A.01.13 A-321.pdf PDF
A.01.13 AD100.pdf PDF
A.01.13 A-100.pdf PDF
A.01.13 07 54 19.pdf PDF
A.01.13 A-403.pdf PDF
A.01.13 10 81 00.pdf PDF
A.01.13 A-113.pdf PDF
A.01.13 A-501.pdf PDF
A.01.13 A-111.pdf PDF
A.01.13 A-112.pdf PDF
A.01.13 A-310.pdf PDF
A.01.13 A-202.pdf PDF
A.01.13 A-201.pdf PDF
A.01.13 A-203.pdf PDF
20-B-0017 Amendment 3.pdf PDF
A.01.13 A-116.pdf PDF
WH 11 Site Visit.pdf PDF
_RTA_Reno_to_Bldg_11_DDRV_Full_Plan_Set.pdf PDF
_P_2015_01503_003_specs_RTA.pdf PDF
A.01.13 WH11 Final Specifications.pdf PDF
20-F-0017 WH 11.pdf PDF
Show all 50

DLA Warehouse 11 Renovation has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renovations to Building 11 DDRV Solicitation No.: W91236-20-B-0017 DSCR Richmond, Virginia

SECTION TABLE OF CONTENTS

DIVISION 02 - EXISTING CONDITIONS

SECTION 02 42 91

REMOVAL AND SALVAGE OF HISTORIC CONSTRUCTION MATERIALS

11/18

PART 1 GENERAL

1.1 REFERENCES

1.2 PROJECT DESCRIPTION

1.2.1 Dust Control

1.2.2 Protection

1.2.2.1 Protection of Existing Historic Property

1.2.2.2 Protection From the Weather

1.2.2.3 Environmental Protection

1.3 SUBMITTALS

1.4 QUALIFICATIONS

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 HAZARDOUS MATERIALS

3.2 SALVAGED ITEMS

3.2.1 Concrete

3.2.2 Masonry

3.2.3 Metals

3.2.4 Doors and Windows

3.2.5 Equipment and Specialty Items

3.2.6 Electrical Equipment

3.3 RECYCLED MATERIALS

3.4 DISPOSITION OF MATERIALS

3.4.1 Material Salvaged for the Contractor

3.4.2 Items Salvaged for the Government

3.4.3 Items Salvaged for the Using Service

3.5 CLEAN-UP

-- End of Section Table of Contents --

SECTION 02 42 91 Page 1

FOR CONSTRUCTION

Amendment 1

SECTION 02 42 91

REMOVAL AND SALVAGE OF HISTORIC CONSTRUCTION MATERIALS

11/18

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910.1000 Air Contaminants

29 CFR 1926.55 Gases, Vapors, Fumes, Dusts, and Mists

40 CFR 261 Identification and Listing of Hazardous Waste

1.2 PROJECT DESCRIPTION

The work includes removal and salvage of identified historic items and materials, and removal of resulting rubbish and debris. General demolition of non-historic materials and removal of resulting rubbish and debris must comply with the requirements of Section 02 41 00 DEMOLITION.

Store salvaged or recycled materials daily in areas and in a manner specified by the Contracting Officer. In the interest of conservation, pursue salvage and recycling to the maximum extent possible. Submit a Work Plan that includes procedures proposed for the accomplishment of the work. The Work Planprocedures must provide for safe conduct of the work, careful removal and disposition of materials specified to be salvaged or recycled, dust control, protection of property which is to remain undisturbed, coordination with other work in progress, and timely disconnection of utility services. Include a detailed description of the methods and equipment to be used for each operation, and the sequence of operations in the Work Plan.

1.2.1 Dust Control

Control the amount of dust resulting from removal, salvage and demolition operations to prevent the spread of dust to occupied portions of the construction site, to avoid creation of a nuisance in the surrounding area and to minimize occupational exposures. Occupational exposures cannot exceed the requirements in 29 CFR 1910.1000 and 29 CFR 1926.55 . Use of water to control dust will not be permitted when it will result in, or create, damage to existing building materials and hazardous or objectionable conditions such as ice, flooding and pollution.

1.2.2 Protection

1.2.2.1 Protection of Existing Historic Property

Survey the site and examine the drawings and specifications to determine

SECTION 02 42 91 Page 2 the extent of work before beginning any removal, salvage or demolition work. Take necessary precautions to avoid damage to existing historic items that are to remain in place, to be reused, or to remain the property of the Government. Repair or restore items damaged by the Contractor to original condition, or replace, as approved by the Contracting Officer.

Coordinate the work of this section with all other work and construct and maintain shoring, bracing and supports, as required. Ensure that structural elements are not overloaded and provide additional supports as may be required as a result of any cutting, removal, or demolition work performed under this contract.

1.2.2.2 Protection From the Weather

Protect the interior of buildings to remain and salvageable materials from the weather at all times. Store salvaged historic materials off the ground and under weathertight covering.

1.2.2.3 Environmental Protection

Comply with the requirements of Section 02 82 16.00 20 EINGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS and 02 83 13.00 20 LEAD IN CONSTRUCTION. Ensure a thorough inspection has been performed for hazardous materials prior to beginning work.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Work Plan ; G

1.4 QUALIFICATIONS

Provide qualified workers trained and experienced in whole-building recycling, including removal and salvage of historic materials. Submit documentation of five consecutive years of work of this type with a list of similar projects identifying when, where, and for whom the work was done. Provide a current point-of-contact for identified references.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 HAZARDOUS MATERIALS

Unforeseen hazardous materials may exist in wall cavities, beneath floors, in chases, inside various components, as well as other building materials. Exercise extreme care when performing demolition and salvage operations to ensure unexpected hazardous materials area not inadvertently disturbed creating a potential exposure concern. If suspect hazardous

SECTION 02 42 91 Page 3 materials are observed or encountered, stop work and notify the Contracting Officer immediately.

3.2 SALVAGED ITEMS

Salvage items to the maximum extent possible. Remove historic items to be salvaged from the structure prior to demolition work. Remove salvageable items by hand labor to the maximum extent possible. Do not damage historic portions of the structure to remain or items identified for salvage. Remove furnishings, equipment, and materials not scheduled for salvage or recycling prior to any salvaging procedures. Keep a complete recording of all salvaged materials including the condition of such materials before, and after, salvage operations.

3.2.1 Concrete

Remove intact and salvage the following concrete items: precast architectural.

3.2.2 Masonry

Remove intact and salvage the following masonry items: brick cornerstones.

3.2.3 Metals

Remove intact and salvage the following metal items: ladders architectural metalwork gratings and metal walkways.

Amendment 1

3.2.4 Thermal and Moisture Protection

Remove intact and salvage the following materials: gutters, leaders, and downspouts.

Amendment 1

3.2.4 Doors and Windows

Remove doors and windows with associated hardware and operating mechanisms intact (including glass) and salvagein accordance with the schedule.

3.2.5 Equipment and Specialty Items

Remove intact and salvage the following equipment and specialty items:

chalkboards and tackboards.

3.2.6 Electrical Equipment

Remove intact and salvage the following electrical fixtures and equipment: telecommunications equipment.

3.3 RECYCLED MATERIALS

Recycle materials to the maximum extent possible. Use hand labor wherever possible to remove recyclable materials. Do not damagehistoric portions of the structure indicated to remain and items identified for salvage while removing materials for recycling. Recycle the following materials:

dimension lumber scrap wood paper and cardboard glass metals.

SECTION 02 42 91 Page 4

3.4 DISPOSITION OF MATERIALS

The Contractor, upon receipt of notice to proceed, is vested with the title to materials and equipment to be demolished, except Government and using service salvage and historical items. The Government will not be responsible for the condition, loss or damage to such property after notice to proceed.

3.4.1 Material Salvaged for the Contractor

Temporarily store salvaged material as approved by the Contracting Officer and remove from Government property before completion of the contract.

Sale of salvaged material on the site is prohibited.

3.4.2 Items Salvaged for the Government

Remove salvaged items to remain the property of the Government in a manner to prevent damage, packed or crated to protect the items from damage, or as directed by the Contracting Officer. Repair or replace items damaged during removal or storage to match existing items. Properly label and identify containers as to contents. Deliver items reserved as property of the Government to the areas designated: as directed by the Contracting Officer.

3.4.3 Items Salvaged for the Using Service

Prior to commencement of work under this contract, remove items reserved as property of the using service: as direted by the Contracting Officer.

3.5 CLEAN-UP

Upon completion of the work, clean portions of structure to remain and adjacent areas and structures of dust, dirt, and debris caused by salvage and demolition operations. Verify that debris and rubbish created by the work is non-hazardous. If any debris and rubbish is suspect hazardous waste characterize it in accordance with 40 CFR 261 . If the debris and rubbish is determined to be hazardous materials notify the Contracting Officer. Remove and transport non-hazardous debris and rubbish in a manner that prevents spillage on streets or adjacent areas. Transport and dispose of all material in accordance with all local, state and Federal regulations. Provide copies of all disposal manifests to the the Contracting Officer.

-- End of Section --