Revised_Attachment_8_-_Daily_Expenditure_Report_Updated_09_May_2018.xlsx

XLSX spreadsheet 85 KB Posted

Attached to
Advanced Contract Initiative (ACI) Temporary Emergency Power (TEMP)
Solicitation number
W911WN-18-R-3005
Issued by

About this file

This document outlines a federal contract opportunity for advanced contract initiative temporary emergency power support. The U.S. Army Corps of Engineers Pittsburgh District will award four contracts to provide generator set installation, fueling, operation, maintenance and repair services in response to natural and man-made disasters. The contracts will cover four geographical quadrants aligned with FEMA regions, with values not to exceed $75-110 million each. Contractors must be able to mobilize resources within 21-24 hours of a task order. Selection will be based on a best value tradeoff evaluation of technical and price proposals submitted in response to a solicitation expected on or around March 5th, with proposals due 30 days thereafter. Services will involve assessing power needs and installing, fueling, operating, maintaining and repairing government-provided diesel generators ranging from 5KW to 3MW at critical public facilities.

Revised Attachment 8 - Daily Expenditure Report

View the file

Other files

File Type Posted
Amendment_5.pdf PDF
Amendment_4.pdf PDF
Revised_Attachment_1_-_Rate_Schedule_Updated_09_May_2018.xlsx XLSX spreadsheet
Revised_TEMPLATE_TABLE_A3-1_Production_Rates_-_09_May_2018.xlsx XLSX spreadsheet
Conformed_Contract_-_10_May_2018.pdf PDF
Amendment_3.pdf PDF
Conformed_Contract_25_April_2018.pdf PDF
Amendment_02.pdf PDF
Revised_Attachment_1_-_Rate_Schedule_Updated_04_April_2018.xlsx XLSX spreadsheet
Revised_Attachment_8_-_Daily_Expenditure_Report_Updated_05_Feb_2018.xlsx XLSX spreadsheet
Revised_TEMPLATE_TABLE_A3-1_Production_Rates.xlsx XLSX spreadsheet
Revised_Attachment_15_-_Small_Biz_Participation_Proposal_Updated_03_April_2018.pdf PDF
W911WN-18-R-3005-0004.pdf PDF
Attachment_10_-_Emergency_Power_Deployment_Packages.pdf PDF
Attachment_1_-_Rate_Schedule_Updated_05_Feb_2018.xlsx XLSX spreadsheet
TEMPLATE_TABLE_A3-1_Production_Rates.xlsx XLSX spreadsheet
Attachment_5_-_PreInstallation_Work_Order_Updated_05_Feb_2018.pdf PDF
RFP_W911WN-18-R-3005.pdf PDF
Attachment_7_-_Deinstallation_Work_Order_Updated_05_Feb_2018_.pdf PDF
Attachment_8_-_Daily_Expenditure_Report_Updated_05_Feb_2018_.xlsx XLSX spreadsheet
Attachment_6_-_Installation_Work_Order_Updated_05_Feb_2018.pdf PDF
Attachment_9_-_DER_Acceptance_Memo.pdf PDF
TEMPLATE_TABLE_B2-1_Asset_Location.xlsx XLSX spreadsheet
TEMPLATE_TABLE_B3-1_Labor_Qual_Certs_Template.xlsx XLSX spreadsheet
Attachment_3_-_Generator_Power_Packs_Updated_05_Feb_2018.pdf PDF
Attachment_13_-_Deployment_Package_Descriptions_Updated_05_Feb_2018.pdf PDF
TEMPLATE_TABLE_B3-2_Equip_Salient_Features_Template.xlsx XLSX spreadsheet
Attachment_15_-_Small_Biz_Participation_Proposal_Updated_26_Feb_2018.pdf PDF
Attachment_17_-_Generator_Inventories_Updated_21_Feb_2018.xlsx XLSX spreadsheet
Attachment_14_-_Past_Performance_Questionaire_Updated_05_Feb_2018.pdf PDF
Attachment_4_-_Generator_Maintenance_Profile_Updated_05_Feb_2018.pdf PDF
Attachment_2_-_BOM_Kit_Updated_05_Feb_2018.pdf PDF
Attachment_16_-_Utilization_of_Small_Biz_Collection_Sheet_Updated_13_Feb_2018.pdf PDF
Attachment_12_-_Wage_Determination_Rates_Updated_05_Feb_2018.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DER Summary

Task Order Number
Cost
Labor Rates$0
Date:xx Mon year
Equipment Rates$0
ISB:
Mob/Demob$0

Servicing Gens $0

Reimbursables$0
Total Cost:
$0.00

ATTACHMENT 8 - Daily Expenditure Report

DER Day 1

Task Order NumberDay 1
RegularStandbyCost
Labor Rates00$0
Date:Day 1RegularStandbyCost
Equipment Rates00$0
ISB:Mob MilesDemob MilesCost
Mob/Demob00$0.00
QuantityCost
Servicing Gens0$0
Cost
Reimbursables$0.00

Day 1 Expenditure: $0.00

Task Order #:Day 1
ISB: DEP: (date)Base YearQuantityDaily
Line ItemLabor RatesRegularStandbyRegularStandbyCost
L01Operations Manager$0
L02Site Manager$0
L03Admin Support$0
L04Yard Superintendent$0
L05Fuel Manager$0
L06Quality Control Manager$0
L07Safety Officer$0
L08Equipment Operator$0
L09Mechanical Team Leader$0
L10Electrical Team Leader$0
L11Mechanic$0
L12Electrician$0
L13Laborer$0
L14Truck Driver$0
L15"contractor labor"$0
L16"contractor labor"$0
L17"contractor labor"$0
L18"contractor labor"$0
Lxx"contractor labor"$0
Labor RatesDay 1
RegularStandbyCost
Totals:00$0
Base YearDay 1
Rate (Day)QuantityDaily
Line ItemEquipment RatesRegularStandbyRegularStandbyCost
E01Crane, Hyd, Self-Propelled (capacity)$0
E02Fork Lift, Rough Terrain,(capacity)$0
E03Lighting Sets, Trailer Mounted 1500 W$0
E04Truck, Pick-up, (capacity)$0
E05Truck, Highway,(capacity)$0
E06Truck, Semi Tractor$0
E07Truck Trailer, Flatbed, <= 15 ton$0
E08Truck Trailer, Flatbed, > 15 ton$0
E09Truck Trailer, Lowboy, <= 50 ton$0
E10Truck Trailer, Lowboy, > 50 ton$0
E11Truck Trailer, Fuel Tanker$0
E12Truck, Fuel, <1000 gal$0
E13Truck, Fuel, 1000 to 4,000 gal$0
E14Truck, Fuel, > 4000 gal$0
E15Tank, Fuel Storage$0
E16Fuel Caddy$0
E17Pump, Fuel, Portable (flow rate)$0
E18Pressure Washer, Low$0
E19Pressure Washer, High$0
E20Office Trailer$0
E21Trailer Euipment stoage$0
E22Conex Container Storage$0
E23Load Bank, < 500 kW$0
E24"contractor equipment"$0
Exx"contractor equipment"$0
Equipment RatesDay 1
RegularStandbyCost
Totals:00$0
Base YearDay 1
Rate per MileActualDaily
Line ItemMobilization/DemobilizatonNTE 200 MilesMob MilesDemob MilesCost
ME02Fork Lift, Rough Terrain,(capacity)$0.00
ME03Lighting Sets, Trailer Mounted 1500 W$0.00
ME15Tank, Fuel Storage$0.00
ME16Fuel Caddy$0.00
ME17Pump, Fuel, Portable$0.00
ME18Pressure Washer, Low, < 5000 psi$0.00
ME19Pressure Washer, High >= 5000 psi$0.00
ME20Office Trailer$0.00
ME21Trailer Euipment storage$0.00
ME22Conex Container Storage$0.00
ME23Load Bank, < 500 kW$0.00
ME24"contractor equipment"$0.00
MEXX"contractor equipment"$0.00
Mob/DemobDay 1
Mob MilesDemob MilesCost
Totals:00$0.00
Base YearDay 1
Rate perDaily
Line ItemParts for Servicing GeneratorsServiceQuantityCost
P010 to 29 kW$0.00
P0230 to 59 kW$0.00
P0360 to 99 kW$0.00
P04100 to 199 kW$0.00
P05200 to 299 kW$0.00
P06300 to 399 kW$0.00
P07400 to 499 kW$0.00
P08500 to 699 kW$0.00
P09700 to 900 kW$0.00
P10901 kW to 1.9MW$0.00
P112 - 3 MW$0.00
Servicing GensDay 1
QuantityCost
Totals:0$0.00
Base YearDay 1
Actual CostsDaily
Line ItemReimbursable ItemsUnitPriceQuantityCost
R1Diesel Fuel - GeneratorsGallons$0.00
R2Fuel for Government Vehicles - GasGallons$0.00
R3Fuel for Government Vehicles - DieselGallons$0.00
R4Travel CostsLSna1
R5Materials and SuppliesLSna1
R6Credit for Recycling BOMLSna1
R7Other Negotiated ItemsLSna1
ReimbursablesDay 1
Cost
Totals:$0.00
Contract:Event Name:
T.O #:
Date:
Day:
ISB:
CategoryLine No.NamePositionCompanyWork LocationStatus (R/S/R&R)Shift (D/N)Per Diem (Y/N)Per Diem Cost Per DayAirline Flight (OW)TaxiAirport Parking Per NightAirline Bag Fee (First Bag)Airline Bag Fee (Second Bag)Lodging Per NightLodging Taxes Per NightHotel Parking Per DayRental CarRental Truck
L1RegularDY$$$$$$$$$$$
L1RegularDY$$$$$$$$$$$
L1StandbyDY$$$$$$$$$$$
L1StandbyDY$$$$$$$$$$$
L1RegularDY$$$$$$$$$$$
L1RegularDY$$$$$$$$$$$
L1R&RNY$$$$$$$$$$$
L1RegularNY$$$$$$$$$$$
L1RegularDY$$$$$$$$$$$
L1RegularNY$$$$$$$$$$$
L1RegularDY$$$$$$$$$$$
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L1
L1
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L1
L1
L2
L2
L2
L2
L2
L2
L2

&14Attachment 8 - Daily Expenditure Report

&P

DER Day 2

Task Order NumberDay 1
RegularStandbyCost
Labor Rates00$0
Date:Day 1RegularStandbyCost
Equipment Rates00$0
ISB:Mob MilesDemob MilesCost
Mob/Demob00$0.00
QuantityCost
Servicing Gens0$0
Cost
Reimbursables$0.00

Day 1 Expenditure: $0.00

Task Order #:Day 1
ISB: DEP: (date)Base YearQuantityDaily
Line ItemLabor RatesRegularStandbyRegularStandbyCost
L01Operations Manager$0
L02Site Manager$0
L03Admin Support$0
L04Yard Superintendent$0
L05Fuel Manager$0
L06Quality Control Manager$0
L07Safety Officer$0
L08Equipment Operator$0
L09Mechanical Team Leader$0
L10Electrical Team Leader$0
L11Mechanic$0
L12Electrician$0
L13Laborer$0
L14Truck Driver$0
L15"contractor labor"$0
L16"contractor labor"$0
L17"contractor labor"$0
L18"contractor labor"$0
Lxx"contractor labor"$0
Labor RatesDay 1
RegularStandbyCost
Totals:00$0
Base YearDay 1
Rate (Day)QuantityDaily
Line ItemEquipment RatesRegularStandbyRegularStandbyCost
E01Crane, Hyd, Self-Propelled (capacity)$0
E02Fork Lift, Rough Terrain,(capacity)$0
E03Lighting Sets, Trailer Mounted 1500 W$0
E04Truck, Pick-up, (capacity)$0
E05Truck, Highway,(capacity)$0
E06Truck, Semi Tractor$0
E07Truck Trailer, Flatbed, <= 15 ton$0
E08Truck Trailer, Flatbed, > 15 ton$0
E09Truck Trailer, Lowboy, <= 50 ton$0
E10Truck Trailer, Lowboy, > 50 ton$0
E11Truck Trailer, Fuel Tanker$0
E12Truck, Fuel, <1000 gal$0
E13Truck, Fuel, 1000 to 4,000 gal$0
E14Truck, Fuel, > 4000 gal$0
E15Tank, Fuel Storage$0
E16Fuel Caddy$0
E17Pump, Fuel, Portable (flow rate)$0
E18Pressure Washer, Low$0
E19Pressure Washer, High$0
E20Office Trailer$0
E21Trailer Euipment stoage$0
E22Conex Container Storage$0
E23Load Bank, < 500 kW$0
E24"contractor equipment"$0
Exx"contractor equipment"$0
Equipment RatesDay 1
RegularStandbyCost
Totals:00$0
Base YearDay 1
Rate per MileActualDaily
Line ItemMobilization/DemobilizatonNTE 200 MilesMob MilesDemob MilesCost
ME02Fork Lift, Rough Terrain,(capacity)$0.00
ME03Lighting Sets, Trailer Mounted 1500 W$0.00
ME15Tank, Fuel Storage$0.00
ME16Fuel Caddy$0.00
ME17Pump, Fuel, Portable$0.00
ME18Pressure Washer, Low, < 5000 psi$0.00
ME19Pressure Washer, High >= 5000 psi$0.00
ME20Office Trailer$0.00
ME21Trailer Euipment storage$0.00
ME22Conex Container Storage$0.00
ME23Load Bank, < 500 kW$0.00
ME24"contractor equipment"$0.00
MEXX"contractor equipment"$0.00
Mob/DemobDay 1
Mob MilesDemob MilesCost
Totals:00$0.00
Base YearDay 1
Rate perDaily
Line ItemParts for Servicing GeneratorsServiceQuantityCost
P010 to 29 kW$0.00
P0230 to 59 kW$0.00
P0360 to 99 kW$0.00
P04100 to 199 kW$0.00
P05200 to 299 kW$0.00
P06300 to 399 kW$0.00
P07400 to 499 kW$0.00
P08500 to 699 kW$0.00
P09700 to 900 kW$0.00
P10901 kW to 1.9MW$0.00
P112 - 3 MW$0.00
Servicing GensDay 1
QuantityCost
Totals:0$0.00
Base YearDay 1
Actual CostsDaily
Line ItemReimbursable ItemsUnitPriceQuantityCost
R1Diesel Fuel - GeneratorsGallons$0.00
R2Fuel for Government Vehicles - GasGallons$0.00
R3Fuel for Government Vehicles - DieselGallons$0.00
R4Travel CostsLSna1
R5Materials and SuppliesLSna1
R6Credit for Recycling BOMLSna1
R7Other Negotiated ItemsLSna1
ReimbursablesDay 1
Cost
Totals:$0.00
Contract:Event Name:
T.O #:
Date:
Day:
ISB:
CategoryLine No.NamePositionCompanyWork LocationStatus (R/S/R&R)Shift (D/N)Per Diem (Y/N)Per Diem Cost Per DayAirline Flight (OW)TaxiAirport Parking Per NightAirline Bag Fee (First Bag)Airline Bag Fee (Second Bag)Lodging Per NightLodging Taxes Per NightHotel Parking Per DayRental CarRental Truck
L1RegularDY$54$-$-$-$-$-$125$35$15$-$100
L1RegularDY$54$-$-$-$-$-$125$35$-$-$-
L1StandbyDY$54$-$-$-$-$-$135$35$15$-$100
L1StandbyDY$56$-$-$-$-$-$195$35$-$35$-
L1RegularDY$56$-$-$-$-$-$195$35$-$35$-
L1RegularDY$$-$-$-$-$-$195$35$-$-$-
L1R&RNY$$-$-$-$-$-$195$35$14$35$-
L1RegularNY$$-$-$-$-$-$149$14$-$-$-
L1RegularDY$$-$-$-$-$-$149$14$-$-$-
L1RegularNY$$-$-$-$-$-$171$25$-$-$-
L1RegularDY$$-$-$-$-$-$171$25$21$0$-
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L1
L1
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L1
L1
L2
L2
L2
L2
L2
L2
L2

&14Attachment 8 - Daily Expenditure Report

&P

DER Day 3

Task Order NumberDay 1
RegularStandbyCost
Labor Rates00$0
Date:Day 1RegularStandbyCost
Equipment Rates00$0
ISB:Mob MilesDemob MilesCost
Mob/Demob00$0.00
QuantityCost
Servicing Gens0$0
Cost
Reimbursables$0.00

Day 1 Expenditure: $0.00

Task Order #:Day 1
ISB: DEP: (date)Base YearQuantityDaily
Line ItemLabor RatesRegularStandbyRegularStandbyCost
L01Operations Manager$0
L02Site Manager$0
L03Admin Support$0
L04Yard Superintendent$0
L05Fuel Manager$0
L06Quality Control Manager$0
L07Safety Officer$0
L08Equipment Operator$0
L09Mechanical Team Leader$0
L10Electrical Team Leader$0
L11Mechanic$0
L12Electrician$0
L13Laborer$0
L14Truck Driver$0
L15"contractor labor"$0
L16"contractor labor"$0
L17"contractor labor"$0
L18"contractor labor"$0
Lxx"contractor labor"$0
Labor RatesDay 1
RegularStandbyCost
Totals:00$0
Base YearDay 1
Rate (Day)QuantityDaily
Line ItemEquipment RatesRegularStandbyRegularStandbyCost
E01Crane, Hyd, Self-Propelled (capacity)$0
E02Fork Lift, Rough Terrain,(capacity)$0
E03Lighting Sets, Trailer Mounted 1500 W$0
E04Truck, Pick-up, (capacity)$0
E05Truck, Highway,(capacity)$0
E06Truck, Semi Tractor$0
E07Truck Trailer, Flatbed, <= 15 ton$0
E08Truck Trailer, Flatbed, > 15 ton$0
E09Truck Trailer, Lowboy, <= 50 ton$0
E10Truck Trailer, Lowboy, > 50 ton$0
E11Truck Trailer, Fuel Tanker$0
E12Truck, Fuel, <1000 gal$0
E13Truck, Fuel, 1000 to 4,000 gal$0
E14Truck, Fuel, > 4000 gal$0
E15Tank, Fuel Storage$0
E16Fuel Caddy$0
E17Pump, Fuel, Portable (flow rate)$0
E18Pressure Washer, Low$0
E19Pressure Washer, High$0
E20Office Trailer$0
E21Trailer Euipment stoage$0
E22Conex Container Storage$0
E23Load Bank, < 500 kW$0
E24"contractor equipment"$0
Exx"contractor equipment"$0
Equipment RatesDay 1
RegularStandbyCost
Totals:00$0
Base YearDay 1
Rate per MileActualDaily
Line ItemMobilization/DemobilizatonNTE 200 MilesMob MilesDemob MilesCost
ME02Fork Lift, Rough Terrain,(capacity)$0.00
ME03Lighting Sets, Trailer Mounted 1500 W$0.00
ME15Tank, Fuel Storage$0.00
ME16Fuel Caddy$0.00
ME17Pump, Fuel, Portable$0.00
ME18Pressure Washer, Low, < 5000 psi$0.00
ME19Pressure Washer, High >= 5000 psi$0.00
ME20Office Trailer$0.00
ME21Trailer Euipment storage$0.00
ME22Conex Container Storage$0.00
ME23Load Bank, < 500 kW$0.00
ME24"contractor equipment"$0.00
MEXX"contractor equipment"$0.00
Mob/DemobDay 1
Mob MilesDemob MilesCost
Totals:00$0.00
Base YearDay 1
Rate perDaily
Line ItemParts for Servicing GeneratorsServiceQuantityCost
P010 to 29 kW$0.00
P0230 to 59 kW$0.00
P0360 to 99 kW$0.00
P04100 to 199 kW$0.00
P05200 to 299 kW$0.00
P06300 to 399 kW$0.00
P07400 to 499 kW$0.00
P08500 to 699 kW$0.00
P09700 to 900 kW$0.00
P10901 kW to 1.9MW$0.00
P112 - 3 MW$0.00
Servicing GensDay 1
QuantityCost
Totals:0$0.00
Base YearDay 1
Actual CostsDaily
Line ItemReimbursable ItemsUnitPriceQuantityCost
R1Diesel Fuel - GeneratorsGallons$0.00
R2Fuel for Government Vehicles - GasGallons$0.00
R3Fuel for Government Vehicles - DieselGallons$0.00
R4Travel CostsLSna1
R5Materials and SuppliesLSna1
R6Credit for Recycling BOMLSna1
R7Other Negotiated ItemsLSna1
ReimbursablesDay 1
Cost
Totals:$0.00
Contract:Event Name:
T.O #:
Date:
Day:
ISB:
CategoryLine No.NamePositionCompanyWork LocationStatus (R/S/R&R)Shift (D/N)Per Diem (Y/N)Per Diem Cost Per DayAirline Flight (OW)TaxiAirport Parking Per NightAirline Bag Fee (First Bag)Airline Bag Fee (Second Bag)Lodging Per NightLodging Taxes Per NightHotel Parking Per DayRental CarRental Truck
L1RegularDY$54$-$-$-$-$-$125$35$15$-$100
L1RegularDY$54$-$-$-$-$-$125$35$-$-$-
L1StandbyDY$54$-$-$-$-$-$135$35$15$-$100
L1StandbyDY$56$-$-$-$-$-$195$35$-$35$-
L1RegularDY$56$-$-$-$-$-$195$35$-$35$-
L1RegularDY$$-$-$-$-$-$195$35$-$-$-
L1R&RNY$$-$-$-$-$-$195$35$14$35$-
L1RegularNY$$-$-$-$-$-$149$14$-$-$-
L1RegularDY$$-$-$-$-$-$149$14$-$-$-
L1RegularNY$$-$-$-$-$-$171$25$-$-$-
L1RegularDY$$-$-$-$-$-$171$25$21$0$-
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L1
L1
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L1
L1
L2
L2
L2
L2
L2
L2
L2

&14Attachment 8 - Daily Expenditure Report

&P

DER Day 4

Task Order NumberDay 1
RegularStandbyCost
Labor Rates00$0
Date:Day 1RegularStandbyCost
Equipment Rates00$0
ISB:Mob MilesDemob MilesCost
Mob/Demob00$0.00
QuantityCost
Servicing Gens0$0
Cost
Reimbursables$0.00

Day 1 Expenditure: $0.00

Task Order #:Day 1
ISB: DEP: (date)Base YearQuantityDaily
Line ItemLabor RatesRegularStandbyRegularStandbyCost
L01Operations Manager$0
L02Site Manager$0
L03Admin Support$0
L04Yard Superintendent$0
L05Fuel Manager$0
L06Quality Control Manager$0
L07Safety Officer$0
L08Equipment Operator$0
L09Mechanical Team Leader$0
L10Electrical Team Leader$0
L11Mechanic$0
L12Electrician$0
L13Laborer$0
L14Truck Driver$0
L15"contractor labor"$0
L16"contractor labor"$0
L17"contractor labor"$0
L18"contractor labor"$0
Lxx"contractor labor"$0
Labor RatesDay 1
RegularStandbyCost
Totals:00$0
Base YearDay 1
Rate (Day)QuantityDaily
Line ItemEquipment RatesRegularStandbyRegularStandbyCost
E01Crane, Hyd, Self-Propelled (capacity)$0
E02Fork Lift, Rough Terrain,(capacity)$0
E03Lighting Sets, Trailer Mounted 1500 W$0
E04Truck, Pick-up, (capacity)$0
E05Truck, Highway,(capacity)$0
E06Truck, Semi Tractor$0
E07Truck Trailer, Flatbed, <= 15 ton$0
E08Truck Trailer, Flatbed, > 15 ton$0
E09Truck Trailer, Lowboy, <= 50 ton$0
E10Truck Trailer, Lowboy, > 50 ton$0
E11Truck Trailer, Fuel Tanker$0
E12Truck, Fuel, <1000 gal$0
E13Truck, Fuel, 1000 to 4,000 gal$0
E14Truck, Fuel, > 4000 gal$0
E15Tank, Fuel Storage$0
E16Fuel Caddy$0
E17Pump, Fuel, Portable (flow rate)$0
E18Pressure Washer, Low$0
E19Pressure Washer, High$0
E20Office Trailer$0
E21Trailer Euipment stoage$0
E22Conex Container Storage$0
E23Load Bank, < 500 kW$0
E24"contractor equipment"$0
Exx"contractor equipment"$0
Equipment RatesDay 1
RegularStandbyCost
Totals:00$0
Base YearDay 1
Rate per MileActualDaily
Line ItemMobilization/DemobilizatonNTE 200 MilesMob MilesDemob MilesCost
ME02Fork Lift, Rough Terrain,(capacity)$0.00
ME03Lighting Sets, Trailer Mounted 1500 W$0.00
ME15Tank, Fuel Storage$0.00
ME16Fuel Caddy$0.00
ME17Pump, Fuel, Portable$0.00
ME18Pressure Washer, Low, < 5000 psi$0.00
ME19Pressure Washer, High >= 5000 psi$0.00
ME20Office Trailer$0.00
ME21Trailer Euipment storage$0.00
ME22Conex Container Storage$0.00
ME23Load Bank, < 500 kW$0.00
ME24"contractor equipment"$0.00
MEXX"contractor equipment"$0.00
Mob/DemobDay 1
Mob MilesDemob MilesCost
Totals:00$0.00
Base YearDay 1
Rate perDaily
Line ItemParts for Servicing GeneratorsServiceQuantityCost
P010 to 29 kW$0.00
P0230 to 59 kW$0.00
P0360 to 99 kW$0.00
P04100 to 199 kW$0.00
P05200 to 299 kW$0.00
P06300 to 399 kW$0.00
P07400 to 499 kW$0.00
P08500 to 699 kW$0.00
P09700 to 900 kW$0.00
P10901 kW to 1.9MW$0.00
P112 - 3 MW$0.00
Servicing GensDay 1
QuantityCost
Totals:0$0.00
Base YearDay 1
Actual CostsDaily
Line ItemReimbursable ItemsUnitPriceQuantityCost
R1Diesel Fuel - GeneratorsGallons$0.00
R2Fuel for Government Vehicles - GasGallons$0.00
R3Fuel for Government Vehicles - DieselGallons$0.00
R4Travel CostsLSna1
R5Materials and SuppliesLSna1
R6Credit for Recycling BOMLSna1
R7Other Negotiated ItemsLSna1
ReimbursablesDay 1
Cost
Totals:$0.00
Contract:Event Name:
T.O #:
Date:
Day:
ISB:
CategoryLine No.NamePositionCompanyWork LocationStatus (R/S/R&R)Shift (D/N)Per Diem (Y/N)Per Diem Cost Per DayAirline Flight (OW)TaxiAirport Parking Per NightAirline Bag Fee (First Bag)Airline Bag Fee (Second Bag)Lodging Per NightLodging Taxes Per NightHotel Parking Per DayRental CarRental Truck
L1RegularDY$54$-$-$-$-$-$125$35$15$-$100
L1RegularDY$54$-$-$-$-$-$125$35$-$-$-
L1StandbyDY$54$-$-$-$-$-$135$35$15$-$100
L1StandbyDY$56$-$-$-$-$-$195$35$-$35$-
L1RegularDY$56$-$-$-$-$-$195$35$-$35$-
L1RegularDY$$-$-$-$-$-$195$35$-$-$-
L1R&RNY$$-$-$-$-$-$195$35$14$35$-
L1RegularNY$$-$-$-$-$-$149$14$-$-$-
L1RegularDY$$-$-$-$-$-$149$14$-$-$-
L1RegularNY$$-$-$-$-$-$171$25$-$-$-
L1RegularDY$$-$-$-$-$-$171$25$21$0$-
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L1
L1
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L2
L1
L1
L2
L2
L2
L2
L2
L2
L2

&14Attachment 8 - Daily Expenditure Report

&P

File details come from the government source that posted it. Updated .