Attachment_13_-_Deployment_Package_Descriptions_Updated_05_Feb_2018.pdf
PDF 645 KB Posted
- Attached to
- Advanced Contract Initiative (ACI) Temporary Emergency Power (TEMP) Federal contract opportunity
- Solicitation number
- W911WN-18-R-3005
About this file
This document outlines requirements for four Advanced Contract Initiative (ACI) Temporary Emergency Power contracts to be awarded by the U.S. Army Corps of Engineers Pittsburgh District. Services required under the contracts include assessing power needs, installing up to 3MW diesel generators provided by FEMA, fueling, operating, maintaining and repairing generators at critical public facilities during disaster relief efforts. Contractors must be able to deploy resources within 21-24 hours of a task order. Four geographical contracts valued up to $75-110 million each will be awarded, covering FEMA Regions I-X and Puerto Rico/US Virgin Islands. Proposals are due 30 days after a March 5, 2018 solicitation. Contractors may bid on any or all areas. Awards will be made using Best Value tradeoff considering technical and price factors outlined in the Request for Proposal.
Attachment 13 - Deployment Package Descriptions
View the file
Other files for this federal contract opportunity
Show all 34
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 13 – Deployment Package Descriptions
Background Information and Deployment Package Types
Background Information USACE has the capability to provide local and state officials broad support for their unmet emergency power needs in coordination with other federal partners such as the Federal Emergency Management Agency (FEMA) and the Department of Energy. This support ranges from technical expertise/assistance to complete management of an emergency power mission including the procurement, installation, and operation of generators. USACE assets required to provide this support include the U.S. Army 249 th Engineer Battalion “Prime Power” (249th), Emergency Power Planning and Response Teams (PRTs) from across USACE, USACE-contracted forces (known as the Advanced Contracting Initiative (ACI) contractor), and USACE Deployable Tactical Operations Systems (DTOS) for communications.
The video listed below highlights the USACE Emergency Power mission and assists emergency planners in understanding the capabilities and implementation of temporary emergency power missions during a disaster.
www.youtube.com/watch?v=cOGaPwlxu0w
During Emergency Power response activities, facilities requiring generators are typically prioritized in the following order:
Life Saving Facilities (911 centers, police, fire stations, and medical facilities) Life Sustaining Facilities (water and wastewater treatment facilities, shelters, and pumping facilities) Other municipal facilities to reinstitute local command and control, and post-event recovery
Technical Assistance Technical assistance the USACE assets can provide before, during, or after an event, includes but is not limited to:
Performing all hazards emergency power planning Assessing emergency power requirements for a facility Assessing conditions and capabilities of existing emergency generation equipment Assessing damaged electrical distribution systems and equipment Completing safety inspections of electrical distribution systems and equipment Troubleshooting, repairing, and operating emergency generation/distribution equipment Installing, operating, fueling, and maintaining emergency power generation equipment
Power Mission Management Complete management of an emergency power mission the USACE assets can provide, includes but is not limited to:
Providing assistance to state and local officials in determining priorities for generator assessments and installations at critical public facilities Procuring and/or leasing generators using USACE’s pre-established contracting tools Assessing facilities to determine generator suitability, placement/location and identification/configuration Preparing, hauling, and installing generators Operating, fueling, servicing, and maintaining installed generators
De-installing generators, which may include remediation of the generator installation site to its pre-installation site condition
Servicing and repairing generators prior to their return to long-term storage, which may include load testing
Replenishing Bill of Materials (BOM) used during execution of the mission
Generator Maintenance Operational maintenance of FEMA generators is performed by a combination of FEMA-contracted support and USACE-contracted support. FEMA-contracted support maintains generators on a routine basis at their long-term storage location. USACE-contracted (ACI contractor) support maintains generators during an emergency and prior to returning generators to their long-term storage location.
Deployment Package Types To align with FEMA’s National Response Framework and to streamline USACE’s response, USACE developed five (5) deployment package for all USACE assets required to support and execute an emergency power mission. The deployment packages are (in order from smallest to largest):
1. Type V Deployment Package
2. Type IV Deployment Package
3. Type III Deployment Package
4. Type II Deployment Package
5. Type I Deployment Package
Attachment 10, Emergency Power USACE Deployment Package, details the Power PRT, 249th and DTOS/CTOC requirements. The table below, ACI Contractor Deployment Packages, details the ACI contractor requirements.
ACI Contractor Deployment Packages Type I Type II Type III Type IV Type V
Initial FEMA-Provided
Generators & BOM
Type II base package plus additional types and quantities of assets.
2 power packs 2 BOM kit >5-acre staging area
1 power pack 1 BOM kit 5-acre staging area
1 power pack 1 BOM kit 5-acre staging area
No ACI Contractor Listed for situational awareness of Offerors
Additional Generator & BOM
Requirements
10 trailer-mounted generators
4 spools of larger cable
5 trailer-mounted generators
2 spools of larger cable
Not Applicable Not Applicable
ACI Contractor Installations
Haul & install 35 generators/day
CONUS: one-way distance of 150 miles
OCONUS: one-way distance of 100 miles
Haul & install 25 generators/day
CONUS: one-way distance of 150 miles
OCONUS: one-way distance of 100 miles
Haul & install 10 generators/day
CONUS: one-way distance of 150 miles
OCONUS: one-way distance of 100 miles
Not Applicable
Mission Operational Period
24/7 operations 21 installations during the day 14 installations at night Staging area operations at night
24/7 operations 20 installations during the day 5 installations at night Staging area operations at night
24/7 operations 10 installations during the day No installations at night Staging area operations at night
Not Applicable
ACI
Contractor-Provided
Fuel
Sufficient for staging area operations for 4 days
Sufficient for 2 days of installations and generator operations
Sufficient for staging area operations for 4 days
Sufficient for 2 days of installations and generator operations
Sufficient for staging area operations for 4 days
Sufficient for 2 days of installations and generator operations
Not Applicable
Staging Area Generator
1 FEMA generator available for use
1 FEMA generator available for use
1 FEMA generator available for use
Not Applicable
*Note 1: All package configurations exclude OCONUS airlift.
*Note2: Advon Team for OCONUS missions is not shown. This team initiates agreements with local vendors and identifies available resources.