This document is an addendum to a solicitation for the construction of a Latrine Annex Building at Fort Benning, Georgia. The solicitation number is W911SF-20-B-0001 and is issued by the Department of the Army Materiel Command Mission and Installation Contracting Command at Fort Eustis. The addendum provides responses to 34 questions from prospective offerors. Key details include confirmation that the basis of design shall follow CMU, brick veneer, and standing seam metal roof construction. A value engineered HVAC system may be proposed if it meets performance requirements. Soil testing and engineering are required. Sod must be installed for 25 feet beyond the building perimeter and maintained for six months after occupancy.
View the file
Other files for this federal contract opportunity
Show all 50
Construct Latrine Annex Building has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT TITLE: Latrine Annex Building 3010, Fort Benning, Georgia
SUBJECT: W911SF‐20‐B‐0001 Addendum No. 1 – RFI Comment Changes
Upon review and responding to request for information changes from soliciting contractors for the subject solicitation, the following changes to the solicitation documents are required:
1. Section L Instructions to Bidders, of the solicitation, Note 1, indicates that the bid opening is on Wednesday, 12 March 2020.
A. The day of the week is revised to read Thursday 12th of March 2020. The time remains unchanged.
2. Section L Instructions to Bidders, of the solicitation, Note 5, indicates that questions concerning this IFB shall be submitted in writing and received no later than Wednesday, 24 February 2020.
A. The day of the week is revised to read Monday 24th of February 2020. The time remains unchanged.
01 General Requirements
3. Please verify that the government will furnish all CAD files that are associated with the current bid drawings. We will utilize them to complete the overall design.
A. Yes. The government will furnish all CAD files that are associated with the current bid drawings.
4. Please verify that the basis of design shall be followed as closely as possible. In other words please verify that a CMU, Brick Veneer, Standing Seam Metal Roof is the required exterior construction type. On past projects competitors were permitted to construct pre cast non‐conventional structures that did not follow the SOW or bid drawing intent. It would make it very difficult for the government to compare apples to apples.
A. Yes. The basis of design shall be followed as closely as possible i.e., CMU, Brick Veneer, Standing Seam Metal Roof is the required exterior construction type.
5. Is the 144r available for this project? If so will it be distributed with an update?
A. See attached 144r.
6. Will a Life Safety Analysis be required of the contractors design team?
A. No. A Life Safety Analysis will NOT be required of the contractors design team.
22 Plumbing
7. The plumbing specification in the project solicitation is not downloadable. Will a plumbing specification be provided in a solicitation update?
A. See attached Plumbing spec, UFGS 22 00 00 Plumbing, General Purpose.
23 HVAC
8. The ERV appears to be quite large and may not fit in the mezzanine space. Will a value engineered HVAC system be acceptable if it meets current scope, Fort Benning, and Energy Code requirements?
A. Yes. A value engineered HVAC system WILL be acceptable if it meets current scope, Fort Benning, and Energy Code requirements.
26 Electrical
9. Will a lightning protection system with UL‐Master Label be required for the latrine annex?
A. No. A lightning protection system with UL‐Master Label will NOT be required for the latrine annex.
28 Electronic Safety and Security
10. Will FA or MNS systems be required for this facility? None are shown in the SOW or bid drawings.
A. No. An FA or MNS systems will NOT be required for this facility.
11. Attached please find the dimensions of the HVAC unit to be placed on the mezzanine. Given the size of the unit, it will need to be set prior to installing roof trusses or a structural opening large enough to install the unit will need to be considered. The unit has a ten (10) to twelve (12) week lead time after shop drawing approval. This will add barriers to the ability to complete the project in 180 days. Plus, once installed the 4x4 removable ceiling will not be adequate for future equipment removal/replacement.
a. Should we proceed as shown?
A. A value engineered HVAC system WILL be acceptable if it meets current performance‐based scope, Fort Benning, and Energy Code requirements.
12. The 20” dia duct from the HVAC unit serving the entrance door area will conflict with mezzanine access ladder/landing. How does the Government want to address this conflict?
A. A value engineered HVAC system WILL be acceptable if it meets current performance‐based scope, Fort Benning, and Energy Code requirements.
13. Please confirm which panel contractor will tie in to for latrine power.
A. Panel NL which is located inside the latrine.
14. What is the distance from the electrical panel to the latrine work site?
A. There is no distance, per se. The panelboard is inside the latrine. This is a new service not associated w/ the existing Bldg 3010.
15. Please confirm that contractor is only responsible to stub out water and sewer 4 feet from latrine.
A. No. Per drawings 44054_14_P1 and 44054_15_P2, Contractor is to stub both sewer and water 5 feet outside the perimeter of the latrine.
16. Please identify what entity is responsible for the cost of the utility company to make the water and sewer connections.
A. The Government will pay the Utility company to make the final connections to water, and sewer utility lines that the contractor has extended to the point of demarcation (5 foot line) shown on the drawings.
17. Please provide the Government's expectation of the hand railing system for the mezzanine. Are they standard pipe rails or can they be made out of FRT wood materials?
A. Per Drawing 44054_6_A2, 001 General 1.7 COMPLETE THE BUILDING'S STRUCTURAL DESIGN FOR LOAD BEARING WALLS, MEZZANINE, CEILING AND ROOF STRUCTURAL SYSTEMS. FRAMING SYSTEM
SHALL BE FIRE RETARDANT TREATED (FRT) WOOD OR STEEL AT CONTRACTOR'S OPTION.
This shall be changed to remove FRT Wood and leave steel as the only option.
a. Are they a one line or two line guard rail systems?
A. Handrail shall be a two line guard rail system.
18. Please provide a specification on the mezzanine ladder required for access to the mezzanine.
A. Steel Telescopic attic stair equal to the basis of design manufactured by Calvert Attic Stairs Calvert USA, Inc. Dolomnons MD 20688 support@calvertstairs.com. Minimum dimensions of door 27.5" w x 43" long nominal; self‐adjusting height, handrail pulldown rod.
19. Please provide the wall assemblies for the plumbing chase walls. Are they CMU walls or framed and sheathed walls?
A. Chase walls are 4"x8"x16" CMU w/ an 8" wide interstitial space.
20. Please confirm that the contractor must install sod to extend 25' beyond the building perimeter and must maintain and water the sod for six months after beneficial occupancy per the project documents.
A. Yes. The contractor must install sod to extend 25' beyond the building perimeter and must maintain and water the sod for six months until sod has been established and taken root and cannot be pulled up by the use of a stiff steel garden rake of 2 inch tines.
21. Sheet A.6 doesn't seem to scale correctly. Can the Government please confirm that the drawing available on BetaSam has the correct scale shown on the drawing?
A. Recommend using the graphic scale provided.
22. Please confirm that a complete a lig site layout and contour grading plan designed by a Professional Civil Engineer is required along with the NPDES/BMP design.
A. Yes. A complete a surveyed site layout and contour grading plan designed by a Professional Civil
Engineer is required along with the NPDES/BMP design.
23. Please confirm that a soil testing of the site soils is a required design submittal and that a professional Geotech engineer must certify that the design of the project has been developed consistent with the industries standards.
A. Yes. Soil testing of the site soils is a required design submittal and that a professional Geotech engineer must certify that the design of the project has been developed consistent with the industries standards.
24. Section 4 Masonry paragraph #2 states that “the building shall be constructed with 8” polished faced concrete units laid in a stacked bond”. Is this correct?
A. No. Per the drawings, exterior walls shall be 8”x8”x16” standard CMU with steel reinforced in‐wall pilasters with all un‐reinforced cells filled with foamed in place insulation. Interior chase walls shall be
4”x8”x16” standard CMU with an 8” interstitial space.
25. Will the engineered structural dwgs be acceptable for the required “masonry shop dwgs” if the structural dwgs contains the information required in the SOW?
A. Yes. The engineered structural dwgs WILL be acceptable as the required “masonry shop dwgs” if the structural dwgs contain the information required in the SOW.
26. Please confirm that a masonry sample panel will be required to be built for the Governments approval prior to starting the masonry work.
A. Yes. A masonry sample panel WILL be required to be built for the Government’s approval prior to starting the masonry work.
27. The masonry spec’s require that “A qualified masonry inspector approved by the Contracting
Officer shall perform the inspection of the masonry work”. Can the Government please provide a list of pre‐approved inspectors or can we deem that if the inspector meets the minimum qualifications outlined in paragraph Masonry 1.5.1 the Government will accept and approve the testing firm?
A. If the inspector meets the minimum qualifications outlined in paragraph Masonry 1.5.1 the
Government will accept and approve the testing firm.
28. Please confirm that the water service for this project is terminated 5’‐0” outside bldg. and that
CWW will bring service to the location 5’‐0” outside the building.
A. Yes. The water service for this project shall be terminated 5’‐0” outside the bldg. perimeter and CWW will bring service to the location 5’‐0” outside the building.
29. Please confirm that the Government requires the building pad to be undercut to a minimum of
2’‐0’ below the bottom of the footings regardless of pending soil test results. The building pad is then to be constructed out of engineered fill material.
A. Yes. The Government requires the building pad to be undercut to a minimum of 2’‐0’ below the bottom of the footings because no soils tests were undertaken during the RFP preparation. However if the pending soil test results prove the existing soils adequate and at the discretion of the Designer of
Record’s Geotech Engineer, the undercutting requirement can be lessened with Government approval.
a. If required to undercut can this excess soil be redistributed (balanced) on site or will the contractor be required to export this soil.
A. Yes. Excess soil resulting from undercutting operations CAN be redistributed (balanced) on site provided positive drainage away from the building is maintained. Otherwise, excess soils will have to be exported.
b. Does the Government have any special specifications or requirements on the engineered fill material?
A. Yes. Per the SOW (paragraph 9, page 24), all structural areas shall be compacted to 98% of the standard proctor, which shall be performed by a materials testing laboratory. All soils, both original and fill, shall be tested in accordance with the procedures outlined in the ASTM manual regarding nuclear density gauge testing.
30. Please provide a specification or acceptable manufacture information on the required
“perforated fiber reinforced plastic faced plywood” for the latrine ceiling. Unable to locate “perforated” frp plywood panels from our suppliers.
A. Per Drawing 44054_10_A6, ceiling panels shall be Pre‐finished FRT fiber reinforced panels with
2”x1/4” solid FRT plastic battens in a 4’x4’ pattern. Perforated is NOT required.
31. Please clarify if the contractor will be required to provide 100% stamped
Architectural/Mechanical/Plumbing and Electrical drawings by an outside design firm or will the project be built with the Government’s current A/MEP designs. We fully understand that civil and structural designs are the responsibility of the contractor.
A. Contractor is required to bring all drawings to a 100% design completion. The main items of work such as architectural materials and finishes, exterior and interior, plumbing, and electrical will be maintained. A value engineered HVAC system WILL be acceptable if it meets current scope, Fort Benning, and Energy Code requirements. Structural drawings will be required on foundations, wall reinforcing and mezzanine. Civil designs will be completed as noted in drawings and/or SOW.
32. Page 48 of the scope of work calls for a KNOX box that holds the key for the padlocked disconnect on the outside of the building. Please confirm this is correct and a KNOX box with a switch that trips the main breaker in the 225A panel in not needed as has been required by the fire marshal for the last few years.
A. Contractor shall provide and install a disconnect switch near meter base with pad‐lock. Contractor shall provide and install a KNOX box near the disconnect switch. The pad‐lock key shall put inside the KNOX box. Contractor shall provide a permanent weatherproof label (Coordinate with Fire Department) next to the KNOX box indicating the pad‐lock key inside the KNOX box. Recess mount the KNOX box between 4 feet to 5 feet above finished grade.
33. On SW corner of Building 3010 there is a concrete access road that begins at 3rd Infantry Division Rd and runs down to the main front entrance to Building 3010. This existing road is not shown on the drawings. On the new gravel access road, is the intention to tie into the existing concrete access road or the front parking lot as is shown on the drawings?
A. The intention is to tie into the front parking lot as is shown on the drawings.
34. Is lightning protection required for this facility?
A. No. A lightning protection system with UL‐Master Label will NOT be required for the latrine annex.