08_ITEM 01.2-8_ADD 04_Section 11 94 10.pdf

PDF 18 KB Posted

Attached to
F-35 THREE BAY SPECIALIZED HANGAR Federal contract opportunity
Solicitation number
W50S9F-22-B-0001
Issued by
Department of the Army National Guard

About this file

This solicitation is an invitation for bid for construction services to build a new three-bay specialized hangar at Dane County Regional Airport - Truax Field in Madison, Wisconsin. The project scope includes demolishing an existing 19,875 square foot building and constructing a new 31,000 square foot hangar with three bays to support F-35 fuel cell operations, indoor wash requirements, squadron-level surface coating operations, and weapons load training. The facility will also include administrative and shop spaces, as well as space for a future paint booth and composite make-up clean/dirty spaces. Additional requirements include a lightning protection system, fall protection, and an Advantor security system. The contract is for a single firm fixed-price award with a performance period of 550 days. The base bid is line item number 0001 for construction of the hangar. The solicitation also includes two options - line item 0002 for a paint/mix addition and line item 0003 for aircraft-rated pavement. The NAICS code is 236220 and the size standard is $39.5 million. The estimated value of construction is between $25-100 million. The bid opening will be conducted according to FAR Subpart 14.4. Interested parties must register in SAM and the solicitation is available on SAM.gov.

View the file

Other files for this federal contract opportunity

Other files attached to F-35 THREE BAY SPECIALIZED HANGAR, newest first.
File Type Posted
Questions and Answers 4.pdf PDF
13_ITEM 01.3-3_ADD 04_02700C-601.pdf PDF
21_ITEM 01.3-11_ADD 04_02700A-501.pdf PDF
FSB2020-270-00 - WI-ANG - 3-Bay Hangar - Addendum 004 COMBINED DRAWINGS.pdf PDF
22_ITEM 01.3-12_ADD 04_02700A-502.pdf PDF
Questions and Answers 3.pdf PDF
W50S9F22B0001 Solicitation - Amend 0003.pdf PDF
08_ITEM 01.2-8_ADD 03_Section 21 13 18.pdf PDF
10_ITEM 01.2-10_ADD 03_Section 26 08 00.pdf PDF
12_ITEM 01.3-2_ADD 03_02700C-100.pdf PDF
25_ITEM 01.3-15_ADD 03_02700A-505.pdf PDF
27_ITEM 01.3-17_ADD 03_02700A-511.pdf PDF
32_ITEM 01.3-22_ADD 03_02700A-702.pdf PDF
35_ITEM 01.3-25_ADD 03_02700FA101.pdf PDF
01_ITEM 01.2-1_ADD 03_Section 02 65 00.pdf PDF
07_ITEM 01.2-7_ADD 03_Section 21 13 13.pdf PDF
W50S9F22B0001 Solicitation - Amend 0002.pdf PDF
02_ITEM 01.2-2_ADD 03_Section 03 30 00.pdf PDF
06_ITEM 01.2-6_ADD 03_Section 10 51 13.pdf PDF
14_ITEM 01.3-4_ADD 03_02700C-402.pdf PDF
Bid Opening Directions.pdf PDF
02_ITEM 01.2-1_ADD 02_PROJECT TOC.pdf PDF
08_ITEM 01.2-9_ADD 02_Section 08 87 35.pdf PDF
17_ITEM 01.3-3_ADD 02_02700C-301.pdf PDF
27_ITEM 01.3-13_ADD 02_02700SF106.pdf PDF
39_ITEM 01.3-25_ADD 02_02700FA101.pdf PDF
40_ITEM 01.3-26_ADD 02_02700FA102.pdf PDF
41_ITEM 01.3-27_ADD 02_02700FA601.pdf PDF
47_ITEM 01.3-33_ADD 02_02700EP701.pdf PDF
31_ITEM 01.3-17_ADD 02_02700A-103.pdf PDF
04_ITEM 01.2-3_ADD 02_Section 01 78 00.pdf PDF
12_ITEM 01.2-13_ADD 02_Section 32 12 15.13.pdf PDF
13_ITEM 01.2-14_ADD 02_Section 32 12 16.16.pdf PDF
21_ITEM 01.3-7_ADD 02_02700S-002.pdf PDF
23_ITEM 01.3-9_ADD 02_02700SF102.pdf PDF
24_ITEM 01.3-10_ADD 02_02700SF103.pdf PDF
25_ITEM 01.3-11_ADD 02_02700SF104.pdf PDF
32_ITEM 01.3-18_ADD 02_02700A-140.pdf PDF
33_ITEM 01.3-19_ADD 02_02700A-201.pdf PDF
45_ITEM 01.3-31_ADD 02_02700EP102.pdf PDF
48_ITEM 01.3-34_ADD 02_02700EP702.pdf PDF
49_ITEM 01.3-35_ADD 02_02700ET101.pdf PDF
FSB2020-270-00 - WI-ANG - 3-Bay Hangar - Addendum 002 Combined Drawings.pdf PDF
ATTACHMENT 7 - 20220208 Single Source Determination - Monaco - Redacted.pdf PDF
W50S9F22B0001 Solicitation - F-35 3-Bay Hangar.pdf PDF
ATTACHMENT 4 - 20220208 Single Source Determination - Advantor - Redacted.pdf PDF
ATTACHMENT 1a - FSB2020-270-00 - WI-ANG - 3-Bay Hangar - ADD 01 COMBINED DRAWINGS (1 of 2).pdf PDF
ATTACHMENT 1b - FSB2020-270-00 - WI-ANG - 3-Bay Hangar - ADD 01 COMBINED DRAWINGS (2 of 2).pdf PDF
ATTACHMENT 3 - Volume 4 - WI ANG F-35 3-Bay CD Specs ADD 01 (2 of 2).pdf PDF
ATTACHMENT 5 - 20220208 Single Source Determination - Andover - Redacted.pdf PDF
Show all 50

F-35 THREE BAY SPECIALIZED HANGAR has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ANG/WI - F-35: 3-Bay Specialized Hangar 20202700F353BAY Addendum No. 04 28 June 2022

SECTION 11 94 10

ROOFTOP FALL PROTECTION ANCHORS

10/11

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI Z359.1 (2016) The Fall Protection Code

OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA)

OSHA 1926.502 Fall Prevention Systems and Criteria and Practices

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-02 Shop Drawings

Fall Protection Anchors ; G

Submit a roof anchor site plan indicating the locations roof anchors.

Provide anchorage design drawings with each page stamped by the designing engineer.

SD-03 Product Data

Fall Protection Anchors ; G

Self-Retracting Lifelines ; G

Submit manufacturer's data and product information for manufactured materials and products, indicating the sizes, descriptions, capacities, test certifications, and other descriptive data showing in sufficient detail that the product complies with the contract requirements. Submit information on the expected performance of the anchors as follows:

Maximum arrest load Maximum loadings of all components Maximum arrest force

SECTION 11 94 10 Page 1

Local/Regional Materials

Documentation indicating distance between manufacturing facility and the project site. Indicate distance of raw material origin from the project site. Indicate relative dollar value of local/regional materials to total dollar value of products included in project.

Waste Management

Documentation indicating percentages by weight of materials and products that are recycled and/or salvaged nonhazardous construction debris.

SD-05 Design Data

Design Analysis And Calculations ; G

SD-08 Manufacturer's Instructions

Manufacturer's Instructions

Indicating the manufacturer's recommended method of installation shall be submitted for anchorage posts.

1.3 SYSTEM DESCRIPTION

Rooftop Fall Protection Anchors shall be designed to secure to a roof surface in quantities and locations shown on the drawings and act as an anchorage connector for leading edge self-retracting lifelines as defined by ANSI Z359.1 , OSHA 1926.502 . Provide five self-retracting lifeline s.

The Fall Protection Anchors shall provide secure anchorage to arrest a fall by the user. The Fall Protection Anchors shall be designed for one user.

1.4 SUSTAINABLE DESIGN REQUIREMENTS

1.4.1 Local/Regional Materials

See Section 01 33 29 SUSTAINABILITY REPORTING for cumulative total local material requirements.

1.5 QUALITY ASSURANCE

a. Design Analysis and Calculations shall be prepared and certified by a Licensed Professional Engineer employed by the Fall Protection manufacturer as a full time fall arrest systems designer.

b. The Fall Protection Installer shall maintain all appropriate insurance as applicable for the design and installation of fall protection systems.

c. The Fall Protection Installer shall be fully certified by the manufacturer in the design and installation of the fall protection system and shall have a minimum of 5 years full time experience with similar systems. Proof of manufacturer's approval shall be in the form of a copy of the Installer's current certificate issued by the manufacturer.

SECTION 11 94 10 Page 2

d. Installation technicians:

1. Lead installation technician shall be fully trained by manufacturer in the installation of the specific system to be installed.

2. The lead installer shall have performed a minimum of five previous similar projects.

3. The lead installer shall have current OSHA 30 hour certification.

4. Copies of training certificates shall be kept at the Fall Protection Contactors location and will be made available upon request.

1.6 PROJECT CONDITIONS

a. Field Measurements: Perform prior to preparation of drawings to ensure required fit and dimensions.

b. Preconstruction Site Survey: Installer shall send a designated project manager to the site, prior to installation.

1. Verify that the fall protection design proposed in the bid documents provides a safe and compliant system that fully protects the users.

2. Field verify system layout to ensure required fit and dimensions.

3. Review site specific safety requirements and obtain a list of any site specific pre installation safety training requirements.

4. Coordinate work done in conjunction with any other trades.

(i.e., Roofing, Mechanical, Electrical)

1.7 DELIVERY, STORAGE AND HANDLING

Store and stage materials in protective packaging at location specified.

Prevent soiling, physical damage or wetting.

PART 2 PRODUCTS

2.1 MATERIALS

2.1.1 General

a. All connectors shall comply with OSHA 1926.502 . Fabricated members required for additional support shall be carbon steel with a corrosion resistant finish.

b. Coordinate anchorage system with supporting structure.

2.2 ROOFTOP FALL PROTECTION ANCHORS

The roof anchors shall be designed to meet a static load of 1,000 lbs and an ultimate force of 5,000 lbs. A static load is defined as one that is continually applied to the anchor such as a worker performing their

SECTION 11 94 10 Page 3 duties. The ultimate force is a one time load applied to the anchor point such as a fall situation. In the event of an ultimate load incident the roof anchor is permitted to bend; however it may not fracture or detach.

Roof anchors shall be designed to be welded to roof structure as shown on drawings.

2.2.1 Lifeline Connection

The lifeline connectors shall be Safety U-bars by Pro-Bel. They shall be stainless steel to meet ASTM A276, Type 304 with 35 Ksi minimum yield strength. Size shall be 3/4 inch minimum diameter material with 1.5 inch eye opening to accept connectors from lifelines.

2.3 SELF-RETRACTING LIFELINES

Provide leading edge type self-retracting lifelines with 33 feet of nylon coated galvanized steel cable lifeline with an integrated shock absorber in a lightweight and durable housing that includes a ergonomic handle.

Provide Diablo Grande SRL lifelines by Guardian or approved equal.

PART 3 EXECUTION

3.1 PREPARATION

a. Before starting the roof construction, determine when the roof anchor(s) will be installed during the construction process.

3.2 INSTALLATION

Fall Protection Anchors shall be installed by Fall Protection Installer's authorized and trained personnel that have been certified by the manufacturer. Install anchorage and fasteners in accordance with the approved design drawings and the Manufacturer's Instructions . If the installation of the anchor posts is not performed by the Fall Protection Installer, then the posts installation shall be inspected, load tested and verified by the Fall Protection Installer.

a. Roof anchors must be installed in accordance with the roof anchor plan. Site work rules must be followed regarding when an installed roof anchor is ready for use (i.e. Properly braced, etc.).

b. Roof anchors must be installed by welding to the roof structure as indicated on the drawings .

3.3 CLEANING

Remove all loose materials, crating and packing materials from premises.

3.4 WASTE MANAGEMENT

Disposal and recycling of waste materials, including corrugated cardboard recycling, shall be in accordance with the Waste Management Plan specified in Section 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT.

Identify manufacturer's policy for collection or return of construction scrap and unused material and packaging material. Institute construction waste separation and recycling to take advantage of manufacturer's programs. When such a service is not available, seek local recyclers to reclaim the materials.

SECTION 11 94 10 Page 4

-- End of Section --

SECTION 11 94 10 Page 5