01_ITEM 01.2-1_ADD 04_PROJECT TOC.pdf

PDF 93 KB Posted

Attached to
F-35 THREE BAY SPECIALIZED HANGAR Federal contract opportunity
Solicitation number
W50S9F-22-B-0001
Issued by
Department of the Army National Guard

About this file

This solicitation is for a single firm fixed-price construction contract to build a new three-bay specialized hangar at Dane County Regional Airport - Truax Field in Madison, Wisconsin. The project involves demolishing an existing 19,875 square foot building and constructing a new 31,000 square foot hangar facility compatible with the F-35 mission. The scope of work includes demolishing Building 414, constructing the three-bay hangar and associated administrative and shop spaces. The hangar bays will include pre-conditioned aircraft air, 270 VDC aircraft power, fire suppression and HVAC. The facility will also require a lightning protection system, interior and exterior fall protection and an Advantor security system. The contract includes a base bid for construction and two options for a paint/mix addition and aircraft rated pavement. The bid opening will be conducted in accordance with FAR Subpart 14.4 on the SAM.gov website. The contract duration is 550 days from notice to proceed. The NAICS code is 236220 and size standard is $39.5 million. The project value is estimated between $25-100 million.

View the file

Other files for this federal contract opportunity

Other files attached to F-35 THREE BAY SPECIALIZED HANGAR, newest first.
File Type Posted
Abstract of Offers.pdf PDF
39_ITEM 01.5-1_ADD 03_Bid Question Attachment_2022.06.14.pdf PDF
06_ITEM 01.2-6_ADD 04_Section 08 33 23.pdf PDF
11_ITEM 01.3-1_ADD 04_02700C-301.pdf PDF
12_ITEM 01.3-2_ADD 04_02700C-401.pdf PDF
20_ITEM 01.3-10_ADD 04_02700A-140.pdf PDF
24_ITEM 01.3-14_ADD 04_02700A-702.pdf PDF
Questions and Answers 2.pdf PDF
00_FSB2020-270-00_WI-ANG_3-Bay_ADD NO. 03_2022.06.14_Narrative.pdf PDF
04_ITEM 01.2-4_ADD 03_Section 05 51 33.pdf PDF
05_ITEM 01.2-5_ADD 03_Section 08 71 00.pdf PDF
17_ITEM 01.3-7_ADD 03_02700SF102.pdf PDF
21_ITEM 01.3-11_ADD 03_02700A-306.pdf PDF
22_ITEM 01.3-12_ADD 03_02700A-307.pdf PDF
26_ITEM 01.3-16_ADD 03_02700A-510.pdf PDF
29_ITEM 01.3-19_ADD 03_02700A-601.pdf PDF
30_ITEM 01.3-20_ADD 03_02700A-602.pdf PDF
GEO TECH REPORT_F-35 Hangar_2020-08-28_FINAL9-10-2020.pdf PDF
W50S9F22B0001 Solicitation - Amend 0002.pdf PDF
02_ITEM 01.2-2_ADD 03_Section 03 30 00.pdf PDF
06_ITEM 01.2-6_ADD 03_Section 10 51 13.pdf PDF
03_ITEM 01.2-2_ADD 02_Section 01 50 00.pdf PDF
07_ITEM 01.2-7_ADD 02_Section 07 27 26.pdf PDF
11_ITEM 01.2-12_ADD 02_Section 26 42 13.pdf PDF
18_ITEM 01.3-4_ADD 02_02700C-401.pdf PDF
22_ITEM 01.3-8_ADD 02_02700SF101.pdf PDF
26_ITEM 01.3-12_ADD 02_02700SF105.pdf PDF
34_ITEM 01.3-20_ADD 02_02700A-202.pdf PDF
44_ITEM 01.3-30_ADD 02_02700EG601.pdf PDF
46_ITEM 01.3-32_ADD 02_02700EP601.pdf PDF
04_ITEM 01.2-3_ADD 02_Section 01 78 00.pdf PDF
12_ITEM 01.2-13_ADD 02_Section 32 12 15.13.pdf PDF
13_ITEM 01.2-14_ADD 02_Section 32 12 16.16.pdf PDF
21_ITEM 01.3-7_ADD 02_02700S-002.pdf PDF
23_ITEM 01.3-9_ADD 02_02700SF102.pdf PDF
24_ITEM 01.3-10_ADD 02_02700SF103.pdf PDF
25_ITEM 01.3-11_ADD 02_02700SF104.pdf PDF
32_ITEM 01.3-18_ADD 02_02700A-140.pdf PDF
33_ITEM 01.3-19_ADD 02_02700A-201.pdf PDF
45_ITEM 01.3-31_ADD 02_02700EP102.pdf PDF
48_ITEM 01.3-34_ADD 02_02700EP702.pdf PDF
49_ITEM 01.3-35_ADD 02_02700ET101.pdf PDF
FSB2020-270-00 - WI-ANG - 3-Bay Hangar - Addendum 002 Combined Drawings.pdf PDF
B.07.Pre-Proposal Slides - F-35 3-Bay Hangar.pdf PDF
ATTACHMENT 8 - SFS Form 12 - Template.xls XLS spreadsheet
ATTACHMENT 9 - Volume 6 - WI ANG F-35 3-Bay GBCI ADD 01.pdf PDF
ATTACHMENT 1a - FSB2020-270-00 - WI-ANG - 3-Bay Hangar - ADD 01 COMBINED DRAWINGS (1 of 2).pdf PDF
ATTACHMENT 1b - FSB2020-270-00 - WI-ANG - 3-Bay Hangar - ADD 01 COMBINED DRAWINGS (2 of 2).pdf PDF
ATTACHMENT 3 - Volume 4 - WI ANG F-35 3-Bay CD Specs ADD 01 (2 of 2).pdf PDF
ATTACHMENT 5 - 20220208 Single Source Determination - Andover - Redacted.pdf PDF
Show all 50

F-35 THREE BAY SPECIALIZED HANGAR has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ANG/WI - F-35: 3-Bay Specialized Hangar 20202700F353BAY Addendum No. 04 28 June 2022

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 20 00 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 91 00.15 10 TOTAL BUILDING COMMISSIONING

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 41 00 DEMOLITION AND DECONSTRUCTION

02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL

02 65 00 UNDERGROUND STORAGE TANK REMOVAL

02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS

02 82 00 ASBESTOS REMEDIATION

02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs

AND MERCURY

02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS (PCBs)

DI VI SI ON 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DI VI SI ON 04 - MASONRY

04 20 00 UNIT MASONRY

04 72 00 CAST STONE MASONRY

DI VI SI ON 05 - METALS

05 12 00 STRUCTURAL STEEL

05 30 00 STEEL DECKS

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 SOLID SURFACING FABRICATIONS

06 73 01 FIBERGLASS REINFORCED PLASTIC (FRP) GRATING

PROJECT TABLE OF CONTENTS Page 1

DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 21 13 BOARD AND BLOCK INSULATION

07 22 00 ROOF AND DECK INSULATION

07 24 00 EXTERIOR INSULATION AND FINISH SYSTEMS

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 27 36 SPRAY FOAM AIR BARRIERS

07 42 13 METAL WALL PANELS

07 42 63 FABRICATED WALL PANEL ASSEMBLIES

07 54 19 POLYVINYL-CHLORIDE ROOFING

07 60 00 FLASHING AND SHEET METAL

07 61 14.00 20 STEEL STANDING SEAM ROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

07 95 00 ARCHITECTURAL EXPANSION JOINTS

DI VI SI ON 08 - OPENI NGS

08 11 13 STEEL DOORS AND FRAMES

08 11 16 ALUMINUM DOORS AND FRAMES

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 33 13 COILING COUNTER DOORS

08 33 23 OVERHEAD COILING DOORS

08 34 16.20 VERTICAL LIFT FABRIC DOORS

08 44 00 CURTAIN WALL AND GLAZED ASSEMBLIES

08 44 26 ALL-GLASS PARTITIONS

08 60 45 SKYLIGHTS AND TRANSLUCENT PANELS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 87 35 ARCHITECTURAL WINDOW FILM

08 91 00 METAL WALL LOUVERS

DI VI SI ON 09 - FI NI SHES

09 06 00 SCHEDULES FOR FINISHES

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 62 38 STATIC-CONTROL FLOORING

09 65 00 RESILIENT FLOORING

09 67 23.13 STANDARD RESINOUS FLOORING

09 67 23.16 FUEL RESISTIVE RESINOUS FLOORING, 5-COAT SYSTEM

09 68 00 CARPETING

09 77 20 FIBERGLASS REINFORCED WALL PANELS

09 90 00 PAINTS AND COATINGS

09 97 13.27 HIGH PERFORMANCE COATING FOR STEEL STRUCTURES

DI VI SI ON 10 - SPECI ALTI ES

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

PROJECT TABLE OF CONTENTS Page 2

10 51 13 METAL LOCKERS

10 53 00 MANUFACTURED CANOPY

DI VI SI ON 11 - EQUI PMENT

11 94 10 ROOFTOP FALL PROTECTION ANCHORS

DI VI SI ON 12 - FURNI SHI NGS

12 24 13 ROLLER WINDOW SHADES

DI VI SI ON 21 - FI RE SUPPRESSI ON

21 13 13 WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION

21 13 18 PREACTION SPRINKLER SYSTEMS, FIRE PROTECTION

DI VI SI ON 22 - PLUMBI NG

22 00 00 PLUMBING, GENERAL PURPOSE

22 31 00 WATER SOFTENERS, CATION-EXCHANGE (SODIUM CYCLE)

DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

23 05 48.19 BRACING FOR HVAC

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 11 20 FACILITY GAS PIPING

23 21 23 HYDRONIC PUMPS

23 23 00 REFRIGERANT PIPING

23 30 00 HVAC AIR DISTRIBUTION

23 31 13.00 40 METAL DUCTS

23 34 23.00 40 HVAC POWER VENTILATORS

23 35 19.00 20 INDUSTRIAL VENTILATION AND EXHAUST

23 36 00.00 40 AIR TERMINAL UNITS

23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLES

23 52 00 HEATING BOILERS

23 74 33.00 40 PACKAGED, OUTDOOR, HEATING AND COOLING MAKEUP

AIR-CONDITIONERS

23 75 15 CUSTOM-PACKAGED, AIRCRAFT PRE-CONDITIONED AIR UNITS

23 80 20.00 10 GAS-FIRED HEATING EQUIPMENT

23 82 19.00 40 FAN COIL UNITS

DI VI SI ON 25 - I NTEGRATED AUTOMATI ON

25 05 11.01 CYBERSECURITY FOR LOW IMPACT HVAC CONTROL SYSTEMS

25 05 11.02 CYBERSECURITY FOR LOW IMPACT PORTABLE GENERATOR LOAD BANK

CONNECTION CABINET CONTROL SYSTEMS

25 05 11.03 CYBERSECURITY FOR LOW IMPACT SWITCH GEAR AUTOMATION

CONTROL SYSTEMS

25 05 11.04 CYBERSECURITY FOR LOW IMPACT FIRE PROTECTION/MASS

NOTIFICATION SYSTEM FACILITY-RELATEDCONTROL SYSTEMS

25 05 11.05 CYBERSECURITY FOR LOW IMPACT ACCESS CONTROL SYSTEM AND

INTRUSION DETECTION SYSTEM FACILITY-RELATED CONTROL

PROJECT TABLE OF CONTENTS Page 3

11 94 10.01 RIGID RAIL FALL RESTRAINT SYSTEM

SYSTEMS

25 05 11.06 CYBERSECURITY FOR LOW IMPACT CCTV SYSTEM FACILITY-RELATED

CONTROL SYSTEMS

25 05 11.07 CYBERSECURITY FOR LOW IMPACT ELECTRICAL METERING AND

NETWORK LIGHTING CONTROLS FACILITY-RELATED CONTROL SYSTEMS

25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END

AND INTEGRATION

DI VI SI ON 26 - ELECTRI CAL

26 05 19.10 10 INSULATED WIRE AND CABLE

26 05 26.00 40 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 08 00 APPARATUS INSPECTION AND TESTING

26 09 43 NETWORK LIGHTING CONTROLS (WIRED)

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 13 SWITCHBOARDS

26 27 13.10 30 ELECTRIC METERS

26 28 00.00 10 MOTOR CONTROL CENTERS, SWITCHBOARDS AND PANELBOARDS

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

26 35 44 270 VDC SOLID STATE CONVERTER

26 36 20 PORTABLE GENERATOR AND LOAD BANK CONNECTION CABINETS

(PGLBCC)

26 41 00 LIGHTNING PROTECTION SYSTEM

26 42 13 GALVANIC (SACRIFICIAL) ANODE CATHODIC PROTECTION (GACP)

SYSTEM

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DI VI SI ON 27 - COMMUNI CATI ONS

27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 51 16 RADIO AND PUBLIC ADDRESS SYSTEMS

DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM,

ADDRESSABLE

DI VI SI ON 31 - EARTHWORK

31 00 00 EARTHWORK

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 01 19.61 SEALING OF JOINTS IN RIGID PAVEMENT

32 11 20 BASE COURSE FOR RIGID PAVING AND SIDEWALK AND SUBBASES

FOR FLEXIBLE PAVING

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 15.13 ASPHALT PAVING FOR AIRFIELDS

32 12 16.16 ROAD-MIX ASPHALT PAVING

32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY

PAVEMENTS

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

32 92 19 SEEDING

DI VI SI ON 33 - UTI LI TI ES

PROJECT TABLE OF CONTENTS Page 4

33 40 00 STORM DRAINAGE UTILITIES

DI VI SI ON 46 - WATER AND WASTEWATER EQUI PMENT

46 25 14 COALESCING OIL-WATER SEPARATORS

-- End of Project Table of Contents --