01_FSB2020-270-00_WI-ANG_3-Bay_ADD NO. 02_2022.06.08_Narrative.pdf
PDF 249 KB Posted
- Attached to
- F-35 THREE BAY SPECIALIZED HANGAR
- Solicitation number
- W50S9F-22-B-0001
- Issued by
-
Department of the Army National Guard
About this file
This federal contract opportunity announcement solicits bids for an unrestricted invitation for bid to construct a new three-bay specialized hangar at Dane County Regional Airport-Truax Field in Madison, Wisconsin to support the F-35 mission. Key requirements include demolishing an existing 19,875 square foot building and constructing a new 31,000 square foot three-bay hangar with pre-conditioned aircraft air, 270VDC aircraft power, fire suppression, and hangar bay HVAC. Additional spaces include administrative areas, shops, and future paint booth and composite spaces. The project also includes lightning protection, interior and exterior fall protection, and an Advantor security system. The base bid is for hangar construction with optional bids for a paint/mix addition and aircraft rated pavement. Brand name requirements specified. The bid opening will be conducted following FAR and DFARS procedures. The contracting agency is the Department of the Army National Guard. The project magnitude is between $25-100 million. The NAICS code is 236220 and size standard is $39.5 million. The contract performance period is 550 days from notice to proceed.
View the file
Other files
Show 40 more
Latest 50 of 147 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
h:\prj\2020\20202700\08-submissions\2022_06_08_add 2\fsb2020-270-00_wi-ang_3-bay_add no. 02_2022.06.08_narrative.docx Page 1 of 9
5801 Broadway Extension, Suite 500 Oklahoma City, OK 73118-7436
405.840.2931 | fsb-ae.com
ADDENDUM NO. 02
Date: 8 June 2022
To: ALL BIDDERS OF RECORD
From: Frankfurt-Short-Bruza Associates, P.C.
5801 N. Broadway Ext., Suite 500 Oklahoma City, OK 73118
Subject: XGFG189002: F-35 3-Bay Specialized Hangar, WI/ANG, Truax Field, Madison, WI
FSB Project No.: FSB2020-270-00
NOTE: This Addendum forms a part of the Contract Documents and modifies the Original Documents dated 22 April 2022.
Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject the Bidder to disqualification.
ATTACHMENTS
Items in this addendum take precedence over the original bid documents. Items not specifically revised remain in effect. This addendum consists of (9) pages and the following attachments:
Specifications:
PROJECT TABLE OF CONTENTS
01 50 00 – TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 78 00 – CLOSEOUT SUBMITTALS
03 30 00 – CAST-IN-PLACE CONCRETE
04 20 00 – UNIT MASONRY
07 27 26 – FLUID-APPLIED MEMBRANE AIR BARRIERS
08 87 35 – ARCHITECTURAL WINDOW FILM
09 06 00 – SCHEDULES FOR FINISHES
11 94 10 – RIGID RAIL FALL RESTRAINT SYSTEM
26 42 13 – GALVANIC (SACRIFICIAL) ANODE CATHODIC PROTECTION (GACP) SYSTEM
32 12 15.13 – ASPHALT PAVING FOR AIRFIELDS
32 12 16.16 – ROAD-MIX ASPHALT PAVING
32 13 14.13 – CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY PAVEMENTS
FSB | DefineDesignDeliver
Drawings:
G-102 – CODE SUMMARY
C-101 – ACCESS PLAN
C-301 – REMOVAL PLAN
C-401 – PROPOSED PLAN
C-402 – TYPICAL SECTION AND PAVEMENT DETAILS
S-001 – GENERAL NOTES
S-002 – FALL ARREST DIAGRAM
SF101 – LOW ROOF FRAMING PLAN – COMPOSITE
SF102 – LOW ROOF FRAMING PLAN – SECTOR ONE
SF103 – LOW ROOF FRAMING PLAN – SECTOR TWO
SF104 – HIGH ROOF FRAMING PLAN – COMPOSITE
SF105 – HIGH ROOF FRAMING PLAN – SECTOR ONE
SF106 – HIGH ROOF FRAMING PLAN – SECTOR TWO
SF210 – FRAMING ELEVATIONS
SF502 – FRAMING DETAILS
AD-101 – COMPOSITE DEMOLITION PLAN
A-103 – PARTIAL FLOOR PLAN – SECTOR ONE
A-140 – ROOF PLAN
A-201 – BUILDING ELEVATIONS
A-202 – BUILDING ELEVATIONS
A-402 – INTERIOR ELEVATIONS
A-500 – DETAILS
A-501 – DETAILS
A-702 – FLOOR FINISH PLAN, ROOM FINISH SCHEDULE – BID OPTION 1
FA101 – FIRE ALARM & MASS NOTIFICATION SYSTEM PLAN – SECTOR 1
FA102 – FIRE ALARM & MASS NOTIFICATION SYSTEM PLAN – SECTOR 2
FA601 – FIRE ALARM & MASS NOTIFICATION SYSTEM RISER DIAGRAM
ES101 – ELECTRICAL SITE PLAN
EG101 – ELECTRICAL GROUNDING PLAN
EG601 – ELECTRICAL GROUNDING ONE-LINE DIAGRAM
EP102 – ELECTRICAL POWER PLAN SECTOR TWO
EP601 – ELECTRICAL ONE-LINE DIAGRAMS
EP701 – ELECTRICAL PANEL SCHEDULES
EP702 – ELECTRICAL PANEL SCHEDULES
ET101 – TELECOMMUNICATION PLAN SECTOR ONE
MODIFICATIONS TO THE CONDITIONS OF THE CONTRACT
None.
MODIFICATIONS TO THE SPECIFICATIONS
ITEM 01.2-1 Refer to attached Project Table of Contents, dated 8 June 2022:
A. Project Table of Contents is hereby revised and re-issued in its entirety to incorporate changes noted as part of this Addendum related to specifications included on the project. Replace Project Table of Contents dated 22 April 2022 with attached revised Project Table of Contents dated 8 June 2022.
ITEM 01.2-2 Refer to attached Specification Section 01 50 00 – TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, dated 8 June 2022:
A. Specification Section 01 50 00 is hereby revised and re-issued in its entirety to strike all requirements for a Government Field Office. Replace Section 01 50 00 dated 23 December 2021 with attached revised Specification Section 01 50 00 dated 8 June 2022.
ITEM 01.2-3 Refer to attached Specification Section 01 78 00 – CLOSEOUT SUBMITTALS, dated 8 June 2022:
A. Specification Section 01 78 00 is hereby revised and re-issued in its entirety to strike Subpart 3.2 Record Drawings.
Replace Section 01 78 00 dated 23 December 2021 with attached revised Specification Section 01 78 00 dated 8 June 2022.
ITEM 01.2-4 Refer to attached Specification Section 03 30 00 – CAST-IN-PLACE CONCRETE, dated 8 June 2022:
B. Specification Section 03 30 00 is hereby revised and re-issued in its entirety to provide updated requirements for Contractor Quality Control included in Subpart 1.6.9.c. Replace Section 03 30 00 dated 22 April 2022 with attached revised Specification Section 03 30 00 dated 8 June 2022.
ITEM 01.2-5 Refer to attached Specification Section 04 20 00 – UNIT MASONRY, dated 8 June 2022:
A. Specification Section 04 20 00 is hereby revised and re-issued in its entirety to remove reference to 07 21 13 from specification. Replace Section 04 20 00 dated 22 April 2022 with attached revised Specification Section 04 20 00 dated 8 June 2022.
ITEM 01.2-6 Refer to attached Specification Section 06 73 01 – FIBERGLASS REINFORCED PLASTIC (FRP) GRATING, dated 23 December 2021:
A. Specification Section 06 73 01 is hereby deleted in its entirety to strike all requirements included in this specification from the project. Remove Section 06 73 01 dated 23 December 2021 from the contract documents.
ITEM 01.2-7 Refer to attached Specification Section 07 27 26 – FLUID-APPLIED MEMBRANE AIR BARRIERS, dated 8 June 2022:
A. Specification Section 07 27 26 is hereby revised and re-issued in its entirety to remove reference to 07 27 19.01 from specification. Replace Section 07 27 26 dated 23 December 2021 with attached revised Specification Section 07 27 26 dated 8 June 2022.
ITEM 01.2-8 Refer to attached Specification Section 07 61 14.00 20 – STEEL STANDING SEAM METAL ROOF, dated 23 December 2021:
A. Specification Section 07 61 14.00 20 is hereby deleted in its entirety to strike all requirements included in this specification from the project. Remove Section 07 61 14.00 20 dated 23 December 2021 from the contract documents.
ITEM 01.2-9 Refer to attached Specification Section 08 87 35 – ARCHITECTURAL WINDOW FILM, dated 8 June 2022:
A. Specification Section 08 87 35 is hereby issued in its entirety to provide requirements for architectural window film or privacy film.
ITEM 01.2-10 Refer to attached Specification Section 09 06 00 – SCHEDULES FOR FINISHES, dated 8 June 2022:
A. Specification Section 09 06 00 is hereby revised and re-issued in its entirety to provide exterior finish/color information. Replace Section 09 06 00 dated 23 December 2021 with attached revised Specification Section 09 06 00 dated 8 June 2022.
ITEM 01.2-11 Refer to attached Specification Section 11 94 10 – RIGID RAIL FALL RESTRAINT SYSTEM, dated
A. Specification Section 11 94 10 is hereby revised and re-issued in its entirety to provide requirements for rigid rail fall restraint system over aircraft in hangar bays. Replace Section 11 94 10 dated 22 April 2022 with attached revised Specification Section 11 94 10 dated 8 June 2022.
ITEM 01.2-12 Refer to attached Specification Section 26 42 13 – GALVANIC (SACRIFICIAL) ANODE CATHODIC PROTECTION (GACP) SYSTEM, dated 8 June 2022:
A. Specification Section 26 42 13 is hereby issued in its entirety to provide requirements for Galvanic (Sacrificial) Anode Cathodic Protection (GACP) Systems on the project.
ITEM 01.2-13 Refer to attached Specification Section 32 12 15.13 – ASPHALT PAVING FOR AIRFIELDS, dated
A. Specification Section 32 12 15.13 is hereby revised and re-issued in its entirety to remove requirements for test section. Replace Section 32 12 15.13 dated 23 December 2021 with attached revised Specification Section 32 12
15.13 dated 8 June 2022.
ITEM 01.2-14 Refer to attached Specification Section 32 12 16.16 – ROAD-MIX ASPHALT PAVING, dated 8 June 2022:
A. Specification Section 32 12 16.16 is hereby revised and re-issued in its entirety to remove requirements for profilograph. Replace Section 32 12 16.16 dated 23 December 2021 with attached revised Specification Section 32 12 16.16 dated 8 June 2022.
ITEM 01.2-15 Refer to attached Specification Section 32 13 14.13 – CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY PAVEMENTS, dated 8 June 2022:
A. Specification Section 32 13 14.13 is hereby revised and re-issued in its entirety to remove requirements for test section; to remove requirements for test section at pilot lane and fill-in lane; and to provide updated requirements for Lump Sum projects. Replace Section 32 13 14.13 dated 23 December 2021 with attached revised Specification Section 32 13 14.13 dated 8 June 2022.
MODIFICATIONS TO THE DRAWINGS
ITEM 01.3-1 Refer to attached Sheet G-102 – CODE SUMMARY, dated 8 June 2022:
A. Sheet G-102 is hereby revised and re-issued in its entirety to remove reference to draft curtains; and to remove reference to HEF systems. Replace Sheet G-102 dated 22 April 2022 with attached revised Sheet G-102 dated 8 June 2022.
ITEM 01.3-2 Refer to attached Sheet C-101 – ACCESS PLAN, dated 8 June 2022:
A. Sheet C-101 is hereby revised and re-issued in its entirety to provide clarification on existing structure to be relocated by Government prior to start of construction. Replace Sheet C-101 dated 23 December 2021 with attached revised Sheet C-101 dated 8 June 2022.
ITEM 01.3-3 Refer to attached Sheet C-301 – REMOVAL PLAN, dated 8 June 2022:
A. Sheet C-301 is hereby revised and re-issued in its entirety to provide clarification on Bid Options. Replace Sheet C- 301 dated 23 December 2021 with attached revised Sheet C-301 dated 8 June 2022.
ITEM 01.3-4 Refer to attached Sheet C-401 – PROPOSED PLAN, dated 8 June 2022:
A. Sheet C-401 is hereby revised and re-issued in its entirety to provide clarification on type of asphalt to be installed at different locations; to provide clarification on Bid Options; and to provide wall construction for wall on east side of facility.
Replace Sheet C-401 dated 23 December 2021 with attached revised Sheet C-401 dated 8 June 2022.
ITEM 01.3-5 Refer to attached Sheet C-402 – TYPICAL SECTION AND PAVEMENT DETAILS, dated 8 June 2022:
A. Sheet C-402 is hereby revised and re-issued in its entirety to provide existing pavement sections for Mitchell Street and the access taxi path (Bid Option); to provide typical detail for pavement sections; and to provide clarification on mow strip section. Replace Sheet C-402 dated 23 December 2021 with attached revised Sheet C-402 dated
ITEM 01.3-6 Refer to attached Sheet S-001 – GENERAL NOTES, dated 8 June 2022:
A. Sheet S-001 is hereby revised and re-issued in its entirety to revise Reinforced Masonry Note 5 to provide for post-installed rebar using epoxy. Replace Sheet S-001 dated 23 December 2021 with attached revised Sheet S-001 dated
ITEM 01.3-7 Refer to attached Sheet S-002 – FALL ARREST DIAGRAM, dated 8 June 2022:
A. Sheet S-002 is hereby revised and re-issued in its entirety to provide fall-protection anchor locations; and to provide updated requirements for rigid rail fall protection systems. Replace Sheet S-002 dated 23 December 2021 with attached revised Sheet S-002 dated 8 June 2022.
ITEM 01.3-8 Refer to attached Sheet SF101 – LOW ROOF FRAMING PLAN – COMPOSITE, dated 8 June 2022:
A. Sheet SF101 is hereby revised and re-issued in its entirety to update plan notes referencing beam bottom flange bracing. Replace Sheet SF101 dated 23 December 2021 with attached revised Sheet SF101 dated 8 June 2022.
ITEM 01.3-9 Refer to attached Sheet SF102 – LOW ROOF FRAMING PLAN – SECTOR ONE, dated 8 June 2022:
A. Sheet SF102 is hereby revised and re-issued in its entirety to update plan notes referencing beam bottom flange bracing. Replace Sheet SF102 dated 23 December 2021 with attached revised Sheet SF102 dated 8 June 2022.
ITEM 01.3-10 Refer to attached Sheet SF103 – LOW ROOF FRAMING PLAN – SECTOR TWO, dated 8 June 2022:
A. Sheet SF103 is hereby revised and re-issued in its entirety to update plan notes referencing beam bottom flange bracing. Replace Sheet SF103 dated 23 December 2021 with attached revised Sheet SF103 dated 8 June 2022.
ITEM 01.3-11 Refer to attached Sheet SF104 – HIGH ROOF FRAMING PLAN – COMPOSITE, dated 8 June 2022:
A. Sheet SF104 is hereby revised and re-issued in its entirety to provide fall-protection anchor locations and associated requirements. Replace Sheet SF104 dated 22 April 2022 with attached revised Sheet SF104 dated 8 June 2022.
ITEM 01.3-12 Refer to attached Sheet SF105 – HIGH ROOF FRAMING PLAN – SECTOR ONE, dated 8 June 2022:
A. Sheet SF105 is hereby revised and re-issued in its entirety to provide fall-protection anchor locations and associated requirements. Replace Sheet SF105 dated 22 April 2022 with attached revised Sheet SF105 dated 8 June 2022.
ITEM 01.3-13 Refer to attached Sheet SF106 – HIGH ROOF FRAMING PLAN – SECTOR TWO, dated 8 June 2022:
A. Sheet SF106 is hereby revised and re-issued in its entirety to provide fall-protection anchor locations and associated requirements. Replace Sheet SF106 dated 22 April 2022 with attached revised Sheet SF106 dated 8 June 2022.
ITEM 01.3-14 Refer to attached Sheet SF210 – FRAMING ELEVATIONS, dated 8 June 2022:
A. Sheet SF210 is hereby revised and re-issued in its entirety to provide clarification on fall arrest rails. Replace Sheet SF210 dated 23 December 2021 with attached revised Sheet SF210 dated 8 June 2022.
ITEM 01.3-15 Refer to attached Sheet SF502 – FRAMING DETAILS, dated 8 June 2022:
A. Sheet SF502 is hereby revised and re-issued in its entirety to provide clarification to Detail C1/SF502. Replace Sheet SF502 dated 23 December 2021 with attached revised Sheet SF502 dated 8 June 2022.
ITEM 01.3-16 Refer to attached Sheet AD-101 – COMPOSITE DEMOLITION PLAN, dated 8 June 2022:
A. Sheet AD-101 is hereby revised and re-issued in its entirety to provide additional information related to existing condition of facility at start of construction. Replace Sheet AD-101 dated 23 December 2021 with attached revised Sheet AD-101 dated 8 June 2022.
ITEM 01.3-17 Refer to attached Sheet A-103 – PARTIAL FLOOR PLAN – SECTOR ONE, dated 8 June 2022:
A. Sheet A-103 is hereby revised and re-issued in its entirety to add Sheet Keynote 14 for AED Cabinet in Corridor, Room 106. Replace Sheet A-103 dated 23 December 2021 with attached revised Sheet A-103 dated 8 June 2022.
ITEM 01.3-18 Refer to attached Sheet A-140 – ROOF PLAN, dated 8 June 2022:
A. Sheet A-140 is hereby revised and re-issued in its entirety to provide fall-protection anchor locations. Replace Sheet A-140 dated 23 December 2021 with attached revised Sheet A-140 dated 8 June 2022.
ITEM 01.3-19 Refer to attached Sheet A-201 – BUILDING ELEVATIONS, dated 8 June 2022:
A. Sheet A-201 is hereby revised and re-issued in its entirety to provide dimensions for translucent panel wall openings.
Replace Sheet A-201 dated 22 April 2022 with attached revised Sheet A-201 dated 8 June 2022.
ITEM 01.3-20 Refer to attached Sheet A-202 – BUILDING ELEVATIONS, dated 8 June 2022:
A. Sheet A-202 is hereby revised and re-issued in its entirety to provide dimensions for translucent panel wall openings.
Replace Sheet A-202 dated 22 April 2022 with attached revised Sheet A-202 dated 8 June 2022.
ITEM 01.3-21 Refer to attached Sheet A-402 – INTERIOR ELEVATIONS, dated 8 June 2022:
A. Sheet A-402 is hereby revised and re-issued in its entirety to provide clarification on requirements and extent of privacy film/Architectural Window Film. Replace Sheet A-402 dated 23 December 2021 with attached revised Sheet A-402 dated 8 June 2022.
ITEM 01.3-22 Refer to attached Sheet A-500 – DETAILS, dated 8 June 2022:
A. Sheet A-500 is hereby revised and re-issued in its entirety to provide for split-face CMU veneer in Detail D3/A-500 in lieu of brick veneer. Replace Sheet A-500 dated 22 April 2022 with attached revised Sheet A-500 dated 8 June 2022.
ITEM 01.3-23 Refer to attached Sheet A-501 – DETAILS, dated 8 June 2022:
A. Sheet A-501 is hereby revised and re-issued in its entirety to remove details non-applicable to the project. Replace
Sheet A-501 dated 23 December 2021 with attached revised Sheet A-501 dated 8 June 2022.
ITEM 01.3-24 Refer to attached Sheet A-702 – FLOOR FINISH SCHEDULE, ROOM FINISH SCHEDULE – BID OPTION 1, dated 8 June 2022:
A. Sheet A-702 is hereby revised and re-issued in its entirety to modify freezer tag to RF3 in plan and Furniture & Equipment Schedule for Bid Option 1. Replace Sheet A-702 dated 23 December 2021 with attached revised Sheet A- 702 dated 8 June 2022.
ITEM 01.3-25 Refer to attached Sheet FA101 – FIRE ALARM & MASS NOTIFICATION SYSTEM PLAN – SECTOR 1, dated
A. Sheet FA101 is hereby revised and re-issued in its entirety to relocate monitor module for AED from Weapons Training, Room 101 to Corridor, Room 106. Replace Sheet FA101 dated 22 April 2022 with attached revised Sheet FA101 dated 8 June 2022.
ITEM 01.3-26 Refer to attached Sheet FA102 – FIRE ALARM & MASS NOTIFICATION SYSTEM PLAN – SECTOR 2, dated
A. Sheet FA102 is hereby revised and re-issued in its entirety to remove monitor module for AED from Corridor, Room 120B. Replace Sheet FA102 dated 22 April 2022 with attached revised Sheet FA102 dated 8 June 2022.
ITEM 01.3-27 Refer to attached Sheet FA601 – FIRE ALARM & MASS NOTIFICATION SYSTEM RISER DIAGRAM, dated
A. Sheet FA601 is hereby revised and re-issued in its entirety to relocate monitor module for AED from Weapons Training, Room 101, to Corridor, Room 106; and to remove monitor module for AED from Corridor, Room 120B.
Replace Sheet FA601 dated 22 April 2022 with attached revised Sheet FA601 dated 8 June 2022.
ITEM 01.3-28 Refer to attached Sheet ES101 – ELECTRICAL SITE PLAN, dated 8 June 2022:
A. Sheet ES101 is hereby revised and re-issued in its entirety to add exterior CT cabinet per updated utility-provider requirements; to provide clarification of proposed stub out locations for switchboard and MTS-HD in Sheet Keynotes 17 and 18. Replace Sheet ES101 dated 23 December 2021 with attached revised Sheet ES101 dated 8 June 2022.
ITEM 01.3-29 Refer to attached Sheet EG101 – ELECTRICAL GROUNDING PLAN, dated 8 June 2022:
A. Sheet EG101 is hereby revised and re-issued in its entirety to tie exterior CT cabinet per updated utility-provider requirements into grounding counterpoise system. Replace Sheet EG101 dated 22 April 2022 with attached revised Sheet EG101 dated 8 June 2022.
ITEM 01.3-30 Refer to attached Sheet EG601 – ELECTRICAL GROUNDING ONE-LINE DIAGRAM, dated 8 June 2022:
A. Sheet EG601 is hereby revised and re-issued in its entirety to provide updated grounding diagram; to provide updated requirements for utility-provided grounding conductors. Replace Sheet EG601 dated 23 December 2021 with attached revised Sheet EG601 dated 8 June 2022.
ITEM 01.3-31 Refer to attached Sheet EP102 – ELECTRICAL POWER PLAN SECTOR TWO, dated 8 June 2022:
A. Sheet EP102 is hereby revised and re-issued in its entirety to modify power locations; and to provide power for breathing air apparatuses. Replace Sheet EP102 dated 22 April 2022 with attached revised Sheet EP102 dated
ITEM 01.3-32 Refer to attached Sheet EP601 – ELECTRICAL ONE-LINE DIAGRAMS, dated 8 June 2022:
A. Sheet EP601 is hereby revised and re-issued in its entirety to add exterior CT cabinet per updated utility-provider requirements to one-line diagram; to revise switchboard current ratings; to add integral metering to the switchboard;
and to provide necessary updates to affected Sheet Keynotes. Replace Sheet EP601 dated 22 April 2022 with attached revised Sheet EP601 dated 8 June 2022.
ITEM 01.3-33 Refer to attached Sheet EP701 – ELECTRICAL PANEL SCHEDULES, dated 8 June 2022:
A. Sheet EP701 is hereby revised and re-issued in its entirety to modify switchboard current ratings; and to provide clarification that Panel HD1 is powered from CT Cabinet. Replace Sheet EP701 dated 23 December 2021 with attached revised Sheet EP701 dated 8 June 2022.
ITEM 01.3-34 Refer to attached Sheet EP702 – ELECTRICAL PANEL SCHEDULES, dated 8 June 2022:
A. Sheet EP702 is hereby revised and re-issued in its entirety to modify loads noted; and to add circuit. Replace Sheet EP702 dated 22 April 2022 with attached revised Sheet EP702 dated 8 June 2022.
ITEM 01.3-35 Refer to attached Sheet ET101 – TELECOMMUNICATION PLAN SECTOR ONE, dated 8 June 2022:
A. Sheet ET101 is hereby revised and re-issued in its entirety to modify Technology Systems Responsibility Matrix Note 9 to indicate requirement for contractor to provide cameras, mounts, and cabling as part of the Base Bid. Replace Sheet ET101 dated 23 December 2021 with attached revised Sheet ET101 dated 8 June 2022.
BIDDER RFI RESPONSES
ITEM 01.4-1 Refer to attached document – BID RFI QUESTIONS AND RESPONSES, dated 8 June 2022, for responses to Bid RFI Questions received by the A/E as of 7 June 2022.
SUSTITUTION REQUESTS
None.
-- END OF ADDENDUM No. 02 --
W
IS C O NS IN
A R C H I T E C T
JASON T.
HOLUBY
A-13101
OKLAHOMA CITY
OK
W
IS C O NS IN
P R
O F
E
S S I O N A L
E N G
I N E
E R
LIANE F
OZMUN
E-48073
OKLAHOMA CITY
OK
W
IS C O NS IN
P R
O F
E
S S I O N A L
E N G
I N E
E R
GENE O.
BROWN
E-47748
OKLAHOMA CITY
OK
W
IS C O NS IN
P R
O F
E
S S I O N A L
E N G
I N E
E R
JOHN T
LITTLE
E-47833
EDMOND
OK
File details come from the government source that posted it. Updated .