The document is a Veterans Health Administration (VHA) Pre-Construction Risk Assessment (PCRA) template for a large-scale elevator renovation project at the Hines VA Hospital in Hines, Illinois. The project involves renovating Elevators P1-P5 and S6-S8 and associated equipment and controls, with a project start date of 09/30/2025 and completion date of 08/20/2028. The PCRA is designed to categorize construction activity types and safety risks, determining necessary precautions to prevent impacts on patients, employees, and contractors during the renovation work.

The document outlines three activity types (Inspection/Upkeep, Small-scale, and Large-scale) with increasingly comprehensive control measures. For this large-scale project, additional hazard analyses and control plans may be required, including excavation safety, dust control, pollution prevention, and crane lift plans. An Infection Control Risk Assessment (ICRA) is deemed necessary, and the project will involve coordination with adjacent areas such as the Elevator Shaft, Elevator Penthouse, Elevator Pit, and Elevator Lobbies. The project manager is Aaron Walsh, and the document has been digitally signed by key personnel including Christopher Jay (Infection Prevention and Control), Neena Dobyne (Safety Officer), and Matthew Kelly (Construction Safety Committee).

View the file

Other files

File Type Posted
36C25225R0036 0007.docx DOCX document
BLDG200 F10R2010.xls XLS spreadsheet
BLDG200F3R2010.xls XLS spreadsheet
BLDG200F2R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att08 GKT15-30W-10_Specification.pdf PDF
BLDG200F1R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att09 Hines State Tax Exempt 2025.pdf PDF
BLDG200F4R2010.xls XLS spreadsheet
BLDG200F11R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att05 Physical Access Control Clarifications.pdf PDF
BLDG200F9R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att11 Photos_Existing Conditions.pdf PDF
S06 36C25225R0036 006_Att12 Sole Source Listing__full.e.pdf PDF
S06 36C25225R0036 006_Att07 26 22 00 Low-Voltage Transformers.pdf PDF
S06 36C25225R0036 0005.pdf PDF
S06 36C25225R0036 0005.docx DOCX document
S06 36C25225R0036 004 578-25-003_Att Finish Schedule.pdf PDF
36C25225R0036 0004.docx DOCX document
S06 36C25225R0036 003 Att1 Sign-in Site Visit_01.pdf PDF
S06 36C25225R0036 003 Att2 Sign-in Site Visit_02_rev.pdf PDF
36C25225R0036 0003.docx DOCX document
S06 36C25225R0036 002 Att1 Sign-in Site Visit_01.pdf PDF
S06 36C25225R0036 002 Att2 Sign-in Site Visit_02.pdf PDF
S06 36C25225R0036 002 578-25-003.docx DOCX document
S06 001 Att1 Sign-in Site Visit_01 for 578-25-003 Elevators 2025.06.18.pdf PDF
36C25225R0036_3.docx DOCX document
36C25225R0036_3.docx DOCX document
S02 Sol R0036 AttE SOW.Att15a_578-25-003 100 perc DWGS_Part 1of5_2025.01.24.pdf PDF
S02 Sol R0036 AttE SOW.Att09_Infection Control Risk Assessment_ICRA-1.3.pdf PDF
S02 Sol R0036 AttE SOW.Att03_Emergency Contact List.pdf PDF
S02 Sol R0036 AttE SOW.Att05_Safety and Health During Construction Activities.pdf PDF
S02 Sol R0036 AttA VAAR 852.219-75 Certification 578-25-003.docx DOCX document
S02 Sol R0036 AttH Past Performance Client Questionnaire 578-25-003.pdf PDF
S02 Sol R0036 AttE SOW.Att15e_578-25-003 100 perc DWGS Part 5of5_2025.01.24.pdf PDF
S02 Sol R0036 AttI Wage Rates IL20250009.R3 2025.05.23 current as of 2025.06.05.pdf PDF
S02 Sol R0036 AttE SOW.Att00_Descriptive Project Scope of Work 578-25-003_r.pdf PDF
S02 Sol R0036 AttF SOW.Att19_Subcontractor Info Consent 578-25-003.pdf PDF
S02 Sol R0036 AttE SOW.Att08_Interim Life Safety Measures_ILSM.pdf PDF
S02 Sol R0036 AttB Contractor Info 578-25-003.docx DOCX document
S02 Sol R0036 AttG Brand Name or Equal_Basis of Design 578-25-003.xlsx XLSX spreadsheet
S02 Sol R0036 AttC Contractor EMR Safety Info 578-25-003.docx DOCX document
S02 Sol R0036 AttE SOW.Att04_No Smoking Policy 10-1-19.pdf PDF
S02 Sol R0036 AttE SOW.Att14a _578-25-003_Replace Elevators B200_SPECS VOL 1of 2_updated.pdf PDF
S02 Sol R0036 AttE SOW.Att15d_578-25-003 100 perc DWGS Part 4of5_2025.01.24.pdf PDF
S02 Sol R0036 AttE SOW.Att01_Contractor Badging_Fingerprint Request Form 2025.pdf PDF
S02 Sol R0036 AttE SOW.Att11_Above Ceiling Entry and Wall Construction Permits.pdf PDF
S02 Sol R0036 AttE SOW.Att06_Pre-Construction Checklist.pdf PDF
S02 Sol R0036 AttE SOW.Att13_OIT Horizontal Cable Requirements.pdf PDF
S02 Sol R0036 AttE SOW.Att12_Cutting Welding and Other Hot Work.pdf PDF
S02 Sol R0036 AttD Financial Disclosure 578-25-003.docx DOCX document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VHA Pre-Construction Risk Assessment (PCRA)

VHA-PCRA-2024-1.1 (May 21, 2024) Page 1 of 5

PCRA Introductory Information and Instructions

Use this template as a baseline for performing facility Pre-Construction Risk Assessments (PCRA) for Construction, Renovation, and Maintenance work (referred to as the “activity” in this document). The template provides minimum requirements for categorizing activity type(s) and safety risk to determine the level of precautions needed to prevent impact related to Construction, Renovation and Maintenance on patients, employees, and contractors.

Ensure that the activity statement of work and any drawings available are used for the PCRA assessment and included in the project file with the completed PCRA.

Communication and coordination of all types of activity with affected areas are to be included among the control measures. The development of communication and coordination plans must begin during the activity planning phase.

Facilities may customize this template to incorporate site-specific information and requirements.

NOTE: This VHA PCRA template pertains specifically to non-infection-related safety for Construction, Renovation, and Maintenance activities. It must be used in conjunction with the VHA Infection Control Risk Assessment (ICRA) for the activity, if required, which specifically addresses infection risks outside the scope of this PCRA.

PERMIT: See the last page of this document for a fillable permit form to be used for posting at the activity site.

Activity Location:

Activity Name, Number, and/or Brief Description:

Table 1 - Construction, Renovation, and/or Maintenance Activity Type and Control Measures NOTE: If any of the bulleted criteria in a higher activity type pertains to the work that will be done (even if the other criteria are in a lower type), use the higher activity type for the VHA PCRA.

Controls defined in Table 1 for the activity must be in place before the activity begins and maintained until work is completed and the area is activated. Control measures for each activity must also include the control measures in the preceding row(s).

As the activity progresses, a full re-evaluation of remaining activity type and risk is required prior to changing the level of control measures.

Activity Type determined from Table 1:

Activity Type and Description Control Measures Inspection/upkeep generally defined as follows:

• Work can be completed in a single shift, not to exceed 10 hours.

• Patients, employees and/or visitors may be in the area depending on the activity.

• Work that does not create dust or debris.

• Work that does not create vapors or fumes.

• Removal of ceiling tile or access to mechanical or electrical chase for visual inspection that will not impair fire safety systems and are limited to 1 tile per 50 square feet with limited

1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.

2. Site visits of construction area are required weekly by member of multi-disciplinary team.

Site visits will be documented on standard checklist.

3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved where a contact is in place. For internal work the

VHA-PCRA-2024-1.1 (May 21, 2024) Page 2 of 5 exposure time (not to exceed an hour for each tile) within the shift.

• Minor interior updates (e.g., replacing floor or ceiling tiles, carpentry work to include hanging signage, and painting with hand tools) that do not create vibration or noise.

• Limited building system maintenance that does not require Lock Out Tag Out (LOTO) such as plumbing on potable systems limited to faucet replacement, steam trap replacement etc. and electrical work such as replacement of bulbs, receptacles, or switches.

shop involved must work with Safety to ensure proper precautions are in place.

4. Must address identified hazards and controls that will be implemented to ensure minimal impact to patients, employees, contractors and facility.

5. Communication and coordination plan for all affected areas

Small scale Construction, Renovation and general maintenance/repair work, generally defined as follows:

• Prolonged work that may take longer than a single shift but not exceeding six months.

• Patients and employees are not to be in the area until activity is completed.

• Work that creates some noise and vibration due to power tool use.

• Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural elements that may o disturb asbestos, lead or silica o create the potential for falling objects o create vibration and/or noise in excess of 80 dB(A) in surrounding areas.

o cause penetrations in fire or smoke barrier

• Plumbing work such as the installation of new sinks, showers and toilets and associated plumbing that requires utility outages or work on the steam system that may require:

o LOTO o The use of compressed gas cylinders

• Electrical work such as installation of conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. Electrical work such as installation of cabling/wiring/conduit for a single device, installation of new device such as a light fixture that require LOTO.

• Air Handler and/or fan shutdown/startup and HVAC work such as replacement of a single diffuser, single terminal unit, a single device and the installation of ductwork, diffusers, and terminal units for an area that may require:

o Work on ladders o Rigging, hoisting or lifting of equipment or materials overhead

• Modification of existing fire alarm and suppression systems requiring system outages and ILSMs or obstruction of exits and or impact on corridors.

• Architectural, structural, or any other work that may cause vapors or fumes such as:

o Roofing work o Flooring work o Painting or other large-scale use of such substances.

All control measures in the row above and the following:

1. Hazard communication chemical inventory required to be provided by the contractor and approved.

2. Where construction, Renovation and maintenance are done in an accredited facility, and ILSM assessment is required to be done and ILSMs put into place in accordance with TJC LS.01.02.01 and the local facility policy including Fire watch if necessary. Staff is trained and the ILSM is verified regularly

3. Hot Work or burn permits in place and staff trained

4. LOTO procedures in place and staff trained on their use

5. Site visits will be reviewed using the criteria in standardized guide.

6. Daily inspections of the site are to be conducted by the General Contractor or shop supervisor and documented on their daily log.

Large-scale construction, renovation, or maintenance generally defined as follows:

• Work exceeding 6 months in duration.

• Patients and employees are not to be in the area until activity is completed.

All control measures in the two rows above and the following Activity Hazard Analyses and Control Plans (check all that apply):

1. Excavation safety plan in place ☐

2. Dust control plan in place ☐

VHA-PCRA-2024-1.1 (May 21, 2024) Page 3 of 5

• Excavation or heavy equipment use taking place o Dig safe required utility location o Trench safety o Dust control plan o Equipment exhaust, Noise, Vibration

• Confined space entry required (permit required or not)

• Requires crane work o General crane work o Lift over buildings

• Includes elevated work o Roof work, fall protection o Window work, scaffolding and fall protection o Odor control

• Welding, cutting or use of torches requiring burn permits

• Demolition of building components and infrastructure including removal of multiple doors, walls, framing, ceilings, flooring, piping, electrical and HVAC that may o require asbestos, lead or silica abatement o create the potential for falling objects o create vibration and/or noise in excess of 90 dB(A) in surrounding areas.

o cause breaches to fire or smoke barrier

• The installation building components such as new walls, ceilings and doors including framing, drywall and associated plaster work that requires transport of significant materials through building and up elevators i.e., weight limits of floors and elevators

• Plumbing work requiring LOTO and system shutdown and startup such as the installation of:

o new medical gas systems, o steam/heating hot water, condensate systems, o Potable water and sanitary drainage, multiple sinks, showers and toilets including associated plumbing.

• Electrical work such as installation of electrical feeders, distribution panels, conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. requiring LOTO and system isolation.

• Installation of fire alarm and suppression systems requiring outages of those systems and ILSMs or closure of exits/corridors

• Mechanical work such as the installation of air handling equipment, associated ductwork, diffusers, heat exchangers, terminal units and controls requiring lifting and support of equipment and systems.

3. Pollution prevention plan in place ☐

4. Dig safe paper work in place ☐

5. Crane lift plan in place ☐

a. Crane placement

b. Crane swing

c. Crane load evaluation

6. Fall protection plan in place and staff trained ☐

7. Confined entry plan in place and staff trained ☐

Table 2. Affected Adjacent Area Assessment In addition to the minimum precautions noted above for the Activity Type, it is critical that the activity be coordinated with the areas adjacent to the activity to ensure operations in those areas are not disrupted or impacted. List the adjacent areas in Table 2 below and develop activity-specific coordination plans and associated communication plans with each area to address activity work that could impact or disrupt the operation of the areas, in general as follows:

• If adjacent area is vacant (e.g., work outside, construction of new building, etc.):

o Coordination is typically not necessary other than potentially traffic flow and pedestrian access.

VHA-PCRA-2024-1.1 (May 21, 2024) Page 4 of 5

• If adjacent area is non-continuously occupied (e.g., areas where outpatient care is provided, employee health, etc.):

o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., conduct work after hours).

• If adjacent area is occupied continuously (e.g., areas where inpatient care is provided, residential areas such as Community Living Centers, etc.):

o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., move affected party temporarily).

Area Service(s)/Type(s) of Area(s)

(e.g., OR, Unit/Ward, Sterile Processing, Administrative, etc)*

Point of Contact

(POC)

POC Contact Information

Construction plan communicated to POC?

Activity Area**

Area Above

Area Below

Adjacent Area 1

Adjacent Area 2

Adjacent Area 3

Adjacent Area 4

* There may be more than one Service/type of area for each row. List all. The information entered on this table must be used in the ICRA if required.

** List the area(s) in which the construction/renovation/maintenance activity will occur.

Infection Control Risk Assessment (ICRA)

Consult with Infection Prevention and Control regarding the assessment of potential patient infection risks associated with the activity and the need for control measures. For example, activities such as a boiler plant project and/or facility steam shutdown, if properly planned, should have minimal to no patient infection risk impacts and likely not to require an ICRA. See VHA Directive 7715 and the VHA ICRA Template for more information.

Is an ICRA required for the Activity? Yes ☐ No ☐

VHAHINDoyleL Typewritten Text x

Pre-Construction Risk Assessment (PCRA) Permit This page must be posted at the entrance to the project area, or other designated area

Unique permit number:

Location and brief description of construction/renovation/maintenance Project manager Project start date Contact phone number Completion date Contractor or lead shop Permit expiration date

Activity Type Inspection/Upkeep, Small-scale, or Large-scale)

Activity Type Control measures to be in place for the duration of the activity (Check the box for the Activity Type to indicate the Control Measures)

Inspection/Upkeep

1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.

2. Site visits of construction area are required weekly by member of multi-disciplinary team. Site visits will be documented on standard checklist.

3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved.

4. Must address identified hazards and controls that will be implemented to ensure minimal impact patients, employees, contractors and facility.

5. Communication and coordination plan for all affected areas

Small-scale

All control measures in the row above and the following:

1. Hazard communication chemical inventory required to be provided by the contractor and approved.

2. ILSMs in place and staff trained on situation

3. Hot Work or burn permits in place and staff trained

4. LOTO procedures in place and staff trained on their use

5. Site visits will be reviewed using the criteria in standardized guide.

6. Daily inspections of the site are to be conducted by the General Contractor and documented on their daily log.

Large-scale

All control measures in both rows above and the following Activity Hazard Analyses and Control Plans as applicable (check all that apply):

1. Excavation safety plan in place ☐

2. Dust control plan in place ☐

3. Pollution prevention plan in place ☐

4. Dig safe paperwork in place ☐

5. Crane lift plan in place ☐

a. Crane placement

b. Crane swing

c. Crane load evaluation

6. Fall protection plan in place and staff trained ☐

7. Confined entry plan in place and staff trained ☐

*The location of all Activity Hazard Analyses and Control Plans (excavation, dust, pollution, etc.) as applicable shall be identified on this permit and shall be made available to all workers on the job.

VHA-PCRA-2024-1.1 (May 21, 2024)

Additional requirements:

Is an Infection Control Risk Assessment (ICRA) required for the Activity? Yes ☐ No ☐ Infection Prevention and Control signature:

Date:

Project Manager signature Date

Safety Officer signature Date

Chair, Construction Safety Committee signature

Date

PERMIT See the last page of this document for a fillable permit form to be used for posting at the activity site: Hines, Illinois
andor Brief Description: 578-25-003 Renovate Elevators in Building 200

Renovation of Elevators P1-P5 and S6-S8 and all associated equipment and controls.

As the activity progresses a full reevaluation of remaining activity type and risk is required prior to changing: Large-scale
Excavation safety plan in place: Off
Dust control plan in place: Off
Dig safe paper work in place: Off
Crane lift plan in place: Off
Fall protection plan in place and staff trained: Off
undefined: Off
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcActivity Area: Elevator Shaft
Point of Contact POCActivity Area: Keith Schmidt
POC Contact InformationActivity Area: (708) 979-2001 Government cell phone
Construction plan communicated to POCActivity Area: Yes
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcArea Above: Elevator Penthouse
Point of Contact POCArea Above: Keith Schmidt
POC Contact InformationArea Above: (708) 979-2001 Government cell phone
Construction plan communicated to POCArea Above: Yes
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcArea Below: Elevator Pit
Point of Contact POCArea Below: Keith Schmidt
POC Contact InformationArea Below: (708) 979-2001 Government cell phone
Construction plan communicated to POCArea Below: Yes
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 1: Elevator Lobbies - Basement through 14th Floor
Point of Contact POCAdjacent Area 1: Joe Tumpis
POC Contact InformationAdjacent Area 1: (708) 202-8387 ext. 21131
Construction plan communicated to POCAdjacent Area 1: Yes
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 2:
Point of Contact POCAdjacent Area 2:
POC Contact InformationAdjacent Area 2:
Construction plan communicated to POCAdjacent Area 2:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 3:
Point of Contact POCAdjacent Area 3:
POC Contact InformationAdjacent Area 3:
Construction plan communicated to POCAdjacent Area 3:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 4:
Point of Contact POCAdjacent Area 4:
POC Contact InformationAdjacent Area 4:
Construction plan communicated to POCAdjacent Area 4:
Is an ICRA required for the Activity: Off
Activity Type InspectionUpkeep Smallscale or Largescale: Large-scale
1 Excavation safety plan in place: Off
2 Dust control plan in place: Off
3 Pollution prevention plan in place: Off
4 Dig safe paperwork in place: Off
5 Crane lift plan in place: Off
6 Fall protection plan in place and staff trained: Off
7 Confined entry plan in place and staff trained: Off
Additional requirements:
Is an Infection Control Risk Assessment ICRA required for the Activity: Yes_2
Pollution prevention plan in place: Off
Unique permit number: 578-25-003 Renovate Elevators in Building 200
Project manager: Aaron Walsh
Contact phone number: (708) 202-8387 ext.21152
Project Start Date_af_date: 09/30/2025
Completion Date_af_date: 08/20/2028
Permit Expiration Date_af_date: 01/01/2029
Contractor or lead shop: TBD
Location and brief description of Construction/Renovation/Maintenance: Renovation of Elevators P1-P5 and S6-S8 and all associated equipment and controls.
Check Box6: Off
Check Box7: Off
Check Box8: Yes
Date10_af_date: 01/28/2025
2025-01-25T11:51:25-0600
AARON WALSH
2025-01-28T13:08:47-0600
NEENA DOBYNE
Project Manager Date Signed_af_date: 01/25/2025
Safety Officer Date Signed_af_date:
2025-01-28T11:35:14-0600
MATTHEW KELLY
CCS Date Signed_af_date:
2025-01-28T11:47:06-0600
CHRISTOPHER JAY