This document is an Amendment (P0006 - Attachment 5) for Solicitation 36C25225R0036, detailing Physical Access Control System requirements for the 578-25-003 Renovate Elevators project in Building 200. The specification mandates installing security cameras (AXIS M3086-V or equal) in elevator cabs and card readers (Signo PIV 40, 40HNKS-03-0059X or equal) in each elevator lobby, with all data routed to Building 200 Telecom Room 1459 on the 14th floor. The new security system must integrate with existing systems, using Milestone Software for cameras and Lenel OnGuard for PIV readers.

The project requires one new workstation and monitor with a split screen to view all eight elevators, to be installed in the Police SOC, Building 1 – Room F108. Specific technical requirements include meeting Physical Security System specifications outlined in project documents, providing necessary power and data connections, and ensuring compatibility with existing security infrastructure. No biometric security or direct data connections between Room 1459 and the Police SOC are required.

View the file

Other files

File Type Posted
36C25225R0036 0007.docx DOCX document
S06 36C25225R0036 006_Att02 25-0725 Supplemental Sketches.pdf PDF
BLDG200F13R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att07 26 22 00 Low-Voltage Transformers.pdf PDF
BLDG200F3R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att12 Sole Source Listing__full.e.pdf PDF
S06 36C25225R0036 006_Att06 26 43 13 Surge Protection Devices - Addendum 1.pdf PDF
BLDG200F7R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att11 Photos_Existing Conditions.pdf PDF
BLDG200F6R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att01 Finish and Lighting Changes.pdf PDF
BLDG200 F10R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att09 Hines State Tax Exempt 2025.pdf PDF
BLDG200F4R2010.xls XLS spreadsheet
BLDG200F11R2010.xls XLS spreadsheet
BLDG200F9R2010.xls XLS spreadsheet
BLDG200BSMTR2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att10 OFFER SCHEDULE.R1 578-25-003 B200 Elevators.pdf PDF
BLDG200F2R2010.xls XLS spreadsheet
BLDG200F1R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att08 GKT15-30W-10_Specification.pdf PDF
BLDG200F8R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att04 _ Wage Rates IL20250009.R3 2025.08.01.pdf PDF
BLDG200F14R2010.xls XLS spreadsheet
BLDG200F5R2010.xls XLS spreadsheet
36C25225R0036 0006.docx DOCX document
S06 36C25225R0036 0005.docx DOCX document
S06 36C25225R0036 0005.pdf PDF
S06 36C25225R0036 004 578-25-003_Att Finish Schedule.pdf PDF
36C25225R0036 0004.docx DOCX document
S06 36C25225R0036 003 Att2 Sign-in Site Visit_02_rev.pdf PDF
36C25225R0036 0003.docx DOCX document
S06 36C25225R0036 003 Att1 Sign-in Site Visit_01.pdf PDF
S06 36C25225R0036 002 Att2 Sign-in Site Visit_02.pdf PDF
S06 36C25225R0036 002 Att1 Sign-in Site Visit_01.pdf PDF
S06 36C25225R0036 002 578-25-003.docx DOCX document
S06 001 Att1 Sign-in Site Visit_01 for 578-25-003 Elevators 2025.06.18.pdf PDF
36C25225R0036 0001.docx DOCX document
36C25225R0036_3.docx DOCX document
S02 Sol R0036 AttA VAAR 852.219-75 Certification 578-25-003.docx DOCX document
S02 Sol R0036 AttC Contractor EMR Safety Info 578-25-003.docx DOCX document
S02 Sol R0036 AttE SOW.Att00_Descriptive Project Scope of Work 578-25-003_r.pdf PDF
S02 Sol R0036 AttE SOW.Att15d_578-25-003 100 perc DWGS Part 4of5_2025.01.24.pdf PDF
S02 Sol R0036 AttE SOW.Att12_Cutting Welding and Other Hot Work.pdf PDF
S02 Sol R0036 AttE SOW.Att18b_Building 220 Colored Space Drawings.pdf PDF
S02 Sol R0036 AttB Contractor Info 578-25-003.docx DOCX document
36C25225R0036_3.docx DOCX document
S02 Sol R0036 AttE SOW.Att09_Infection Control Risk Assessment_ICRA-1.3.pdf PDF
S02 Sol R0036 AttE SOW.Att14a _578-25-003_Replace Elevators B200_SPECS VOL 1of 2_updated.pdf PDF
S02 Sol R0036 AttE SOW.Att07_Pre-Construction Risk Assessment_PCRA 1.1.pdf PDF
Show 40 more

Latest 50 of 73 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

578-25-003 Renovate Elevators in Building 200

Physical Access Control System

- The new elevators shall meet the Physical Security System requirements as outlined in the project Specifications.

- This includes security cameras in the elevator cabs and card readers in each elevator lobby, along with the associated power and data connections. All data from the elevator penthouse to be run to Building 200 Telecom Room 1459 – 14th floor.

- Basis of Design o Security cameras - AXIS M3086-V or equal o Card readers – Signo PIV 40, 40HNKS-03-0059X or equal

- The new security system should integrate with the existing system o Cameras use Milestone Software o PIV Readers use Lenel OnGuard

- Only one (1) new workstation and one (1) new monitor is necessary, with a split screen to view all eight elevators. To be installed in the Police SOC, Building 1 – Room F108.

- No data connections between 1459 and the Police SOC are required.

- No biometric security is required.

Solicitation 36C25225R0036 Project 578-25-003 Renovate Elevators in Bldg 200 Amendment P0006 - Attachment 5