ENG Form 6282 is a U.S. Army Corps of Engineers (USACE) Site Safety & Health Officer (SSHO) Designation Letter template used to designate personnel responsible for overseeing and implementing a prime contractor's Safety & Occupational Health (SOH) program. The form must be signed by the company official responsible for the SOH program, such as a Corporate Safety Manager. Contractors are required to submit this signed designation letter to the Government Designated Authority (GDA) as part of the Accident Prevention Plan, along with an instructor-signed OSHA 30-hour card (or course completion certificate if within 90 days of completion) and proof of 24 hours of SOH competency training within the last three years.

The form establishes three SSHO designation levels with corresponding training and experience requirements. Level 1 requires 5 years of cumulative safety experience within the last ten years managing or implementing SOH programs on similar projects, plus 24 hours of documented formal classroom or online SOH-related training within the past five years, with recertification every three years. Level 2 requires 3 years of cumulative safety experience within the last ten years on similar projects and the same 24-hour training requirement. Level 3 designates a Qualified or Competent Person. Part I of the form is completed by the company's SOH program official, who certifies the designated SSHO meets minimum training and experience requirements and has authority to stop work when required. Part II is completed by the designated SSHO with name, date, and signature confirmation.

View the file

Other files

File Type Posted
PWS - FYXX B1 Project Appendix D Required Submittals Reports Meetings YYYYMMDD.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS TE-4 Service Order Forms 250523.pdf PDF
PWS - FYXX B1 Project Appendix E RMS YYYYMMDD.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS TE-3 Monthly Progress Report Format 250523.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS Appendix A Technical Exhibits 250523.pdf PDF
PWS - FYXX B1 Fort Hood Doors Appendix C Performance Requirements Summary 250523.pdf PDF
DRAFT_PWS - FY25 B1 Ft Cavazos Doors MS TE-5 Engineer Form 3394 08012021.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS Appendix E RMS 20250523.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS Appendix C Performance Requirements Summary 250523.pdf PDF
PWS - FYXX B1 Project Appendix H Service Order Process YYYYMMDD.pdf PDF
PWS - FYXX B1 Fort Hood Doors MS Appendix A Technical Exhibits.pdf PDF
PWS - FYXX B1 Fort Hood Doors MS 251124.pdf PDF
DRAFT_PWS - FY25 B1 Ft Cavazos Doors MS TE-2 Equipment List_250523.xlsx XLSX spreadsheet
PWS - FY25 B1 Ft Cavazos Doors MS Appendix G Acronyms and Definitions 250523.pdf PDF
PWS - FYXX B1 Project Appendix F Applicable Codes Standards and Regulations YYYYMMDD.pdf PDF
FT Hood Overhead Doors_Sources Sought_MKT RSRCH.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS Appendix B.2 APP Worksheet Eng_Form_6293_Aug 2024.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS Appendix D Required Submittals 250523.pdf PDF
DRAFT_PWS - FY25 B1 Ft Cavazos Doors Appendix B.2 APP Worksheet Eng_Form_6293_Aug 2024.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS Appendix H Service Order Process 250523.pdf PDF
PWS - FYXX B1 Project Appendix G Acronyms and Definitions YYYYMMDD.pdf PDF
DRAFT_PWS- FY25 B1 Ft Cavazos Doors MS TE-6 Wkly CMPM Data Templat_250523.xlsx XLSX spreadsheet
PWS - FYXX B1 Project TE-3 Monthly Progress Report Format YYYYMMDD.pdf PDF
PWS - FYXX B1 Project TE-4 Service Order Forms YYYYMMDD.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ENG FORM 6282, AUG 2023

U.S. Army Corps of Engineers (USACE)

SITE SAFETY & HEALTH OFFICER (SSHO) DESIGNATION LETTER

For use of this form, see EM 385-1-1; the proponent agency is CESO.

Purpose: This document designates personnel responsible for overseeing and ensuring the implementation of the prime contractor's Safety & Occupational Health (SOH) program. This designation letter will be signed by the company's official responsible for the SOH program (e.g., Corporate Safety Manager).

Submit the following documentation to the Government Designated Authority (GDA) as part of the Accident Prevention Plan: 1) This signed SSHO Designation Letter (Eng Form 6282); 2) An instructor-signed OSHA 30-hour card (or course completion certificate if within 90 days of completing the OSHA 30-hour training); and 3) proof of 24 hours of competency of SOH training within the last 3 years.

PART I: COMPLETED BY COMPANY'S SOH PROGRAM OFFICIAL

1. Project Name 2. Contract Number

3. Location

4. The designated SSHO on this form meets the minimum EM 385-1-1 training and experience requirements for the selected level below and is knowledgeable of the SOH requirements for this project and has the authority to stop work when required.

SSHO Level Experience Competency Training OSHA 30-Hour

Qualified or Competent Person

3 years of cumulative safety experience, within the last 10 years, managing or implementing a SOH program on projects similar in industry type, size, and complexity as the project described in the contract scope of work.

24 hours of documented formal classroom or online SOH-related training within the past five years and must maintain competency by taking 24 hours every three-year period for the duration of the contract.

Construction or General Industry

5 years of cumulative safety experience, within the last ten years, managing or implementing a SOH program on projects similar in industry type, size, and complexity as the project described in the contract scope of work.

24 hours of documented formal classroom or online SOH-related training within the past five years and must maintain competency by taking 24 hours every three-year period for the duration of the contract.

Construction or General Industry Level 1

Level 2

Level 3

5. Summary of required safety experience:

By my signature below, I certify that the information I provided on this form is true and correct to the best of my knowledge.

Company SOH Official Name Company SOH Official Title

Company SOH Official Signature Date

PART II: COMPLETED BY DESIGNATED SSHO

SSHO Name Date SSHO Signature

ENG FORM 6282, AUG 2023

U.S. Army Corps of Engineers (USACE)

SITE SAFETY & HEALTH OFFICER (SSHO) DESIGNATION LETTER

For use of this form, see EM 385-1-1; the proponent agency is CESO.

Purpose: This document designates personnel responsible for overseeing and ensuring the implementation of the prime contractor's Safety & Occupational Health (SOH) program. This designation letter will be signed by the company's official responsible for the SOH program (e.g., Corporate Safety Manager).

Submit the following documentation to the Government Designated Authority (GDA) as part of the Accident Prevention Plan: 1) This signed SSHO Designation Letter (Eng Form 6282); 2) An instructor-signed OSHA 30-hour card (or course completion certificate if within 90 days of completing the OSHA 30-hour training); and 3) proof of 24 hours of competency of SOH training within the last 3 years.

PART I: COMPLETED BY COMPANY'S SOH PROGRAM OFFICIAL

4. The designated SSHO on this form meets the minimum EM 385-1-1 training and experience requirements for the selected level below and is knowledgeable of the SOH requirements for this project and has the authority to stop work when required.

SSHO Level Experience Competency Training OSHA 30-Hour Qualified or Competent Person 3 years of cumulative safety experience, within the last 10 years, managing or implementing a SOH program on projects similar in industry type, size, and complexity as the project described in the contract scope of work.

24 hours of documented formal classroom or online SOH-related training within the past five years and must maintain competency by taking 24 hours every three-year period for the duration of the contract.

Construction or General Industry 5 years of cumulative safety experience, within the last ten years, managing or implementing a SOH program on projects similar in industry type, size, and complexity as the project described in the contract scope of work.

24 hours of documented formal classroom or online SOH-related training within the past five years and must maintain competency by taking 24 hours every three-year period for the duration of the contract.

Construction or General Industry By my signature below, I certify that the information I provided on this form is true and correct to the best of my knowledge.

PART II: COMPLETED BY DESIGNATED SSHO

1.0 darwin.chen@usace.army.mil 2023-05-05 Forms Design Team Darwin Chen 2023-08-30

SITE SAFETY & HEALTH OFFICER (SSHO) DESIGNATION LETTER

SITE SAFETY & HEALTH OFFICER (SSHO) DESIGNATION LETTER

PrintButton1:
saveas:
TextField1:
lev1: 0
lev2: 0
lev3: 0
SignatureField1:
DateField1:

File details come from the government source that posted it. Updated .