This is a Performance Work Statement (PWS) Technical Exhibit documenting Service Order Forms and submission requirements for corrective maintenance packages under a federal contract.

The document establishes three mandatory Service Order Forms that contractors must submit with corrective maintenance packages: (1) the Service Order Form, required for all service orders and to be provided in Excel format upon contract award; (2) the Service Order Sole Source Justification Form, required when only one source is solicited for subcontractors or materials exceeding $2,500.00, which must include detailed justification selecting from eight FAR-referenced reasons for sole sourcing and require prime contractor signature certification; and (3) the Statement of Competition & Price Reasonableness Determination Form, required for all service orders with materials and/or subcontractor quotes exceeding $2,500.00. The Statement of Competition form requires contractors to list all solicited subcontractors and material vendors with their bid amounts and validity periods, document any declined bids with supporting emails, and justify subcontractor selection based on either low bid or best value with detailed explanation. The Price Reasonableness Determination section requires contractors to establish price reasonableness through one of five methods: competition (two or more qualifying bids), historical data from previous similar work, industry data from catalogs or internet research, R.S. Means or similar estimating software, or other documented methods, with supporting documentation required for all methods except competition. All forms require prime contractor signature certifying accuracy of submitted information, and the Contracting Officer reserves the right to reject any Price Reasonableness Determination deemed inadequate.

View the file

Other files

File Type Posted
PWS - FYXX B1 Project TE-3 Monthly Progress Report Format YYYYMMDD.pdf PDF
PWS - FYXX B1 Project Appendix G Acronyms and Definitions YYYYMMDD.pdf PDF
DRAFT_PWS- FY25 B1 Ft Cavazos Doors MS TE-6 Wkly CMPM Data Templat_250523.xlsx XLSX spreadsheet
FT Hood Overhead Doors_Sources Sought_MKT RSRCH.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS TE-3 Monthly Progress Report Format 250523.pdf PDF
PWS - FYXX B1 Project Appendix H Service Order Process YYYYMMDD.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS Appendix E RMS 20250523.pdf PDF
DRAFT_PWS - FY25 B1 Ft Cavazos Doors MS TE-5 Engineer Form 3394 08012021.pdf PDF
DRAFT_PWS - FY25 B1 Ft Cavazos Doors Appendix B.2 APP Worksheet Eng_Form_6293_Aug 2024.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS Appendix B.1 SSHO_Designation_Eng_Form_6282_2023Aug28.pdf PDF
PWS - FYXX B1 Project Appendix F Applicable Codes Standards and Regulations YYYYMMDD.pdf PDF
PWS - FYXX B1 Project Appendix D Required Submittals Reports Meetings YYYYMMDD.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS TE-4 Service Order Forms 250523.pdf PDF
PWS - FYXX B1 Fort Hood Doors Appendix C Performance Requirements Summary 250523.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS Appendix G Acronyms and Definitions 250523.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS Appendix A Technical Exhibits 250523.pdf PDF
PWS - FYXX B1 Fort Hood Doors MS Appendix A Technical Exhibits.pdf PDF
PWS - FYXX B1 Fort Hood Doors MS 251124.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS Appendix H Service Order Process 250523.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS Appendix D Required Submittals 250523.pdf PDF
PWS - FYXX B1 Project Appendix E RMS YYYYMMDD.pdf PDF
PWS - FY25 B1 Ft Cavazos Doors MS Appendix C Performance Requirements Summary 250523.pdf PDF
DRAFT_PWS - FY25 B1 Ft Cavazos Doors MS TE-2 Equipment List_250523.xlsx XLSX spreadsheet
PWS - FY25 B1 Ft Cavazos Doors MS Appendix B.2 APP Worksheet Eng_Form_6293_Aug 2024.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT

PWS Technical Exhibit 4 FYXX B1 <Contract Name> Service Order Forms

TE-4.1 General The Contractor shall submit the following Service Order Forms with Corrective Maintenance packages in accordance with Appendix H.

TE-4.1.1. Service Order Form This form is required for all Service Orders. An Excel version will be provided to the Contractor upon award.

TE-4.1.2. Service Order Sole Source Justification Form This form is required for all Service Orders where only one source was solicited for subcontractor or materials over $2,500.00.

The Contractor shall insert the following into the respective fields:

a. Site: The facility where work takes place for the respective Service Order.

b. Contract Number: The contract number. If this is a task order, provide the overarching contract number, followed by a “/”, and then the task order number.

c. Date: Insert the date.

d. Prime Contractor: The Prime Contractor on this contract/task order.

e. Service Order Scope of Work: The Scope of Work for the respective Service Order. (A summary of the SOW from the Service Order Form is acceptable)

f. Cost: The Service Order total cost.

g. Check Boxes: Check the applicable box for the respective Service Order. A Service

Order may only be sole sourced for one of the eight reasons included on this form.

h. Further Justification: This box must be filled out or the Service Order will be returned.

The Contractor shall include a further and detailed description of why competition could not be sought in addition to checking one of the eight boxes.

i. Prime Contractor Signature: A representative of the Prime Contractor shall sign this box certifying all information provided on this form is accurate.

TE-4.1.3. Statement of Competition & Price Reasonableness Determination Form This form is required for all service orders with materials and/or subcontractor quotes exceeding $2,500.00.

TE-4.1.3.1. Section 1 – Statement of Competition:

The Contractor shall insert the following into the respective fields:

a. Service Order No.: Include the Service Order number here.

b. Location: The facility where work takes place for the respective Service Order.

c. Total Service Order Cost: The Service Order total cost.

d. Scope of Work: The Scope of Work for the respective Service Order. (A summary of the

SOW from the Service Order Form is acceptable)

e. Competitive bids table: The Contractor shall list each subcontractor/material vendor solicited (or if material from a website, list the website/vendor), the total subcontract/material amount, and how long the bid is valid (if applicable). If a subcontractor declined to bid, the Contractor shall put “NO BID” in the bid amount. If a vendor declines to bid, the Contractor shall include an email of the vendor declining to bid in the Service Order package, or the email of the Prime Contractor asking for a quote if no response was received.

f. Comments: The Contractor shall include comments if necessary.

g. Justification for subcontractor selection:

a. Low Bid: The Contractor shall check this box if the lowest bid/amount is the selected choice.

PWS Technical Exhibit 4 FYXX B1 <Contract Name> Service Order Forms

b. Best Value: If the Contractor does not select the low bidder, the Contractor shall check this box and provide a detailed explanation as to why they did not select the low bidder. (Best solution, low bidder did not address all repairs, etc.)

TE-4.1.3.2. Section 2 – Price Reasonableness Determination:

The Contractor shall insert the following into the respective fields:

a. Checkboxes:

a. Competition: The Contractor shall check this box if two or more bids were received that meet the requirements of the SOW.

b. Historical Data: The Contractor shall check this box if previous similar work or past service orders were used to determine price reasonableness. This cannot be the only form of price reasonableness, if used it must be used along with another form of acceptable price reasonableness. If this box is checked, the referenced historical data must be included in the Service Order package.

c. Industry data: The Contractor shall check this box if catalogs, internet research, etc. were used to determine a fair and reasonable price. The Contractor shall include referenced data in the Service Order package.

d. R.S. Means: The Contractor shall check this box if R.S. Means or other estimating software was used to determine price reasonableness. The Contractor shall include referenced data in the Service Order package.

e. Other: If the Contractor uses another method to determine price reasonableness, include it here. The Contractor shall provide supporting documentation if necessary. The KO reserves the right to reject a Price Reasonableness Determination.

b. Signature: A representative of the Prime Contractor shall sign this form certifying all information provided on this form is accurate.

CONTRACTOR: CONTRACT NO.:

FACILITY NAME : TASK ORDER NO.:

FACILITY LOCATION: CMMS SERVICE ORDER NO:

HNC SERVICE ORDER NO: INITIATOR:

SERVICE ORDER DATE:

One of these boxes must be checked: ROUTINE URGENT EMERGENCY

Reg Labor Hours Reg Labor Rate Overtime Labor Hours OT Labor Rate Total

Description QTY Part # Manufacturer Unit Unit Price Amount each -$ -$ each -$ -$ each -$ -$ each -$ -$ each -$ -$

Trip Description Travelers Days Per Diem (Total) Roundtrip Mileage Mileage Rate Travel Cost $0.00 -$ -$

ME&I 0 0 -$ Roundtrip Airfare -$ ME&I @75% (first and last day) 0 0 -$ Lodging 0 0 -$

Lodging ME&I ME&I @ 75% Standard Rate -$ -$ -$

TOTAL TRAVEL COST -$

Cost Labor Total -$ -$ Materials Cost -$ -$ Tax 0.00% -$ -$ Shipping -$ -$ Travel Cost -$ -$ Prime Total -$ -$ Subcontract Total -$ -$ Prime Contractor SO Fee 0.00% -$ -$ Emergency SO Fee 0.00% -$ -$ Subcontractor Markup 0.00% -$

-$ TOTAL COST -$

I concur this is a valid requirement to meet operational needs covered by this contract.

DESIGNATED GOVERNMENT REPRESENTATIVE:

DATE

SIGNED:

CONTRACTOR

I certify the services described above have been satisfactorily completed

PART II - COST SUMMARY

Contractor confirms there is an USACE accepted AHA associated with the work being performed in this SO included in the APP.

AHA identifier or tracking

SERVICE ORDER FORM

PART I - SERVICE ORDER INFORMATION

SERVICE ORDER SOW:

Contractor acknowledges there is NOT an AHA associated with the work being performed in this SO included in the APP. AHA is attached for review with the SO.

Contractor acknowledges there is an activity associtated with the SO that requires an additional plan or program that will be included in an APP addendum.

CEHNC Safety Compliance

Contractor Signature:_____________________

SCA/CBA or DBA (Select One) SCA/CBA DBA

QUALITY ASSURANCE EVALUATOR

PART IV - CERTIFICATION OF SERVICES

SIGNED:

PART III - AUTHORIZATION

$0.00

Not To Exceed (NTE)Firm-Fixed Price (FFP)FUNDING CLIN:

DATE

$0.00

Contractor acknowledges receipt of KO/SOA approved Service Order

DATE

Notice To Proceed to perform this SO is authorized:

CONTRACTING OFFICER/SERVICE ORDER ADMINISTRATOR

SUBCONTRACTORS

PRIME CONTRACTOR LABOR UTILIZED (add rows if necessary)

TOTAL REGULAR LABOR

TOTAL MATERIALS

Totals

Labor Classification

PRIME CONTRACTOR TRAVEL

Check all applicable boxes:

Inbrief Conducted: Date Work Completed: Outbrief Conducted:

Subcontractor Total

Subcontractor

PRIME CONTRACTOR PARTS/MATERIALS/EQUIPMENT (add rows if necessary)

DRAFT Bid Amount Valid Until

(signature) (date) (printed name)

** PROPOSAL INFORMATION **

** REQUIRED for all service orders with materials and/or subcontractor quotes exceeding $2,500.00 **

Competitive bids were solicited & results are as follows:

SECTION 1 - STATEMENT OF COMPETITION

Service Order No.:

Location:

Total Price for Approval:

Scope of Work

Comments:

Completed by:

SECTION 2 - PRICE REASONABLENESS DETERMINATION

Justification for subcontractor selection:

Low Bid Best Value (complete scope of work, best technical solution, value added, etc)

Please explain:

How did you determine price reasonableness? * if other than Competition, PRD documentation must be provided

Competition (PRD not needed if two or more valid quotes received) Historical Data (previous similar work, past service orders) Industry Data (catalog/internet research, etc) R.S. Means Other (please explain):

Subcontractor

DISCLOSURE STATEMENT

This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed – in whole or in part – for any purpose other than to evaluate this proposal or quotation. If, however, a contract is awarded to this offeror as a result of – or in connection with –the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government’s right to use information contained in this data if it is obtained from another source without restriction.

The data subject to this restriction are contained in all sheets of this proposal.

Contractor Logo Here

Sole Source * Sole Sorce Justification Form Provided. **Not required if multiple bids solicited and only one received**

Comments:

STATEMENT OF COMPETITION &

PRICE REASONABLENESS DETERMINATION

a0edsdfk Rectangle

SOLE SOURCE JUSTIFICATION

SITE:

DATE:

CONTRACT No:

VENDOR:

SERVICES REQUESTED:

ESTIMATED COST:

Utility services available from only one source. IAW FAR 6.302-1(b)(3)

Engineering or R & D capability to be provided by an educational or non-profit institution or federally funded R & D Center. IAW FAR 6.302-3

Only known source of supply. IAW FAR 6.302-1

Compatibility – Unique supplies or services available from only one source or supplier with unique capabilities. IAW FAR 6.302-1(1)(b)(1) Example: direct replacement for a component part; material / equipment / component is required for use in existing equipment; and substitutes cannot be used because of electrical, mechanical, or physical reasons.

Unusual or compelling urgency. IAW FAR 6.302-2 Example: delay of an award would result in serious injury, financial or other, to the government.

Justification provided.

Agency standardization program dictates that only specified makes and models of technical equipment and parts will satisfy the agency’s need for additional units or replacement items, and only one source is available. IAW FAR 6.302- (b) (4)

Limited rights in data, patent rights, copyrights, or secret process. IAW FAR 6.302-1(b)(2)

Repair/maintenance by original manufacturer or authorized agency to preserve conditions of warranty.

FURTHER JUSTIFICATION: **REQUIRED** (if space is not enough, attach additional sheet)

Contract Maintenance Manager

REASON FOR LACK OF COMPETITION:

archive PWS - FYXX B1 Project TE-4 Service Order Forms YYYYMMDD.pdf
FY23 B1 PWS - 88th RD KC Region TE-7 Service Order Forms 20221205.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
FY23 B1 PWS - 88th RD Columbus Region TE-7 Service Order Forms 20221205.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
FY23 B1 PWS - 88th RD Indianapolis Region TE-7 Service Order Forms 20221123.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
HNC BaseOps SOF(SO#) non GSA 20221123.pdf
SO form
FY23 B1 PWS - 88th RD KC Region TE-7 Service Order Forms 20221205.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
FY23 B1 PWS - 88th RD Columbus Region TE-7 Service Order Forms 20221205.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
FY23 B1 PWS - 88th RD Indianapolis Region TE-7 Service Order Forms 20221123.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
HNC BaseOps SOF(SO#) non GSA 20221123.pdf
SO form
archive PWS - FYXX B1 Project TE-4 Service Order Forms YYYYMMDD.pdf
FY23 B1 PWS - 88th RD KC Region TE-7 Service Order Forms 20221205.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
FY23 B1 PWS - 88th RD Columbus Region TE-7 Service Order Forms 20221205.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
FY23 B1 PWS - 88th RD Indianapolis Region TE-7 Service Order Forms 20221123.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
HNC BaseOps SOF(SO#) non GSA 20221123.pdf
SO form
FY23 B1 PWS - 88th RD KC Region TE-7 Service Order Forms 20221205.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
FY23 B1 PWS - 88th RD Columbus Region TE-7 Service Order Forms 20221205.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
FY23 B1 PWS - 88th RD Indianapolis Region TE-7 Service Order Forms 20221123.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
HNC BaseOps SOF(SO#) non GSA 20221123.pdf
SO form
BaseOps PRD and SSJ Form 20240124.pdf
TE-3.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All)
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
PWS - FY22 B1 USAG-Alaska CM TE-3 Service Order Forms 20220720.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All)
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
PWS - DIA Region V FSS TE-8 Service Order Forms 20220705.pdf
TE-8.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required if multiple subcontractor bids are solicited and only one received)
PWS - FY22 B1 Wainwright CM TE-3 Service Order Forms 20220630.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All)
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
HNC BaseOps SOF(SO#) non GSA 20220630.pdf
SO form
SOF(SO#) Wainwright 20220630.pdf
SO form
Statement of Competition and PRD 20220705.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All)
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
PWS - DIA Region V FSS TE-8 Service Order Forms 20220705.pdf
TE-8.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required if multiple subcontractor bids are solicited and only one received)
PWS - FY22 B1 Wainwright CM TE-3 Service Order Forms 20220630.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All)
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
HNC BaseOps SOF(SO#) non GSA 20220630.pdf
SO form
SOF(SO#) Wainwright 20220630.pdf
SO form
PWS_FY22_B1_Fort Stewart Urgent_Emergency HVAC SOs_TE-1 Service Order Forms 20220809.pdf
TE-1.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
PWS - 88th RD KC Region TE-7 Service Order Forms 20220720.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
SOF(SO#) Wainwright 20220630.pdf
SO form
HNC BaseOps SOF(SO#) non GSA 20220809.pdf
SO form
Base Ops PRD and SSJ Form 27 Mar 2024.pdf
TE-3.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All)
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
PWS - FY22 B1 USAG-Alaska CM TE-3 Service Order Forms 20220720.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All)
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
PWS - DIA Region V FSS TE-8 Service Order Forms 20220705.pdf
TE-8.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required if multiple subcontractor bids are solicited and only one received)
PWS - FY22 B1 Wainwright CM TE-3 Service Order Forms 20220630.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All)
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
HNC BaseOps SOF(SO#) non GSA 20220630.pdf
SO form
SOF(SO#) Wainwright 20220630.pdf
SO form
Statement of Competition and PRD 20220705.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All)
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
PWS - DIA Region V FSS TE-8 Service Order Forms 20220705.pdf
TE-8.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required if multiple subcontractor bids are solicited and only one received)
PWS - FY22 B1 Wainwright CM TE-3 Service Order Forms 20220630.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel or Word version for Contractor use upon contract award. Sample forms are included.
Service Order Form (All)
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor above $2,500)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
HNC BaseOps SOF(SO#) non GSA 20220630.pdf
SO form
SOF(SO#) Wainwright 20220630.pdf
SO form
PWS_FY22_B1_Fort Stewart Urgent_Emergency HVAC SOs_TE-1 Service Order Forms 20220809.pdf
TE-1.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
PWS - 88th RD KC Region TE-7 Service Order Forms 20220720.pdf
TE-7.1 General.
The Contractor shall submit the following Service Order Forms with Corrective Maintenance, Alterations, and New Work requests. The Government will provide an Excel version of the Service Order Form for Contractor use upon contract award. The Statement...
Service Order Form (All).
Statement of Competition and Price Reasonableness Determination (All with materials and/or subcontractor cost above $2,500.00)
Sole Source Justification (Sole Source only; not required for lack of competition, i.e., multiple subcontractors/vendors solicited and only one response)
SOF(SO#) Wainwright 20220630.pdf
SO form
HNC BaseOps SOF(SO#) non GSA 20220809.pdf
SO form
SubcontractorRow1:
Bid AmountRow1:
SubcontractorRow2:
Bid AmountRow2:
SubcontractorRow3:
Bid AmountRow3:
SubcontractorRow4:
Bid AmountRow4:
Comments:
printed name:
Check Box1: Off
Check Box2: Off
Check Box3: Off
Check Box4: Off
Text8:
Text9:
Text11:
Date1_af_date:
Date2_af_date:
Date3_af_date:
Date13_af_date:
Text15:
Check Box9: Off
Contract Maintenance Manager:
Text1:
Text2:
Text3:
Date4_af_date:
Text5:
Text6:
Check Box 1: Off
Check Box 2: Off
Check Box 3: Off
Check Box 4: Off
Check Box 5: Off
Check Box 6: Off
Check Box 8: Off
Check Box 7: Off
Text10:

File details come from the government source that posted it. Updated .