Summary: Rogers Early Elementary School Roofing Replacement Project Specification

This is a project specification document prepared by Melvindale Schools (located in Allen Park, Michigan) for the complete roofing replacement at Rogers Early Elementary School, issued on August 10, 2026. The project scope includes a full roof tear-off and replacement of an existing aggregate-surfaced built-up roofing (BUR) system on three designated roof areas (Areas 1, 2, and 3) totaling 24,545 square feet with a slope of 1/4 inch per 12 inches. The work consists of complete reroofing preparation including removal of existing BUR membrane and flashings, installation of a new three-ply hot-applied asphalt built-up roofing system on a gypsum deck with polyisocyanurate insulation, stone aggregate surfacing, base flashings, and associated sheet metal flashing and trim work. The roofing system is specified as Tremco THERMastic products, with the project managed under a single prime contract. A preliminary roofing conference is required before work begins, and the roofing system manufacturer's technical representative (Luke Idoni, Field Advisor, 810-280-5194) will conduct inspections at commencement and upon completion. The contract requires compliance with NRCA and FM standards, with the owner maintaining building occupancy during construction, necessitating work limitations to normal business hours (7:00 a.m. to 5:00 p.m., Monday through Friday) with 72-hour advance notice for any disruptive activities.

The project includes provisions for unit price work, with Unit Price No. 1 covering deck material replacement and Unit Price No. 5 addressing existing wood nailer replacement at specified rates per measurement unit. A 20-year manufacturer warranty from Tremco CPG Inc. and a 2-year installer warranty are specified, with manufacturer inspections required at years 2, 5, 10, and 15 following completion. The roofing installer must be an employer of manufacturer-trained and certified workers with a full-time on-site supervisor possessing minimum five years' comparable experience. The specification document references related work in Division 07 sections for sheet metal flashing and trim and manufactured roof expansion joints, and requires temporary protection measures for existing roofing systems that will remain, with all demolition materials becoming contractor property unless otherwise indicated. The project is subject to EPA notification regulations and local hauling and disposal requirements, with contractor responsibility for engaging a qualified roofing inspector for a minimum of three full-time days per 40-hour work week to perform quality assurance testing and inspections.

View the file

Other files

File Type Posted
Allendale Elementary- AOC.pdf PDF
MELNAP Schools Summer of 2027 Roofing Scope of Work.docx DOCX document
Wood-Curb-Model.pdf PDF
Project-Allendale Elementary Roofing Replacement.docx DOCX document
Plumbing-Vent-Model.pdf PDF
Hot-Stack-Penetration.pdf PDF
Door-Threshold-Model.pdf PDF
TLRFIA-over-Steel-Model.pdf PDF
Conduit-or-Piping-Support.pdf PDF
Dail-Water-Stop-Tie-In-Model.pdf PDF
FAMILIAL RELATIONSHIP DISCLOSURE STATEMENT.docx DOCX document
Project-Allendale Elementary Roofing Replacement.pdf PDF
Metal-Sleeve-and-Storm-Collar.pdf PDF
Gauge-or-Thickness-Guide.pdf PDF
Base-Sheet-Fastener-7-Inch.pdf PDF
Pitch-Pocket-with-Grout.pdf PDF
Rogers Early Elementary- AOC.pdf PDF
Project-Rogers Early Elementary School Roofing Replacement.pdf PDF
Area-Divider-Model.pdf PDF
Light-Metal-Roof-Edge (1).pdf PDF
MELNAP Schools Summer of 2027 Roofing Bid Form.doc DOC document
FAQs PW April 2025.pdf PDF
Prevailing Wage Rates.pdf PDF
Roof-Drain-with-Gravel-Guard.pdf PDF
Curb-for-Air-Handling-Unit.pdf PDF
Equipment-Stand-Rain-Collar.pdf PDF
Flashing-for-Non-Wall-Supported (1).pdf PDF
Roof-Hatch-Model.pdf PDF
Slip-Metal-Skirt-Flashing.pdf PDF
Light-Metal-Parapet-Cap.pdf PDF
Metal-Flashing,-Round-to-Square.pdf PDF
Piping-Through-Roof-Deck.pdf PDF
Notice To Bidders MELNAP Summer of 2027.docx DOCX document
AFFIDAVIT OF COMPLIANCE IRAN.docx DOCX document
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Melvindale Schools Date of Issue (08/10/2026)

Rogers Early Elementary School

Rogers Early Elementary School Roofing Replacement

DIVISION 01 - GENERAL REQUIREMENTS

011000 Summary

012200 Unit Prices

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

070150.19 Preparation for Re-Roofing

075113.11 Built-Up Asphalt Roofing, Hot-Applied

076200.02 Sheet Metal Flashing and Trim (Short Form)

077129 Manufactured Roof Expansion Joints

Melvindale Schools
Date of Issue (08/10/2026)

Rogers Early Elementary School

Rogers Early Elementary School Roofing Replacement

000110 - Page 1 of 1

TABLE OF CONTENTS

COPYRIGHT: 2020 by The American Institute of Architects (AIA). Exclusively published and distributed by Deltek, Inc., for the AIA. Tremco modifications were made with permission and Tremco CPG Inc. reserves all rights thereto.

DESIGN PROFESSIONAL: The attached PRODUCT MASTERSPEC section(s) are licensed by Deltek, Inc., for limited distribution by Tremco CPG Inc. and are prepared as a courtesy for use by design professional of record on a single project. Review and accept changes and modify according to project requirements and design professional's practice, who assumes responsibility for document contents consistent with licensing statutes of the Project state.

FACILITY OWNER: The attached PRODUCT MASTERSPEC section(s) are licensed by Deltek, Inc., for limited distribution by Tremco CPG Inc. and are prepared as a courtesy for use by facility owner on a single project.

For more information about Tremco roofing products, contact Tremco Roofing and Building Maintenance Division, Beachwood, OH 44122, (800) 562 - 2728, Web address: www.tremcoroofing.com

Melvindale Schools
Date of Issue (08/10/2026)

Rogers Early Elementary School

Rogers Early Elementary School Roofing Replacement

000100 - Page 1 of 1

COPYRIGHT

SECTION 011000 - SUMMARY

This pre-edited TremSpec section provides a description of the overall scope of work, identifies the parties, and stipulates restrictions on the free movement of the Contractor's personnel on site. Certain fields in this document autofill from project/spec data entered elsewhere.

This Section and other Division 01 Sections is intended for use when an Architect is NOT involved in the design and specification of the Work of the Project. The WORK COVERED article is useful for projects where several roofing systems are required; this portion can be coordinated with Section 070150.19 "Preparation for Reroofing." This Section may be used in careful coordination with the Owner's Architect (or Engineer, or Roof Consultant) when applicable; or defer to Architect to provide Division 01 Sections.

To view non-printing Editor's Notes (in Word.doc) that provide guidance for editing, change setting in Word to View Hidden Text and Print Hidden Text. This is a global setting in Word. View and manually delete all editor’s notes from Word.doc specification sections before issuing a Word.doc outside for Tremco.

GENERAL

SUMMARY

Section Includes:

Edit list below based upon requirements retained in this Section.

Project information.

Work covered by Contract Documents.

Access to site.

Coordination with occupants.

Work restrictions.

Specification and drawing conventions.

PROJECT INFORMATION

Facility Owner Information:

Owner's name auto-fills from the information in Sales Force / MyOLI; it may be overwritten when a different name is required.

Owner Name: Melvindale Northern Allen Park Schools.

Retain and edit paragraph and subparagraphs below if an Architect, Owner's Consultant or Tremco Roofing Advisor will serve as contact point for bidders and for Contractor. Tremco personnel are not “consultants” and shall not be named as such, in this Paragraph, except as described for WTI/WTC in a limited capacity. For a licensed Professional Engineer, WTI/WTC, or an independent Roof Consultant select "Owner's Consultant." For a Tremco Rep (not WTI/WTC) select "Roofing Advisor."

Roofing Advisor:

Select the appropriate type option and insert the contact person's name, title, company and contact information, as applicable.

Roofing System Manufacturer's Representative: Luke Idoni; Field Advisor;;(810) 280-5194; Lidoni@tremcoinc.com.

Edit the following paragraph to designate who is responsible for addressing questions. Designate different types of questions to different designees, use the following paragraph in conjunction with the first subparagraph. If directing "all" questions to one designee, delete the first subparagraph below.

Direct all questions to Roofing Advisor.

Where individual specification sections refer to Owner, Owner may elect to delegate submittal and response responsibilities to Roofing Advisor.

Facility Information:

Building Name: Rogers Early Elementary School.

Building Location: 5000 Shenandoah Ave, Allen Park. MI 48101.

Project Information:

Project name auto-fills from the information in Sales Force; it may be overwritten when a different name is required.

Project Name: Rogers Early Elementary School Roofing Replacement.

WORK COVERED BY CONTRACT DOCUMENTS

Roof Area numbers/designations must match drawings. You may group multiple roof areas/sections under a single listing provided that each roof area/section follows the same general scope of work as described herein and in the referenced section(s). For example: "Roof Areas 1, 3, 4, 7 and 8" or "Classroom wings." This template provides 3 groupings for providing general work descriptions; additional description may be added using in-line editing features.

The Work of Project is defined by the Contract Documents and consists of the following:

Roof Area(s) / Section(s): 1, 2, and 3.

Insert the total area of THIS/THESE roof(s) in sq. ft. and/or m2 1 sq. ft. = 0.0929 sq. m. If description includes multiple roof areas, list the total of all roof applicable/identified areas. Insert area AND select either sq. ft. OR sq. m. If both IP and SI measurements are required use in-line editing to revise. Delete this for WTI/WTC GC/CM projects.

Total Area of Roof(s): 24,545 sq. ft.

Insert slope of THIS roof. Use Slope of "Existing Roof" for restorations. (1/8 in./ft. = 1:96; 1/4 in./ft. = 1/48; 1/2 in./ft. = 1:24; 1 in./ft. = 1:12) For IP measurement insert slope in inches AND include either "inch per 12 inches" OR "inches per ft" option For SI measurement insert ratio such as 1:XX and delete both the inches and ft options. When both IP and SI measurements are required use in-line editing to revise.

Slope of Existing Roof: 1/4 inch per 12 inches.

Retain and edit following subparagraphs below to describe work applicable to this roof area.

The Work of the Project includes:

Re-roofing preparation specified in Division 07 Section "Preparation for Re-Roofing."

Replacement roofing specified in Division 07 Section 075113.11 - Built-Up Asphalt Roofing, Hot-Applied.

Type of Contract:

Project will be constructed under a single prime contract.

ACCESS TO SITE

Use of Site, Limited: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

Use of Site: Limit use of Project site to work in areas indicated and as directed by Owner. Do not disturb portions of Project site beyond areas in which the Work is indicated, including designated lay-down areas.

Driveways, Walkways and Entrances: Keep driveways, facility loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

Schedule deliveries to minimize use of driveways and entrances by construction operations.

Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

Retain "Condition of Existing Building" Paragraph below if the Work involves existing occupied building.

Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

COORDINATION WITH OCCUPANTS

Owner Occupancy: Owner will occupy site including existing and adjacent building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.

Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.

Notify Owner not less than 72 hours in advance of activities that will affect Owner's operations.

WORK RESTRICTIONS

Work Restrictions, General: Comply with restrictions on construction operations.

Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

When no other times are provided, select the default hours of 7:00 a.m. - 5:00 p.m. and "As authorized by Owner."

On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, unless otherwise indicated or approved by Owner.

The following subparagraphs are optional.

Weekend Hours: As authorized by Owner.

Early Morning Hours: As authorized by Owner.

Hours for Utility or Services Shutdowns: As authorized by Owner.

Hours for noisy or disruptive activity: As authorized by Owner.

Retain "Existing Utility Interruptions" Paragraph below for existing utilities. Coordinate with requirements for temporary utilities specified in Section 015000 "Temporary Facilities and Controls."

Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

Notify Owner not less than two days in advance of proposed utility interruptions.

Obtain Owner's written permission before proceeding with utility interruptions.

Retain "Noise, Vibration, and Odors" Paragraph below for work in or near occupied facilities.

Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.

Notify Owner not less than two days in advance of proposed disruptive operations.

Obtain Owner's written permission before proceeding with disruptive operations.

Retain paragraph below and select bracketed option to correspond to Owner's requirements regarding smoking. Delete paragraph if Owner has no restrictions.

Nonsmoking Project: Use of tobacco products on the Project site is not permitted.

Controlled Substances: Use of other controlled substances on the Project site is not permitted.

Retain and edit one or both of the following two paragraphs as applicable. Delete if not applicable Employee Identification: Provideidentification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.

Employee Screening: Comply with Owner's requirements for drug and background screening of Contractor personnel working on Project site.

Maintain list of approved screened personnel with Owner's representative.

SPECIFICATION AND DRAWING CONVENTIONS

Do not delete or modify the following Article.

Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

Specification requirements are to be performed by Contractor unless specifically stated otherwise.

Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings.

PRODUCTS (Not Used) EXECUTION (Not Used)

Melvindale Schools
Date of Issue (08/10/2026)

Rogers Early Elementary School

Rogers Early Elementary School Roofing Replacement

END OF SECTION 011000

011000 - Page 4 of 4

SUMMARY

This pre-edited TremSpec section specifies administrative requirements for Unit Price work. Coordinate scheduled unit prices with Document 004322 Unit Prices Form. Sample unit prices included in the schedule at the end of this section are coordinated with the Bid Form.

This Section and other Division 01 Sections is intended for use when an Architect is NOT involved in the design and specification of the Work of the Project. This Section may be used in careful coordination with the Owner's Architect (or Engineer, or Roof Consultant) when applicable; or defer to Architect to provide Division 01 Sections.

SECTION 012200 - UNIT PRICES

GENERAL

SUMMARY

Section includes administrative and procedural requirements for unit prices.

Related Requirements:

DEFINITIONS

Definition in this article expands that contained in AIA Document A701 and revises the definition for the Contract.

Unit price is an amount incorporated in the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased.

PROCEDURES

Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.

Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.

Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.

List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.

PRODUCTS (Not Used)

EXECUTION

SCHEDULE OF UNIT PRICES

The sample schedule of unit prices in this article illustrates several types of common occurrences where unit prices allow indeterminate work elements to be bid under lump-sum contracts. Revise paragraphs below to suit Project and coordinate numbering. Add to, or replace IP measurements with SI measurements when required.

Unit Price No. 1: Deck material replacement:

Description: Remove existing deck material and replace with new material according to Division 07 Section "Preparation for Re-roofing".

Unit of Measurement: 1 sq. ft.

Unit Price No. 5: Existing wood nailer replacement Description: Provide new pressure-treated wood nailers according to Division 06 Section "Miscellaneous Rough Carpentry."

Unit of Measurement: 1 lineal ft of 2x4-inch lumber.

Melvindale Schools
Date of Issue (08/10/2026)

Rogers Early Elementary School

Rogers Early Elementary School Roofing Replacement

END OF SECTION 012200

012200 - Page 2 of 2

UNIT PRICES

SECTION 070150.19 - PREPARATION FOR RE-ROOFING

This pre-edited MasterSpec section specifies preparation for re-roofing and rehabilitation projects, including full and partial tear-off of existing roofing, patching and reinforcing existing roofing, and uplift securement. This Section is intended to take the place of Section 024116 "Selective Demolition" for re-roofing work. Included are options for salvaging and recycling of demolition and construction waste and management of refrigerant that are compatible with but not necessarily limited to compliance with sustainable design requirements.

To view non-printing Editor's Notes (in Word.doc) that provide guidance for editing, change setting in Word to View Hidden Text and Print Hidden Text. This is a global setting in Word. View and manually delete all editor’s notes from Word.doc specification sections before issuing a Word.doc outside for Tremco.

GENERAL

SUMMARY

Section Includes:

Revise list below to suit Project.

Roof replacement preparation consisting of full roof tear-off of roof system at designated roof areas.

Removal of flashings and counterflashings.

Temporary roofing.

Temporary roof drainage.

Removal and reinstallation of indicated components, accessories, and equipment.

Edit "Related Information" Paragraph below as required to coordinate work specified in several sections. Only list sections that are actually included in the Project Manual and available to the Contractor.

Related Information:

Division 01 Section "Summary" for use of the premises and phasing requirements, and for restrictions on use of the premises due to Owner or tenant occupancy.

Division 07 Section "Sheet Metal Flashing and Trim" for formed metal roof flashings and counterflashings.

DESCRIPTION OF WORK

Coordinate Roof Area names/numbers with those indicated on roof drawing. Use in-line editing to revise as necessary. Add additional paragraphs and subparagraphs as necessary.

Re-roofing preparation Work consists of the following:

Preparation for Roof replacement:

Roof Area(s): 1, 2, and 3.

Existing Roof Type: Aggregate BUR.

Existing Deck Type: Gypsum deck.

Roof tear-off.

Salvaging of non-hazardous demolition and construction waste.

Roof ply reinforcement.

Uplift securement.

Removal of base flashings.

Temporary roof membrane.

MATERIALS OWNERSHIP

Insert subparagraphs as needed to list items to be salvaged and delivered to the Owner and/or to be salvaged by the Contractor for subsequent sale or use on another facility. Such items may be identified on drawings if not listed in this section.

Except for items or materials indicated to be reused, reinstalled, or otherwise indicated to remain Owner's property, demolished materials shall become Contractor's property and shall be removed from Project site.

DEFINITIONS

Roofing Terminology: Refer to ASTM D1079 "Standard Terminology Relating to Roofing and Waterproofing" and applicable edition of NRCA's "The NRCA Roofing Manual: Membrane Roof Systems" and NRCA’s Glossary for definition of terms related to roofing work in this Section.

Edit list to retain applicable definitions of the Work required.

Existing Roofing System: Roofing system identified above, including roof covering/membrane, roof insulation, surfacing, and components and accessories between deck and roof covering/membrane.

Full Roof Tear-Off: Removal of existing membrane roofing system from deck.

Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and reinstalled.

Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.

Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations.

Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.

PREINSTALLATION MEETINGS

Retain "Preliminary Roofing Conference" Paragraph below for all reroofing projects.

Preliminary Roofing Conference: Before starting removal Work, conduct conference at Project site.

Coordinate with roofing preinstallation meetings specified in Division 07 roofing section(s).

Review methods and procedures related to roofing tear-off, including, but not limited to, the following:

Edit the list below to suit Project conditions.

Reroofing preparation, including roofing system manufacturer's written instructions.

Temporary protection requirements for existing roofing system components that are to remain.

Existing roof drains and roof drainage during each stage of reroofing, and roof-drain plugging and plug removal.

Construction schedule and availability of materials, Installer's personnel, equipment, and facilities needed to avoid delays.

Existing roof deck conditions and other conditions requiring Owner notification.

Existing roof deck removal procedures and Owner notifications.

Condition and acceptance of existing roof deck and base flashing substrate for reuse.

Structural loading limitations of roof deck during reroofing.

Base flashings, special roofing details, drainage, penetrations, equipment curbs, and condition of other construction that affect reroofing.

HVAC shutdown and sealing of air intakes.

Shutdown of fire-suppression, -protection, and -alarm and -detection systems.

Governing regulations and requirements for insurance and certificates if applicable.

ACTION SUBMITTALS

Action submittals are submittals requiring responsive action and return of reviewed documents to Contractor.

Product Data: For each type of product indicated.

INFORMATIONAL SUBMITTALS

Digital Images or Videos: Show existing conditions of adjoining construction and site improvements, including exterior and interior finish surfaces, which might be misconstrued as having been damaged by reroofing operations. Submit before Work begins.

"Schedule of Re-Roofing Preparation Activities" Paragraph below may be used to track Contractor's progress; it may also be used to determine that work will not interfere with Owner's operations.

Schedule of Re-Roofing Preparation Activities: Indicate the following:

Detailed sequence of re-roofing preparation work, with starting and ending dates for each activity. Ensure occupants' on-site operations are uninterrupted.

Interruption of utility services. Indicate how long utility services will be interrupted.

Coordination for shutoff, capping, and continuation of utility services.

Use of elevator and stairs.

Coordination of Owner's continuing occupancy of portions of existing building.

Landfill records may be required by Owner when discarded roofing materials contain hazardous wastes.

Landfill Records: Indicate receipt and acceptance of hazardous wastes, such as asbestos-containing material, by a landfill facility licensed to accept hazardous wastes.

QUALITY ASSURANCE

Installer Qualifications: Installer of new membrane roofing system.

Regulatory Requirements:

Comply with governing EPA notification regulations before beginning membrane roofing removal.

Comply with hauling and disposal regulations of authorities having jurisdiction.

PROJECT / FIELD CONDITIONS

Edit the following paragraph and subparagraphs as applicable.

Owner will occupy portions of building immediately below reroofing area.

Conduct reroofing so Owner's operations will not be disrupted.

Provide Owner with not less than 72 hours' written notice of activities that may affect Owner's operations.

Coordinate work activities daily with Owner so Owner can place protective dust or water leakage covers over sensitive equipment or furnishings, shut down HVAC and fire-alarm or -detection equipment if needed, and evacuate occupants from below the work area.

Retain subparagraph below if known impaired deck areas or if special protection is not provided below the work area.

Before working over structurally impaired areas of deck, notify Owner to evacuate occupants from below the affected area.

Verify that occupants below the work area have been evacuated before proceeding with work over the impaired deck area.

Protect building to be reroofed, adjacent buildings, walkways, site improvements, exterior plantings, and landscaping from damage or soiling from reroofing operations.

Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.

Retain paragraph below and revise to suit Project.

Conditions existing at time of inspection for bidding will be maintained by Owner as far as practical.

Retain first paragraph below if limiting construction loads on existing roof deck and building structure. Revise to suit Project.

Limit construction loads on roof to rooftop equipment wheel loads and uniformly distributed loads not exceeding recommendations of Contractor's professional engineer based upon site inspection and analysis.

Weather Limitations: Proceed with reroofing preparation only when existing and forecasted weather conditions permit Work to proceed without water entering existing roofing system or building.

Remove only as much roofing in one day as can be made watertight in the same day.

Daily Protection: Coordinate installation of roofing so insulation and other components of roofing system not permanently exposed are not subjected to precipitation or left uncovered at the end of the workday or when rain is forecast.

Retain one of two "Hazardous Materials" paragraphs below or delete both if certain that no hazardous materials (asbestos-containing materials) will be encountered during reroofing.

Hazardous Materials: It is not expected that hazardous materials such as asbestos-containing materials will be encountered in the Work.

Use this subparagraph and one of the sub-subparagraphs when there is a chance that asbestos might be encountered, but is not expected.

If materials suspected of containing hazardous materials are encountered, do not disturb; immediately notify Owner.

Use the first subparagraph when Owner will arrange for discovered asbestos containing material (ACM) to be removed under a separate contract. Use the second subparagraph when the Contractor will be required to remove ACM (by adjustment to the contract sum). Retain requirements elsewhere in this Section for Contractor to be licensed accordingly, and for legal disposal of ACM.

Hazardous materials will be removed by Owner under a separate contract.

Obtain direction from Owner before proceeding with work in the affected area.

PRODUCTS

TEMPORARY PROTECTION MATERIALS

Retain this article if temporary protection materials are required for roof areas that are to remain.

EPS Insulation: Molded (expanded) polystyrene, ASTM C578.

Plywood: NIST DOC PS 1, Grade CD, Exposure 1.

Oriented Strand Board (OSB): NIST DOC PS 2, Exposure 1.

This Article includes materials for repairing or replacing common deck types. Retain and edit this article to suit project conditions. The components listed in this Section are suitable for incidental deck repair/replacement; delete the referenced Section option. If extensive deck repair or replacement is anticipated, include and refer to the indicated Sections and delete the subparagraphs.

DECK REPAIR/REPLACEMENT MATERIALS

Gypsum deck may be replaced with metal deck and insulation infill or with gypsum deck materials listed in subparagraphs.

Gypsum Deck Repair Materials: Replace deteriorated gypsum deck with metal deck.

ROOFING INFILL, PATCHING AND REPLACEMENT MATERIALS

General: Use roofing infill materials matching existing membrane roofing system materials unless otherwise indicated.

The following subparagraphs are optional. Select one of the following subparagraphs or delete both.

Roof patches MUST meet external fire and wind uplift requirements, whenever the infill materials used differ from the existing roofing system components Use materials specified in Division 07 roofing, unless otherwise indicated.

Retain the following three paragraphs as applicable to project. Include and edit referenced sections in the Project Manual.

Wood Blocking, Curbs, Cants and Nailers:

Reuse existing wood components that exhibit no signs of deterioration or other conditions detrimental to securement of new roofing system in conformance with specified requirements.

TEMPORARY ROOFING MATERIALS

Design and selection of materials for temporary roofing are responsibilities of Contractor.

TEMPORARY ROOF DRAINAGE

Design and selection of materials for temporary roof drainage are responsibilities of the Contractor.

AUXILIARY RE-ROOFING MATERIALS

General: Auxiliary reroofing preparation materials recommended by roofing system manufacturer for intended use and compatible with components of new membrane roofing system.

Fasteners: Factory-coated steel fasteners with metal or plastic plates listed in FM Approvals' RoofNav, and acceptable to new roofing system manufacturer.

Include referenced section in Project Manual.

Metal Flashing Sheet: Metal flashing sheet is specified in Division 07 Section "Sheet Metal Flashing and Trim."

EXECUTION

PREPARATION, GENERAL

Retain and edit applicable paragraphs from examples below.

Protection of In-Place Conditions: Protect existing roofing system that is indicated not to be reroofed.

Retain first subparagraph below if portions of roof area are to remain unaltered. Typically, retain if reroofing work is carried out on or above existing roof that is to remain and there is a possibility of items falling on roof below.

Protect existing roofing system that is indicated not to be reroofed.

Retain first subparagraph below, which is an example only, if prescribing materials to be used as protection. Delete or revise to suit Project. If existing membrane roofing system that is to remain is under warranty, revise to add warrantor's protection requirements.

Loosely lay 1 inch (25 mm) minimum thick, molded expanded polystyrene (EPS) insulation over the roofing membrane in areas indicated.

Loosely lay 15/32-inch (12-mm) plywood or OSB panels over EPS. Extend EPS past edges of plywood or OSB panels a minimum of 1 inch (25 mm).

Limit traffic and material storage to areas of existing roofing membrane that have been protected.

Maintain temporary protection and leave in place until replacement roofing has been completed. Remove temporary protection on completion of reroofing.

Retain the following when work involves protection of existing roofs that are under warranty.

Comply with requirements of existing roof system manufacturer's warranty requirements.

Seal or isolate windows that may be exposed to airborne substances created in removal of existing materials.

Shut off rooftop utilities and service piping before beginning the Work.

Select all that apply. This is primarily intended for roof drains.

Test existing roof drains to verify that they are not blocked or restricted.

Immediately notify Owner of any blockages or restrictions.

Depending on duration of equipment shutdown and occupancy of building, revise first paragraph below if necessary to specify special work hours (for example, nights or weekends) for portions of roof near air intakes. If necessary to deactivate all or a portion of fire-detection system, revise paragraph to add special measures, such as a fire watch.

Coordinate with Owner to shut down air-intake equipment in the vicinity of the Work.

Cover air-intake louvers before proceeding with reroofing work that could affect indoor air quality or activate smoke detectors in the ductwork.

Pollution Control: Comply with environmental regulations of authorities having jurisdiction. Limit spread of dust and debris.

Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

Remove debris from building roof by chute, hoist, or other device that will convey debris to grade level.

Temporary Weather Protection: During removal operations, have sufficient and suitable materials on-site to facilitate rapid installation of temporary protection in the event of unexpected rain.

Roof Drainage Protection: Maintain roof drainage in functioning condition to ensure roof drainage at end of each workday.

Prevent debris from entering or blocking roof drainage and conductors.

Use plugs specifically designed for this purpose.

Remove plugs at end of each workday, when no work is taking place, or when rain is forecast.

If roof drainage components are temporarily blocked or unserviceable due to roofing system removal or partial installation of new membrane roofing system, provide alternative drainage method to remove water and eliminate ponding.

Do not permit water to enter into or under existing membrane roofing system components that are to remain.

ROOF TEAR-OFF

Retain and edit applicable paragraphs from below.

Retain option in first paragraph below if Owner intends to authorize each day's work. Specify restrictions or limitations that will be placed on Installer to limit unscheduled delays.

Notify Owner each day of extent of roof tear-off proposed for that day.

Lower removed roofing materials to ground and onto lower roof levels, using dust-tight chutes or other acceptable means of removing materials from roof areas.

GRAVEL-SURFACED BUR/MB ROOFS ONLY.

Remove loose aggregate from aggregate-surfaced built-up bituminous roofing using a dry vacuum.

Remove walkways, pavers and accessories from roofing membrane.

Roof Drainage: Remove roof drainage items indicated for removal.

Remove Flashings: Remove roof flashings indicated for removal.

Edit the following to suit project conditions.

Remove base flashings and counter flashings.

Remove perimeter edge flashings and gravel stops.

Remove copings.

Remove expansion-joint covers.

Remove flashings at pipes, curbs, mechanical equipment, and other penetrations.

Full Roof Tear-Off: Remove existing roofing membrane and other membrane roofing system components down to the deck.

Remove roof insulation.

Remove fasteners from deck.

Edit the following to describe reuse or replacement of perimeter metal systems. Retain subparagraph and applicable option when replacing edge metals with new formed- or manufactured-systems.

Roof Edge Specialties: Replace existing perimeter metal systems with new perimeter metal systems.

New perimeter metal systems (fascia and coping) are specified in Division 07 Section "Sheet Metal Flashing and Trim."

Inspect wood blocking, curbs, and nailers for deterioration and damage.

Remove deteriorated or unsuitable wood blocking, curbs, and nailers.

Replace existing wood components that exhibit signs of deterioration or other conditions detrimental to securement of roofing system components, including roof edge flashings.

Reuse of Existing Wood Nailers: Permitted where type, size and securement are in accordance with ANSI/SPRI/FM 4435 ES-1; and existing wood nailers exhibit no signs of deterioration or other conditions detrimental to securement of new roofing system in conformance with specified requirements.

DECK PREPARATION

Retain this article for full roof tear-off or partial roof tear-off.

Inspect deck after tear-off of membrane roofing system.

Verify that deck is sound and dry.

If broken or loose fasteners that secure deck panels to one another or to structure are observed or if deck appears or feels inadequately attached, immediately notify Owner. Do not proceed with installation until directed by Owner.

Unsuitable Deck: If deck surface is not suitable for receiving new roofing or if structural integrity of deck is suspect, immediately notify Owner.

Do not proceed with installation until directed by Owner.

Retain and edit Deck Repair/Replacement Article when applicable and to suit project conditions. Coordinate carefully with Part 2 Material listing and/or referenced Sections.

DECK REPAIR/REPLACEMENT

Repair existing deck to provide smooth working surface for installation of roof system.

Replace deck that cannot be repaired to sound condition.

Gypsum Deck Replacement:

Sawcut and remove section of spalled or deteriorated gypsum deck.

Install gypsum deck repair materials, including formboard, mesh, bonding agent and gypsum in accordance with manufacturer's instructions.

Delete above paragraph and retain the following 3 paragraphs if using steel deck to replace defective gypsum deck.

Install new steel angles between Tees and weld in place.

Install new steel deck in accordance with SDI, Design Manual for Composite Decks, Form Decks, Roof Decks.

Provide roof insulation board in thickness required to match existing adjacent deck height.

EQUIPMENT REMOVAL AND REINSTALLATION

General: Remove, store, protect and reinstall rooftop equipment as required to accommodate roof tear-off and subsequent roofing work.

Raise roof curbs, equipment mountings and other roof penetration flashings as required to accommodate additional insulation thickness and maintain base flashing height of not less than 8 inches (200 mm), unless otherwise indicated.

Provide wood assemblies and additional support with miscellaneous galvanized steel angles, as required to rebuild or raise existing roof curbs.

Extend vent and soil stacks and other roof penetrations, using matching materials, as required to accommodate additional insulation thickness.

Extend existing ductwork inside existing roof curbs to accommodate extension of curb.

Use materials matching existing ductwork; minimum of 20 ga. (0.9 mm) galvanized duct with Pittsburgh folded seam slip joints-typical.

Rooftop Equipment, Electrical: Engage a qualified electrician to perform electrical disconnection and reconnection.

Disconnect, reroute, extend and reconnect existing power feeders and control circuits (conduit and wiring) feeding the existing roof mounted equipment which is indicated to be raised and/or relocated to a new elevation/location and as required by the Contract.

Provide weatherproof exterior junction boxes, when required.

Make connections to mechanical equipment by using a maximum 18-inch (450 mm) length of liquid-tight flexible steel conduit.

Rigid connections to mechanical equipment are not permitted.

Relocate and reconnect existing disconnect switches presently installed on existing roof mounted equipment indicated to be raised and/or relocated.

Reinstall designated equipment.

Make electrical reconnections in accordance with applicable code and authorities having jurisdiction.

Recharge HVAC equipment with refrigerant required by equipment manufacturer.

Coordinate with Owner to test equipment and verify proper operation.

TEMPORARY ROOFING MEMBRANE

Delete this article if not required.

Install approved temporary roofing membrane over area to be reroofed.

Remove temporary roofing membrane before installing new roofing membrane.

BASE FLASHING REMOVAL

Remove existing base flashings around parapets, curbs, walls, and penetrations.

Clean substrates of contaminants, such as asphalt, sheet materials, dirt, and debris.

Do not damage metal counterflashings that are to remain.

Replace metal counterflashings damaged during removal with counterflashings specified in Division 07 Section "Sheet Metal Flashing and Trim."

DISPOSAL

Collect demolished materials and place in containers. Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.

Storage or sale of demolished items or materials on-site is not permitted.

Transport and legally dispose of demolished materials off Owner's property.

CLEANING

Clean adjacent structures and improvements of dust, dirt, and debris caused by preparation for re-roofing operations. Return adjacent areas to condition existing before operations began.

Melvindale Schools
Date of Issue (08/10/2026)

Rogers Early Elementary School

Rogers Early Elementary School Roofing Replacement

END OF SECTION 070150.19

070150.19 - Page 10 of 10

PREPARATION FOR RE-ROOFING

SECTION 075113.11 - BUILT-UP ASPHALT ROOFING, HOT-APPLIED

This Tremco MasterSpec-based section specifies Tremco THERMastic hot-applied built-up asphalt and hybrid built-up roof (BUR) systems, consisting of multiple plies set in hot asphalt adhesive, with roofing accessories including membrane flashings, substrate board, vapor/air barrier, insulation, cover board, fasteners, and granular, aggregate or smooth-coating surfaces.

The companion Sections 076200 "Sheet Metal Flashing and Trim", 077100 "Roofing Specialties", and 077129 "Manufactured Roof Expansion Joints" specify the low-slope metal flashings and custom or manufactured roof edge, copings and certain roof drainage items that together with the work of this section form the total roof system. Warranty requirements for this Section cross-reference these sections.

Roofing Installer's Warranty Form is now Section 070101.01 MEMBRANE ROOFING INSTALLER'S WARRANTY. Be sure to include this document in your project when required.

To view non-printing Editor's Notes (in Word.doc) that provide guidance for editing, change setting in Word to View Hidden Text and Print Hidden Text. This is a global setting in Word. View and manually delete all editor’s notes from Word.doc specification sections before issuing a Word.doc outside for Tremco.

GENERAL

SUMMARY

Section Includes:

A BUR system utilizes asphalt-fiberglass plies (felts). A Hybrid BUR system utilizes SBS MB sheets in the roof membrane such as BURmastic Composite Ply and POWERply sheets.

Adjust list below to correspond to roof system products selected in Part 2 and assembly described in Part 3.

Hot-applied three-ply built-up asphalt roofing system on gypsum deck, including but not limited to:

Base Sheet (Anchor Sheet) is on the deck, under the insulation. Base-Ply Sheet is the first ply in the roof membrane. Retain below if applying base sheet (anchor sheet) BENEATH roof insulation. A base sheet (anchor sheet) may also be used in conjunction with a vapor retarder.

Base sheet (Anchor sheet).

Roof insulation.

Roof insulation cover board.

Include base-ply only if using a sheet that is different from the ply sheet(s), such as an MB sheet for a hybrid system (a base-ply sheet is a single sheet).

Roof membrane base-ply sheet.

Roof membrane ply sheet(s).

Roofing membrane cap sheet.

Base flashings.

Stone aggregate, ceramic granules and certain acrylic coatings require an adhesive surfacer.

Roof surfacing consisting of stone aggregate.

Walkway material.

Retain optional "Related Sections" paragraph below as required to coordinate work specified in several sections. Only list sections that are actually included in the Project Manual and available to the Contractor.

Related Sections:

Division 07 Section "Preparation for Re-Roofing" for removal of existing roofing; inspection, repair and replacement of existing deck/substrate, if required to receive new roofing.

Division 07 Section "Sheet Metal Flashing and Trim" for shop- formed sheet metal items including roof drainage system items, roof penetration flashings, roof drainage systems, counterflashings and reglets.

Division 07 Section "Manufactured Roof Expansion Joints" for premanufactured roof expansion-joint assemblies.

DEFINITIONS

Roofing Terminology: Refer to ASTM D1079 "Standard Terminology Relating to Roofing and Waterproofing" and NRCA's Glossary for definition of terms related to roofing work in this Section.

Retain paragraph below if using traditional roofing asphalt complying with ASTM D312/D312M; delete if only SEBS-modified roofing asphalt complying with ASTM D6152/D6152M is required.

Hot Roofing Asphalt: Roofing asphalt heated to its equiviscous temperature, the temperature at which its viscosity is 125 centipoise for mop-applied roofing asphalt and 75 centipoise for mechanical spreader-applied roofing asphalt, within a range of plus or minus 25 deg. F (14 deg. C), measured at the mop cart or mechanical spreader immediately before application.

PREINSTALLATION MEETINGS

Select design professional if applicable or delete both when a design professional is not involved. Owner's Consultant shall be a licensed Professional Engineer (P.E.), Registered Roof Consultant (RRO), or similar, under direct contract with the Owner for design and/or administration of the Project. Tremco persons are NOT Consultants.

Preinstallation Roofing Conference: Conduct conference at Project site.

Meet with Owner, Owner's insurer if applicable,, roofing Installer, roofing system manufacturer's representative, and installers whose work interfaces with or affects roofing, including installers of roof accessories and roof-mounted equipment.

Review drawings and specifications.

Review methods and procedures related to roofing installation, including manufacturer's written instructions.

Review and finalize construction schedule and verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays.

Examine substrate conditions and finishes for compliance with requirements, including flatness and fastening.

Review structural loading limitations of roof deck during and after roofing.

Review base flashings, special roofing details, roof drainage, roof penetrations, equipment curbs, and condition of other construction that will affect roofing system.

Review temporary protection requirements for roofing system during and after installation.

Review roof observation and repair procedures after roofing installation.

ACTION SUBMITTALS

Action submittals are submittals requiring responsive action and return of reviewed documents to Contractor.

Product Data: For each type of product indicated.

Shop Drawings: For roofing system. Include plans, elevations, sections, details, and attachments to other work.

Provide roof plan showing orientation and types of roof deck, orientation of membrane roofing, and fastening spacings and patterns for mechanically fastened components.

Base flashings and membrane terminations.

Indicate that details meet requirements of NRCA and FM required by this Section.

Retain one or more subparagraphs below if required for Project.

Layout and thickness of insulation.

Tapered insulation layout, including slopes.

Crickets, saddles, and tapered edge strips, including slopes.

Insulation fastening patterns for corner, perimeter, and field-of-roof locations.

Membrane securement, fastening or adhesion requirements.

INFORMATIONAL SUBMITTALS

Informational submittals are submittals that require review, but they do not require responsive action and return of reviewed documents to Contractor, provided submittals comply with requirements. If rejected, submittals with responsive action must be returned to Contractor.

Qualification Statements: For Installer.

Include letter from Manufacturer written for this Project indicating approval of Installer.

Contractor's Product Certificate: Submit signed certification, on company letterhead, indicating products intended for Work of this Section, including product names and numbers and manufacturers' names, with statement indicating that products to be provided meet the requirements of the Contract Documents.

RETAIN FOR ALL PROJECTS.

Manufacturer's Instructions: Submit copy of manufacturer's written installation instructions for specified roofing system.

CLOSEOUT SUBMITTALS

Maintenance Data: To include in maintenance manuals.

Warranties: Executed copies of warranties.

QUALITY ASSURANCE

Installer Qualifications: An employer of workers trained and certified by manufacturer, including a full-time on-site supervisor with a minimum of five years' experience installing products comparable to those specified, able to communicate verbally with Contractor,, and employees, and qualified by the roofing system manufacturer to install manufacturer's product and furnish warranty of type specified.

Manufacturer Qualifications: Approved manufacturer with roofing systems comparable to those specified for this Project, with minimum five years' experience in manufacture of comparable products in successful use in similar applications, and able to furnish warranty with provisions matching specified requirements.

Retain the following paragraph and subparagraphs for all projects that include Job Site Inspection provided and paid for by the Contractor:

- For Public Projects: Retain bracketed option and both subparagraphs and DO NOT EDIT OR ALTER IN ANY OTHER WAY.

- For Private Projects: Subparagraph 2. may be deleted, but is recommended to be retained as written.

Coordinate with Field Quality Control Article; if Owner engages Inspector, delete this Paragraph in its entirety.

Roofing Inspector Qualifications: A technical representative of manufacturer not engaged in the sale of products and experienced in the installation and maintenance of the specified roofing system, qualified to perform roofing observation and inspection specified in Field Quality Control Article, to determine Installer's compliance with the requirements of this Project, and approved by the manufacturer to issue warranty certification. The Roofing Inspector shall be one of the following:

An authorized full-time technical employee of the manufacturer.

An independent party certified as a Registered Roof Observer by the International Institute of Building Enclosure Consultants (formerly the Roof Consultants Institute) retained by the Contractor or the Manufacturer and approved by the Manufacturer.

Manufacturer's Installation Instructions: Obtain and maintain on-site access to manufacturer's written recommendations and instructions for installation of products.

DELIVERY, STORAGE, AND HANDLING

Deliver roofing materials to Project site in original containers with seals unbroken and labeled with manufacturer's name, product brand name and type, date of manufacture, approval or listing agency markings, and directions for storing and mixing with other components.

Store liquid materials in their original undamaged containers in a clean, dry, protected location and within the temperature range required by roofing manufacturer.

Protect stored liquid material from direct sunlight.

Discard and legally dispose of liquid material that cannot be applied within its stated shelf life.

Protect roof insulation materials from physical damage and from deterioration by sunlight, moisture, soiling, and other sources.

Store in a dry location.

Comply with insulation manufacturer's written instructions for handling, storing, and protecting during installation.

Handle and store roofing materials and place equipment in a manner to avoid permanent deflection of deck.

PROJECT / FIELD CONDITIONS

Retain, revise, or delete paragraphs and subparagraphs in this article to suit Project.

NOTE: The first two paragraphs below reinforce requirements that are included in Section 070150.19…