Project_Contract_Forms.pdf
PDF 401 KB Posted
- Solicitation number
- 25-ITB-078
- Issued by
- Glades County, Brownsville CDP, Florida
About this file
This document is a collection of standard project forms and administrative procedures issued by Flagler County, Florida for construction contracts and contract administration. The forms serve as required submissions for contractual and administrative compliance throughout the project lifecycle, from initial payment applications through final project closeout. The document outlines 12 standardized forms that contractors must complete and submit, including the Application and Certificate for Payment (PF-2), submitted monthly by the prime contractor for progress payments; the Continuation Sheet (PF-3) providing itemized breakdowns of monthly payments; the Agreement Amendment form (PF-4) for contract revisions; and various lien release and affidavit forms (PF-5 through PF-10) required during project closeout. Additionally, the forms include the Certificate of Substantial Completion (PF-11) and Certificate of Final Completion (PF-12), both prepared by the County Engineer to document project milestones. All forms must be completed in ink or typewritten with all blank spaces filled in and submitted to the Office of the County Engineer. These standardized forms constitute extensions of contractual conditions and general specification requirements for all Flagler County construction projects.
The forms establish critical payment and lien procedures for contract administration, requiring contractors to submit notarized affidavits certifying payment of all debts, claims, and supplier obligations as conditions for receiving progress and final payments. Contractors must provide partial releases of lien with each invoice beginning with the second progress payment application, and must furnish complete lien releases from all subcontractors and material suppliers as part of closeout documentation. The surety company must provide written consent to final payment in accordance with Florida Statutes Section 255.05(11). All forms reference compliance with Florida lien law (Florida Statutes Chapter 713) and require proper notarization and execution by authorized representatives. The forms do not specify funding sources, set-asides, or pricing terms, as they function as administrative templates applicable to multiple Flagler County construction projects, including the referenced Beach Nourishment Project - Reach II, which is funded through the Florida Department of Environmental Protection under Agreement No. 23FL2.
View the file
Other files
Show 40 more
Latest 50 of 90 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PF – 1 ( 1 of 1)
PROJECT FORMS
ARTICLE 1 - INSTRUCTIONS
1.1. The following forms and certificates are samples of those to be used by the Contractor for submissions for Contractual and administrative requirements.
1.2. Requirements and instructions on the forms constitute extensions of, or additions to, the Contractual conditions of the Contract and the general requirements of the specification.
1.3. Do not detach, or otherwise remove sample project forms from specifications.
1.4. Prepare all forms as required with all blank spaces filled in, in ink or typewritten.
1.5 Submit all Forms to the Office of the County Engineer
ARTICLE 2 - PROJECT FORM LISTING
Part 1: Standard Contract Administration Forms
Application and Certificate for Payment (PF – 2) (Prepared and submitted by prime contractor monthly for progress payment)
Continuation Sheet (PF – 3) (Prepared and submitted by prime contractor as itemized breakdown of monthly progress payment)
Agreement Amendment (PF – 4) (Prepared by Engineer for contract revision)
Contractor's Affidavit for Payment of Debts and Claims (PF – 5) (Prepared and submitted by prime contractor as part of project close-out documentation to be accompanied by separate release or waivers of lien from sub-contractors and material and equipment suppliers)
Contractor's Affidavit of Release of Liens (Final Release) (PF – 6) (Prepared and submitted by prime contractor as part of project close-out documentation)
Consent of Surety Company To Final Payment (PF – 7) (Prepared and submitted by prime contractor as part of project close-out documentation)
Partial Release of Lien (PF – 8) (Submitted monthly by prime contractor with each invoice beginning with the second progress payment application)
Conditional Final Release and Waiver of Lien (PF – 9) (Prepared and submitted by prime contractor as part of project close-out documentation)
Final Release of Lien (PF -10) (Prepared and submitted by prime contractor as part of project close-out documentation)
Certificate of Substantial Completion (PF – 11) (Prepared by Engineer)
Certificate of Final Completion (PF – 12) (Prepared by Engineer)
PAYMENT APPLICATION FORM
FLAGLER COUNTY APPLICATION FOR PAYMENT NO. ____________________
CONTRACTOR: _____________________________ ENGINEER: Flagler County Engineering Dept.
(Address:)
Bunnell, Florida 32110
ORIGINAL CONTRACT SUM $
NET REVISIONS $
CONTRACT SUM TO DATE $
TOTAL COMPLETE TO DATE $
Less: Retainage @ ____% $
EARNED LESS RETAINAGE $
PAYMENT FOR STORED MATERIALS $
TOTAL LESS RETAINAGE $
TOTAL REVISIONS LESS PREVIOUS PAYMENTS MADE $
NET REVISIONS: $______________________ AMOUNT DUE THIS APPLICATION $_______________________
CONTRACTOR:______________________________
BY:
SIGNED:
NOTARY PUBLIC:
DATE: ______________ MY COMMISSION EXPIRES: _______________
RECOMMENDED FOR ACCEPTANCE AND PAYMENT:
DATE: _______________ COUNTY ENGINEER:
CHANGE ORDER
No._____ Approval
DATE
Payment in the amount shown is due for work performed during the period of _________ thru ________, as detail on the attached Schedule of Payments. The present status of the Account for this Contract is :
Project Name & No.: __________________________________________________________________________________
The undersigned certifies that the Work covered by this Application for Payment has been completed in accordance with the Contract Documents and/or any Amendments thereto, that all amounts due Subcontractors and Suppliers for Work, for which previous Applications for Payment were issued and payment has been received from Flagler County, has been paid by him; that all Subcontractors and Suppliers have issued Releases of Lien and the current payment shown herein is now due.
1769 E. Moody Blvd. Bldg. 2
Subscribed & Sworn to before me this ____day of
PF - 2
ADDITION DEDUCTION
AMENDMENTS TO CONTRACT PAYMENT DUE THIS APPLICATION
APPLICATION FOR PAYMENT CONTINUATION FORM
FLAGLER COUNTY - CONTRACTOR'S APPLICATION FOR PAYMENT - SHEET ______ OF ______
PROJECT NAME: PROJ. NO.: SCHEDULE:
CONTRACTOR: COVERING PERIOD: THRU
APPLICATION No. DATE: BY: REVIEWED BY:
NO. PREVIOUS TOTAL THIS PERIOD TOTAL TO DATE PREVIOUS TOTAL THIS PERIOD TOTAL TO DATE
PF - 3
ITEM
DESCRIPTION
CONTRACT
QUANTITY UNIT UNIT
PRICE
QUANTITY INSTALLED & COMPLETE DOLLAR AMOUNT
PF-4
AMENDMENT TO AN AGREEMENT
BETWEEN FLAGLER COUNTY
AND
Contractor Name____________________________________________ Project Name_______________________________________________
County Project No. ________________________
Flagler County, Florida, a political subdivision (COUNTY) and (CONTRACTOR) hereby enter into this Amendment to the Agreement executed on .
WHEREAS, COUNTY AND CONTRACTOR have entered into an Agreement for on , .
WHEREAS, the PARTIES have entered into a Amendment on , for the purpose of:
1. The ending date for the AGREEMENT subsequent to this Amendment.
2. All Terms and Conditions of the original Contract and any subsequent amendments thereto shall remain unmodified and shall remain in full force and effect.
3. This Amendment must be accepted by the CONTRACTOR and Contract Surety and must be approved by the Flagler County Board of County Commissioners to become effective.
AMOUNT TIME
Original Contract Agreement........................ $ _____________
CHANGES BY PREVIOUS AMENDMENTS:
NO. DATE APPROVED
TOTAL CHANGES BY AMENDMENT NO. thru $
TOTAL CONTRACT prior to this Amendment (No. )........................$
TOTAL This Amendment..........................................................................$
NEW CONTRACT (All Amendments)...................................................... $
PF-4
ACCEPTANCE: (CONTRACTOR)
I (We) agree to perform the work required by this Amendment No.
________ for the amount and within the time allocated all in accordance with Contract Plans, Specifications and related Documents.
NAME:
WITNESS:
(Signature)
BY: DATE:
(Typed or Printed) (Signature)
WITNESS:
(Signature) (Typed/Printed Name & Title)
(Typed or Printed)
SURETY
I (We) have reviewed the foregoing Contract and Amendment and have adjusted the Contract Sureties to Conform with this Amendment.
SURETY:
BY: DATE:
(Typed/Printed Name & Title) (Agent-In-Fact Certification Attached)
RECOMMENDED: RECOMMENDED:
Flagler County Engineering Dept.
(Date) (Date)
(Typed/Printed Name & Title)
APPROVED AS TO FORM: APPROVED: FLAGLER COUNTY
Flagler County Legal Dept.
____________________________________ BY:
(Date) (Date)
PF - 5
CONTRACTOR’S OWNER
AFFIDAVIT OF ENGINEER
PAYMENT OF CONTRACTOR
DEBTS AND CLAIMS SURETY
OTHER
TO: (OWNER) : FLAGLER COUNTY PROJECT NO.: ______________________________
BOARD OF COUNTY COMMISSIONERS
CONTRACT FOR: _______________________________________________________________________________________________________________
CONTRACTOR (NAME, ADDRESS) CONTRACT DATE:_______________________________________
STATE OF: _________________________
COUNTY OF: _______________________
The undersigned, pursuant to the Standard Conditions of the Contract for Construction, hereby certifies that, except as listed below, he has paid in full or has otherwise satisfied all obligations for all materials and equipment furnished, for all work, labor, and services performed, and for all known indebtedness and claims against the Contractor for damages arising in any manner in connection with the performance of the Contract referenced above for which the Owner or his property might in any way be held responsible.
EXCEPTIONS: (If none, write “NONE”. If required by the Owner, the Contractor shall furnish bond satisfactory to the Owner for each exception).
SUPPORTING DOCUMENTS ATTACHED HERETO: CONTRACTOR:____________________________
1. Consent of Surety to Final Payment, Whenever Surety is involved
Consent of Surety is required. ADDRESS:_________________________________
Indicate attachments (YES___) (NO ____)
The following supporting documents should be attached hereto if required by the OWNER. BY: ______________________________________
1. Contractor’s Release or Waiver of Liens, conditional upon receipt of Final Payment. Subscribed and Sworn to before me this _____ Day of _________, 20__
2. Separate Release or Waivers of Leans from Sub-contractors and material and equipment suppliers to the extent required by the Owner, accomplished by a list thereof. NOTARY PUBLIC: ______________________
3. Contractor’s Affidavit of Release of Liens My Commission Expires:________________
PF - 6
CONTRACTOR’S OWNER
AFFIDAVIT OF ENGINEER
RELEASE OF LIENS CONTRACTOR
OTHER
TO: (OWNER) FLAGLER COUNTY PROJECT NO.: ______________________________
CONTRACT FOR: ________________________________________________________________________________________________
CONTRACTOR (NAME, ADDRESS) CONTRACT DATE:_______________________________________
The undersigned, pursuant to the Standard General Conditions of the Contract for Construction, hereby certifies that all Contractors, all Sub-contractors, all suppliers of material and equipment and all performers of work, labor or services who have or may have liens against any property of the Owner arising in any manner out of the performance of the Contact referenced above have been paid in full.
EXCEPTION: (If none, write “NONE”. If required by the Owner, the Contractor shall furnish bond satisfactory to the Owner for each exception).
SUPPORTING DOCUMENTS ATTACHED HERETO: CONTRACTOR: ___________________________
1. Contractor’s Release or Waiver of Liens, conditional upon receipt ADDRESS:_________________________________ of Final Payment. _________________________________
2. Separate Release or Waivers of Liens from Sub-contractors and equipment suppliers, to the extent required by the Owner, accompanied by a list thereof. BY: _______________________________________
Subscribed and Sworn to before me this ______Day of _____________, 20___
NOTARY PUBLIC:______________________________
My Commission Expires:___________________________
PF - 7
CONSENT OF OWNER
SURETY COMPANY ENGINEER
TO FINAL PAYMENT CONTRACTOR
OTHER
TO: (OWNER) PROJECT NO.: _____________________________________
FLAGLER COUNTY
CONTRACT FOR: __________________________________________________________________________________________
CONTRACTOR: (NAME, ADDRESS)
CONTRACT DATE:_______________________________________
Pursuant to § 255.05(11), Florida Statutes, and in accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the (Insert Name and Address of Surety Company)
SURETY COMPANY:
on Bond of (Insert Name and Address of Contractor)
CONTRACTOR:
hereby approves of the Final Payment to the Contractor, and agrees that Final Payment to the Contractor shall not relieve the Surety Company of any of its obligations to (Insert Name and Address of Owner).
OWNER:
Flagler County Board of County Commissioners, with an address of 1769 E. Moody Boulevard, Building 2, Bunnell, Florida 32110 as set for in the said Surety Company’s Bond.
IN WITNESS WHEREOF, the Surety Company has hereunto set its hand the _______Day of _______________________, _______.
SURETY COMPANY
ATTEST: ________________________________________________
(SEAL) SIGNATURE OF AUTHORIZED REPRESENTATIVE
TITLE
PF – 8
WAIVER AND RELEASE OF LIEN
UPON PROGRESS PAYMENT
“PARTIAL RELEASE OF LIEN”
The undersigned Lienor, in consideration of $____________________________________, ____________________________________hereby waives and releases its lien and right to
(COMPANY/CONTRACTOR)
claim a lien for labor, services, or materials furnished through ____________ to _____________
(DATE) (DATE)
to the Flagler County Board of County Commissioners on the job of
PROJECT NO. ________________________________
PROJECT NAME: ___________________________________________________________
to the following described property: _______________________________________________
(DESCRIPTION OF PROPERTY)
This waiver and release does not cover any retention or labor, services, or materials furnished after the date specified.
This Partial Release is furnished in accordance with 713.2(3), Florida Statutes.
DATED on _______________________, 20 ____
By:___________________________________ (Signature of Lienor)
(Printed Name & Title)
Lienor’s Name and Address: __________________________________________________
STATE OF FLORIDA
COUNTY OF ____________
Sworn to (or affirmed) and subscribed before me this ________ day of _____________, 20___ by ____________________________________.
SIGNATURE OF NOTARY PUBLIC
Print, Type or Stamp Commissioned Name
Personally Known ______________ OR Produced Identification _____________
Type of Identification Produced ___________________________________
PF – 9
CONDITIONAL FINAL RELEASE AND WAIVER OF LIEN
The undersigned Lienor, in consideration of $____________________________________, ____________________________________hereby waives and releases its lien and right to
(COMPANY/CONTRACTOR)
claim a lien for labor, services, or materials furnished through ____________ to _____________
(DATE) (DATE)
to the Flagler County Board of County Commissioners on the job of
PROJECT NO. _____________________________
PROJECT NAME: ___________________________________________________________
to the following described property: _______________________________________________
(Description of Property)
This undersigned certifies that all labor, services, and/or materials described herein have been provided to the execution and delivery of this document.
The Conditional Final Release and Lien Waiver is conditioned upon the undersigned receiving $____________________ for the work described in this Release and Waiver.
The Conditional Final Release is furnished in accordance with 713.20, Florida Statutes.
DATED on ________, _______________, 20 ____
By:____________________________________________
(Printed Name & Title) Lienor’s Name and Address: ______________________________________________________
STATE OF FLORIDA
COUNTY OF ____________
Print, Type or Stamp Commissioned Name
Personally Known ______________ OR Produced Identification ___________________
PF – 10
WAIVER AND RELEASE OF LIEN
UPON FINAL PAYMENT
The undersigned lienor, in consideration of the final payment in the amount of $________________________, hereby waives and releases its lien and right to claim a lien for labor, services, or materials furnished to the Flagler County Board of County Commissioners on the job of
PROJECT NO.:_____________________
PROJECT NAME: ____________________________________________________________
to the following described property: _______________________________________________
(Description of Property)
This Final Release is furnished in accordance with 713.2(5), Florida Statutes.
DATED on ________, _______________, 20 ____
By:___________________________________
(Printed Name & Title)
Lienor’s Name and Address: _____________________________________________
STATE OF FLORIDA
COUNTY OF ____________
Print, Type or Stamp Commissioned Name
Personally Known ______________ OR Produced Identification ______________
PF – 11 (1 of 2)
CERTIFICATE OF SUBSTANTIAL COMPLETION
PROJECT: ___________________________________________________________________
CONTRACT DATE:______________________________________
COUNTY PROJECT NO.: ________________________
This Certificate of Substantial Completion applies to:
_____ All work under Contract _____ Portion of work described as follows:
The Work to which this Certificate applies has been inspected by authorized representatives identified below and that Work is hereby declared to be substantially complete in accordance with the Contract Documents on:______________________
(DATE)
A tentative list of items to be completed or corrected is attached hereto. This list may not be all-inclusive, and the failure to include an item in it does not alter the responsibility of Contractor to complete all the Work in accordance with the Contract Documents. The items in the tentative list shall be completed or corrected by the Contractor.
SIGNED:
CONTRACTOR: ____________________________________________________________
By: __________________________________________ Date:______________________________________
FLAGLER COUNTY CONSTRUCTION ENGINEERING & INSPECTION (CEI)
(CEI FIRM)_________________________________________________________________
FLAGLER COUNTY PROJECT MANAGER
OTHER____________________________________________________________________
PF – 11 (2 of 2)
TENTATIVE LIST OF ITEMS TO BE COMPLETED OR CORRECTED
(PUNCH LIST)
PROJECT: ________________________________________ DATE:___________________
COUNTY PROJECT NO.: ___________________________________
CONTRACTOR: ______________________________________________________
This list may not be all-inclusive, and the failure to include an item does not alter the responsibility of the Contractor to complete all the Work in accordance with the Contract Documents.
ITEM NO. DESCRIPTION
PF - 12
CERTIFICATE OF FINAL COMPLETION
PROJECT: _______________________________________________________________
CONTRACT DATE:_____________
COUNTY PROJECT NO.: ____________________________
This Certificate of Final Completion applies to:
_____ All work under Contract _____ Portion of work described as follows:
The Work to which this Certificate applies has been inspected by authorized representatives identified below and that Work is hereby declared to be complete in accordance with the Contract Documents on:________________________________
(DATE)
The tentative list (punch list) of items to be completed or corrected provided with the Certificate of Substantial Completion has been addressed. Failure to have included an item in the does not alter the responsibility of Contractor to complete all the Work in accordance with the Contract Documents.
The date of Final Completion is the date upon which all guarantees and warranties begin.
FINAL COMPLETION DATE:________________________________________
SIGNED:
CONTRACTOR: ____________________________________________________________
FLAGLER COUNTY CONSTRUCTION ENGINEERING & INSPECTION
REPRESENTATIVE: _______________________________________________
FLAGLER COUNTY PROJECT MANAGER
| PF-1_Project_Forms |
| PF-2_Application_Pay_Form |
| Sheet1 |
| PF-3_Application_For_Payment_Continuation_Form |
| Sheet1 |
| PF-4_Amendment_Form |
| PF-5_Contractor_AFF_Payment_Debts_and_Claims |
| CONTRACTOR’S OWNER |
| TO: (OWNER) : FLAGLER COUNTY PROJECT NO.: ______________________________ |
| PF-6_Contractor_AFF_Release_of_Liens |
| CONTRACTOR’S OWNER |
| AFFIDAVIT OF ENGINEER |
| TO: (OWNER) FLAGLER COUNTY PROJECT NO.: ______________________________ |
| PF-7_Consent_Surety_Final_Payment |
| CONSENT OF OWNER |
| SURETY COMPANY ENGINEER |
| TO: (OWNER) PROJECT NO.: _____________________________________ |
| PF-8_Partial_Release_Form |
| Lienor’s Name and Address: __________________________________________________ |
| STATE OF FLORIDA |
| Print, Type or Stamp Commissioned Name |
| PF-9_Conditional_Final_Release_Waiver_Form |
| Lienor’s Name and Address: ______________________________________________________ |
| ______________________________________________________ |
| ______________________________________________________ |
| STATE OF FLORIDA |
| Print, Type or Stamp Commissioned Name |
| PF-10_Final_Release_Form |
| Lienor’s Name and Address: _____________________________________________ |
| STATE OF FLORIDA |
| Print, Type or Stamp Commissioned Name |
| PF-11_Substantial_Completion_Certificate |
| PF-12_Final_Completion_Certificate |
File details come from the government source that posted it. Updated .