Attachment_23_Flagler_County_Physical_Monitoring_Plan_2025-01-13.pdf

PDF 82 KB Posted

Attached to
Flagler County Beach Nourishment Project - Reach II FPN 429573-1-38-01
Solicitation number
25-ITB-078
Issued by
Glades County, Brownsville CDP, Florida

About this file

This is a Physical Monitoring Plan document prepared by Foth and Olsen for the Flagler County Beach and Dune Restoration Project: Reach 2, coordinated with the Florida Department of Environmental Protection (FDEP) Joint Coastal Permit 0379716-001-JC and the U.S. Army Corps of Engineers (USACE) DA Permit SAJ-2019-02065. The plan establishes comprehensive physical monitoring protocols to evaluate project performance, assess impacts to adjacent shorelines, and determine future renourishment needs throughout the design life of the restoration project. Monitoring activities include topographic and bathymetric profile surveys of the beach and offshore areas extending approximately 3,000 feet along the adjacent shoreline north and south of the project area and a minimum of 3,000 feet offshore; borrow area bathymetric surveys conducted on single-beam or multibeam collection with grid lines spaced no more than 500 feet apart; sand sampling and laboratory analysis following project completion; controlled digital color aerial orthophotography acquired from public or commercial sources; and engineering monitoring reports submitted to FDEP within 90 days of survey completion. The monitoring schedule commences with pre-construction surveys completed within 90 days prior to construction and post-construction surveys completed within 60 days following project completion, with subsequent biennial monitoring continuing until the next nourishment event or expiration of the design life.

The monitoring plan incorporates technical specifications and standards established in the FDEP Monitoring Standards for Beach Erosion Control Projects dated October 2014. Engineering reports shall assess project performance through analysis of beach volume and shoreline position changes, examine erosion and accretion patterns, identify potential cause-and-effect relationships, and provide comparative review of project performance to detect any adverse shoreline impacts attributable to the project. All baseline and survey data must be submitted in digital ASCII format consistent with FDEP technical specifications. The plan coordinates closely with monitoring of the adjacent USACE project (FDEP Permit 0378136-001-JC) to ensure consistent data collection and analysis methodologies across the broader coastal restoration initiative.

View the file

Other files

File Type Posted
Flagler_County_Beach_Nourishment_Project_-_Reach_II_FPN_429573-1-38-01_(Addendum_#7_Revision).pdf PDF
Example_Photography_of_Concrete_Debris.pdf PDF
Contract_Form.pdf PDF
Contract_Form.pdf PDF
Federal_Requirements.pdf PDF
Federal_Requirements.pdf PDF
Flagler_County_Construction_Beach_Fill_Plans_2026-03-04_RevSHT26.pdf PDF
Flagler_County_Construction_Beach_Fill_Plans_2026-03-04_RevSHT26.pdf PDF
23FL2_A2_Flagler_County_Hurricane_Recovery_Project.pdf PDF
23FL2_A2_Flagler_County_Hurricane_Recovery_Project.pdf PDF
FLAGLER_INTERIM_TECH_REPORT_[OA]_25_NOV_2019.pdf PDF
FLAGLER_INTERIM_TECH_REPORT_[OA]_25_NOV_2019.pdf PDF
USACE_2015_Feasability_Study_-_AppendixD_Geotechnical.pdf PDF
USACE_2015_Feasability_Study_-_AppendixD_Geotechnical.pdf PDF
[Q]_20251014-SP_Proffered_Permit_Form.pdf PDF
[Q]_20251014-SP_Proffered_Permit_Form.pdf PDF
Example_Warranty_Bond_Form.pdf PDF
Example_Warranty_Bond_Form.pdf PDF
Example_Payment_and_Performance_Bond_Form_337_18_Version_May_6_2014_doc.pdf PDF
Example_Payment_and_Performance_Bond_Form_337_18_Version_May_6_2014_doc.pdf PDF
2025-03_BeachProfiles_NAVD88.CSV CSV file
2025-03_BeachProfiles_NAVD88.CSV CSV file
Attachment_23_Flagler_County_Physical_Monitoring_Plan_2025-01-13.pdf PDF
2019-05_BorrowArea_NAVD88.txt TXT text file
2019-05_BorrowArea_NAVD88.txt TXT text file
Flagler_County_Construction_Beach_Fill_Plans_2026-03-04_RevSHT25.pdf PDF
Flagler_County_Construction_Beach_Fill_Plans_2026-03-04_RevSHT25.pdf PDF
README.txt TXT text file
README.txt TXT text file
Project_Contract_Forms.pdf PDF
Project_Contract_Forms.pdf PDF
2026-02-02_Flagler_Phase_2_Bid_Schedule_revised.pdf PDF
2026-02-02_Flagler_Phase_2_Bid_Schedule_revised.pdf PDF
Flagler_2020_Geotechnical_Investigation.pdf PDF
Flagler_2020_Geotechnical_Investigation.pdf PDF
[T]_20251016_PA_4673-01484_PN_714658_and_PA_4680-00153_PN_714659_DOCUMENT_SOU.pdf PDF
[T]_20251016_PA_4673-01484_PN_714658_and_PA_4680-00153_PN_714659_DOCUMENT_SOU.pdf PDF
Flagler_County_Permit_Mod_Attachment_16f_Sediment_QAQC_Plan.pdf PDF
Flagler_County_Permit_Mod_Attachment_16f_Sediment_QAQC_Plan.pdf PDF
[S]_Vessel_Strike_Avoidance_Measures.pdf PDF
[S]_Vessel_Strike_Avoidance_Measures.pdf PDF
[R]_OCS_A_0572_BOEM_Lease_Flagler_Phase_II_Executed_8-21-2025.pdf PDF
[R]_OCS_A_0572_BOEM_Lease_Flagler_Phase_II_Executed_8-21-2025.pdf PDF
FO_Flagler_County_Beach_and_Dune_Restoration_Project_-_0379716-003-JM.pdf PDF
FO_Flagler_County_Beach_and_Dune_Restoration_Project_-_0379716-003-JM.pdf PDF
2024-03_Flagler_Geotechnical_Investigation.pdf PDF
2024-03_Flagler_Geotechnical_Investigation.pdf PDF
Flagler_Reach_2_Tech_Specs_Formatted.pdf PDF
24-PC-01778_Flagler_Final_Report_[July_2024].pdf PDF
24-PC-01778_Flagler_Final_Report_[July_2024].pdf PDF
Show 40 more

Latest 50 of 90 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment #23

PHYSICAL MONITORING PLAN

Physical Monitoring Plan Flagler County Beach and Dune Restoration Project: Reach 2 FDEP JCP 0379716-001-JC 23-1 Foth | Olsen

Flagler County Beach and Dune Restoration Project: Reach 2

Flagler County, FL

MODIFICATION REQUEST

FDEP Joint Coastal Permit (0379716-001-JC) &

USACE DA Permit (SAJ-2019-02065 (SP-TMM)

SUPPORTING INFORMATION

Physical monitoring will continue from the pre-construction data and include data collection during the construction phase and post-construction. The long-term, post-construction monitoring will provide the data to evaluate project performance, impacts to adjacent shorelines, guidance for possible adjustments or modifications of future work, and to help identify the need for renourishment. Table 23.1 summarizes the planned monitoring schedule. This schedule will continue biennially until either the next nourishment or expiration of the design life. A renourishment event will restart the physical monitoring plan. Monitoring of this project will be coordinated closely with the monitoring of the adjacent USACE project (FDEP Permit 0378136-

001-JC) and be in accordance with the standards set-out in the FDEP Monitoring Standards for

Beach Erosion Control Projects dated October 2014.

Table 23.1: Flagler County beach/dune restoration project physical monitoring schedule.

Monitoring

Event

Profile

Surveys

Borrow Area

Surveys

Sand

Sampling

Aerial

Photography

Engineering

Report

Pre-Construction X X X1 X2

Post-Construction X X X X2 X

Year 1 X X2 X

Year 2 X X2 X

Year 3 X X2 X

Year 4

Year 5 X X2 X

1. Pre-Construction sand sampling collected as part of project development and presented in Attachments 16 & 17.

2. Aerial Photography to be acquired from commercially available sources.

Williams_MaK 0379716-003-jm

Physical Monitoring Plan Flagler County Beach and Dune Restoration Project: Reach 2 FDEP JCP 0379716-001-JC 23-2 Foth | Olsen

Beach Profile Survey: Topographic and bathymetric profile surveys of the beach and offshore shall be collected as listed in Table 23.1. A complete beach survey was completed in

February 2024 for the purpose of developing this permit modification request. A pre-construction survey will be completed within 90 days prior to the commencement of construction. The post-construction survey will be completed within 60 days following the completion of the project.

Beach profile surveys shall be conducted during a spring or early summer month, typically June.

Each survey should be conducted as close as practicable during the same month of the year. If there are less than six months between the post-construction survey and the first annual monitoring survey, the permittee can request to delay the first annual monitoring survey to the next year.

Beach profile surveys shall be collected at each of the published FEDP reference monuments within the beach fill area and extend approximately 3,000 ft along the adjacent shoreline north and south of the project area. Profile surveys will be conducted along published azimuths and extend a minimum of 3,000 ft offshore from the control monument or -30 ft

NAVD88, whichever is greater. Where practicable, survey data shall extend a minimum of 150 ft landward of the vegetation line or to the R-monument, whichever is more landward.

Borrow Area Surveys: Bathymetric surveys of the borrow area shall be collected concurrently with beach profile surveying, or as close as reasonably possible. A pre-construction survey will be completed within 90 days prior to the commencement of construction. The post-construction survey will be completed within 60 days following the completion of the project. A prior design survey of the offshore borrow area may be submitted for the preconstruction survey if consistent with the other requirements.

The bathymetric surveys shall encompass the entire dredged portion of the borrow area.

The surveys may be conducted on single-beam grid lines across the borrow area and shall be spaced to provide sufficient detail for accurate volumetric calculations but spaced not more than a maximum of 500 ft apart, and shall extend a minimum of 50 ft beyond the boundaries of the borrow site; or conducted alternatively by multibeam collection extending a similar 50 ft beyond the boundaries of the borrow site. The technical specifications provided in the FDEP Monitoring

Standards for Beach Erosion Control Projects dated October 2014 will be applied.

Sand Sampling: Beach sand sample collection and laboratory analysis shall be performed following the completion of the project as described in ITEM #16f: Sediment Quality

Assurance/Quality Control Plan and in accordance with FDEP Monitoring Standards for Beach

Erosion Control Projects dated October 2014.

Aerial Photography: Controlled digital color aerial orthophotography shall be acquired from public or commercially available sources, such as FDEP, USGS, USACE, Nearmap©, etc.

Aerial imagery will be acquired over a concurrent physical extent to the post-construction survey

Physical Monitoring Plan Flagler County Beach and Dune Restoration Project: Reach 2 FDEP JCP 0379716-001-JC 23-3 Foth | Olsen and each annual survey, and as close to the date of the beach profile surveys as possible. The photography shall be color vertical photos and centered on the local shoreline. The quality of acquired photos shall meet technical specifications provided in the FDEP Monitoring Standards for Beach Erosion Control Projects dated October 2014.

Engineering Report: Engineering monitoring reports shall be formulated and submitted to

FDEP along with the monitoring data within 90 days following completion of the post-construction survey and each annual and biennial monitoring survey for the first three-years and fifth year following project completion. The purpose of each report shall be to summarize the annual and biennial as well as cumulative database and to assess project performance including beach volume and shoreline position changes. The engineering report shall include plots of survey profiles and graphic representation of temporal and cumulative volumetric and shoreline position change for the entire monitoring area. Volumetric changes at each survey profile will also be presented in tabular form. Analyses shall discuss the data, shoreline change trends, and the performance of the beach fill project. The study will also seek to identify erosion and accretion patterns and any potential cause and effect relationship. In addition, the report will include a comparative review of project performance and identify any potential adverse shoreline impacts that may be attributable to the project. All baseline and survey data shall be submitted in a digital (ASCII) format consistent with the technical specifications provided in the FDEP Monitoring Standards for Beach Erosion

Control Projects dated October 2014.