This document is a Task Group Instruction (TGI) for the USS Blue Ridge (LCC-19) detailing a specific maintenance task to replace the peel and stick nonskid system in the 7-72-2-L passage. The work involves replacing approximately 13 square feet of second platform deck plating, including vertical surfaces up to 6 inches from the deck, located between frames 72 and 74 on the port side. The work is part of a larger ship repair and maintenance project scheduled for January 12, 2026 to May 15, 2027.

The TGI specifies technical requirements for the nonskid deck covering, which must conform to MIL-PRF-24667, Type XI, Composition PS. The Ship Repair Facility and Japan Regional Maintenance Center (SRF-JRMC) will provide supporting services including crane and rigging, utility services, safety inspections, and quality assurance. The document notes a potential lead hazard and is part of the larger USS Blue Ridge maintenance availability, with a job number of ES01-NPJB and a planning acceptance process involving multiple personnel from Code 231B and Code 333.

View the file

Other files

File Type Posted
TGI_3819P13506A01_c0v0.pdf PDF
TGI_3819P14203_A01_c2v1.pdf PDF
TGI_3819P12387A01_c0v1.pdf PDF
TGI_3819P12388A01_c1v1.pdf PDF
TGI_3819P12354A01_c2v2.pdf PDF
TGI_3819P12335A01_c1v0.pdf PDF
TGI_3819P12317A01_c0v0.pdf PDF
TGI_3819P12316A01_c5v3.pdf PDF
TGI_3819P12310A01_c4v1.pdf PDF
TGI_3819P12311A01_c0v0.pdf PDF
N6264925RA0210003.pdf PDF
TGI_3819P59302A01_c1v1.pdf PDF
TGI_3819P14213A01_c0v0.pdf PDF
TGI_3819P14203_T04_c0v0.pdf PDF
TGI_3819P14206T01_c0v0.pdf PDF
2.03 Solicitation N6264925RA0210002.pdf PDF
TGI_3819P14211A01_c0v0.pdf PDF
TGI_3819P14214A01_c0v0.pdf PDF
TGI_3819P16729A02_c0v1.pdf PDF
TGI_3819P51405A01_c0v0.pdf PDF
TGI_3819P51401A01_c1v2.pdf PDF
TGI_3819P12388A01_c1v1.pdf PDF
TGI_3819P12393_A01_c0v0.pdf PDF
TGI_3819P14203_T01_c0v0.pdf PDF
TGI_3819P12318A01_c2v3.pdf PDF
TGI_3819P12335A01_c1v0.pdf PDF
TGI_3819P12357_A01_c0v0.pdf PDF
TGI_3819P12357_T01_c0v0.pdf PDF
TGI_3819P12340A01_c1v0.pdf PDF
TGI_3819P12323A01_c1v1.pdf PDF
TGI_3819P12341A01_c0v0.pdf PDF
TGI_3819P12312A01_c0v0.pdf PDF
Attachment VII Warranty Tracking Information.pdf PDF
Attachment IV RFI.docx DOCX document
Attachment III TYCOM1_GFP_List_V3.xlsx XLSX spreadsheet
TGI_3819P14212A01_c0v0.pdf PDF
TGI_3819P51404A01_c0v0.pdf PDF
TGI_3819P14206T03_c0v0.pdf PDF
TGI_3819P12387A01_c0v1.pdf PDF
TGI_3819P14206A01_c0v2.pdf PDF
TGI_3819P12364A01_c0v0.pdf PDF
TGI_3819P13506A01_c0v0.pdf PDF
TGI_3819P14203_T04_c0v0.pdf PDF
TGI_3819P12321A01_c1v1.pdf PDF
TGI_3819P12342A01_c0v0.pdf PDF
TGI_3819P12336A01_c0v0.pdf PDF
TGI_3819P12320A01_c0v0.pdf PDF
TGI_3819P12354A01.pdf PDF
TGI_3819P12305A01_c0v0.pdf PDF
Attachment IV RFI (fillable).pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

20-AUG-2024 1015

20.14.12.0.8874 (April 2024) ICN: 3819P14215 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 7-72-2-L DC A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 64511

CU PHASE TITLE: *F/O - REPLACE PEEL AND STICK NONSKID SYSTEM IN 7-72-2-L

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 3

ES01NPJB

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

HAGA, MASAMICHI 231B 3152432513 06-APR-2024

APPROVED BY: CODE: PHONE: DATE:

NAKANO, SEIICHI 231B 3152434519 06-APR-2024

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

ES01-NPJB

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE 7-72-2-L 7 U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

142A0015

1 SCOPE/PURPOSE:

1.1 Title: Peel and Stick Nonskid System in 7-72-2-L; replace

1.2 Location of Work:

1.2.1 Passage (7-72-2-L)

1.3 Identification:

1.3.1 Quantity (13 SF), Second Platform Deck Plating in 7-72-2-L, Frames between 72 and 74, including vertical surface up to height of 6 inches from deck in and around peel and stick deck covering area, Port

Remarks: See Sketch Enclosure-01 for location detail

1.4 Security Classification: None.

TGI Short Form

20-AUG-2024 1015

20.14.12.0.8874 (April 2024) (Continued) ICN: 3819P14215 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 7-72-2-L DC A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 64511

CU PHASE TITLE: *F/O - REPLACE PEEL AND STICK NONSKID SYSTEM IN 7-72-2-L

FOUO Pg 2 of 3

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1.5 Initial Condition:

1.5.1 Potential Lead Hazard.

1.6 Contractor work start date: 1/12/2026

1.7 Contractor work completion date: 5/15/2027

2. PROCEDURE:

2.1 Accomplish the requirements of 009-32 of Ref. No. One, including Table 2, Line(s) 25, for each area listed in 1.3.1.

2.1.1 Accomplish the requirements of 009-26 of Ref No. One, including Attachment G, for installation of new peel and stick nonskid deck covering. Application of peel and stick nonskid deck covering must conform to MIL-PRF-24667, Type XI, Composition PS.

2.2 Notes:

2.2.1 Planner: Code 231B M. Haga, 243-2513

2.2.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.2.3 JCN ES01-NPJB is related to this TGI.

2.3 Government Furnished Material (GFM): None.

2.4 SRF-JRMC will provide the following service work: (TGI No. 3819P14215S02)

2.4.1 [C740] Crane and crane rigging service.

2.4.2 [X99E] Utility service, electrical.

2.4.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

2.4.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.4.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.4.6 [C133] QA inspection for (G) symbol(s).

20-AUG-2024 1015

20.14.12.0.8874 (April 2024) (Continued) ICN: 3819P14215 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 7-72-2-L DC A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 64511

CU PHASE TITLE: *F/O - REPLACE PEEL AND STICK NONSKID SYSTEM IN 7-72-2-L

FOUO Pg 3 of 3

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

2.1 PNTR HRs, CARP HRs, QA HRs 22/KE PC N

CFM for all paints, peel and stick nonskid, thinner, sampler/analyze lead, and misc such as covering materials, and other consumables.

22/MQ CS N

Process Funding Document. 10/CT OM N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

ATTACHMENT LIST

TITLE FILE NAME SAVED DATE

ENCLOSURE-01 3819P14215A01-Sketch.pdf 07-MAR-2024 0000

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P14215 KEY OP: A01

Sketch

3819P14215A01 ENCLOSURE-01 Sheet 1 of 2

DETAIL 2-A

Sketch

3819P14215A01 ENCLOSURE-01 Sheet 2 of 2

DETAIL PLAN VIEW 2-A

PASSAGE 7-72-2-L

8”

24”

20”

FR 72 BHD 73.5

24”

FR 73