This Task Group Instruction (TGI) details specific maintenance and repair work for the Anti-Roll Tank (7-52-01-W) on the USS BLUE RIDGE (LCC-19). The document outlines a comprehensive set of tasks including visual inspection, cleaning, preservation, and structural repairs for the tank and associated components. Key requirements include:
The work involves cleaning the tank to Level III standards, conducting a visual inspection of existing preservation coating, marking corroded or damaged areas, and submitting a detailed report. Specific repair tasks include welding and filling 10 manhole cover bolting ring holes, vee-out and weld repairs of one linear foot of deteriorated welds, base metal weld buildup of 60 square inches of plate defects, and removal and replacement of 10 square feet of deteriorated plate and 4 linear feet of defective stiffener. The work is part of a larger ship repair and maintenance project scheduled from January 12, 2026 to May 15, 2027, with the repairs to be conducted at the Fleet Activities Yokosuka Naval Base in Japan.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
FOUO: Public availability to be determined under 5 USC 552
TASK GROUP INSTRUCTION
AIM REV 20.11.4.0 (OCTOBER 2020)
TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:
NO.: BLST TK 7-52-01-W AY A 0 1
SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE:
F/O - CLEAN, INSPECT, REPAIR, AND PRESERVE ANTI-ROLL TANK (7-52-01-W)
PREPARING ACTIVITY:
PREPARED BY: CODE PHONE DATE
NORIYUKI TAKEUCHI 231B. 315-243-9983 19-JAN-2024
APPROVED BY: CODE PHONE DATE
RYOUTA TAKAGI 231B 315-243-4502 19-JAN-2024
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
REASON FOR WORK/NEED FOR CHANGE:
Paragraph 5.8.4 is incorrect.
CHANGE INSTRUCTIONS:
CH1: Correct Paragraph 5.8.4. (2/3/2024)
SPECIAL REQUIREMENTS:
SURFMEPP
This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required.
CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
ACCEPTANCE OF COMPLETED WORK
PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:
REQUIRED:☐YES ☒NO
RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
TGI NO.: BLST TK 7-52-01-W AY A 0
FOUO
SHIP: LCC-19 CHG/VER: 1/0
LIST OF EFFECTIVE PAGES
SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.
1-5 J-1 M-1
1. SCOPE/PURPOSE
1.1 Title: Anti-Roll Tank (7-52-01-W); clean, inspect, repair, and preserve
1.2 Location of Work:
1.2.1 Anti-Roll Tank (7-52-01-W)
1.2.2 Storeroom (6-52-5-A)
1.2.3 Storeroom (6-52-4-A)
1.3 Identification:
1.3.1 Quantity (One EA), Anti-Roll Tank
Tank No.: 7-52-01-W Capacity: 100,576 Gallons
1.3.2 Quantity (2 EA), Manhole Cover Plate(s) for 7-52-01-W
Manhole No(s).: 6-52-2 and 6-58-1 Size: 15 Inches x 23 Inches Material: Steel
1.3.3 Quantity (2 EA), Bolting Ring for Manhole Cover Plate(s) for 7-52-01-W Manhole No(s).: 6-52-2 and 6-58-1 Material: Steel
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Potential Lead Hazard.
1.6 Contractor work start date:
1.7 Contractor work completion date:
2. REFERENCES:
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N
3 TM S9086-
CJ-STM-
010/CH-075
Fasteners 7 N
1/12/2026
5/15/2027
FOUO
SHIP: LCC-19 CHG/VER: 1/0
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
4 DWG 103-
2491033
2 PLATF FR 52-98 J Y AL
L
5 DWG 114-
2491164
ANTI-ROLL TANK BHD C Y AL
6 DWG 100-
2491003
SHELL PLTG & STGR FRAME 51
1/2 -102 1/4 CL TO 4 TH DECK
G Y AL
7 DWG 101-
2491021
WEBS FR 54, 56, 58, 60 & 62 J Y AL
8 DWG 103-
2491036
1ST PLATF PLTG FR 52-98 G Y AL
9 DWG 114-
2491156
AGC19 TRANSV BHD FR 52 & 64 G Y AL
3. APPENDICES:
3.1 Appendix “J” TGI Job Summary Information Sheet
3.2 Appendix "M" TGI Material List
3.3 Appendix “D” Deficiency Form
4. GENERAL REQUIREMENTS:
4.1 Not Applicable.
5. PROCEDURE:
5.1 Accomplish the requirements of 099-902YO of 2.2 for each tank listed in 1.3.1.
5.1.1 Accomplish a visual inspection of each tank listed in 1.3.1 for existing preservation coating.
5.1.1.1 Mark each corroded, damaged and/or deteriorated coating area in each tank.
5.1.1.2 Submit one legible copy, in hard copy or approved transferrable media, of a report with a sketch listing results of the requirements of 5.1.1.1 to the SUPERVISOR.
5.1.2 Accomplish the requirements of 009-107 of 2.1.
5.1.2.1 Ensure General Cleaning must be Level III.
5.1.3 Accomplish installation of each manhole cover for each tank listed in 1.3.1 in accordance with Figure 075-4-1 of 2.3.
5.2 Weld fill, drill, and tap a total 10 each stripped manhole cover bolting ring holes for each tank listed in 1.3.1 as designated by the SUPERVISOR. See 5.8.5.
5.2.1 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column A, Lines One through 7.
5.3 Repair each tank listed in 1.3.1, based on the CCIMS assessment report as designated by the SUPERVISOR, using 2.4 through 2.9 for guidance. See 5.8.4 through 5.8.6.
5.3.1 Vee-out and weld a total of one linear feet of each deteriorated and damaged weld. Each area of repair must include deck, bulkhead, shell plating, and overhead.
5.3.2 Chip and grind each surface flush in way of each repair.
5.3.3 Base metal weld buildup a total of 60 square inches of each plate defect in the tank.
FOUO
SHIP: LCC-19 CHG/VER: 1/0
5.3.3.1 For bidding purposes the base metal weld buildup must be one quarter inch thick.
5.3.3.2 Surface must be ground to sound metal prior to base metal weld buildup.
5.3.3.3 Fill each local pit and groove with weld material prior to application of each principal build up layer.
5.3.3.4 Grind each surface of completed base weld metal buildup smooth if greater than 1/8 inch above plate surface.
5.3.4 Remove existing, fabricate and install new a total of 10 square feet of deteriorated plate.
5.3.5 Remove existing, fabricate and install new a total of 4 linear feet of defective stiffener.
5.3.6 Accomplish the requirements of 009-12 of 2.1, including Table 2, Columns A, Lines One through 7.
5.3.6.1 Accomplish nondestructive testing in accordance with Line 11.
5.3.7 Accomplish the requirements of 009-25 of 2.1 for an air hose, water hose, or vacuum box test of each new insert weld seam. Allowable leakage: None.
5.4 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line(s) 11, for tank side surface, and Table 3, Line(s) 25, for storeroom side surface of each cover plate listed in 1.3.2.
5.5 Accomplish the requirements of 009-32 of 2.1 for each bolting ring listed in 1.3.3.
5.6 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line(s) 11, for a total of 979 square feet of defective painted surfaces, for each tank listed in 1.3.1, as designated by the SUPERVISOR.
5.6.1 The preservation area must not exceed 10 square feet per one area.
5.7 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
5.8 Notes:
5.8.1 Planner: Code 231B N. Takeuchi, 243-9983
5.8.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
5.8.3 This TGI meets the intent of DDG CSWT File Nos. 123-133, 123-142, and 123-143.
5.8.4 CCIMS assessment of each tank listed in 1.3.1 will be accomplished by SRF-JRMC (TGI No. 3819P12335I01), and the Project team will provide the assessment report with engineering evaluation under DL process for front loading structure repair.
5.8.5 Removal and installation of interferences, and gas free operation, preservation of boundary spaces relating to front loading structure repair are not included in this TGI. They will be covered by a DL in the future based on Contractor submitted condition report.
5.8.6 Materials for structure members relating to front loading repair will be provided in the future as a DL based on Contractor submitted condition report.
5.8.7 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkhead normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The
FOUO
SHIP: LCC-19 CHG/VER: 1/0
closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.
5.8.8 JCNs ER01-ZAK8, ER01-ZAX3, and ER01-ZAW5 are related to this TGI.
5.9 Government Furnished Material (GFM): None.
5.10 SRF-JRMC will provide the following service work: (TGI No. 3819P12335S02).
5.10.1 [C740] Crane and crane rigging service.
5.10.2 [X99E] Utility service, electrical.
5.10.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
5.10.4 [C106.1] Safety inspection for SRF-JRMC employees.
5.10.5 [C106.2] Gas free inspection for SRF-JRMC employees.
5.10.6 [C133] QA inspection for (G) symbol(s).
5.10.7 [C135] QA inspection for (G) symbol(s).
5.10.8 [C250] Technical support.
FOUO
J-1
SHIP: LCC-19 CHG/VER: 1/0
APPENDIX "J"
TGI JOB SUMMARY INFORMATION SHEET
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
BLST TK 7-52-01-W AY A 0 0
CU PHASE TITLE:
F/O - CLEAN, INSPECT, REPAIR, AND PRESERVE ANTI-ROLL TANK (7-52-01-W)
PRIMARY COMPONENT:
COMPONENT UNIT LIST (FOR ASSEMBLIES):
MANHOLE 6-58-1 HA BLST 7-52-01-W TK MANHOLE 6-52-2 HA
ATTACHMENT LIST:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA ,TAKEHIDE
JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:
3819P12335 A01
TOTAL MAT’L COST TOTAL DURATION:
CU PHASE DESCRIPTION:
The purpose of this TGI is to clean, inspect, repair, and preserve anti-roll tank (7-52-01-W).
Location of Work:
Anti-Roll Tank (7-52-01-W) Storeroom (6-52-5-A) Storeroom (6-52-4-A)
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
5.1 LBR HRs, PNTR HRs 22 KE PC
5.2 SFTR HRs, WELD HRs, PNTR HRs, QA HRs 22 KE PC
5.3 SFTR HRs, WELD HRs, CARP HRs, PNTR HRs, QA HRs 22 KE PC
5.4 PNTR HRs, QA HRs 22 KE PC
5.5 PNTR HRs, RGRS HRs, QA HRs 22 KE PC
5.6 PNTR HRs, QA HRs 22 KE PC
5.7 PNTR HRs, QA HRs 22 KE PC
Dewatering and Cleaning Work CFM for marine chemist, gaskets, fasteners, tank watch cost, and MISC.
22 MQ CS
Structural Work CFM for fire watch cost, tank watch cost, MT inspection cost, air compressor rental cost and fuel oil cost for air hose test, lead sampling/analysis cost, and MISC such as electrode, gases, temporary closure, covering materials, and other consumable.
22 MQ CS
Preservation Work CFM for all paints, thinner, tank watch cost, grits including disposal cost, and MISC such as covering material and other consumable.
22 MQ CS
Process Funding Document. 10 CT OM
FOUO
M-1
SHIP: LCC-19 CHG/VER: 1/0
APPENDIX “M”
TGI MATERIAL LIST
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
BLST TK 7-52-01-W AY A 0 0
CU PHASE TITLE:
F/O - CLEAN, INSPECT, REPAIR, AND PRESERVE ANTI-ROLL TANK (7-52-01-W)
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV
JOB ORDER: KEY OP:
3819P12335 A01
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
NOTES:
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR APPENDIX "D"
DEFICIENCY FORM
☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One)
2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
LCC-19 BLST TK 7-52-01-W AY A 0
4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:
3819P12335 A01
7. DESCRIPTION:
8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
9. CORRECTIVE ACTION:
10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
FOR NON-NUCLEAR USE ONLY
11. RFD/RFW REQ’D ☐ LAR REQ'D ☐
ILS MOD REQ’D ☐
SRD/PLAN REV REQ'D ☐
DWG NO.: _____________________ S/A NO.: ___________________
12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:
SATISFACTORY:
13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
YES ☐ NO ☐
14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE:
15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
_________:YES ☐ NO ☐
16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE (DR ONLY)
DL’s ISSUED
(DR ONLY)
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
LCC-19 BLST TK 7-52-01-W AY A 0