TGI_3819P13506A01_c0v0.pdf
PDF 127 KB Posted
- Attached to
- USS BLUE RIDGE (LCC-19) 5C1 DSRA TYCOM 1
- Solicitation number
- N6264925RA021
About this file
This document is a Task Group Instruction (TGI) for repair work on the USS BLUE RIDGE (LCC-19), specifically focused on repairing the transverse bulkhead plate frame 40 in section 5-40-1-L. The TGI details a comprehensive repair project involving multiple locations including the crew work/rest areas, living spaces, storage rooms, and officers' offices. The work encompasses removing and reinstalling Collection, Holding and Transfer (CHT) piping, fabricating and installing new bulkhead plates, and addressing potential hazards including lead and asbestos.
The repair is scheduled to begin on 1/12/2026 and complete by 5/15/2027, with the Navy's Ship Repair Facility and Japan Regional Maintenance Center (SRF-JRMC) providing government-furnished material and services. Special requirements include working through fire zone boundaries, requiring non-flammable closures, and maintaining specific cleanliness standards for piping systems. The instruction involves multiple technical teams and requires detailed certification processes, air hose testing of new welds, and comprehensive documentation of the repair work.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
FOUO: Public availability to be determined under 5 USC 552
TASK GROUP INSTRUCTION
AIM REV 20.11.4.0 (OCTOBER 2020)
TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:
NO.: TRANSV BHD 5-40-1-L AY A 0 0
SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE:
F/O - REPAIR TRANSVERSE BULKHEAD PLATE FRAME 40 IN 5-40-1-L
PREPARING ACTIVITY:
PREPARED BY: CODE PHONE DATE
YOUHEI ARAKAWA 231B 315-243-4496 13-MAY-2024
APPROVED BY: CODE PHONE DATE
RYOUTA TAKAGI 231B 315-243-4502 13-MAY-2024
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
REASON FOR WORK/NEED FOR CHANGE:
CHANGE INSTRUCTIONS:
SPECIAL REQUIREMENTS:
This work Affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required.
CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III
CLASS P-2 PIPING
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
ACCEPTANCE OF COMPLETED WORK
PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:
REQUIRED:☐YES ☒NO
RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
TGI NO.: TRANSV BHD 5-40-1-L AY A 0
FOUO
SHIP: LCC-19 CHG/VER: 0/0
LIST OF EFFECTIVE PAGES
SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.
1-4 J 1-2 M 1-3
1. SCOPE/PURPOSE
1.1 Title: Transverse Bulkhead Plate Frame 40 in 5-40-1-L; repair
1.2 Location of Work:
1.2.1 Crew WR, WC, SH and Decontamination Station (5-40-1-L)
1.2.2 Crew Living Space (5-30-01-L)
1.2.3 Storage Room (6-36-3-A)
1.2.4 LCPO Office (6-40-1-Q)
1.2.5 Division Officer’s Office (6-40-3-Q)
1.3 Identification:
1.3.1 Quantity (One AY), Collection, Holding and Transfer (CHT) Piping including Rubber Elbow of Water Closet, drain header of water closet
Size: 4 Inch IPS (4.500 Inch OD X 0.109 Inch WT) 3 Inch IPS (3.500 Inch OD X 0.095 Inch WT) 2 Inch IPS (2.375 Inch OD X 0.083 Inch WT)
Material: Cu-Ni 90-10, Cu-Ni 70-30 and Rubber Specification: MIL-T-16420
Remarks: See Sheet One (Zone 4-A) of 2.4, Sheet One (Zone 5-A) of 2.5, Sheet 3 (Zone 18-E) of 2.6 and Sheet 10 of 2.7 for detail.
1.3.2 Quantity (One Lot), Bulkhead Plate, Transverse Watertight Bulkhead Frame 40, Starboard
Remarks: See 2.3 for material and details.
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Potential Lead Hazard.
1.5.2 Potential Asbestos Hazard.
1.6 Contractor Work start date: 1/12/2026
1.7 Contractor Work completion date: 5/15/2027
2. REFERENCES:
FOUO
SHIP: LCC-19 CHG/VER: 0/0
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N
3 PDD 114-
ELM-240183
RPR of Corroded TRANSV BHD in Crew WR, WC, SH and DECONTN
STA (5-40-1-L)
- Y AL
L
4 DWG 505-
2492260
PLMB DRAINS - FR30 - 52 5TH DK
& BEL PLAN
F Y AL
5 DWG 505-
2492847
PLMB DRAINS – FR 40-52 SECT E Y AL
6 DWG 505-
8519728
WASTE AND SOIL DRAIN
SYSTEM INSTALLATION FOR
PIPING UPGRADE, 4TH DK &
BELOW, FWD
- Y 3
7 DWG 505-
2492270
MISC DETS FOR PLMB & POT W
SYS
G Y 10
8 DWG 545-
2492627
WELDED BHD OR DK SLEEVES
FOR IPS PIPING
C N
9 DWG 104-
2491047
5TH DK PLTG STEM - FR 51 1/2 H Y AL
3. APPENDICES:
3.1. Appendix “J” TGI Job Summary Information Sheet
3.2. Appendix "M" TGI Material List
3.3. Appendix “D” Deficiency Form
4. GENERAL REQUIREMENTS:
4.1 Not Applicable.
5. PROCEDURE:
5.1 Remove and reinstall each CHT piping listed in 1.3.1 for supporting of structural work, using 2.3 through 2.9 for guidance.
5.1.1 Accomplish the requirements of 009-09 of 2.1 for certification process.
5.1.2 Accomplish the requirements of 009-12 of 2.1, including Table One, Column(s) A, Lines One through 10.
5.1.3 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column(s) A, Lines One through 7.
5.1.4 Accomplish the requirements of 009-25 of 2.1 for a local air hose test of each new weld of each deck sleeve.
Allowable leakage: None.
5.2 Remove existing, fabricate and install new each bulkhead plate listed in 1.3.2 in accordance with 2.3.
5.2.1 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column(s) A, Lines One through 7.
5.2.2 Accomplish the requirements of 009-25 of 2.1 for a local air hose test of each new weld of each bulkhead plate. Allowable leakage: None.
5.3 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
5.4 Notes:
5.4.1 Planner: Code 231B Y. Arakawa, 243-4496
FOUO
SHIP: LCC-19 CHG/VER: 0/0
Planner: Code 233 M. Yamaguchi, 080-9350-1450 Planner: Code 234 T. Shibano, 243-3583 Planner: Code 234 Y. Yajima, 243-0977
5.4.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
5.4.3 This TGI is in response to CCIMS report No. CCIMS-G1N6-LCC19-059-23 from TGI No. 3819M11002I03
(SRF-JRMC TGI).
5.4.4 This TGI clears DFS LCC-19-1021-2023 in its entirety.
5.4.5 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.
5.4.6 JCN CI01-L016 is related to this TGI.
5.5 Government Furnished Material (GFM):
5.5.1 SRF-JRMC will provide GFM listed in Appendix “M”.
5.6 SRF-JRMC will provide the following service work: (TGI No. 3819P13506S02)
5.6.1 [C740] Crane and crane rigging service.
5.6.2 [X99E] Utility service, electrical.
5.6.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
5.6.4 [C106.1] Safety inspection for SRF-JRMC employees.
5.6.5 [C106.2] Gas free inspection for SRF-JRMC employees.
5.6.6 [C133] QA inspection for (G) symbol(s).
FOUO
J-1
SHIP: LCC-19 CHG/VER: 0/0
APPENDIX "J"
TGI JOB SUMMARY INFORMATION SHEET
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
TRANSV BHD 5-40-1-L AY A 0 0
CU PHASE TITLE:
F/O - REPAIR TRANSVERSE BULKHEAD PLATE FRAME 40 IN 5-40-1-L
PRIMARY COMPONENT:
COMPONENT UNIT LIST (FOR ASSEMBLIES):
CMPT 5-30-01-L MS CMPT 6-36-3-A MSCMPT 5-40-1-L MSSEW 5-40-1-L PP SEW 6-40-3-Q
PP
ATTACHMENT LIST:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA ,TAKEHIDE
JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:
3819P13506 A01
TOTAL MAT’L COST TOTAL DURATION:
CU PHASE DESCRIPTION:
The purpose of this TGI is to repair transverse bulkhead plate frame 40 in -40-1-L.
Location of Work:
Crew WR, WC, SH and Decontamination Station (5-40-1-L) Crew Living Space (5-30-01-L) Storage Room (6-36-3-A) LCPO Office (6-40-1-Q) Division Officer’s Office (6-40-3-Q)
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
5.1 PFTR HRs, PNTR HRs, WELD HRs, QA HRs 22 KE PC
5.2 SFTR HRs, WELD HRs, SMTL HRs, ELEC HRs, INSL HRs, CARP HRs, PNTR HRs, RGRS HRs, QA HRs
22 KE PC
5.3 PNTR HRs, QA HRs 22 KE PC
Structural Work CFM for all paints, thinner, grits, including waste disposal cost, fire watch watch cost, lead sampling/ analysis cost, asbestos sampling/analysis cost for compartment insulation, air compressor rental cost and fuel oil cost for air hose test, and MISC such as electrode, gases, ---continue to below---
22 MQ CS
---continued from above--- deck covering material, temporary closure and covering material, gaskets, rivets, fasteners, wires, and other consumable.
22 MQ CS
Piping Work CFM marine chemist cost, fire watch cost, air compressor rental cost, fuel oil cost, welding rod, paint, MISC such as saw blades, painting material, plastic bag/sheet and etc.
22 MQ CS
Electrical Work CFM for misc material and other consumable.
22 MQ CS
FOUO
J-2
SHIP: LCC-19 CHG/VER: 0/0
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
Lagging Work CFM for asbestos sampler and analysis cost, paints, covering material, and MISC such as other consumable material.
22 MQ CS
Process Funding Document. 10 CT OM
FOUO
M-1
SHIP: LCC-19 CHG/VER: 0/0
APPENDIX “M”
TGI MATERIAL LIST
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
TRANSV BHD 5-40-1-L AY A 0 0
CU PHASE TITLE:
F/O - REPAIR TRANSVERSE BULKHEAD PLATE FRAME 40 IN 5-40-1-L
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV
JOB ORDER: KEY OP:
3819P13506 A01
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
001 M PLATE,ME, ORDERED FOR
KTR
ORIG: C231B, Y.ARAKAWA,
PHONE: 243-4496
9B 9515 001533217 NA 4 N 41235131 14/SF
002 M PLATE,ME, ORDERED FOR
KTR
ORIG: C231B, Y.ARAKAWA,
PHONE: 243-4496
9B 9515 001533223 NA 4 N 41235132 4/SF
003 M INSULATI, ORDERED FOR KTR
ORIG: C231B, Y.ARAKAWA,
PHONE: 243-4496
9Q 5640 008096312 NA 4 N 41235133 5/EA
004 M INSULATI, ORDERED FOR KTR
ORIG: C231B, Y.ARAKAWA,
PHONE: 243-4496
9Q 5640 008096315 NA 4 N 41235134 2/EA
005 M TAPE,TEX, ORDERED FOR
KTR
ORIG: C231B, Y.ARAKAWA,
PHONE: 243-4496
9B 8315 002671632 NA 4 N 41235136 1/RO
006 M TAPE,TEX, ORDERED FOR
KTR
ORIG: C231B, Y.ARAKAWA,
PHONE: 243-4496
9B 8315 002671633 NA 4 N 41235137 1/RO
NOTES:
FOUO
M-2
SHIP: LCC-19 CHG/VER: 0/0
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
007 M ADHESIVE, ORDERED FOR
KTR
ORIG: C231B, Y.ARAKAWA,
PHONE: 243-4496
9B 8040 002738708 NA 4 Y 41235122 1/GL
008 M CAP,SNAP, ORDERED FOR
KTR
ORIG: C231B, Y.ARAKAWA,
PHONE: 243-4496
9B 5325 007377648 NA 4 N 41235138 50/EA
400 M COUPLING,TUBE, COUPLING,
4, CN 90-10, BW
ORDERED FOR KTR, ORG:
C234,T. SHIBANO, TEL: 243-
9B 4730 007225474 NA 4 N 41205142 2/EA
401 M COUPLING,TUBE, COUPLING,
2, CN 90-10, BW
ORDERED FOR KTR, ORG:
C234,T. SHIBANO, TEL: 243-
9B 4730 005423290 NA 4 N 41205143 4/EA
402 M BACKINGR, BACKING RING, 4"
IPS, CU-NI 90/10, 200 PSIG,
MIL-STD-22
ORDERED FOR KTR, ORG:
C234,T. SHIBANO, TEL: 243-
9B 4730 LL4558786 NA 4 N 41207455 2/EA
403 M BACKING, BACKING RING,
2"IPS, CU-NI 90/10, 200PSIG,
MIL-STD-22
ORDERED FOR KTR, ORG:
C234,T. SHIBANO, TEL: 243-
9B 4730 LL4558779 NA 4 N 41207459 4/EA
404 M BACKING,, BACKING RING,
3"IPS, CU-NI 90/10, 200PSIG,
MIL-STD-22
ORDERED FOR KTR, ORG:
C234,T. SHIBANO, TEL: 243-
9B 4730 LL4558783 NA 4 N 41207456 2/EA
450 M CLOTH,PLAIN WEAVE, H/W
GLASS CLOTH,
C234 Y.YAJIMA, 243-0977
ORDERED FOR KTR
9B 8305 001487364 NA 4 N 41185005 1/RO
451 M INSULATI, INSULATION,
FIBROUS GLASS, THERMAL,
BLANKET WITHOUT BINDER,
UNFACED, SIZE: 5FT W X 45FT
L X 1"THK, MIL-DTL-32585,
TYPE I, FORM 3, NSN: 5640-00-
173-6591 (NSN MISTAKENLY
INDICATES FACING D, BUT
CORRECT ITEM IN THIS NSN
IS UNFACED.)
ORIG: C234 Y.YAJIMA, 243-
ORDERED FOR KTR
9Q 5640 LL9607458 NA 4 N 41187407 1/RO
452 M ADHESIVE, ADHESIVE FOR
INTAKE INSULATION
ORDERED FOR KTR
C234 Y.YAJIMA, 243-0977
9B 8040 002738708 NA 4 Y 41185006 1/GL
453 M ADHESIVE, ADHESIVE FOR
PLASTIC TUBE
ORDERED FOR KTR
C234 Y.YAJIMA, 243-0977
9B 8040 008419773 NA 4 Y 41185007 2/PT
FOUO
M-3
SHIP: LCC-19 CHG/VER: 0/0
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
454 M INSULATI, INSULATION, PIPE,
BRAND: K-FLEX ECO,
SPECIFICATION COMPLIANCE:
EB 4013, FOR SIZE: 4" IPS,
SIZE: 4-1/2" ID X 3/4" THK X 6
FT LG, UI: EA/6 FT(ONE
CONTINUOUS LENGTH
REQUIRED), MATL: NON-
HALOGEN
ORIG:C-234 Y.YAJIMA, 243-
ORDERED FOR KTR
9B 5970 LL9607848 NA 4 N 41187412 2/EA
455 M SILICA PIPE COVER, SILICA
PIPE COVER, 14 INCH IPS X 2
INCH THK, 3 FT LONG PER EA,
2 EA/BX, NON ASBESTOS,
ORIG:C234 Y.YAJIMA, 243-0977
ORDERED FOR KTR
9B 5640 LL9301047 NA 4 N 41207414 2/EA
456 M CEMENT,INSULATION,H,
CEMENT, 45LB/BG,
ORIGI C234 Y.YAJIMA, 243-
ORDERED FOR KTR
9Q 5640 002264540 NA 4 Y 41185008 1/BG
457 M SILICA PIPE COVER, KEICAL
ACE SUPER SILICA, TOMBO,
SIZE: 16" X 2" THK (50MM) X 2'
LENGTH (610MM), 2EA/BOX.
*MUST BE ORDERED IN
MULTIPLES OF 2EA*
ORDERED FOR KTR
C234 Y.YAJIMA, 243-0977
9Q 5640 LL4610111 NA 4 N 41207802 2/EA
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR APPENDIX "D"
DEFICIENCY FORM
☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One)
2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
LCC-19 TRANSV BHD 5-40-1-L AY A 0
4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:
3819P13506 A01
7. DESCRIPTION:
8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
9. CORRECTIVE ACTION:
10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
FOR NON-NUCLEAR USE ONLY
11. RFD/RFW REQ’D ☐ LAR REQ'D ☐
ILS MOD REQ’D ☐
SRD/PLAN REV REQ'D ☐
DWG NO.: _____________________ S/A NO.: ___________________
12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:
SATISFACTORY:
13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
YES ☐ NO ☐
14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE:
15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
_________:YES ☐ NO ☐
16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE (DR ONLY)
DL’s ISSUED
(DR ONLY)
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
LCC-19 TRANSV BHD 5-40-1-L AY A 0
File details come from the government source that posted it. Updated .