TGI_3819P14212A01_c0v0.pdf
PDF 436 KB Posted
- Attached to
- USS BLUE RIDGE (LCC-19) 5C1 DSRA TYCOM 1
- Solicitation number
- N6264925RA021
About this file
This document is a Task Group Instruction (TGI) for structural repair and preservation work on the USS BLUE RIDGE (LCC-19), specifically focusing on repair and preservation of structural members in the Sprinkler Maintenance Room (7-68-2-Q) and adjacent spaces. The detailed instruction covers multiple locations including the Small Arms Magazine, Passage, and Distillate Fuel Overflow/Ballast areas, with specific requirements for removing and replacing bulkhead plates, insulation coaming, and conducting preservation work on interior surfaces totaling 195 square feet.
The work involves precise technical specifications, including removing existing temporary doubler plates, fabricating and installing new components, welding, and conducting air hose tests with zero allowable leakage. The instruction identifies potential lead and asbestos hazards and requires special considerations for fire zone boundaries, including the fabrication of a non-flammable closure. The contractor work is scheduled to start on 1/12/2026 and complete by 5/15/2027, with multiple planning and technical references provided, including NAVSEA Standard Items and specific repair plan documents. The work will be performed at the Fleet Activities Yokosuka Naval Base in Japan.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
FOUO: Public availability to be determined under 5 USC 552
TASK GROUP INSTRUCTION
AIM REV 20.11.4.0 (OCTOBER 2020)
TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:
NO.: STRL IN 7-68-2-Q AY A 0 0
SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE:
F/O - REPAIR AND PRESERVE STRUCTURAL MEMBER IN 7-68-2-Q
PREPARING ACTIVITY:
PREPARED BY: CODE PHONE DATE
HIROYUKI TANAKA 231B 315-243-4491 01-MAY-2024
APPROVED BY: CODE PHONE DATE
RYOUTA TAKAGI 231B 315-243-4502 01-MAY-2024
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
REASON FOR WORK/NEED FOR CHANGE:
CHANGE INSTRUCTIONS:
SPECIAL REQUIREMENTS:
This Work Affects a Fire Zone Boundary. Fabrication and/or Staging of a Non-Flammable Closure is Required.
HOT WORK IN MAGAZINE AND ADJACENT SPACES IAW S6740-AA-SAF-010 AND NAVSEA OP 4
CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
ACCEPTANCE OF COMPLETED WORK
PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:
REQUIRED:☐YES ☒NO
RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
TGI NO.: STRL IN 7-68-2-Q AY A 0
FOUO
SHIP: LCC-19 CHG/VER: 0/0
LIST OF EFFECTIVE PAGES
SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.
1-4 J-1 M-1 Sketch (1)
1. SCOPE/PURPOSE
1. SCOPE/PURPOSE:
1.1 Title: Structural Member in 7-68-2-Q; repair and preserve
1.2 Location of Work:
1.2.1 Sprinkler Maintenance Room (7-68-2-Q)
1.2.2 Small Arms Magazine (7-69-2-M)
1.2.3 Passage (7-72-2-L)
1.2.4 Distillate Fuel Overflow or Ballast (9-64-0-F)
1.3 Identification:
1.3.1 Quantity (One Lot), Bulkhead Plate, Transverse Bulkhead in 7-68-2-Q, Frame 72, Port
Material: OS, MIL-S-22698 GR-A, 10.2 LBs Plate Remarks: See Section 3-A of 2.3 for detail
1.3.2 Quantity (One Lot), Insulation Coaming in 7-69-2-M, Frames between 72 and 73, Port
Base Material: OS, ASTM A1011, 0.125 Inch Thickness Sheet Remarks: See Plan 3-C of 2.3 for detail
1.3.3 Quantity (One Lot), Longitudinal Bulkhead Plating in 7-72-2-L, Frames between 72 and 73, Port
Base Material: OS, MIL-S-22698 GR-A, 10.2 LBs Plate Remarks: See Elevation 3-B of 2.3 for detail
1.3.4 Quantity (195 SF in Total), Interior Surface in 7-68-2-Q
1.3.4.1 Quantity (15 SF), First Platform Plating, Frames between 68 and 70
Remarks: See Sketch Enclosure-01 for location detail
1.3.4.2 Quantity (180 SF), Entire Second Platform Plating, including vertical surface up to height of 12 inches from deck
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Potential Lead Hazard
FOUO
SHIP: LCC-19 CHG/VER: 0/0
1.5.2 Potential Asbestos Hazard
1.6 Contractor work start date:
1.7 Contractor work completion date:
2. REFERENCES:
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N
3 PDD 114-
ELM-240231
Rpr Plan Of Corroded Transv Wtrtt Bhd Fr 72 In Spr Maint Room (7-68- 2-Q)
- Y AL
L
4 PDD 114-
ELM-240045
Temp Rpr Plan Of Transv Wtrtt Bhd Fr 72 In Spr Maint Room (7-68-2-Q)
- Y AL
L
3. APPENDICES:
3.1. Appendix “J” TGI Job Summary Information Sheet
3.2. Appendix "M" TGI Material List
3.3. Appendix “D” Deficiency Form
4. GENERAL REQUIREMENTS:
4.1 Not Applicable.
5. PROCEDURE:
5.1 Remove existing, fabricate and install new each bulkhead plate listed in 1.3.1 in accordance with 2.3.
5.1.1 Remove existing temporary doubler plate and sealing compound, using 2.4 for guidance.
5.1.2 Fabricate and install each new insulation coaming listed in 1.3.2 in accordance with 2.3.
5.1.3 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column(s) A, Lines One through 7.
5.1.4 Accomplish the requirements of 009-25 of 2.1 for a local air hose test of each new weld of each bulkhead plate.
Allowable leakage: None.
5.2 Accomplish build up weld of remining bolt holes on each existing longitudinal bulkhead plating listed in 1.3.3 in accordance with 2.3.
5.2.1 Shape remaining hole to minimum 20 degrees countersink.
5.2.2 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column(s) A, Lines One through 7.
5.2.3 Accomplish the requirements of 009-25 of 2.1 for a local air hose test of each new weld of the longitudinal bulkhead plating. Allowable leakage: None.
5.3 Accomplish the requirements of 009-32 of 2.1, including Table 3, Line(s) 6, for each area listed in 1.3.4.
1/12/2026
5/15/2027
FOUO
SHIP: LCC-19 CHG/VER: 0/0
5.4 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
5.5 Notes:
5.5.1 Planner: Code 231B H. Tanaka, 243-4491
Planner: Code 231B M. Haga, 243-2513 Planner: Code 233 M. Takemura, 080-9350-1458
5.5.2 This TGI clears DFS LCC-19-1049-2023 in its entirety.
5.5.3 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.
5.5.4 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
5.5.5 Opening, initial cleaning, and closing of each space listed in 1.2.4 will be covered by TGI No. 3819P12318A01
(KTR TGI)
5.5.6 JCNs ES01-NPEM, ES01-NPJ9, ES01-NPJA, and OW01-8646 are related to this TGI.
5.6 Government Furnished Material (GFM):
5.6.1 SRF-JRMC will provide GFM listed in Appendix “M”.
5.7 SRF-JRMC will provide the following service work: (TGI No. 3819P14212S02).
5.7.1 [C740] Crane and crane rigging service.
5.7.2 [X99E] Utility service, electrical.
5.7.3 [X99M] Utilities service, including low pressure air supply, water supply, and steam supply.
5.7.4 [C106.1] Safety inspection for SRF-JRMC employees.
5.7.5 [C106.2] Gas free inspection for SRF-JRMC employees.
5.7.6 [C133] QA Inspection for (G) symbol(s).
FOUO
J-1
SHIP: LCC-19 CHG/VER: 0/0
APPENDIX "J"
TGI JOB SUMMARY INFORMATION SHEET
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
STRL IN 7-68-2-Q AY A 0 0
CU PHASE TITLE:
F/O - REPAIR AND PRESERVE STRUCTURAL MEMBER IN 7-68-2-Q
PRIMARY COMPONENT:
COMPONENT UNIT LIST (FOR ASSEMBLIES):
CMPT 7-69-2-M MS CMPT 7-72-2-L MSCMPT 7-68-2-Q MS
ATTACHMENT LIST:
1. ENCLOSURE-01 (3819P14212-Sketch.pdf) saved on 23-APR-2024 0000.
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA ,TAKEHIDE
JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:
3819P14212 A01
TOTAL MAT’L COST TOTAL DURATION:
CU PHASE DESCRIPTION:
The purpose of this TGI is to repair and preserve structural member in 7-68-2-Q.
Location of Work:
Sprinkler Maintenance Room (7-68-2-Q) Small Arms Magazine (7-69-2-M) Passage (7-72-2-L) Distillate Fuel Overflow or Ballast (9-64-0-F)
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
5.1 SFTR HRs, WELD HRs, INSL HRs, ELEC HRs, CARP
HRs, PNTR HRs, RGRS HRs, QA HRs
22 KE PC
5.2 SFTR HRs, WELD HRs, QA HRs 22 KE PC
5.3 INSL HRs, PNTR HRs, RGRS HRs, QA HRs 22 KE PC
5.4 PNTR HRs, QA HRs 22 KE PC
Structure and Preservation Work CFM for marine chemist, all paints, thinner, grits including disposal cost, peel and stick nonskid, firewatch and tank watch cost, air compressor rental cost and fuel oil cost for air hose test, sampler/analysis cost for asbestos/lead, ---continue to below---
22 MQ CS
---continued to from above---and misc such as electrode, gases, temporary covering and closure material, and other consumable.
22 MQ CS
Electrical Work CFM for fastener, plastic bag and insulation tape.
22 MQ CS
Process Funding Document. 10 CT OM
FOUO
M-1
SHIP: LCC-19 CHG/VER: 0/0
APPENDIX “M”
TGI MATERIAL LIST
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
STRL IN 7-68-2-Q AY A 0 0
CU PHASE TITLE:
F/O - REPAIR AND PRESERVE STRUCTURAL MEMBER IN 7-68-2-Q
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV
JOB ORDER: KEY OP:
3819P14212 A01
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
001 M PLATE,ME, ORDER FOR KTR
ORIG: C231B, H.TANAKA, 243-
SIZE: 2FT X 3FT
9B 9515 001533184 NA 4 N 41135184 6/SF
002 M SHEET,METAL, ORDER FOR
KTR
ORIG: C231B, H. TANAKA, 243-
9B 9515 015087795 NA 4 N 41135187 1/SH
003 M INSULATI, ORDER FOR KTR
ORIG: C231B, H.TANAKA, 243-
9Q 5640 008096312 NA 4 N 41135188 10/EA
004 M TAPE,TEX, ORDER FOR KTR
ORIG: C231B, H. TANAKA, 243-
9B 8315 002671632 NA 4 N 41135189 1/RO
005 M TAPE,TEX, ORDER FOR KTR
ORIG: C231B, H. TANAKA, 243-
9B 8315 002671633 NA 4 N 41135190 1/RO
006 M ADHESIVE, ORDER FOR KTR
ORIG: C231B, H.TANAKA, 243-
9B 8040 002738708 NA 4 Y 41135192 1/GL
007 M CAP,SNAP, ORDER FOR KTR
ORIG: C231B, H.TANAKA, 243-
9B 5325 007377648 NA 4 N 41135193
100/EA
NOTES:
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR APPENDIX "D"
DEFICIENCY FORM
☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One)
2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
LCC-19 STRL IN 7-68-2-Q AY A 0
4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:
3819P14212 A01
7. DESCRIPTION:
8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
9. CORRECTIVE ACTION:
10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
FOR NON-NUCLEAR USE ONLY
11. RFD/RFW REQ’D ☐ LAR REQ'D ☐
ILS MOD REQ’D ☐
SRD/PLAN REV REQ'D ☐
DWG NO.: _____________________ S/A NO.: ___________________
12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:
SATISFACTORY:
13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
YES ☐ NO ☐
14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE:
15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
_________:YES ☐ NO ☐
16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE (DR ONLY)
DL’s ISSUED
(DR ONLY)
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
LCC-19 STRL IN 7-68-2-Q AY A 0
SKETCH
ENCLOSURE-01 SHEET 1 OF 13819P14212A01
Location for Preservation Work of OVHD Plating in 7‐68‐2‐Q
Located from WT BHD 68 to 60” AFT and from the INBD LONG BHD (Positioned 60” Port of Centerline) to 36” OTBD.
FR 68
ELEVATION 1-A
LKG FWD
PLAN VIEW
FR 65 - FR 73
‐ Preservation area
LEGEND
Sprinkler Maintenance Room (7‐68‐2‐Q)
60”
36”