Annex 1604000 C Wastewater Rev 2 13 JUN.docx

DOCX document 36 KB Posted

Attached to
Operation & Maintenance of the Southern and Northern Regional Tertiary Treatment Plants on MCB Camp Pendleton
Solicitation number
N6247319R0033
Issued by

View the file

Other files

File Type Posted
Amendment 0005_N6247320R0033.pdf PDF
AMENDMENT 0004.pdf PDF
Amendment 0003_N6247320R0033.pdf PDF
P-1046B Construction Plans 04-05-2016.pdf PDF
RW_Overall.pdf PDF
EXHIBIT D REVISED _ Safety Data & Narrative.docx DOCX document
SRTTP & NRTTP Chemical Usage 2017 & 2018.xlsx XLSX spreadsheet
RWPS Electrical Equipment List.xlsx XLSX spreadsheet
Amendment 0002_N6247320R0033.pdf PDF
ELIN Pricing Schedule REVISED.xls XLS spreadsheet
EXHIBIT B REVISED _ Recent Relevant Experience of the Firm.docx DOCX document
RWPS Equipment List.xlsx XLSX spreadsheet
Rules and Regs Final_Signed April 2013 Edition.pdf PDF
SierraOne Equipment List.xlsx XLSX spreadsheet
Amendment 0001_N6247320R0033.pdf PDF
Annex 0200000 C Management and Administration (SW SubKtr Safety) Revision 13 JUN.docx DOCX document
Annex 1503030 J Integrated Solid Waste Management v2.2.doc DOC document
ELINS Unpopulated.xls XLS spreadsheet
Annex 1503020 C Pest Control v2.3.docx DOCX document
NRTTP Equipment List.xlsx XLSX spreadsheet
SRTTP Equipment List.xlsx XLSX spreadsheet
EXHIBIT F _ Individual Small Business Subcontracting Plan.docx DOCX document
SRTTP EquipmentList_OM.xls XLS spreadsheet
SRTTP-NRTTP LOADINGS.XLSX XLSX spreadsheet
Annex 1503020 F Pest Control v2.3.doc DOC document
SRTTP Electrical Equipment List.xlsx XLSX spreadsheet
EXHIBIT D _ Safety Data & Narrative.docx DOCX document
Annex 1503010 F Custodial v2.3.doc DOC document
EXHIBIT B _ Recent Relevant Experience of the Firm.docx DOCX document
Annex 1503010 C Custodial v2.3 ck.doc DOC document
EXHIBIT G _ Request for Information (RFI).docx DOCX document
Section J Documents Exhibits & other Attachments Annex 0200000 J Management and Administration ver 2 5.doc DOC document
Annex 0100000 C General Information ver 2.2 (revised 040715).doc DOC document
EXHIBIT A _ Financial Questionnaire.docx DOCX document
NRTTP Electrical Equipment List.xlsx XLSX spreadsheet
SCA Wage Determination 16 SEP 19 .pdf PDF
Annex 1503050 C Grounds Maint & Landscaping v2.5.doc DOC document
EXHIBIT C _ Technical Capability (1).docx DOCX document
Annex 1604000 F Wastewater Ver 2.2.doc DOC document
EXHIBIT E _ Past Performance Questionnaire (Form PPQ).docx DOCX document
Annex 1503050 F Grounds Maint & Landscaping v2.3.doc DOC document
Annex 1503020 J Pest Control v2.4.docx DOCX document
NRTTP Boundary Map.pdf PDF
SRTTP Compliance Equipment List.xlsx XLSX spreadsheet
Annex 1503050 J Grounds Maint & Landscaping v2.6.docx DOCX document
Section F Deliveries or Performance Annex 0200000 F Management and Administration v2.8 (revised 12-6-2018).docx DOCX document
SRTTP Boundary Map.pdf PDF
Annex 1503010 J Custodial v2.3.doc DOC document
Annex 1503030 F Integrated Solid Waste Management v2.3.doc DOC document
Annex 1503030 C Integrated Solid Waste Management v2.3.doc DOC document
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ANNEX 1604000

WASTEWATER

SECTION C

1604000 - Wastewater

Table of Contents

Spec Item
Title
1
General Information
1.1
Concept of Operations
2
Management and Administration
2.1
Definitions and Acronyms
2.2
Personnel
2.2.1
Certification, Training and Licensing
2.3
Special Requirements
2.3.1
Fees, Fines, and Penalties
2.4
References and Technical Documents
3
Recurring Work
3.1
Operation
3.1.1
Wastewater Effluent Quality
3.1.2
Minimum Operator Attendance
3.1.3
Operating Records, Logs, and Reports
3.2
Preventive Maintenance
3.2.1
Sewage Pipelines N/A
3.2.2
Manholes N/A
3.2.3
Wet Wells
3.2.4
Wastewater Instrumentation Systems
3.2.5
Sewage Sump Pumps
3.2.6
Ocean Outfall Pump Station
3.3
Integrated Maintenance Program
3.3.1
Wastewater Treatment Plant
3.4
Inspection Program
3.4.1
Sewage Collection Pipelines N/A
3.4.2
Manhole
3.4.3
Wet Well
3.5
Other Recurring Services
3.5.1
Cleaning of Sewer Pipeline N/A
3.5.2
Wet Well Services
3.5.2.1
Wet Well Pumping N/A
3.5.2.2
Wet Well Cleaning
4
Non-Recurring Work

1604000 - Wastewater

Spec Item
Title
Description
1
General Information
The Contractor shall provide all labor, management, supervision, tools, material, and equipment to continuously operate, maintain, and repair the Southern & Northern Regional Tertiary Treatment Plants (SRTTP & NRTTP) located in Areas 20 and 52, at MCB Camp Pendleton, CA.
1.1
Concept of Operations
The intent of 1604000 Wastewater is to specify the requirements to provide Wastewater utilities. Included are services such as operating, maintaining and repairing the Wastewater treatment plant and collection system.

The following services are not included in this Template:

· The point of demarcation is where the wastewater exits the building. All components prior to this point of demarcation are considered part of the facility and are included in 1502000, Facilities Investment.

· Repairs to the facilities (building structures) and trouble call response for Wastewater are included in 1502000 Facilities Investment.

1604000 - Wastewater

Spec Item
Title
Description
2
Management and Administration
2.1
Definitions and Acronyms
Definitions and Acronyms are listed in J-1604000-01.
2.2
Personnel
The Contractor shall provide personnel with the qualifications, technical knowledge, experience and skills required to efficiently operate, maintain and repair the Wastewater Treatment Plant and Collection System.
2.2.1
Certification, Training and Licensing
The Contractor shall employ certified wastewater treatment plant operators who are experienced in similar plants and systems to perform the requirements of this functional section.

Each Wastewater Treatment Plant Operator must possess or have received through reciprocity a current/valid operator's certificate issued by the Wastewater Works Operators Certification Board of Examiners from the State of California. The Chief Plant Operator, shift supervisors, and operators shall meet requirements of Title 23, Division 3, Chapter 26 classification requirements of the California Code of Regulations. At a minimum, a Grade IV Chief Plant Operator is required and will be responsible for overall operation of the wastewater treatment plants.

The chemist and the laboratory analyst shall complete yearly training in order to keep the personnel updated with the latest local and Federal environmental regulations, public health concerns, laboratory procedures, and safety requirements.

2.3
Special Requirements
Safety requirements, operational restrictions, coordination requirements, workmanship, materials, equipment, and tools. Add additional 2.3.X Spec Items as required.
2.3.1
Fees, Fines, and Penalties
The Contractor shall be responsible for all fees, fines, and penalties assessed by the State if discharge permits are violated in the course of operations or maintenance.
2.4
References and Technical Documents
References and Technical Documents are listed in J-1604000-01.

1604000 - Wastewater

Spec Item
Title
Performance Objective
Related Information
Performance Standard
3
Recurring Work
The Contractor shall efficiently operate and maintain the wastewater treatment plant and collection system to safely collect, treat and dispose of wastewater to ensure all sewage requirements are continually met.

The current Wastewater Treatment Plant and Reclaim System Description and Inventory is provided in J-1604000-03.

The Contractor shall shut-down, restart, and perform operational checks on all equipment affected by both scheduled and unscheduled utility outages at no additional cost to the Government.

The Contractor shall be responsible for managing and controlling traffic issues resultant from sewage system work in a safe manner at all times.

Comply with traffic control requirements in the Camp Pendleton Requirements. Typically, a 21 calendar day review period is required prior for approval.

The Contractor shall develop and submit a Critical Spare Parts Inventory per Section F and shall maintain on hand the critical spare parts required to keep the entire system in continuous service. The Historical Critical Spare Parts Inventory can be found in J-1604000-04.

Sewage is continuously and safely collected, treated and disposed.

Effluent complies with the regulatory discharge permit.

No spills are the result of Contractor negligence.

3.1
Operation
The Contractor shall operate the wastewater treatment plant to efficiently and safely collect, treat and dispose of wastewater such that the effluent complies with the regulatory discharge permit 24 hours per day, seven days per week, throughout the contract period.
Operation consists of “watch-standing” or attendance type work by a sufficient staff of qualified persons during a specified time period to collect, treat and dispose of the measurable quantities and quality of effluent to ensure safe, reliable, efficient collection, treatment and disposal of wastewater.

Operation of wastewater treatment plant includes equipment and system components, such as, sewage holding tanks, lift stations, pumps, screens, oil/water separators, filters, chemical and biological treatment, valves and automatic controls, and tasks, such as, monitoring and regulation of equipment controls, maintaining operating records, logs, and reports, and examination, lubrication and minor adjustment of equipment and system components.

The Contractor shall ensure plant and system configuration drawings or diagrams are created and kept current.

Plant and systems components shall be efficiently and safely operated per ANSI and AWWA Standards, OMSI and other specific operating manuals, procedures, and instructions; however, avoid specifying process.

Safe operation shall ensure that all wastewater treatment plant equipment requiring operator attendance is staffed by qualified personnel at all times of operation. The KO shall be notified immediately if unsafe conditions are discovered.

The sewage treatment plant shall be operated 24 hours a day and staffed onsite 8 hours a day.

The Contractor shall provide the required chemicals to operate the Plants (hypochlorite, methanol, alum, & etc.)

MCB CAMPEN will conduct all sampling of wastewater and sludge, analytical testing, and reporting for Permit compliance. The contractor is responsible for process control sampling. The contractor will be required to validate the flow-weighted signal to the auto samplers at all compliance sites once per year.

Standard Operating Procedures shall be submitted in accordance with Section F. One hard copy of the current Standard Operating Procedures, operating records, logs, reports, and procedures shall be available on site at all times.

The average volume of wastewater processed is two million gallons per day at the SRTTP and 0.5 million gallons per day at NRTTP. Historical Chemical and Material Usage is provided in J-1604000-05.

Plant and equipment and components are efficiently, safely and continuously operated per specified operating criteria to collect, treat and dispose of wastewater and effluent complies with the regulatory discharge permit.

Unscheduled interruptions are minimized such that collection demand and effluent quality requirements are met 99.9 percent of the time annually.

3.1.1
Wastewater Effluent Quality
The Contractor shall produce treated wastewater effluent that complies with the regulatory discharge permit.
Wastewater effluent quality shall meet all Federal, state and local authorities’ regulations, certifications and requirements.

Wastewater effluent quality shall comply with NPDES Order No. R9-2013-0112 (currently being revised) and MRP Order No. R9-2018-0023

Sampling and analysis conducted by the contractor shall be for process control. Compliance sampling and analysis will be conducted by the Government.

If wastewater chemistry is confirmed, through independent laboratory analyses, to not be in compliance with quality standards, the Contractor shall immediately notify the DGA and adjust the wastewater chemistry within one days to meet all regulatory and discharge permit requirements.

Laboratory Analysis of Wastewater Effluent Reports shall be submitted per Section F.

Wastewater effluent complies with the regulatory discharge permit.

3.1.2
Minimum Operator Attendance
The Contractor shall provide wastewater treatment certified plant operators and support personnel in sufficient quantities of staffing per shift to efficiently and safely operate equipment at all times of operation.
All personnel operating the plant shall meet the training and certification standards in Spec Item 2.2.1.

Contractor shall submit a Schedule of Operator Attendance per Section F.

The minimum numbers and types of wastewater treatment plant operators, support personnel, and supervisory operators in direct responsible charge, shall comply, by each applicable shift, with NPDES Order No. R9-2013-0112 (currently being revised) and MRP Order No. R9-2018-0023.

3.1.3
Operating Records, Logs, Permits, and Reports
The Contractor shall prepare, submit and maintain operating records, logs and reports for in-process tracking of plant output characteristics to ensure records, logs, and reports are current and complete.

The Contractor shall develop and update operating procedures to ensure operating processes and Plant and Systems configuration are current.

Per approved operating permit, LANTNAVFACENGCOMINST 11300.4, DoD FGS, or local installation instruction, a monthly Operating Records Report shall be submitted to the KO within three days following the end of the month during which work is performed and shall include copies of daily operating logs, chemical content, pressure readings, chemical dosages, filter backwash frequencies, flow rates, and other laboratory records, maintenance records, corrosion tests, personnel records, emergency condition records, and operating costs.

The Contractor shall provide all permit requirements in the plant report. (Spill Prevention Plan, Spill response Plan, and Etc.)

All required operating records, logs, and reports are maintained current and complete and applicable copies provided to the KO per Section F.

All required procedures are maintained current and complete.

3.2
Preventive Maintenance (PM) Program
The Contractor shall develop and implement a PM program for wastewater collection and Recycle water systems to ensure proper operation, to minimize breakdowns, to maximize useful life and meet all applicable discharge permit requirements.
The Contractor shall develop and submit a PM program per Section F.

The Contractor is fully responsible for and shall perform any repairs, including replacement, discovered during scheduled maintenance work up to a total of $1000 per occurrence in direct material and labor cost under Recurring portion of the contract. Incidental repairs work performed under maintenance are not considered a trouble call.

Notification of repair work exceeding the incidental repairs limit shall be submitted to the KO within two hours of identification. Trouble calls or Non-Recurring work may be issued for repairs exceeding the incidental repairs limit.

The Contractor shall not use breakdown maintenance as part of the PM program.

The PM program for wastewater systems shall provide economical approach manufacturer’s recommended procedures, OEM standards, NASSCO standards, WEF standards, ASME standards, and maintenance required to satisfy equipment warranties and keep wastewater systems in normal working condition and in compliance with the discharge permit requirements.

Excessive or repeated system or equipment breakdowns or deficiencies may indicate the need to adjust or modify the Contractor’s PM program. These changes will be made at no additional cost to the Government.

If the KO determines that the objective and standards are not met, the Contractor shall adjust or modify the Contractor’s PM program at no additional cost to the Government.

The PM program inventories are listed in the Wastewater Treatment Plant and Collection System Description and Inventory as provided in J-1604000-03.

The Contractor shall submit a Monthly PM Work Schedule per Section F.

Maintenance is accomplished in accordance with the Contractor’s maintenance program plan and work schedule.

PM is performed in accordance with manufacturers’ recommended procedures, OEM standards, ASME, WEF, and NASSCO.

Unscheduled interruptions are minimized such that collection demand and effluent quality requirements are met 99 percent of the time annually.

NPDES and MRP discharge permit requirements are meet.

3.2.1
Sewage Pipeline
N/A
N/A
N/A
3.2.2
Manholes
N/A
N/A
N/A
3.2.3
Wet Wells
The Contractor shall maintain wet wells within the Plants boundaries to ensure system integrity and extend the operational life of the wet well.
The Contractor shall repair all concrete spalling, perform repair, and install a complete epoxy coating of the wet well.

The Contractor shall submit Pre-repair and Post- Repair Reports on Wet Wells in accordance with NASSCO standards per Section F.

All work is performed in accordance with the Contractor’s maintenance program plan and work schedule.

The wet well shall be fully restored and repaired to meet the latest ASME and NASSCO standards.

3.2.4
Wastewater Instrumentation Systems

The Contractor shall maintain wastewater instrumentation systems to ensure proper operation, to minimize breakdowns, and to maximize useful life.

The contractor shall maintain the Industrial Control System (ICS) to ensure proper operation, to minimize breakdowns, and to maximize useful life.

The Contractor shall be responsible for ensuring all equipment and components of the instrumentation system are maintained; all sensors operate correctly, all controller elements receive signals properly, and the PLC is in optimum working order. The contractor shall be responsible for ensuring all equipment and components of the ICS are maintained. The contractor will be required to maintain an ISP connection to allow for remote connectivity and alarms while the plant in not manned.

The Contractor will be responsible to maintain and update ICS with all patches, and upgrades with software licenses.

The contractor is required to maintain operational the radio communication system for the operation of offsite facilities. This includes radio repeaters, power, and associated appurtenances. Offsite locations include Gooseneck Lake pump station, Horse Lake pump station, Lemon Grove pump station, Reservoir 16151, Ysidora Flats reservoirs, AWT brine valve, and radio pathways to SRTTP. Offsite locations include 52 Area recycled water reservoir and radio pathways to NRTTP.

The Contractor is responsible for maintaining the RTU when it is an integrated component of the PLC.

All repairs and replacements shall be performed per AWWA, ANSI, and NFPA Standards, OMSI, equipment manufacturer’s recommendations.

All work is performed in accordance with the Contractor’s maintenance program plan and work schedule.

Wastewater instrumentation system maintenance program meets the latest ASME, NASSCO standards, manufacturer’s recommended procedures and OEM standards.

3.2.5
Sewage Sump Pumps
The Contractor shall maintain sewage sump pumps to ensure proper operation, to minimize breakdowns, and to maximize useful life.
The Contractor personnel working on sump pumps must possess applicable state and local licensing/certification requirements.

Sump pump operator maintenance shall be performed in accordance with applicable federal, state and local statutes and regulations, and with DoD policies, instructions and guidance.

All work is performed in accordance with the Contractor’s maintenance program plan and work schedule.

Sump pump operator maintenance program meets manufacturer’s recommended procedures and OEM standards.

3.2.6
Ocean Outfall Pump Station
The Contractor shall maintain the South Regional Tertiary Treatment Plants (SRTTP) Oceanside Ocean Outfall Pump Station. (OOOPS)
The Contractor shall be responsible for ensuring all equipment and components of the lift station and associated appurtenances are maintained and functional to the Camp Pendleton/City of Oceanside boundary.

The system is inclusive of the components, appurtenances, and supporting systems that make a fully functioning system.

Monitoring of alarms will be required and communication to the control room maintained at all times.

All work is performed in accordance with OEM standards and recommended procedures.

3.2.7
Reclaimed Water and Recycle Water Use Systems
The contractor shall optimize the delivery, application, and consumption of reclaimed water to further the goal of MCB CAMPEN to

maximize the use of reclaimed water.

Monthly reports and an annual summary shall be submitted to MCB CAMPEN via the FEAD accounting for all reclaimed water (flow and volume) to each use site (daily, monthly, and annual basis) and all site maintenance and management activities performed. The contractor will coordinate the delivery of reclaimed water (timing, flow, and volume) with MCB CAMPEN.

All pipelines, sprinkler systems, runoff control, turf and vegetation, and access for the Horse Pasture. (Other areas are managed by MCB Camp Pendleton). Refer to record and construction drawings for more detail.

The Contractor shall maintain they systems to a fully functional and operable condition in accordance to guideline and standards established by MCB Camp Pendleton

3.3
Integrated Maintenance Program (IMP)
The Contractor shall develop and implement an IMP for the wastewater treatment plant to ensure all equipment and components remain in optimum condition and sustain maximum life
The Contractor shall develop and submit an IMP per Section F.

The IMP shall include the Contractor’s approach for integrated maintenance, including maintenance and inspection tasks, schedules for planned work accomplishment, plan for minimizing occurrence of repair and downtime, process for the identification of the need for repairs, and the process for scheduling and completing repair work.

IMP, inclusive of repair and replacement, shall be performed per ASME and NASSCO standards, and equipment manufacturer's recommendations and commercially accepted practices.

All plant and system malfunctions and breakdowns requiring repair or replacement shall have immediate response within one hour following Contractor discovery or Government notification and worked continuously to completion.

As part of the IMP, the Contractor has full responsibility for any individual occurrence of repair, including replacement, up to and including $10,000 in direct material and labor cost. The Contractor shall, per Annex 2, notify the KO upon identification that the repair will exceed the liability limit listed above. If the estimated cost of the repair exceeds the Recurring liability limit, the Government may order the work under the Non-Recurring section of this contract; however, the Government will only be liable for the amount of cost exceeding the Recurring liability limit. Additionally, the Government may perform Non-recurring work by Camp Pendleton Government Staff.

The Contractor shall perform all repairs, whether identified as part of their routine IMP accomplishment, QC inspections, or notification from the Government that a breakdown or malfunction has occurred.

If the Government identifies a problem or a need for repair, the Government will contact the work reception desk. Service trouble calls will not be issued for accomplishment of repairs on systems and equipment maintained under IMP.

The Contractor shall submit a Monthly IMP Schedule and IMP Maintenance and Repair Status Report per Section F.

The IMP inventories are listed in the Wastewater Treatment Plant and System Inventory as provided in J-1604000-03.

Maintenance is performed in accordance with the Contractor's IMP and work schedule.

The wastewater treatment plant is maintained and repaired to sustain a fully functional and operable condition in accordance with ASME, WEF, NASSCO, and OEM specifications.

Unscheduled interruptions are minimized such that collection demand and effluent quality requirements are met 99.9 percent of the time annually.

NPDES discharge permit requirements are met.

When repair is complete the facility, system, or equipment does not present any hazard or danger to personnel.

3.3.1
Wastewater Treatment Plant
The Contractor shall maintain the wastewater treatment plant to ensure proper operation, to minimize breakdowns, to maximize useful life, and meet all applicable discharge permit requirements.
The Maintenance shall include all equipment and components of the wastewater treatment plant such as, sewage holding tanks, lift stations, pumps, screens, oil/water separators, filters, chemical treatment, valves, automatic controls, plant and collection system piping, manholes, backflow service, flow meter service, electrical service, vactor service, solar panel cleaning, instrumentation, HVAC, septic tanks, and vector control within the boundaries of the Plants.

Contractor shall submit a Schedule to Replace Expendable Components, such as filters and chemicals, of the wastewater treatment plant per Section F.

Maintenance is performed per Contractor's IMP and work schedule.

Maintenance of the sewage treatment plant is performed in accordance with manufacturers’ recommended procedures and ASME, WEF, NASSCO, and OEM standards.

NPDES discharge permit requirements are meet.

3.4
Inspection Program
The Contractor shall develop and implement an inspection program for sewer systems to ensure a complete assessment of condition in a timely manner.
The Contractor shall develop an inspection program for sewer systems. The Contractor shall submit the Inspection Program and Schedule per Section F.

Inspection is performed in accordance with ASME, WEF, NASSCO, and OEM standards.

Inspections are performed per the Contractor’s inspection program and work schedule.

All photographs and video footage shall be of a quality capable of showing all damage and defects clearly.

3.4.1
Sewage Collection Pipelines
N/A
N/A
N/A
3.4.2
Manholes
The Contractor shall inspect manholes to ensure a complete assessment of condition in a timely manner.
Contractor shall submit Manhole Reports per Section F providing recommendations for correction of any observed issues.
Inspection performed, recorded, and reported in compliance with the latest MACP standards and ASME guidance.
3.4.3
Wet Wells
The Contractor shall inspect wet wells to ensure a complete assessment of condition in a timely manner.
Contractor shall submit Wet Well Reports per Section F providing recommendations for correction of any observed issues.
Inspection performed, recorded, and reported in compliance with the latest NASSCO standards and ASME guidance.
3.5
Other Recurring Services

The Contractor shall perform other recurring services for sewer systems and equipment to ensure they are fully functional and operational.

Systems and equipment are in an operable condition and function properly in accordance with specified standards.

Other recurring services are completed in a timely manner.

3.5.1
Cleaning of Sewer Pipeline
N/A
N/A
N/A
3.5.2
Wet Well Services
The Contractor shall clean and pump wet wells within in the Plants boundaries to ensure proper operations and prepare wet wells for inspection and maintenance.
The Contractor shall submit a Schedule of Wet Well Services per Section F.

Services are completed per the Contractor’s schedule.

No spills as the result of Contractor operations.

Wet wells are in normal working condition.

3.5.2.1
Wet Well Pumping
N/A
N/A
N/A
3.5.2.2
Wet Well Cleaning
The Contractor shall clean wet wells within in the Plants boundaries to ensure all waste and debris is fully removed from wet well surface and equipment.
The Contractor shall remove all run-off liquid from the cleaning of the wet well.

The Contractor shall prepare and submit a Wet Well Cleaning Report per Section F.

All surfaces and equipment are free of waste and debris.

3.5.3
Equipment Condition Report (ECR)
The Contractor shall create an Equipment Condition Report
The Contractor shall perform an initial Equipment Conditions Report assessment of all systems and equipment and system components identified herein, including the Industrial Control System

The ECR shall be submitted within 60 days after award and conducted during the Phase-in of the contract.

The ECR shall include an individualized quote for necessary repairs, to include itemizing all material, parts, labor hours, estimated timeline of remaining useful life of the equipment using UPL Non-recurring work labor rates and awarded rates.

1604000 - Wastewater

Spec Item
Title
Performance Objective
Related Information
Performance Standard
4
Non-Recurring Work
Non-Recurring work may be ordered utilizing DoD EMALL in accordance with Section H or on a task order in accordance with the PROCEDURES FOR ISSUING ORDERS clause in Section G. The order will specify the exact locations and types of work to be accomplished. The period of performance will be specified in each order.
Refer to Non-Recurring ELINs for task listings, descriptions and related requirements. All periods of performance are measured from issue date of order to acceptance of the work. Performance Standards for Non-Recurring work will be the same as those in Spec Item 3 where applicable.

File details come from the government source that posted it. Updated .