Amendment 0002_N6247320R0033.pdf

PDF 209 KB Posted

Attached to
Operation & Maintenance of the Southern and Northern Regional Tertiary Treatment Plants on MCB Camp Pendleton
Solicitation number
N6247319R0033
Issued by

View the file

Other files

File Type Posted
Amendment 0005_N6247320R0033.pdf PDF
AMENDMENT 0004.pdf PDF
Amendment 0003_N6247320R0033.pdf PDF
P-1046B Construction Plans 04-05-2016.pdf PDF
RW_Overall.pdf PDF
EXHIBIT D REVISED _ Safety Data & Narrative.docx DOCX document
SRTTP & NRTTP Chemical Usage 2017 & 2018.xlsx XLSX spreadsheet
RWPS Electrical Equipment List.xlsx XLSX spreadsheet
ELIN Pricing Schedule REVISED.xls XLS spreadsheet
EXHIBIT B REVISED _ Recent Relevant Experience of the Firm.docx DOCX document
RWPS Equipment List.xlsx XLSX spreadsheet
Rules and Regs Final_Signed April 2013 Edition.pdf PDF
SierraOne Equipment List.xlsx XLSX spreadsheet
Amendment 0001_N6247320R0033.pdf PDF
Annex 0200000 C Management and Administration (SW SubKtr Safety) Revision 13 JUN.docx DOCX document
Annex 1503030 J Integrated Solid Waste Management v2.2.doc DOC document
ELINS Unpopulated.xls XLS spreadsheet
Annex 1503020 C Pest Control v2.3.docx DOCX document
NRTTP Equipment List.xlsx XLSX spreadsheet
SRTTP Equipment List.xlsx XLSX spreadsheet
EXHIBIT F _ Individual Small Business Subcontracting Plan.docx DOCX document
SRTTP EquipmentList_OM.xls XLS spreadsheet
SRTTP-NRTTP LOADINGS.XLSX XLSX spreadsheet
Annex 1503020 F Pest Control v2.3.doc DOC document
SRTTP Electrical Equipment List.xlsx XLSX spreadsheet
EXHIBIT D _ Safety Data & Narrative.docx DOCX document
Annex 1503010 F Custodial v2.3.doc DOC document
EXHIBIT B _ Recent Relevant Experience of the Firm.docx DOCX document
Annex 1503010 C Custodial v2.3 ck.doc DOC document
EXHIBIT G _ Request for Information (RFI).docx DOCX document
Section J Documents Exhibits & other Attachments Annex 0200000 J Management and Administration ver 2 5.doc DOC document
Annex 0100000 C General Information ver 2.2 (revised 040715).doc DOC document
EXHIBIT A _ Financial Questionnaire.docx DOCX document
NRTTP Electrical Equipment List.xlsx XLSX spreadsheet
SCA Wage Determination 16 SEP 19 .pdf PDF
Annex 1503050 C Grounds Maint & Landscaping v2.5.doc DOC document
EXHIBIT C _ Technical Capability (1).docx DOCX document
Annex 1604000 F Wastewater Ver 2.2.doc DOC document
Annex 1604000 C Wastewater Rev 2 13 JUN.docx DOCX document
EXHIBIT E _ Past Performance Questionnaire (Form PPQ).docx DOCX document
Annex 1503050 F Grounds Maint & Landscaping v2.3.doc DOC document
Annex 1503020 J Pest Control v2.4.docx DOCX document
NRTTP Boundary Map.pdf PDF
SRTTP Compliance Equipment List.xlsx XLSX spreadsheet
Annex 1503050 J Grounds Maint & Landscaping v2.6.docx DOCX document
Section F Deliveries or Performance Annex 0200000 F Management and Administration v2.8 (revised 12-6-2018).docx DOCX document
SRTTP Boundary Map.pdf PDF
Annex 1503010 J Custodial v2.3.doc DOC document
Annex 1503030 F Integrated Solid Waste Management v2.3.doc DOC document
Annex 1503030 C Integrated Solid Waste Management v2.3.doc DOC document
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The Purpose of this Amendment 0002 is to extend the proposal due date, provide revised Exhibits and Attachment, include additional Attachments, and respond to Requests for Information (RFIs).

1. CONTRACT ID CODE PAGE OF PAGES

1 14

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Jan-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6247320R0033

X 9B. DATED (SEE ITEM 11)

12-Dec-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Jan-2020

CODE

NAVFAC SOUTHWEST

CAMP PENDLETON FEAD/CODE ROPCN

MARINE CORPS BASE CAMP PENDLETON

PO BOX 555229 BLDG 22101

CAMP PENDLETON CA 92055-5229

N62473 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6247320R0033

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0002

AMENDMENT 0002

The Purpose of this Amendment 0002 is to extend the proposal due date, provide revised Exhibits and Attachment, include additional Attachments, and respond to Requests for Information, as follows:

1) The proposal due date has been extended from January 13, 2020 to January 24, 2020 at 2:00 pm Pacific Standard

Time (PST).

2) The following Exhibits and Attachment have been revised:

Exhibit B Exhibit D ELIN Pricing Schedule

3) The following Attachments have been added:

RWPS Electrical Equipment List RWPS Equipment List SierraOne Equipment List SRTTP & NRTTP Chemical Usage 2017 & 2018 DO_0007-P110_Rec Dwgs_Rev 2 090911 & Rev 3_100331 P-1046B Construction Plans 04-05-2016 Rule and Regs Final _ Signed April 2013 Edition RW _ Overall

4) The following are Responses to Requests for Information:

Question #1: The SF 1449 Block 6 has a solicitation issue date of 06-Dec-2019 and in Block 8 an Offer due date/local time of 12:00 PM 06 Jan 2020. However, Beta.sam.gov has a solicitation issue date of 12 Dec at 9:41 PM and a due date of 13 January 2020 at 12 PM PST, which appears to have been modified to 13 December at 6:39 AM PST. Please clarify due date.

Response #1: Please reference Amendment 0001. Amendment 0001 was issued to provide clarification of the solicitation issuance date and the proposal due date. This Amendment 0002 extends the proposal due date.

Question #2: On page 13 of 26, Factor 1 indicates (i) Submit a minimum of one and a maximum of two relevant projects on Exhibit B. However, the instructions at the top of Exhibit B says "… may submit a minimum of two and maximum of five …". The Evaluation Criteria on page 14 paragraph (vi) states that the Government will only review two projects. Please confirm.

Response #2: The Government will only review a maximum of two (2) projects from each offeror. Please see REVISED Exhibit B.

Question #3: Page 13 of 26, paragraph (ii), subparagraph 6) requires demonstrated experience in Annex 1604000 Wastewater. However, Annex 1604000 is nowhere to be found on Exhibit B. Please provide a new Exhibit B with Annex 1604000 listed as one of the annexes for which we are to provide a description of services.

Response #3: Please see REVISED Exhibit B.

Question #4: Exhibit B includes annexes that don't seem to be applicable (e.g., Annex 0700000 - Ordnance) and is missing applicable annexes (e.g., Annex 1604000 Wastewater). Please provide corrected Exhibit B.

Response #4: Please see REVISED Exhibit B.

Question #5: Exhibit B includes a table requiring total contract price for several annexes, and two columns for $ self-performed and % self-performed. Are we to segregate costs by each annex as a portion of the total contract value for O&M work?

Response #5: Yes, contract price and self-performance amounts (% and $) must be identified by each relevant annex or as other work. Paragraph 11 provides instructions on completing the table.

Question #6: Please clarify if we are to include only FAR Clause 52.212-3, or the entire Online Representations and Certifications.

Response #6: Please include a copy of the Online Representations and Certifications from the SAM, at the following website: www.sam.gov , as well as all completed applicable sections of the FAR Clause 52.212-3, Offeror Representations and Certifications – Commercial Items (Mar 2015).

Question #7: Page 11, Tab #6 outlines the Small Business participation goals. Please confirm the percentage goals only apply to the work to be subcontracted.

Response #7: Page 11, Tab #6 references NAVFAC’s command-wide small business subcontracting targets.

Question #8: The SCA Wage Determination is dated 16 SEP 19. Will NAVFAC provide the most current SCA Wage Determination?

Response #8: The most current SCA Wage Determination at the time of the Solicitation was Wage Determination No.: 2015-5636, Revision No,: 11, with a Date of Last Revision of 09/16/2019.

Question #9: The instructions in the RFP for Exhibit D (page 15 of 26) says that the Safety Narrative shall be limited to four (4) pages. However, the text on the form for question 7 says that the Safety Narrative shall not exceed two (2) pages. Please clarify.

Response #9: The safety narrative shall be limited to four (4) 8.5” x 11” pages. Please see REVISED Exhibit D.

Question #10: Please clarify that the font size for Factor 2, Exhibit C is 12-Point Times New Roman, while the remainder of the document can be either 10 or 12 point.

Response #10: Page 4 of 26 of the RFP provides that the font size requirement for proposals shall be 10 or 12 point.

All other required submittals should follow the requirements for said submittals.

Question #11: The RFP (page 13 of 26) indicates that the project experience contract must be 50% complete, whereas Exhibit B requires 100% complete. Please confirm 50% complete is correct.

Response #11: Pursuant to Factor 1 – Recent Relevant Experience of the Firm subparagraph 2), a relevant project is defined as at least 50% complete in terms of amount paid for contract performance.

Question #12: Factor 1 of the RFP states that project experience must have been "awarded within the last five (5) years prior to the initial solicitation issuance date;". Operations & Maintenance contracts typically run anywhere from 5 - 20 years in duration (from award through options years). We respectfully request the Government revise this to state "awarded within last ten (10) years."

Response #12: A response will be forthcoming.

Question #13: Please confirm contractor must obtain and maintain Air Pollution Control District (APCD) permits on required equipment (generators, heavy equipment) at both plants.

Response #13: Confirmed. All required APCD permits must be obtained and maintained for both plants by the contractor. The contractor shall coordinate submittal of all required permits through the Government.

Question #14: Please confirm contractors must file an official report to the Base within 2 hours (short form) and 24 hours (long form) of any discharge or spill.

Response #14: Follow spill reporting requirements per the State issued permits. Additionally, the following reporting requirements must be followed:

• The contractor must contact the Unity room and/or Base wastewater operations as soon as the spill has been identified.

• If a facility operated under this contract causes a spill, a short form spill notification will be required to the Base within 2 hours if identified as a Category 1 spill and greater than 1,000 gallons has spilled and has the potential to reach a surface water.

• If a facility operated under this contract causes a spill not meeting the previous requirement, a short form spill notification form will be required within 24 hours.

• A long form spill notification form will be required within 24 hours of the end of any spill event.

Question #15: Please confirm contractor must maintain the regulated pressure devices on backflow preventers on Base fire hydrants.

Response #15: Confirmed. Approval to use backflow devices on any hydrant must be approved by the Government prior to use. If backflow devices are installed, the contractor is responsible for maintaining and providing certification reports to the Government.

Question #16: Please confirm contractor must use a certified electrician for any and all repairs of electrical equipment including the solar panels, over 50 V.

Response #16: Confirmed. The contractor must use a certified electrician for any and all repairs of electrical equipment over 50 V. NFPA and OSHA standards should be followed.

Question #17: Please confirm contractor is required to have all flow meters and instrumentation inspected and calibrated on an annual basis by a 3rd party agent.

Response #17: Confirmed. All flow meters and instrumentation must be inspected and calibrated on an annual basis by a 3rd party agent to comply with State issued permits.

Question #18: Please confirm contractor is required to have all fire extinguishers filled and inspected on an annual basis by a 3rd party agent.

Response #18: Confirmed. All fire hydrants are to be filled and inspected on an annual basis by a 3rd party agent.

Monthly inspections shall be conducted to comply with NFPA requirements.

Question #19: Please confirm the Chief Plant Operator (CPO) is required to obtain and maintain a Recycled Water Site Supervisor Training Certificate.

Response #19: The contractor will be required to have a person designated on staff to be the Recycled Water Site Supervisor for designated recycled water sites; the designated individual shall obtain and maintain a Recycled Water Site Supervisor Training Certificate. The Base Recycled Water Rules and Regulations provide further requirements of the Recycled Water Site Supervisor. See attached file labeled Rule and Regs Final _ Signed April 2013 Edition.

Question #20: Please confirm contractor is required to obtain and maintain RCRA / DOT Hazardous Materials Training Certificate at all times.

Response #20: Confirmed. The contractor is required to obtain and maintain RCRA/DOT Hazardous Materials Training Certificate at all times.

Question #21: Please confirm the contractor’s staff is required to obtain and maintain a Roadway Work Protection Certification from North County Transit District (NCTD) to perform any work on Air Relief Valves located near the NCTD railroad tracks.

Response #21: Confirmed. A Roadway Work Protection Certification from NCTD is required to perform any work on air relief valves located near NCTD tracks.

Question #22: Please confirm contractor is responsible for implementing the Storm Water Pollution Prevention Plan (SWPPP) and attend annual training.

Response #22: Confirmed. The contractor is responsible for implementing the SWPPP and attending annual training.

Question #23: Please confirm all Above Ground Storage Tanks require maintenance, specialized training, and an annual inspection from the Base as part of this contract.

Response #23: All above ground storage tanks require maintenance, specialized training, and annual inspection conducted by the contractor. Inspections shall be documented and filed for regulatory inspection.

Question #24: Please confirm the contractor’s staff is required to obtain and maintain current Range Safety Training Certificate to perform any work on Air Relief Valves located on the active shooting range.

Response #24: The contractor is required to obtain and maintain current Range Safety Officer Certification for any work performed in a training area or range to comply with the Camp Pendleton Requirements.

Question #25: Will the contractor be responsible for any required upgrades to solar panel remote communications and monitoring system?

Response #25: Any required upgrades outside of normal preventative maintenance work should be submitted as a non-recurring work request.

Question #26: Is the current contractor using Maximo for the CMMS system? Please confirm if the new contract requires data migration and integration into Maximo and that contractors should price that effort.

Response #26: The current contract does not use Maximo for the CMMS system. The new contract requires the data to be migrated and integrated into Maximo.

Question #27: Does O&M include TAPS 1, TAPS 2, TAPS 12, LS 51, Gooseneck Pump Station, and above ground appurtenances and underground piping?

Response #27: The O&M does not include TAPS 1, TAPS 2, TAPS 12, LS 51 or associated appurtenances. The O&M does include Gooseneck Pump Station and associated pipeline and appurtenances.

Question #28: Section refers to operate and maintain a collection system. Please confirm the components of collection system are included in this service contract.

Response #28: The collection system components include the upstream manhole to each plant and any associated pipelines downstream of this point.

Question #29: If all off site lift stations are not included in this contract, will the contractor be responsible for the disconnection of all alarms and remote controls that are presently being used at both the SRTTP and the NRTTP?

Response #29: The alarms and controls to these facilities should remain, but can de disabled at the SCADA system.

Question #30: Lemon Grove Pump Station is not clearly identified in the Boundary Map. Please confirm if Lemon Grove is included in the scope of this contract.

Response #30: Confirmed. Lemon Grove is included in the scope of this contract, and identified on the SRTTP Boundary Map.

Question #31: Does the scope of this contract include emergency response to underground pipeline breaks and repairs for spills? What is the minimum response time required?

Response #31: Pursuant to Spec Item 3.3 – Integrated Maintenance Program (IMP), the scope of this contract does include emergency response, which includes underground pipeline breaks and repairs; the minimum response time required is within one hour following Contractor discovery or Government notification.

Question #32: Does the scope of this contract require repair equipment such as back hoes, dump trucks, graders be maintained at Camp Pendleton for emergency response in the event of pipeline repairs and spills?

Response #32: The contractor is required to make emergency repairs in the event of a pipeline break, failure of equipment, or spill. It is up to the contractor to determine if they need equipment staged at Camp Pendleton to meet emergency services needs.

Question #33: Is the O&M contractor required to retain a full staff of mechanics, electricians, and pipefitters for all emergency repairs and meet minimum response time?

Response #33: This is a performance-based contract; the Performance Work Statement (PWS) does not instruct the contractor how to do the work but instead describes performance objectives, performance standards, and measurable outcomes. Consequently, it is up to the contractor to determine if retention of a full staff of mechanics, electricians, and pipefitters is needed for all emergency repairs to meet the minimum response time.

Question #34: Do all compliance instruments require annual calibration reports from a Third Party? This is a requirement per the NPDES and Master Reclamation Permit.

Response #34: All compliance instruments require annual calibration to comply with State issued permits.

Question #35: Taps 1 & 2 are vital for remote communications with the reclaimed water system. If the contractor is not responsible for these systems, will the contractor be responsible for maintaining the radio communications on these critical links?

Response #35: The contractor is responsible for maintaining the communication system for the recycled water facilities.

Question #36: Do all emergency generators require annual/semi-annual preventative maintenance by a Third Party?

Response #36: All emergency generators require at least annual maintenance to comply with their APCD permit.

Question #37: Does the O&M contractor assume that the minimum requirements for all personnel stationed at either plant (SRTTP and NRTTP) possess a Grade 3 wastewater certificate, (Designated Operator In-Charge), since each facility is rated at Grade 4? Please confirm that all on-call emergency and weekend duty operators must possess a Grade 3 wastewater certificate. Please confirm that any operator providing remote on-call remote support also possess Grade 3 certification.

Response #37: The contractor is required to comply with Title 23 requirements.

Question #38: If a repair exceeds $10,000, what mechanism does the government use to secure funding to reimburse the O&M contractor and what documentation (including back-up, vendor quotes, or competitive bids) is required from the O&M contractor to be reimbursed? What is the typically timeframe from repair to contractor reimbursement?

Response #38: If a repair is expected to exceed $10,000, the contractor must notify the Government representative prior to beginning work. This type of work can be conducted using the non-recurring line item after a modification has been awarded.

Question #39: In the event of an emergency repair over $10,000 that has an immediate impact on process control that will lead to compliance violation, does the O&M contractor have the ability to proceed with the repairs and is there a ceiling on the amount that the O&M contractor is allowed to repair in an emergency event?

Response #39: Under no circumstances may the contractor perform work without prior authorization from the Government; this government official must be authorized to bind the Government, such as a warranted Contracting Officer, Contracting Officer’s Authorized Representative (COAR), or a Government-wide Commercial Purchase Card (GCPC) Holder. This is a Firm Fixed Price contract; the Government is not committed to paying for service rendered without the prior consent and authorization of the Government.

Question #40: In the event of an equipment failure that requires emergency repairs, is the O&M contractor responsible for regulatory fines? Does this include sewage spills at treatment plants and reclaimed water lines?

Will the contractor be responsible for fines from MCBCP in the event of these occurrences which are non-reportable?

Response #40: Regulatory fines will be passed on to the contractor if the cause is due to equipment failure, sewage spills, or other activities the contractor has a responsibility to maintain and is due to contractor neglect or improper operation.

Question #41: Will the contractor be responsible for fees, fines, and penalties if MCBCP does not actually receive a fine from the regulatory agencies?

Response #41: The contractor will not be responsible for fines if MCBCP does not receive a fine from a regulatory agency. However, non-monetary penalties may be implemented for failure to comply with regulatory requirements.

Question #42: Are reclaimed water spills categorized as sewer spills and are reclaimed spills under 50,000 gallons and sewer spills under than 1,000 gallons non-reportable as long as they do no enter the waters of the United States?

Response #42: Refer to the State issued permits for categorization of sewage spills. All sewage spills meeting Category 1, 2, or 3 are reportable. The Master Recycling Permit R9-2018-0023 provides the reporting requirements for recycled water spills. Recycled water spills are not considered sanitary sewer overflows.

Question #43: Are there minimum amounts of sewer and reclaimed water spills that are not considered reportable and thus, not subject to fines to the O&M contractor?

Response #43: Refer to the State issued permits for categorization of sewage spills. All sewage spills meeting Category 1, 2, or 3 are reportable. The Master Recycling Permit R9-2018-0023 provides the reporting requirements for recycled water spills.

Question #44: In the event of an effluent exceedance caused by a slug load or the discharge of a non-domestic sewer slug, will the contractor be responsible for fines or a violation?

Response #44: Regulatory fines will be passed on to the contractor if the failure is due to equipment failure, sewage spills, or other activities the contractor has responsibility to maintain and is due to contractor neglect or improper operation.

Question #45: What does incidental engineering support mean? Mechanical, electrical, SCADA, etc? Can MCBCP quantify the level of effort historically required? Will the contractor be responsible for these costs or is the cost reimbursable by the Government?

Response #45: Incidental engineering support refers to any mechanical, civil, electrical, SCADA, etc. work to support preventative maintenance activities within the scope of the contract. If non-recurring work is required, the engineering support for this effort would be identified in this scope.

Question #46: Annex 0100000 states “Operate and maintain all wastewater conveyance etc.” Please confirm this does not include sewer collection systems and lift stations?

Response #46: This does not include the sewage collection system or lift station upstream of the first manhole at each treatment plant.

Question #47: Since both facilities (SRTTP and NRTTP) utilize activated sludge processes, please confirm that a water treatment plant operator grade 3 and above CANNOT be utilized as the person responsible for process changes at each facility or the person in charge or on-call.

Response #47: A water treatment operator cannot be utilized as the person responsible for process control changes at each facility. Wastewater treatment operators must meet Title 23 requirements to operate these facilities.

Question #48: When the Base conducts compliance sampling, what is the expected turnaround time of the results for the O&M contractor to review?

Response #48: Compliance sampling results are submitted to the RWQCB on a monthly basis in the month following the sampling event, per permit requirements. Typically, sample results are discussed with the contractor at monthly QC meetings the month after samples have been taken. The Base will notify the contractor of a high result upon receipt of such information from the lab. The contractor shall take process control samples for internal use.

Question #49: 24-hour composite compliance samplers are to be operated by MCBCP. Please confirm the contractor is only responsible for the flow weighted signal to the sampler?

Response #49: The contractor is responsible for the flow weighted signal to the sampler, annual validation of the signal, and power to the samplers.

Question #50: What condition is the current process control/SCADA program at each facility (SRTTP & NRTTP)? Are the Operating Systems still supported by the vendors? In the event of a SCADA failure due to lack of support from vendors, will the O&M contractor be responsible for overtime, engineering, and SCADA support needed to ensure continued operations?

Response #50: The SCADA systems have not had major updates since installation. The SCADA system should be evaluated as part of the equipment condition report. The contractor is responsible for operating the system in its current condition and is responsible for support needed to ensure continued operation. O&M manuals are provided for installed equipment.

Question #51: How many miles and sizes are the reclaimed water and brine line?

Response #51: The brine line is not the responsibility of this contract. The recycled water system under this contract is approximately 21 miles long and has pipeline diameters sized between 6 inches to 20 inches.

Question #52: How many appurtenances are on each of the reclaimed water line and brines line? What regular or preventative maintenance is required on each of these lines to prevent spills.

Response #52: Drawings are provided showing the pipeline and associated appurtenances for each recycled water alignment. This is a performance-based contract; the PWS does not instruct the contractor how to do the work but instead describes performance objectives, performance standards, and measurable outcomes. The contractor shall provide staffing to meet the requirements of the RFP.

Question #53: Please confirm that the equipment provided in the RFP (golf carts, trucks, trailers, fork lifts, back hoes, graders, bob cats, water tank/buffalo, first aid stations/kits, spill kits, arc flash suits, lock out tag out boards, and safety equipment) belong to the current operator and are not Government furnished equipment.

Response #53: The equipment provided in the RFP (golf carts, trucks, trailers, fork lifts, back hoes, graders, bob cats, water tank/buffalo, first aid stations/kits, spill kits, arc flash suits, lock out tag out boards, and safety equipment) belong to the current contractor and are not government-furnished equipment.

Question #54: Has the new reclaimed water groundwater recharge systems at the “Bell” and Red Beach been fully checked and tested for functionality with the existing reclaimed water system at the SRTTP?

Response #54: The new recycled water systems at Ysidora Flats and to Red Beach have not been fully checked and tested for functionality. The facilities built with project P1046B will be fully functional when turned over to the O&M contractor.

Question #55: Has the new reclaimed water system at the NRTTP been fully checked and tested for functionality?

Response #55: The new recycled water system at the NRTTP has not been fully checked and tested for functionality. The facilities built with project P1046B will be fully functional when turned over to the O&M contractor.

Question #56: Does maintaining of roads include dirt roads and access roads to facilities located outside the SRTTP and the NRTTP such as: Gooseneck PS, Horse Lake, Reservoir 16151, San Mateo perc pond, Sierra perc pond, and radio towers?

Response #56: Maintenance of the roads to external facilities is not included in the scope of this contract.

Maintenance of facilities within the fence line of the external facilities is included in the scope of this contract.

Question #57: Does radio pathway include the advanced water treatment plant (AWT) brine valve?

Response #57: Maintaining the radio pathway from the AWT brine valve to the SRTTP is included in the scope of this contract.

Question #58: If equipment fails after serving its useful life and industry expectations, will the full cost be the burden of the contracting operator?

Response #58: Costs associated with replacing equipment outside the identified PM work in the scope of work should be identified and submitted for non-recurring line item work.

Question #59: Project experience requires that a project, contract, or task order must have been awarded within the last 5 years. Since most O&M contracts include a Base Year plus 4 to 9 Option Years, are Offerors permitted to submit an Option year as relevant project as long as it was awarded within the last 5 years and meets all other minimum requirements as indicated in Factor 1?

Response #59: A response will be forthcoming.

Question #60: There are some minor typos, omissions, and formula errors in the ELIN Spreadsheet, as follows:

• The South plant is identified as AA and the North Bland as AB for the Base Period Recurring Costs under Custodial, ISWM, and Grounds. In the option periods, North is identified as AA and South as AB. Is this intentional?

• Cell C16 on ELINS – 1st-Opt Per-Non-recurring worksheet references the Base Year. Should this cell reference option year 1?

• The heading in row 4 of ELINS-2nd Option Period Recurring worksheet identifies CLIN9001. Should this be 9002?

• The heading in row 6 of ELINS-2nd Option Period Recurring worksheet identifies the sheet as Line Item 0003 – Firm Fixed Price – First Option Period. Should this reference Line Item 0005 and the second option period?

• The heading in row 4 of ELINs-2nd Opt Per-Non-recurring worksheet identifies CLIN9001. Should this be 9002?

• The heading in row 6 of ELINs-2nd Opt Per-Non-recurring worksheet identifies the sheets as Line Item 0004 and First Option Period. Should this reference Line Item 0006 and the second option period?

• Cell C16 on ELINS – 2nd-Opt Per-Non-recurring worksheet references the Base Year. Should this cell reference option year 2?

• The heading in row 4 of ELINS-3rd Option Period Recurring worksheet identifies CLIN9001. Should this be 9003?

• The heading in row 6 of ELINS-3rd Option Period Recurring worksheet identifies the sheet as Line Item 0003 – Firm Fixed Price – First Option Period. Should this reference Line Item 0007 and the third option period?

• Cell B33 on ELINS – 3r Opt Period Recurring references a total for C001 through C004. Should this reference D001 through D004?

• The heading in row 4 of ELINs-3rd Opt Per-Non-recurring worksheet identifies CLIN9001. Should this be 9003?

• The heading in row 6 of ELINs-3rd Opt Per-Non-recurring worksheet identifies the sheets as Line Item 0004 and First Option Year. Should this reference Line Item 0008 and the third option year?

• Cell C16 on ELINS – 3rd Opt Per-Non-recurring worksheet references the Base Year. Should this cell reference option year 3?

• The heading in row 4 of ELINS-4th Option Period Recurring worksheet identifies CLIN9001. Should this be 9004?

• The heading in row 6 of ELINs-4th Opt Per-Non-recurring worksheet identifies the sheets as Line Item 0004 and First Option Period. Should this reference Line Item 0009 and the fourth option period?

• The heading in row 4 of ELINs-4th Opt Per-Non-recurring worksheet identifies CLIN9001. Should this be 9004?

• The heading in row 6 of ELINs-4th Opt Per-Non-recurring worksheet identifies the sheets as Line Item 0004 and First Option Year. Should this reference Line Item 0010 and the fourth option year?

• Cell C16 on ELINS – 4th Opt Per-Non-recurring worksheet references the Base Year. Should this cell reference option year 4?

Response #60: Please see REVISED ELIN Pricing Schedule.

Question #61: Will MCBCP provide the Electronic Operation and Maintenance Support Information (eOMSI) manuals for all equipment specified to maintain and repair?

Response #61: The Electronic Operation and Maintenance Support Information (eOMSI) manuals will be provided to the winning contractor.

Question #62: Will the contractor be responsible for using distilled water for routine cleaning of solar panels located at the SRTTP site, NRTTP parking cover, and Sierra Percolation Ponds?

Response #62: Cleaning of the solar panels shall be conducted per the OMSI.

Question #63: Please confirm that DBIDS Program allows for access to the base for 3 years and not 1 year?

Currently, DBIDS are only 1 year duration.

Response #63: Please refer to the Camp Pendleton website at https://www.pendleton.marines.mil/Base- Access/Contractors-Vendors/ for DBIDS access information. Currently DBIDS access is issued for one year of duration.

Question #64: Please confirm if all contractor employees working at the plants must be U.S. Citizens to obtain base access through DBIDS.

Response #64: Please refer to the Camp Pendleton website at https://www.pendleton.marines.mil/Base- Access/Contractors-Vendors/ for DBIDS access information.

Question #65: Factor 4, Past Performance requires that a CPARS be submitted if one is available. For construction projects that included an O&M period of 12 months or more, the CPARS does not discuss or evaluate the O&M performance of the contractor. In that instance, are Offerors permitted to provide a PPQ specifically addressing the O&M performance?

Response #65: If a CPARS is not available, Factor 4 – Past Performance on Page 17 of 26 of the Solicitation provides “If a completed CPARS evaluation is available, it shall be submitted with the proposal. If there is not a completed CPARS evaluation, the PPQ included in the solicitation is provided for the offeror or their team members to submit to the client for each project the offeror includes in their proposal for Factor 1 – Recent, Relevant Experience of the Firm.”

Question #66: Many recent O&M contracts at DoD facilities are part of longer-term design-build-operate contracts. As such the "award date" is greater than 5 years ago. The O&M, either as an exercised option or a continuation of the contract will have started within the past 5 years, however, is not a stand-alone contract. May Offerors use that experience, as long as the annual costs are broken out.

Response #66: A response will be forthcoming.

Question #67: Attachment J-1503030-03 indicates “5278B 1,*-CY”. Can we assume that this indicates 1-8 CY bin?

Response #67: Yes, 1- 8 CY.

Question #68: Please confirm that the contractor is not responsible for hauling away sludge/biosoilds from the SRTTP and NRTTP.

Response #68: The contractor is not responsible for hauling away sludge/biosolids from the SRTTP and NRTTP.

However, the contractor is responsible for loading the trucks brought in to remove the sludge/biosolids, as well as cleaning up the beds.

Question #69: 2.6.6 states that all work orders must be completed in Maximo on the day that they were done. Does the base supply a computer, operating system, and licenses for the MAXIMO CMMS system?

Response #69: The Base will not supply a computer, operating system, or licenses for the contractor to access Maximo. The contractor will be required to obtain a Common Access Card (CAC) from the Government to access Maximo. Maximo is accessible from the internet and does not require a license.

Question #70: 2.7.1.1 states that the PM or alternate shall be on-site during the Government's regular working hours and shall be available on-site within one hour after the Government's regular working hours. In this context, is the PM the CPO?

Response #70: The CPO can be the PM if the CPO meets the qualifications/requirements of the Project Manager defined in the description column of section 2.7.1.1.

Question #71: Can you provide the current / desired staffing for each facility?

Response #71: This is a performance-based contract; the PWS does not instruct the contractor how to do the work but instead describes performance objectives, performance standards, and measurable outcomes. The contractor shall provide staffing to meet the requirements of the RFP.

Question #72: In ANNEX 1604000 Section C 2.2.1 it describes requirements for the Chemist and Laboratory Analyst. If compliance sampling is conducted by an outside lab, are these individuals required for staffing?

Response #72: A Chemist and Laboratory Analyst is not required. The contractor is required to have staff with experience to conduct process control analysis.

Question #73: We have not been able to locate the Chemical and Material Usage list in Section J 1604000-05, Spare Parts Inventory in Section J-1604000-04 and Reclaimed System Inventory in Section J-1604000-03. Please provide.

Response #73: Chemical usage for 2017 and 2018 is attached and labeled SRTTP NRTTP Chemical Usage 2017 2018.xlsx. The disinfection chemical for recycled water changed to bulk sodium hypochlorite in 2019 and is not included in the chemical usage estimates. Attachments are provided for the Wastewater Treatment Plant and Recycled Water Inventory and labeled as follows: RWPS Equipment List, SierraOne Equipment List, and RWPS Electrical Equipment List.

Question #74: Can you provide a list of subcontractors authorized to access the Base Property for the following services:

1. Instrument and radio repairs and maintenance

2. Concrete tank repair and restoration

3. Controls and integration repairs and maintenance

4. Janitorial services

5. Landscape services

Response #74: All subcontractors must meet the Base access requirements of Annex 0200000 C Management and Administration.

4) All other terms and conditions remain unchanged.

(End of Summary of Changes)