This document is an amendment to a solicitation for a design-build electrical power plant project at Camp Lemonnier, Djibouti. The amendment extends the proposal due date from October 31, 2023 to November 7, 2023 at 2:00 PM local time in Norfolk, VA. It provides responses to contractor questions, revises drawings and specifications, and includes additional attachments. The project involves construction of a new electrical power plant building housing five 4.5 megawatt diesel generators and support facilities, with remote coolers, fuel storage, site utilities, and demolition. An option is included for a second phase adding five additional generators, coolers, fuel tanks, and support facilities. Rights to generator and SCADA software and operating systems are required.
The amendment revises drawings and specifications, responds to contractor questions on technical details, fuel analysis, and DPAS rating requirements. It extends the proposal due date and provides additional attachments related to drawings of floor plans, elevations, and signage details.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
MILCON PROJECTS P-332 and P-334 ELECTRICAL POWER PLANT, CAMP LEMONNIER, DJIBOUTI
See Block 14 SF30 Continuation Page
1. CONTRACT ID CODE PAGE OF PAGES
J 1 11
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Sep-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6247023R0001
X 9B. DATED (SEE ITEM 11)
19-Jul-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Sep-2023
CODE
COMNAVFACSYSCOM ATLANTIC
6506 HAMPTON BLVD
NORFOLK VA 23508-1278
N62470 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6247023R0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0005
The purpose of this amendment is to:
1. Extend the proposal due date
2. Respond to Preproposal Inquires (PPIs)
3. Revise Drawings
4. Revise the Solicitation
5. Provide Attachments
1. The proposal due date is extended from Tuesday, 31 October 2023 at 2:00 PM Norfolk, VA local time to Tuesday, 07 November 2023 at 2:00 PM Norfolk, VA local time.
2. Responses to PPIs
80. Inquiry: (Reference: Drawing No: CD101) In Drawing no CD101 Note-5, RFP says Removal of generators will be in phases, southwest three generators will be removed first and after construction is complete for P332/P334 Power Plant, the northeast three generators will be removed. Please clarfiy, what is meant by "after construction is complete for P332/P334 Power Plant", is the new power plant building only meant to be constructed or power plant building with 2 ea base generators inside (DG-10 and DG-09) installed and commissioned?
Response: CD101, General Note 5 is deleted. Refer to Specification 01 11 00 and 01 14 00 for phasing descriptions. See amendment detail below.
81. Inquiry: (Reference: Drawing No: CD101) In Drawing no CD101 Note-5, RFP says Removal of generators will be in phases, southwest three generators will be removed first and after construction is complete for P332/P334 Power Plant, the northeast three generators will be removed.
There are 6 generators and 8 separately placed, in total 14 ea generators to be demolished in drawing CD101. We believe Note-5 refers to generator bundle with 6 generators. Please kindly clarify if any phasing requirement is needed for demolishing of 8 separately placed generator bundle.
Response: CD101, General Note 5 is deleted. Refer to Specification 01 11 00 and 01 14 00 for phasing descriptions. See amendment detail below
82. Inquiry: (Reference: SPEC NO:SECTION 25 10 11) Please clarify existing SCADA system installer company and brand name.
Response: The existing SCADA HMI is: ADVANTECH co.; Model no. PPC-3190-RE4BE; Part
no. PPC-3190-RE4BU; Controller: WOODWARD EasyGEN 3000 8446-1061 REV:4 RP-
3000XT. Use of this data requires review of the solicitation in its entirety in order to comply fully with the solicitation requirements.
83. Inquiry: (Reference: MP601-4) The combined peak cooling load of all equipment outlined in
MP601-MP604 amounts to 5,552 kW. The chillers are sized for 3,327 kW of cooling which is o/a 60% of the simultaneous maximum peak of the scheduled equipment load. Please confirm the cooling plant capacity is not to exceed 3,327 kW.
Response: Total probable chilled water load is 2472.67 KW at peak. Each chiller is sized for
1663.5 KW. One chiller will handle the load for 67% of the time and the second chiller will ramp up for the extreme temperatures and loads. This is to allow the main chiller to remain at the efficient operating capacity.
84. Inquiry: (Reference: PL102) A floor drain is not shown for the emergency eyewash/shower in battery room 115. Please confirm a floor drain is not required for battery room 1125.
Response: A floor drain is not required per the IPC as noted in the UFC 3-420-01, Appendix D.
85. Inquiry: (Reference: P-602) Per the equipment schedule both the P-11 and P-11A emergency plumbing fixtures call for “visual and audible alarm.” Will these devices need to be monitored and reported to the control room? If so, which building system will be monitoring these points?
Response: Visual and audible plumbing alarm devices will not be monitored.
86. Inquiry: (Reference: SCADA – 251011) Please provide current SCADA system manufacturer and
PCS system (Brand and model) monitoring and controlling PP2A that this contract is required to interface with as stated under specification 251011 Paragraph 1.1.
3000XT. Use of this data requires review of the solicitation in its entirety in order to comply fully
87. Inquiry: (Reference: 37 OF 40; Attachment H; para 2 and 3) As per the documents new SCADA system shall be integrated with existing SCADA system.
We couldn’t find any detail related to existing SCADA system , can you please clarify what is the make and model of existing SCADA system as well as the interfaces between the existing prime power plants?
3000XT. Use of this data requires review of the solicitation in its entirety in order to comply fully
88. Inquiry: (Reference: 5 of 53; 1.2 (Solicitation Document N6247023R0001); para 3) Could you provide a list of existing equipment that need to be integrated to the new power plant?
Response: This is not available. Propose in accordance with the solicitation.
89. Inquiry: (Reference: 5 of 53; 1.2 (Solicitation Document N6247023R0001); para 3) Please provide the specifications of the fuel which will be supplied for the generators.
Response: Review solicitation documents in their entirety, particularly, SPEC Section 26 32 15 ENGINE-GENERATOR SET STATIONARY 4500 KW WITH AUXILIARIES. Propose in accordance with the solicitation.
90. Inquiry: Are there any network drawings for the existing facility?
Response: If available, information may be provided to the selectee of the contract award. Propose in accordance with the solicitation.
91. Inquiry: (Reference: ATCH H; Sheet SB105) Drawing A1. See area located between the following grid lines 1 to 2 and B to C. The Floor Grating is called out with two Keyed Note Tags (both #1 and #3). It appears Keyed Note #1 was added by error. Correct and clarify.
Response: Keynote 1 is correct, Delete Keynote 3 at this location. See amendment detail below.
92. Inquiry: (Reference: ATCH H; Sheet SB301) Drawings C1 & C2 both reference Sheet S100.
Sheet S100 is NOT included in the Drawing Set or Index. Please correct the reference.
Response: Correct sheet reference is SB100. See amendment detail below.
93. Inquiry: (Reference: ATCH H; Sheet AE102) Please provide a detail for the utility trenches showing what is expected as the piping penetrate through the 3 hour rated wall on gridline 3?
Response: The 3-hour rated wall extends to down to the trench floor. It is expected the necessary wall penetrations will be made to accommodate the piping with the gaps filled after pipe installations with 3-hour rated firestop sealant that is UL Fire Resistance listed or FM APP GUIDE approved. Refer to specification section 07 84 00 Firestopping for additional information.
94. Inquiry: (Reference: ATCH H; Sheet AE102) Correct Key Note Tags for Downspouts shown at grid line A. Leaders are not pointing to the downspout location. See stack between gridlines 1&2 and 4&5.
Response: Leaders between Column Lines 2 & 3 and 4 & 5 intend to point to downspouts to the east of the exhaust stacks.
95. Inquiry: (Reference: ATCH H; Sheet AE103) Correct Key Note Tags for Downspouts shown at grid line A. Leaders are not pointing to the downspout location. See stack between gridlines 9&10 and 11&12.
Response: Leaders between Column Lines 9 & 10 and 11 & 12 intend to point to downspouts to the east of the exhaust stacks.
96. Inquiry: (Reference: ATCH H; Sheet AE103) The bar grating shown around the Transformers on
Sheet AE103 include a callout #64, which indicates "Metal Louver over Containment Dike".
Correct Keyed Note #64 to say "Metal Bar Grating over Containment Dike".
Response: Key note 64 should read "Metal bar grating over containment dike." See amendment detail below.
97. Inquiry: (Reference: ATCH H; Sheet AE104) Correct the leader for Keyed Note #17 located near grid lines E-9. The leader is errantly located, the gutter is located to the right of the arrow head.
Response: Leader for Keynote 17 south of Column Line 9 along Column Line E intends to point to the prefinished metal gutter along Column Line E.
98. Inquiry: (Reference: ATCH H; Sheet AE201) Exterior light fixture is missing from drawings D1, located between Gridlines 1&2.
Response: Light fixture should be shown between Col. Lines 3&4 as indicated on EL102A. It is shown between 1&2 for Detail D1. See amendment detail below.
99. Inquiry: (Reference: ATCH H; Sheet AE201) Drawings D1 includes Center Line of Downspouts.
However, there is a dimension missing from the first downspout near gridline 1. Additionally between gridlines 4 to 10 there are 4 "CL OF DOWNSPUTS", but there are only 3 Downspouts.
Please correct drawing.
Response: The missing dimension should read "9800". There are 3 downspouts between column lines 4 through 10. Please disregard the additional "CL OF DOWNSPOUT" text. See amendment detail below.
100. Inquiry: (Reference: ATCH H; Sheet AE201) Keyed Note #16 indicates "Prefinished Metal
Downspout with splash block". However when you look at Drawings D1, none of these can be seen. Recommend that you add to the Keyed Note that these items are "Beyond".
Response: Related to PPI #99, the dimensions (including the missing one) indicate 7 downspout locations. See amendment detail below.
101. Inquiry: (Reference: ATCH H; Sheet AE201) Drawing D1 near gridline 13, there is a Keyed Note
#32. #32 is calling out metal joints. Most of the exterior wall has Keyed Note #54 Concrete Reveal. Please clarify if #32 is correct and if so suggest detailing what is required.
Response: The Keynote 32 in the location mentioned should be numbered 54. Please refer to details B1, C1 & D1 on sheet AE502. See amendment detail below.
102. Inquiry: (Reference: ATCH H; Sheet AE201) Drawing A1 near gridline 1, there is a Keyed Note
#32. #32 is calling out metal joints. Most of the exterior wall has Keyed Note #54 Concrete Reveal. Please clarify if #32 is correct and if so suggest detailing what is required.
Response: The Keynote 32 in the location mentioned should be numbered 54. Please refer to details B1, C1 & D1 on sheet AE502. See amendment detail below.
103. Inquiry: (Reference: ATCH H; Sheet AE201) Drawing A1 between gridlines 11&12. There is a
Keyed Note #30 that the leader is off target. Please correct.
Response: Leader for Keynote 30 east of Column Line 12 in detail A1 intends to point to the insulated hollow metal doors and frame just east of Column Line 12.
104. Inquiry: (Reference: ATCH H; Sheet AE201) Drawing A1 near gridline 1, there is a Keyed Note
#30. #30 is calling out a door which in concealed by the AHU. Recommend calling out #30 to be "Beyond".
Response: Leader for Keynote 30 points to a location between Column Lines 1 & 2 in detail A1 where an insulated hollow metal door and frame are obscured by rooftop mechanical equipment.
See amendment detail below.
105. Inquiry: (Reference: ATCH H; Sheet AE402) Drawing A1. What is the object located in the upper right hand corner of the drawing that would seem to impeed access to the stairs? Assume this is mechanical equipment not intended to be shown on this detail. Correct Drawing.
Response: The object referenced is mechanical equipment, however it does not impede stair access. There is access around the north side of the equipment. See amendment detail below.
106. Inquiry: (Reference: ATCH H; Sheet AE501) Drawing C2. Fix the leaders for "MTL Roof Truss, See Structural." and "Concrete slab on steel deck, see structural.".
Response: In detail C2, arrowheads on leaders for notes calling out concrete slab on steel deck and metal roof truss intend to point to the concrete slab on metal deck and the metal roof truss, respectively, just above the arrowheads in question.
107. Inquiry: (Reference: ATCH H; Sheet AF101) Two Fire Extingisher Signs are missing near
Vestibuile 116, see A1/IF101. Are FE Clearance painting on the floor required? Please clarify.
Response: Please refer to sheet AF102 for signage in this area. Fire extinguisher floor painting is required for the fire extinguishers in the southeast corner of Engine Hall 117 and the northeast corner of Engine Hall 123, both near Vestibule 116. See amendment detail below.
108. Inquiry: (Reference: ATCH H; Sheet AF101) Fire Extingisher Sign is missing in Corridor 102, see A1/IF101. Is a FE Clearance painting on the floor required? Please clarify.
Response: Please refer to sheet AF102 for signage in this area. Fire extinguisher floor painting is required for the fire extinguisher in Corridor 102. See amendment detail below.
109. Inquiry: (Reference: ATCH H; Sheet AF101) Is a FE Clearance painting on the floor required for the FE located in Control 106? Please clarify.
Response: Propose in accordance with the solicitation.
110. Inquiry: (Reference: ATCH H; Sheet AF101) Fire Extingisher Sign is missing in Mechanical 113, see A1/IF101. Is a FE Clearance painting on the floor required? Please clarify.
Response: Please refer to sheet AF101 for signage in this area. Fire extinguisher floor painting is required for the fire extinguisher in Mechanical 113. See amendment detail below.
111. Inquiry: (Reference: ATCH H; Sheet AF102) Is a FE Clearance painting on the floor required for the FE located in Day Tank 126? Please clarify.
112. Inquiry: (Reference: ATCH H; Sheet AF102) Directly outside the door from Day Tank 126 there is an FS2 tag. Change this to FS1 as this is an eye wash and shower.
Response: Confirmed. Change sign directly outside of Day Tank 126 from a FS2 to a FS1 for an eye wash and shower on sheet AF102. See amendment detail below.
113. Inquiry: (Reference: ATCH H; Sheet AF102) Directly outside the door from Lube Oil 127 there is an FS1 tag. Change this to FS2 as this is a Fire Extinguisher.
Response: Confirmed. Change sign directly outside of Lube Oil 127 from a FS1 to a FS2 fire extinguisher on sheet AF102. See amendment detail below.
114. Inquiry: (Reference: ATCH H; Sheet AF102) Is a FE Clearance painting on the floor required for the FE located in Electrical 114? Please clarify.
Response: Fire extinguisher floor painting is required for the fire extinguisher in Electrical 114.
See amendment detail below.
115. Inquiry: (Reference: ATCH H; Sheet AF102) North side of Engine Hall 123 there is an FS2 tag.
Change this to FS1 as this is an eye wash and shower.
Response: Confirmed. Change the sign on the North side of the Engine Hall from a FS2 to a FS1 for an eye wash and shower on sheet AF102. See amendment detail below.
116. Inquiry: (Reference: ATCH H; Sheet IF101) Key Plan indicates Partial A & B. There is no sheet for Partial Plan B. Is there FF&E requirments for Partial B? Is so provide Partial B.
Response: FF&E for area B of the building is limited and is shown on sheet IF101 in detail A4, B4 and C4. See General Note 1 on sheet IF101.
117. Inquiry: (Reference: 26 32 15.00; 2.6) The 25mm FOS and FOR lines shown on MP701 are too small for the basis-of-design CAT C280-16 option. 40mm or 50mm is recommended for the application due to high recirculating flow rates, and because the onboard pumps are sensitive to inlet pressure restrictions. Recommend investigation of flow and pressure requirements, and revision to correct line size. The 56.8 L/min fuel flow rate listed on MP602 is not accurate for the CAT package, but may be consistent with the alternative. Pump inlet pressure at the engine-driven pump is sensitive to flow restrictions, and adequate line sizing is essential.
Response: The size on the typical section MP410 is correct and is a typical pipe size requirement for supply and return piping. Please refer to this drawing for bid purposes as applied to all generators. The number for fuel consumption is correct on the schedule sheet MP602. This is the amount of fuel consumed at full power not full flow with recirculation.
118. Inquiry: (Reference: EW601, EW602) Can modified electrical single line diagrams be provided showing the single line if only Price Schedule Item 1 is awarded? This would remove all ambiguity on which electrical items are included in the base bid and which are future options. The drawing set is only presented as projects P332/P334 as a whole. Since the bidding contractors do not have clear delineation of the price schedule line items on the drawings, the base bid of P332 will vary between bidding contractors.
119. Inquiry: (Reference: Attachment H; dwg MP301-MP302) We do not see the silencers in the design of the stack. Is that on purpouse?
Can we have other stack design as long as we fulfill the materials, height, noise, emission and other requirement? For example encaged steel structure with multiple ducts for maybe more than 2 engines.
Response: Silencers were not used due to the exhaust back pressure requirements of the generators/engines. The selective catalytic reduction and associated exhaust stack restricts the use of a silencer exhaust maximum back pressure requirement. Stack design is as stated in the contract drawings and cannot be altered without being vetted from the designer of record (DOR) and Contracting Officer. Propose in accordance with the solicitation.
120. Inquiry: (Reference: Attachment H; dwg MP603) Radiator schedule :
- Can we have other quantity and power of fans per radiator? Can we do our own design?
- Fans are mentionned as "belt driven". Can we take direct drive fans ?
Response: Sound criteria is an important performance element due to the close proximity to the living quarters. The design is as stated in the contract drawings and cannot be altered without being vetted from the DOR and Contracting Officer. Propose in accordance with the solicitation.
121. Inquiry: (Reference: Attachment H; dwg 603) Fan schedule : Fans are mentionned as "belt driven". Can we take direct drive fans ?
Response: See PPI #120 response above.
122. Inquiry: (Reference: 840 of 1014; 26 42 13 (Attachment H - Specifications 2 of 3); 2.1.1 g and h)
1. Kindly note that as per point no. 2.1.1.g and h of Section 26.42.13 ( Cathodic Protection ) of technical specification , the CP system designed by Bidder should be Compatible to the existing CP system which may be a REMOTE MONITORED CP SYSTEM. Please note that the scope of the CP system for this Project is very limited and confirmed to be a very small area. Therefore, the Bidder feels that the remote monitoring provision for this Project is not cost-effective and necessary. Bidder wants to propose a manually monitored CP system wherein the monitoring could be done by checking the monitoring Boxes mounted in the site. Please confirm that this is acceptable
123. Inquiry: (Reference: 263215; 2.5) Please provide a complete fuel analysis of the existing fuel used on base for PP2 and PP3(which is expected to be the same for PP4). This analysis should include sulfur content in ppm. The spec clearly says "Each engine must operate on No. 2-D ulra low sulfur diesel fuel conforming to ASTM D975". Quality of diesel fuel can signifigantly negatively affect generator kW output and emissions cannot be met.
Response: Fuel analysis not available. Propose in accordance with the solicitation.
124. Inquiry: (Reference: FAR 52.211-14) The RFP includes FAR 52.211-14 NOTICE OF PRIORITY
RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY
PROGRAM USE (APR 2008) which states: Any Contract awarded as a result of this solicittion will be DX rted order; X DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations Systems (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.
Please confirm the DPAS rating of this project is DO-C-2 and if it is, we request the rating be changed to DX.
Response: DPAS rating is DO-C2. Propose in accordance with the solicitation.
3. Revise Drawings
NAVFAC DWG NO. 14124390 (CD101) DEMOLITION PLAN
Delete General Note 5.
NAVFAC DWG NO. 14124420 (SB105) SLAB-ON-GRADE PLAN – AREA A
Delete the Key Note 3 symbol shown between Grid Line B and C and between Grid Line 1 and 2.
NAVFAC DWG NO. 14124422 (SB301) FOUNDATION SECTIONS
In Section C1, delete note “UNDERCUT FOOTING SUBGRADE AND BACKFILL, SEE SHEET S100” and replace with “UNDERCUT FOOTING SUBGRADE AND BACKFILL, SEE SHEET SB100”.
NAVFAC DWG NO. 14124452 (AE103) PARTIAL GROUND FLOOR PLAN - B
In Keynote Schedule, revise Keynote 64 from “METAL LOUVER OVER CONTAINMENT DIKE” to
“METAL BAR GRATING OVER CONTAINMENT DIKE”.
NAVFAC DWG NO. 14124456 (AE201) EXTERIOR ELEVATIONS
In Detail A1, revise Keynote 32 to Keynote 54 near Column Line 1. Add “BEYOND” to Keynote 30 near Column Line 1. In Detail B1, revise Keynote 32 to Keynote 54 near Column Line A. In Detail D1, move arrowhead to light fixture near roof between Column Lines 1 and 2. Move light fixture up near roof between Column Lines 3 and 4. Revise Keynote 32 to Keynote 54 near Column Line 13. Add downspout dimension starting at Column Line 1. Add “BEYOND” to “CL OF DOWNSPOUT” for downspouts behind exhaust stacks between Column Lines 2 and 3, 4 and 5, at Column Line 7, between Column Lines 9 and 10, and between Column Lines 11 and 12.
NAVFAC DWG NO. 14124461 (AE402) STAIR PLANS
In Detail A1, mechanical equipment hidden from view for clarity.
NAVFAC DWG NO. 14124472 (AF101) GROUND LEVEL FINISH AND SIGNAGE PLAN -
PARTIAL A
In Mechanical Room 113, add C-1 fire extinguisher sign.
NAVFAC DWG NO. 14124473 (AF102) GROUND LEVEL FINISH AND SIGNAGE PLAN -
PARTIAL B
In Corridor 102, add C-1 fire extinguisher sign.
NAVFAC DWG NO. 14124473 (AF102) GROUND LEVEL FINISH AND SIGNAGE PLAN -
PARTIAL B
Outside Day Tank Room 126 at eye wash station, delete sign callout “FS2” and replace with sign callout “FS1” for an eye wash and shower.
NAVFAC DWG NO. 14124473 (AF102) GROUND LEVEL FINISH AND SIGNAGE PLAN -
PARTIAL B
Outside Lube Oil Room 127, delete sign callout “FS1” and replace with sign callout “FS2” for a fire extinguisher.
NAVFAC DWG NO. 14124473 (AF102) GROUND LEVEL FINISH AND SIGNAGE PLAN -
PARTIAL B
In Electrical Room 114, delete sign callout “FS1” and replace with sign callout “FS2” for a fire extinguisher.
NAVFAC DWG NO. 14124473 (AF102) GROUND LEVEL FINISH AND SIGNAGE PLAN -
PARTIAL B
In Engine Hall Room 123 on North side, delete sign callout “FS2” and replace with sign callout “FS1” for an eye wash and shower.
NAVFAC DWG NO. 14124475 (AG601) SIGNAGE DETAILS AND SCHEDULE
In Signage Schedule, add C-1 fire extinguisher sign for rooms 102 Corridor and 113 Mechanical.
4. Revise the Solicitation
Page 5:
CURRENT:
1.2 GENERAL OVERVIEW OF CONTRACT SCOPE
1.2.1 This project constructs a new electrical Power Plant with ancillary support facilities, fuel storage, and connections to the existing distribution system for Camp Lemonnier, Djibouti (CLDJ).
The project provides for a new electrical Power Plant building comprised of a high bay Engine hall housing five (5) 4.5 megawatt (minimum) diesel generators and a single-story, low-roof area including a power plant control room and other plant operations support spaces with a total building area of approximately 2400 square meters. Remote coolers, required cybersecurity, paving/site improvement, site utilities (electrical, mechanical, telecommunications, etc.) and required demolition will also be provided.
FY2024 MILCON Project P334 will be included as an option and consists of a second set of five (5) 4.5 megawatt (minimum) generators, associated remote coolers, new fuel farm storage tanks (uncovered), emergency/backup fuel off-load facility, required cybersecurity, supporting facilities, and required demolition.
REVISED TO:
1.2 GENERAL OVERVIEW OF CONTRACT SCOPE
1.2.1 This project constructs a new electrical Power Plant with ancillary support facilities, fuel storage, and connections to the existing distribution system for Camp Lemonnier, Djibouti (CLDJ).
The project provides for a new electrical Power Plant building comprised of a high bay Engine hall housing five (5) 4.5 megawatt (minimum) diesel generators and a single-story, low-roof area including a power plant control room and other plant operations support spaces with a total building area of approximately 2400 square meters. Remote coolers, required cybersecurity, paving/site improvement, site utilities (electrical, mechanical, telecommunications, etc.) and required demolition will also be provided. This project includes provision to the government of all necessary rights (royalty-free) to programming and software systems used in the generators, and in the Supervisory Control and Data Acquisition (SCADA) and its components, and any operating software developed and utilized under this contract for industrial processes, to enable the Government to access, modify, integrate, and control as needed for maintenance and operation of, and improvements to, the Power Plant and facilities.
FY2024 MILCON Project P334 will be included as an option and consists of a second set of five (5) 4.5 megawatt (minimum) generators, associated remote coolers, new fuel farm storage tanks (uncovered), emergency/backup fuel off-load facility, required cybersecurity, supporting facilities, and required demolition, inclusive of rights as set out above.
CURRENT:
ALL SUBMITTALS MUST BE RECEIVED AT THE LOCATION SPECIFIED ABOVE PRIOR TO
2:00PM Norfolk, VA local time, Tuesday, 31 October 2023. LATE SUBMITTALS WILL NOT BE
CONSIDERED. LATE RESPONSES WILL BE HANDLED IN ACCORDANCE WITH FAR 52.215-1.
THE GOVERNMENT WILL NOT BE HELD RESPONSIBLE FOR DELAYS OF ANY
COMMERCIAL CARRIER.
REVISED TO:
ALL SUBMITTALS MUST BE RECEIVED AT THE LOCATION SPECIFIED ABOVE PRIOR TO
2:00PM Norfolk, VA local time, Tuesday, 07 November 2023. LATE SUBMITTALS WILL NOT BE
CONSIDERED. LATE RESPONSES WILL BE HANDLED IN ACCORDANCE WITH FAR 52.215-1.
THE GOVERNMENT WILL NOT BE HELD RESPONSIBLE FOR DELAYS OF ANY
COMMERCIAL CARRIER.
5. Provide Attachments
• Attachment K - P332 Elect Pwr Plnt FDA - AE103 - PARTIAL GROUND FLOOR PLAN – B
• Attachment L - P332 Elect Pwr Plnt FDA - AE105 - ROOF PLAN
• Attachment M - P332 Elect Pwr Plnt FDA - AE201 - EXTERIOR ELEVATIONS
• Attachment N - P332 Elect Pwr Plnt FDA - AE402 - STAIR PLANS
• Attachment O - P332 Elect Pwr Plnt FDA - AF101 - GROUND LEVEL FINISH AND SIGNAGE PLAN -
PARTIAL A
• Attachment P - P332 Elect Pwr Plnt FDA - AF102 - GROUND LEVEL FINISH AND SIGNAGE PLAN -
PARTIAL B
• Attachment Q - P332 Elect Pwr Plnt FDA - AG601 - SIGNAGE DETAILS AND SCHEDULE
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 31-Oct-2023 02:00 PM to 07-Nov-2023 02:00 PM.