This document provides specifications for a plumbing system for a new electrical power plant at Camp Lemonnier, Djibouti. The specifications cover materials, products and equipment required for the plumbing system, including pipes, fittings, hangers, valves, fixtures, backflow preventers and drains. Key items specified include various types of pipes and joining materials, fixtures such as flush valve water closets, lavatories, drinking water coolers and emergency eyewashes, and floor drains. The specifications also provide performance and quality standards for materials and products to ensure code compliance, durability and proper functioning of the plumbing system. Submittal requirements and timelines are included for items such as product data, shop drawings and operation and maintenance documentation.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WORK ORDER NO.
At the
PREPARED BY:
Architectural:
Civil:
Mechanical:
Electrical:
Structural:
APPROVED BY:
Specifications:
For Commander, NAVFAC:
Date:
Submitted By: Date:
UNCLASSIFIED/FOR OFFICIAL USE ONLY
Mechanical:
Electrical:
Scott Almond, PE Nathan Broach, PE
Help Note All fields can be edited. If you have trouble selecting a field, either use the tab key or click "highlight fields" in Acrobat 7. Fields that are not needed can be selected and deleted. Tool tips with "additional field" can be deleted or changed. The contract number can also be deleted or changed.
clacross Image
P-332/P-334 Electrical Power Plant eProjects Work Order No.: 1643338 Camp Lemonnier, Djibouti, Djibouti
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 01 15 02/11, CHG 1: 08/14 LIST OF DRAWINGS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK
01 13 00.20 08/08 SUPPLEMENTARY CONDITIONS FOR PROJECTS
IN DJIBOUTI AREA
01 14 00 11/11, CHG 13: 08/21 WORK RESTRICTIONS
01 20 00 11/20, CHG 2: 08/21 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 1: 08/21 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 05/17, CHG 7: 11/21 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
01 32 17.00 20 05/18, CHG 3: 08/20 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 11/20, CHG 2: 11/21 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 42 15 02/14 METRIC MEASUREMENTS
01 45 00.00 20 11/11, CHG 8: 02/21 QUALITY CONTROL
01 45 35 11/20 SPECIAL INSPECTIONS
01 50 00 11/20, CHG 1: 08/21 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 11/15, CHG 5: 08/21 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19, CHG 3: 11/21 PROJECT IDENTIFICATION
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 02/15, CHG 3: 08/21 FACILITY ELECTRONIC OPERATION AND
MAINTENANCE SUPPORT INFORMATION (eOMSI)
01 91 00.15 20 02/21, CHG 1: 05/21 TOTAL BUILDING COMMISSIONING
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 05/10, CHG 2: 02/19 DEMOLITION AND DECONSTRUCTION
02 81 00 11/18 TRANSPORTATION AND DISPOSAL OF
HAZARDOUS MATERIALS
02 83 00 11/18 LEAD REMEDIATION
02 84 16 05/20 HANDLING OF LIGHTING BALLASTS AND
LAMPS CONTAINING PCBs AND MERCURY
DI VI SI ON 03 - CONCRETE
03 30 00 02/19, CHG 3: 11/21 CAST-IN-PLACE CONCRETE
03 42 13.00 10 05/16 PLANT-PRECAST CONCRETE PRODUCTS FOR
BELOW GRADE CONSTRUCTION
DI VI SI ON 05 - METALS
05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
PROJECT TABLE OF CONTENTS Page 1
05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS
05 51 00 02/17, CHG 1: 05/17 METAL STAIRS
05 51 33 02/16, CHG 2: 02/18 METAL LADDERS
05 52 00 02/18, CHG 1: 02/20 METAL RAILINGS
DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 05 23 08/19 PRESSURE TESTING AN AIR BARRIER SYSTEM
FOR AIR TIGHTNESS
07 13 53 02/16, CHG 1: 08/17 ELASTOMERIC SHEET WATERPROOFING
07 14 00 02/12, CHG 2: 02/18 FLUID-APPLIED WATERPROOFING
07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION
07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION
07 24 00 05/11, CHG 4: 08/18 DIRECT APPLIED EXTERIOR FINISH SYSTEMS
07 27 10.00 10 08/19, CHG 1: 02/20 BUILDING AIR BARRIER SYSTEM
07 27 19.01 05/17, CHG 2: 08/20 SELF-ADHERING AIR BARRIERS
07 54 19 02/13, CHG 3: 02/21 POLYVINYL-CHLORIDE ROOFING
07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 11 16 05/17, CHG 2: 11/18 ALUMINUM DOORS AND FRAMES
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 33 23 08/20 OVERHEAD COILING DOORS
08 51 13 05/19 ALUMINUM WINDOWS
08 71 00 02/16, CHG 3: 08/20 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 METAL WALL LOUVERS
DI VI SI ON 09 - FI NI SHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 30 10 08/20 CERAMIC TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 62 38 08/17, CHG 1: 08/18 STATIC-CONTROL FLOORING
09 67 23.13 11/19 STANDARD RESINOUS FLOORING
09 67 23.15 02/21 FUEL RESISTIVE RESINOUS FLOORING,
3-COAT SYSTEM
09 90 00 02/21 PAINTS AND COATINGS
09 97 13.17 05/22 THREE COAT EPOXY INTERIOR COATING OF
WELDED STEEL PETROLEUM FUEL TANKS
09 97 13.27 02/21 HIGH PERFORMANCE COATING FOR STEEL
STRUCTURES
DI VI SI ON 10 - SPECI ALTI ES
10 14 00.20 08/20 INTERIOR SIGNAGE
10 26 00 08/20 WALL PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
PROJECT TABLE OF CONTENTS Page 2
DI VI SI ON 12 - FURNI SHI NGS
12 00 01.00 20 014/22 FURNITURE, FIXTURES AND EQUIPMENT
PACKAGE
12 24 13 08/20 ROLLER WINDOW SHADES
DI VI SI ON 13 - SPECI AL CONSTRUCTI ON
13 34 19 08/20, CHG 1: 02/21 METAL BUILDING SYSTEMS
13 48 73 05/20, CHG 1: 08/20 SEISMIC CONTROL FOR MECHANICAL
EQUIPMENT
DI VI SI ON 21 - FI RE SUPPRESSI ON
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
DI VI SI ON 22 - PLUMBI NG
22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE
22 05 48.00 20 04/06, CHG 1: 05/15 MECHANICAL SOUND, VIBRATION, AND
SEISMIC CONTROL
22 15 26.00 20 04/06 GENERATOR COMPRESSED AIR SYSTEM AND
PIPING
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 08 00.00 20 02/21, CHG 1: 05/21 COMMISSIONING OF MECHANICAL AND
PLUMBING SYSTEMS
23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 21 23 08/17 HVAC CHILLED WATER PUMPS
23 25 00 11/08 CHEMICAL TREATMENT OF WATER FOR
MECHANICAL SYSTEMS
23 30 00 05/20 HVAC AIR DISTRIBUTION
23 64 10 11/16, CHG 2: 08/18 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 08/09, CHG 5: 11/19 CHILLED, AND COOLING WATER PIPING
SYSTEMS
DI VI SI ON 25 - I NTEGRATED AUTOMATI ON
25 05 11.23 05/21 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS BUILDING CONTROL
SYSTEM AND ADVANCED METER
INFRASTRUCTURE (AMI)
25 05 11.26 05/21 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS UTILITY CONTROL SYSTEMS
25 08 11.00 20 11/20 RISK MANAGEMENT FRAMEWORK FOR
FACILITY-RELATED CONTROL SYSTEMS
25 10 11 10/22 SUPERVISORY CONTROL AND DATA
PROJECT TABLE OF CONTENTS Page 3
ACQUISITION (SCADA) SYSTEM FRONT END
AND INTEGRATION
DI VI SI ON 26 - ELECTRI CAL
26 05 48.00 10 10/07 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 08 00 11/21 APPARATUS INSPECTION AND TESTING
26 11 13.13 10/22 PACKAGED ADJUSTABLE SPEED DRIVE (ASD)
BUILDING
26 11 16 11/21 SECONDARY UNIT SUBSTATIONS
26 11 20 05/19 UTILITY TRANSFORMERS (ISOLATION)
26 12 19.10 05/19, CHG 1: 11/19 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED
TRANSFORMERS
26 13 13 11/21 METAL-CLAD SWITCHGEAR
26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM
26 23 00 05/15, CHG 2: 11/19 LOW-VOLTAGE SWITCHGEAR
26 27 14.00 20 02/21, CHG 1: 05/21 ELECTRICITY METERING
26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
26 32 15.00 05/20 ENGINE-GENERATOR SET STATIONARY 4500
KW, WITH AUXILIARIES
26 36 23 05/20, CHG 1: 08/21 AUTOMATIC TRANSFER SWITCHES AND
BY-PASS/ISOLATION SWITCH
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
26 42 13 05/21 CATHODIC PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DI VI SI ON 27 - COMMUNI CATI ONS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
28 08 10 05/16 ELECTRONIC SECURITY SYSTEM ACCEPTANCE
TESTING
28 10 05 05/16 ELECTRONIC SECURITY SYSTEMS (ESS)
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DI VI SI ON 31 - EARTHWORK
31 23 00.00 20 02/11, CHG 2: 08/15 EXCAVATION AND FILL
31 31 16.13 08/16 CHEMICAL TERMITE CONTROL
31 35 19.99 05/22 TRIAXIAL GEOGRID
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 11 23 08/17 AGGREGATE BASE COURSES
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 13 15.20 11/10, CHG 1: 05/21 CONCRETE PAVEMENT FOR CONTAINMENT DIKES
32 15 00 05/17 AGGREGATE SURFACING
PROJECT TABLE OF CONTENTS Page 4
32 16 19 05/18 CONCRETE SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 31 13.53 11/21 HIGH-SECURITY FENCES AND GATES
32 35 16 09/22 SOUND BARRIER
DI VI SI ON 33 - UTI LI TI ES
33 01 50.31 02/20 LEAK DETECTION FOR FUELING SYSTEMS
33 01 50.55 02/21 CLEANING OF PETROLEUM STORAGE TANKS
AFTER INSTALLATION
33 08 55 08/19 FUEL DISTRIBUTION SYSTEM START-UP
33 09 52 11/18 PLANT CONTROL SYSTEM
33 11 00 02/18 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 11/21 STORMWATER UTILITIES
33 52 10 11/18, CHG 1: 11/20 FUEL SYSTEMS PIPING (SERVICE STATION)
33 52 23.15 11/18 POL SERVICE PIPING WELDING
33 52 40 11/18, CHG 2: 11/20 FUEL AND DIESEL EXHAUST FLUID SYSTEMS
PIPING
33 52 43.23 08/18, CHG 1: 02/21 FUEL, DEF, LUBE OIL, AND GENERATOR
COOLING PUMPS
33 52 43.28 08/18 FILTER SEPARATOR
33 52 80 02/10 LIQUID FUELS PIPELINE COATING SYSTEMS
33 56 10 05/19, CHG 1: 11/20 FACTORY-FABRICATED FUEL AND DIESEL
EXHAUST FLUID (DEF) STORAGE TANKS
33 56 19 05/15, CHG 1: 11/20 FUEL IMPERMEABLE LINER SYSTEM
33 57 55 11/18, CHG 1: 11/20 FUEL AND DIESEL EXHAUST FLUID SYSTEM
COMPONENTS
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DI VI SI ON 41 - MATERI AL PROCESSI NG AND HANDLI NG EQUI PMENT
41 22 13.14 11/19, CHG 1: 02/21 BRIDGE CRANES, OVERHEAD ELECTRIC, TOP
RUNNING
DI VI SI ON 44 - POLLUTI ON AND WASTE CONTROL EQUI PMENT
44 41 00 08/20 WATER POLLUTION CONTAINMENT AND
CLEANUP EQUIPMENT
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 5
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 6
SECTION 21 13 13
WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
08/20
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME B16.1 (2020) Gray Iron Pipe Flanges and Flanged Fittings Classes 25, 125, and 250
ASME B16.3 (2016) Malleable Iron Threaded Fittings, Classes 150 and 300
ASME B16.4 (2016) Standard for Gray Iron Threaded Fittings; Classes 125 and 250
ASME B16.21 (2021) Nonmetallic Flat Gaskets for Pipe Flanges
AMERICAN SOCIETY OF SANITARY ENGINEERING (ASSE)
ASSE 1013 (2021) Performance Requirements for Reduced Pressure Principle Backflow Prevention Assemblies
ASSE 1015 (2021) Performance Requirements for Double Check Backflow Prevention Assemblies
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C104/A21.4 (2016) Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water
AWWA C110/A21.10 (2012) Ductile-Iron and Gray-Iron Fittings for Water
AWWA C111/A21.11 (2017) Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings
AWWA C203 (2020) Coal-Tar Protective Coatings and Linings for Steel Water Pipelines - Enamel and Tape - Hot-Applied
AWWA M14 (2015) Manual: Recommended Practice for Backflow Prevention and Cross-Connection Control
SECTION 21 13 13 Page 1
ASTM INTERNATIONAL (ASTM)
ASTM A47/A47M (1999; R 2018; E 2018) Standard Specification for Ferritic Malleable Iron Castings
ASTM A53/A53M (2020) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A135/A135M (2021) Standard Specification for Electric-Resistance-Welded Steel Pipe
ASTM A153/A153M (2016a) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware
ASTM A183 (2014; R 2020) Standard Specification for Carbon Steel Track Bolts and Nuts
ASTM A536 (1984; R 2019; E 2019) Standard Specification for Ductile Iron Castings
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/
MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS
INDUSTRY (MSS)
MSS SP-71 (2018) Gray Iron Swing Check Valves, Flanged and Threaded Ends
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 13 (2019; Errata 19-1; Errata 19-2; TIA 19-1;
TIA 19-2; TIA 19-3; TIA 19-4; Errata 19-3;
Errata 20-4; TIA 19-5; TIA 19-6) Standard for the Installation of Sprinkler Systems
NFPA 24 (2022) Standard for the Installation of Private Fire Service Mains and Their Appurtenances
NFPA 101 (2021; TIA 21-1) Life Safety Code
NFPA 291 (2016) Recommended Practice for Fire Flow Testing and Marking of Hydrants
NFPA 1963 (2019) Standard for Fire Hose Connections
NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES
(NICET)
NICET 1014-7 (2012) Program Detail Manual for Certification in the Field of Fire Protection Engineering Technology (Field Code 003) Subfield of Automatic Sprinkler
SECTION 21 13 13 Page 2
System Layout
UNDERWRITERS LABORATORIES (UL)
UL 199 (2020) UL Standard for Safety Automatic Sprinklers for Fire-Protection Service
UL 312 (2010; Reprint Mar 2018) UL Standard for Safety Check Valves for Fire-Protection Service
UL 405 (2013; Bul. 2020) UL Standard for Safety Fire Department Connection Devices
UL 668 (2004; Reprint Jul 2016) UL Standard for Safety Hose Valves for Fire-Protection Service
UL Fire Prot Dir (2012) Fire Protection Equipment Directory
1.2 SYSTEM DESCRIPTION
Provide wet pipe sprinkler system(s) in all areas of the building. Except as modified herein, the system must meet the requirements of NFPA 13 .
Pipe sizes which are not indicated on the Contract drawings must be determined by hydraulic calculations.
1.2.1 Hydraulic Design
1.2.1.1 Basis for Calculations
A waterflow test was performed on 10/20/2021 along Third Street and resulted in a static pressure of 448.2 kPa with a residual pressure of
413.7 kPa while flowing 8086 L/min. Perform a fire hydrant flow test prior to shop drawing submittal in accordance with NFPA 291 . Results must include hydrant elevations relative to the building and hydrant number/identifiers for the tested hydrants, including which were flowed, which had a gauge. This information must be presented in a tabular form if multiple hydrants were flowed. The results must be included with the hydraulic calculations. Hydraulic calculations must be based on flow test noted in this paragraph, unless verified by the NAVFAC Atlantic Fire Protection Engineer and approved by Contracting Officer. Hydraulic calculations must be based upon the Hazen-Williams formula with a "C" value noted in NFPA 13 for piping, and 140 for existing underground piping.
1.2.1.2 Hydraulic Calculations
a. Water supply curves and system requirements must be plotted on semi-logarithmic graph (N^1.85) paper so as to present a summary of the complete hydraulic calculation.
b. Provide a summary sheet listing sprinklers in the design area and their respective hydraulic reference points, elevations, minimum discharge pressures and minimum flows. Elevations of hydraulic reference points (nodes) must be indicated.
c. Documentation must identify each pipe individually and the nodes connected thereto. Indicate the diameter, length, flow, velocity, friction loss, number and type fittings, total friction loss in the
SECTION 21 13 13 Page 3 pipe, equivalent pipe length and Hazen-Williams coefficient for each pipe.
d. Where the sprinkler system is supplied by interconnected risers, the sprinkler system must be hydraulically calculated using the hydraulically most demanding single riser. The calculations must not assume the simultaneous use of more than one riser.
e. All calculations must include the backflow preventer manufacturer's stated friction loss at the design flow or 83 kPa for reduced pressure backflow preventer, whichever is greater.
f. All calculations must be performed back to the actual location of the flow test, taking into account the direction of flow in the service main at the test location.
g. For gridded systems, calculations must show peaking of demand area friction loss to verify that the hydraulically most demanding area is being used. A flow diagram indicating the quantity and direction of flows must be included.
1.2.1.3 Design Criteria
Hydraulically design the system to discharge a minimum density as indicated on the drawings. Hydraulic calculations must be in accordance with the Area/Density Method of NFPA 13 . Add an allowance for exterior hose streams as indicated on the drawings to the sprinkler system demand at the point of connection to the existing water system.
1.2.2 Sprinkler Coverage
Sprinklers must be uniformly spaced on branch lines. Provide coverage throughout 100 percent of the building. This includes, but is not limited to, telephone rooms, electrical equipment rooms (regardless of the fire resistance rating of the enclosure), boiler rooms, switchgear rooms, transformer rooms, attached electrical vaults and other electrical and mechanical spaces. Coverage per sprinkler must be in accordance with NFPA 13 . Provide sprinklers below all obstructions in accordance with NFPA 13 . Exceptions are as follows:
a. Sprinklers may be omitted from small rooms which are exempted for specific occupancies in accordance with NFPA 101 .
1.2.3 Qualified Fire Protection Engineer (QFPE)
An individual who is a licensed professional engineer (P.E.) who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveying (NCEES) and has relevant fire protection engineering experience. Services of the QFPE must include:
a. Reviewing SD-02, SD-03, and SD-05 submittal packages for completeness and compliance with the provisions of this specification.
b. Provide a letter documenting that the SD-02, SD-03, and SD-05 submittal package has been reviewed and noting all outstanding comments.
c. Performing in-progress construction surveillance prior to installation
SECTION 21 13 13 Page 4 of ceilings (rough-in inspection).
d. Witnessing pre-Government and final Government functional performance testing and performing a final installation review.
e. Signing applicable certificates under SD-07.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Partial submittals and submittals not fully complying with NFPA 13 and this specification section must be returned disapproved without review. SD-02, SD-03 and SD-05 must be submitted simultaneously.
Shop drawings (SD-02), product data (SD-03) and calculations (SD-05) must be prepared by the designer and combined and submitted as one complete package. The QFPE must review the SD-02/SD-03/SD-05 submittal package for completeness and compliance with the Contract provisions prior to submission to the Government. The QFPE must provide a Letter of Confirmation that they have reviewed the submittal package for compliance with the contract provisions. This letter must include their professional engineer stamp and signature. Partial submittals and submittals not reviewed by the QFPE must be returned disapproved without review.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Qualified Fire Protection Engineer (QFPE); G
Sprinkler System Designer; G
Sprinkler System Installer; G
SD-02 Shop Drawings
Shop Drawing; G
SD-03 Product Data
Pipe; G
Fittings; G
Valves, including gate, check, butterfly, and globe; G
Relief Valves; G
Sprinklers ; G
Pipe Hangers and Supports ; G
Sprinkler Alarm Switch; G
Valve Supervisory (Tamper) Switch; G
SECTION 21 13 13 Page 5
Fire Department Connection; G
Backflow Prevention Assembly; G
Air Vent; G
Hose Valve; G
Seismic Bracing; G
Nameplates; G
SD-05 Design Data
Seismic Bracing; G
Load calculations for sizing of seismic bracing
Hydraulic Calculations; G
SD-06 Test Reports
Test Procedures; G
SD-07 Certificates
Verification of Compliant Installation; G
Request for Government Final Test; G
SD-10 Operation and Maintenance Data
Operating and Maintenance (O&M) Instructions; G
Spare Parts Data; G
SD-11 Closeout Submittals
As-built drawings
1.4 QUALITY ASSURANCE
1.4.1 Preconstruction Submittals
Within 36 days of contract award but no less than 30 days prior to commencing work on site, the prime Contractor must submit the following for review and approval. SD-02, SD-03 and SD-05 submittals received prior to the review and approval of the qualifications will be returned Disapproved Without Review.
1.4.1.1 Shop Drawing
Three copies of the shop drawings, no later than 28 days prior to the start of system installation. Working drawings conforming to the requirements prescribed in NFPA 13 and must be no smaller than the Contract Drawings. Each set of drawings must include the following:
a. A descriptive index with drawings listed in sequence by number. A legend sheet identifying device symbols, nomenclature, and conventions
SECTION 21 13 13 Page 6 used in the package.
b. Floor plans drawn to a scale not less than 1:100 clearly showing locations of devices, equipment, risers, and other details required to clearly describe the proposed arrangement.
c. Actual center-to-center dimensions between sprinklers on branch lines and between branch lines; from end sprinklers to adjacent walls; from walls to branch lines; from sprinkler feed mains, cross mains and branch lines to finished floor and roof or ceiling. A detail must show the dimension from the sprinkler and sprinkler deflector to the ceiling in finished areas.
d. Longitudinal and transverse building sections showing typical branch line and cross main pipe routing, elevation of each typical sprinkler above finished floor and elevation of "cloud" or false ceilings in relation to the building ceilings.
e. Plan and elevation views which establish that the equipment will fit the allotted spaces with clearance for installation and maintenance.
f. Riser layout drawings drawn to a scale of not less than 1:25 to show details of each system component, clearances between each other and from other equipment and construction in the room.
g. Details of each type of riser assembly, pipe hanger, sway bracing for earthquake protection, and restraint of underground water main at point-of-entry into the building, and electrical devices and interconnecting wiring. The dimension from the edge of vertical piping to the nearest adjacent wall(s) must be indicated on the drawings when vertical piping is located in stairs or other portions of the means of egress.
h. Details of each type of pipe hanger and related components.
1.4.1.2 Product Data
Three copies of annotated catalog data to show the specific model, type, and size of each item. Catalog cuts must also indicate the NRTL listing.
The data must be highlighted to show model, size, options, and other pertinent information, that are intended for consideration. Data must be adequate to demonstrate compliance with all contract requirements.
Product data for all equipment must be combined into a single submittal.
1.4.1.3 Hydraulic Calculations
Calculations must be as outlined in NFPA 13 except that calculations must be performed by computer using software intended specifically for fire protection system design using the design data shown on the drawings.
1.4.1.4 Operating and Maintenance (O&M) Instructions
Submit in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA as supplemented and modified by this specification section.
Provide six manuals and one pdf version on electronic media. The manuals must include the manufacturer's name, model number, parts list, list of parts and tools that should be kept in stock by the owner for routine maintenance, troubleshooting guide, and recommended service organization
SECTION 21 13 13 Page 7
(including address and telephone number) for each item of equipment.
Submit spare parts data for each different item of material and equipment specified. The data must include a complete list of parts and supplies, and a list of parts recommended by the manufacturer to be replaced after 1-year and 3 years of service. Include a list of special tools and test equipment required for maintenance and testing of the products supplied.
1.4.2 Qualifications
1.4.2.1 Sprinkler System Designer
The sprinkler system designer must be certified as a Level III Technician by National Institute for Certification in Engineering Technologies (NICET) in the Water-Based Systems Layout subfield of Fire Protection Engineering Technology in accordance with NICET 1014-7 .
1.4.2.2 Sprinkler System Installer
The sprinkler system installer must be regularly engaged in the installation of the type and complexity of system specified in the contract documents, and must have served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.
1.4.3 Regulatory Requirements
Equipment and material must be listed or approved. Listed or approved, as used in this Section, means listed, labeled or approved by a Nationally Recognized Testing Laboratory (NRTL) such as UL Fire Prot Dir or FM APP GUIDE. The omission of these terms under the description of an item or equipment described must not be construed as waiving this requirement. All listings or approvals by testing laboratories must be from an existing ANSI or UL published standard. The recommended practices stated in the manufacturer's literature or documentation are mandatory requirements.
1.5 DELIVERY, STORAGE, AND HANDLING
Protect all equipment delivered and placed in storage from the weather, excessive humidity and temperature variations, dirt and dust, or other contaminants. All pipes must be either capped or plugged until installed.
1.6 EXTRA MATERIALS
Spare sprinklers and wrench(es) must be provided as spare parts in accordance with NFPA 13 .
PART 2 PRODUCTS
2.1 MATERIALS AND EQUIPMENT
2.1.1 Standard Products
Provide materials, equipment, and devices listed for fire protection service when so required by NFPA 13 or this specification. Select material from one manufacturer, where possible, and not a combination of manufacturers, for a classification of material. Material and equipment must be standard products of a manufacturer regularly engaged in the
SECTION 21 13 13 Page 8 manufacture of the products for at least 2 years prior to bid.
2.1.2 Nameplates
Major components of equipment must have the manufacturer's name, address, type or style, model or serial number, catalog number, date of installation, installing Contractor's name and address, and the contract number provided on a new name plate permanently affixed to the item or equipment. Nameplates must be etched metal or plastic, permanently attached by screws to control units, panels or adjacent walls.
2.1.3 Identification and Marking
Pipe and fitting markings must include name or identifying symbol of manufacturer and nominal size. Pipe must be marked with ASTM designation. Valves and equipment markings must have name or identifying symbol of manufacturer, specific model number, nominal size, name of device, arrow indicating direction of flow, and position of installation (horizontal or vertical), except if valve can be installed in either position. Markings must be included on the body casting or on an etched or stamped metal nameplate permanently on the valve or cover plate.
2.1.4 Pressure Ratings
Valves, fittings, couplings, alarm switches, and similar devices must be rated for the maximum working pressures that can be experienced in the system, but in no case less than 1207 kPa.
2.2 UNDERGROUND PIPING COMPONENTS
2.2.1 Pipe
Pipe must comply with NFPA 24 . Minimum pipe size is 150 mm. Piping more than 1.50 meters outside the building walls must comply with Section 33 11 00 WATER UTILITY DISTRIBUTION PIPING. A continuous section of welded stainless steel fire water service piping from a point outside the building perimeter to a flanged fitting at least 304 mm above the finished floor within the building is acceptable.
2.2.2 Fittings and Gaskets
Fittings must be ductile-iron conforming to AWWA C110/A21.10 with cement mortar lining conforming to AWWA C104/A21.4 . Gaskets must be suitable in design and size for the pipe with which such gaskets are to be used.
Gaskets for ductile-iron pipe joints must conform to AWWA C111/A21.11 .
2.2.3 Buried Utility Warning and Identification Tape
Provide detectable aluminum foil plastic backed tape or detectable magnetic plastic tape manufactured specifically for warning and identification of buried piping. Tape must be detectable by an electronic detection instrument. Provide tape, 80 mm minimum width, color coded for the utility involved with warning and identification imprinted in bold block letters continuously and repeatedly over the entire tape length.
Warning and identification must read "CAUTION BURIED WATER PIPING BELOW" or similar wording. Use permanent code and letter coloring unaffected by moisture and other substances contained in trench backfill material.
SECTION 21 13 13 Page 9
2.3 ABOVEGROUND PIPING COMPONENTS
2.3.1 Steel Piping Components
2.3.1.1 Steel Pipe
Except as modified herein, steel pipe must be black as permitted by NFPA 13 and conform to the applicable provisions of ASTM A53/A53M, ASTM A135/A135M or ASTM A153/A153M .
Steel pipe must be minimum Schedule 40 for sizes 50 mm and less; and minimum Schedule 10 for sizes larger than 50 mm. Steel piping with wall thickness less than Schedule 40 must not be threaded.
2.3.1.2 Fittings
Fittings must be welded, threaded, or grooved-end type. Threaded fittings must be cast-iron conforming to ASME B16.4 , malleable-iron conforming to ASME B16.3 or ductile-iron conforming to ASTM A536. Plain-end fittings with mechanical couplings, fittings that use steel gripping devices to bite into the pipe, steel press fittings and field welded fittings are not permitted. Fittings, mechanical couplings, and rubber gaskets must be supplied by the same manufacturer. Threaded fittings must use Teflon tape or manufacturer's approved joint compound. Reducing couplings are not permitted except as allowed by NFPA 13 .
2.3.1.3 Grooved Mechanical Joints and Fittings
Joints and fittings must be designed for not less than 1200 kPa service and the product of the same manufacturer. Field welded fittings must not be used. Fitting and coupling housing must be malleable-iron conforming to ASTM A47/A47M, Grade 32510; ductile-iron conforming to ASTM A536, Grade 65-45-12. Rubber gasketed grooved-end pipe and fittings with mechanical couplings are permitted in pipe sizes 50 mm and larger. Gasket must be the flush type that fills the entire cavity between the fitting and the pipe. Nuts and bolts must be heat-treated steel conforming to ASTM A183 and must be cadmium-plated or zinc-electroplated.
2.3.1.4 Flanges
Flanges must conform to NFPA 13 and ASME B16.1 . Gaskets must be non-asbestos compressed material in accordance with ASME B16.21 , 1.6 mm thick, and full face or self-centering flat ring type.
2.3.2 Flexible Sprinkler Hose
The use of flexible hose is not permitted.
2.3.3 Pipe Hangers and Supports
Provide galvanized pipe hangers, supports and seismic bracing and supports in accordance with NFPA 13 . Design and install seismic protection in accordance with the requirements of NFPA 13 section titled "Protection of Piping Against Damage Where Subject to Earthquakes for Seismic Design Category "D".
2.3.4 Valves
Provide valves of types approved for fire service. Valves must open by
SECTION 21 13 13 Page 10 counterclockwise rotation.
2.3.4.1 Control Valve
Manually operated sprinkler control/gate valve must be as indicated on the drawings and must be listed.
2.3.4.2 Check Valves
Check valves must comply with UL 312 . Check valves 100 mm and larger must be of the swing type, have a clear waterway and meet the requirements of MSS SP-71 , for Type 3 or 4. Inspection plate must be provided on valves larger than 150 mm.
2.3.4.3 Hose Valve
Valve must comply with UL 668 .
2.3.5 Riser Check Valves
Provide riser check valve, pressure gauges and main drain.
2.4 ALARM INITIATING AND SUPERVISORY DEVICES
2.4.1 Sprinkler Alarm Switch
Vane or pressure-type flow switch(es). Connection of switch must be by the fire alarm installer. Vane type alarm actuating devices must have mechanical diaphragm controlled retard device adjustable from 10 to 60 seconds and must instantly recycle.
2.4.2 Valve Supervisory (Tamper) Switch
Switch must be integral to the control valve or suitable for mounting to the type of control valve to be supervised open. The switch must be tamper resistant and contain SPDT (Form C) contacts arranged to transfer upon removal of the housing cover or closure of the valve of more than two rotations of the valve stem.
2.5 BACKFLOW PREVENTION ASSEMBLY
Reduced-pressure principle valve assembly backflow preventer complying with ASSE 1013 , ASSE 1015 and AWWA M14. Each check valve must have a drain. Backflow prevention assemblies must have current "Certificate of Approval from the Foundation for Cross-Connection Control and Hydraulic Research, FCCCHR List" and be listed for fire protection use. Listing of the specific make, model, design, and size in the FCCCHR List is acceptable as the required documentation.
2.5.1 Backflow Preventer Test Connection
Test connection must consist of a series of listed hose valves with 65-mm National Standard male hose threads with cap and chain.
2.6 FIRE DEPARTMENT CONNECTION
Fire department connection must be projecting type with cast-brass body, matching wall escutcheon lettered "Auto Spkr" with a polished-brass finish. The connection must have individual self-closing clappers, caps
SECTION 21 13 13 Page 11 with drip drains and chains. Female inlets must have 65-mm diameter American National Fire Hose Connection Screw Threads (NH) per NFPA 1963 .
Comply with UL 405 .
2.7 SPRINKLERS
Sprinklers must comply with UL 199 and NFPA 13 . Sprinklers with internal O-rings are not acceptable. Sprinklers in high heat areas including attic spaces or in close proximity to unit heaters must have temperature classification in accordance with NFPA 13 . Extended coverage sprinklers are permitted for loading docks, residential occupancies and high-piled storage applications only.
2.7.1 Pendent Sprinkler
Pendent sprinkler must be recessed quick-response type with nominal K-factor as indicated on the drawings. Pendent sprinklers must have a polished chrome finish. Assembly must include an integral escutcheon.
2.7.2 Upright Sprinkler
Upright sprinkler must be brass quick-response type and have a nominal K-factor as indicated on the drawings. Sprinklers in the Engine Halls must be intermediate temperature rated or higher as permitted by NFPA 13 ..
2.8 ACCESSORIES
2.8.1 Sprinkler Cabinet
Provide spare sprinklers in accordance with NFPA 13 and must be placed in a suitable metal or plastic cabinet of sufficient size to accommodate all the spare sprinklers and wrenches in designated locations. Spare sprinklers must be representative of, and in proportion to, the number of each type and temperature rating of the sprinklers installed as required by NFPA 13 . At least one wrench of each type required must be provided.
2.8.2 Pendent Sprinkler Escutcheon
Escutcheon must be two-piece metallic type with a depth of less than 19 mm and suitable for installation on pendent sprinklers. The escutcheon must have a factory finish that matches the pendent sprinkler.
2.8.3 Pipe Escutcheon
Provide split hinge metal plates for piping entering walls, floors, and ceilings in exposed spaces. Provide polished stainless steel plates or chromium-plated finish on copper alloy plates in finished spaces. Provide paint finish on metal plates in unfinished spaces.
2.8.4 Relief Valve
Relief valves must be listed and installed at the riser in accordance with
NFPA 13 .
2.8.5 Air Vent
Air vents must be of the automatic type and piped to drain to the building exterior.
SECTION 21 13 13 Page 12
2.8.6 Identification Sign
Valve identification sign must be minimum 150 mm wide by 50 mm high with enamel baked finish on minimum 1.214-mm steel or 0.6-mm aluminum with red letters on a white background or white letters on red background. Wording of sign must include, but not be limited to "main drain", "auxiliary drain", "inspector's test", "alarm test", "alarm line", and similar wording as required to identify operational components. Where there is more than one sprinkler system, signage must include specific details as to the respective system.
PART 3 EXECUTION
3.1 VERIFYING ACTUAL FIELD CONDITIONS
Before commencing work, examine all adjoining work on which the contractor's work that is dependent for perfect workmanship according to the intent of this specification section, and report to the Contracting Officer's Representative a condition that prevents performance of first class work. No "waiver of responsibility" for incomplete, inadequate or defective adjoining work will be considered unless notice has been filed before submittal of a proposal.
3.2 INSTALLATION
The installation must be in accordance with the applicable provisions of NFPA 13 , NFPA 24 and publications referenced therein. Locate sprinklers in a consistent pattern with ceiling grid, lights, and air supply diffusers. Install sprinkler system over and under ducts, piping and platforms when such equipment can negatively affect or disrupt the sprinkler discharge pattern and coverage.
a. Piping offsets, fittings, and other accessories required must be furnished to provide a complete installation and to eliminate interference with other construction.
b. Wherever the contractor's work interconnects with work of other trades the Contractor must coordinate with other Contractors to insure all Contractors have the information necessary so that they may properly install all necessary connections and equipment. Identify all work items needing access (dampers and similar equipment) that are concealed above hung ceilings by permanent color coded pins/tabs in the ceiling directly below the item.
c. Provide required supports and hangers for piping, conduit, and equipment so that loading will not exceed allowable loadings of structure. Submittal of a bid must be a deemed representation that the contractor submitting such bid has ascertained allowable loadings and has included in his estimates the costs associated in furnishing required supports.
3.2.1 Waste Removal
At the conclusion of each day's work, clean up and stockpile on site all waste, debris, and trash which may have accumulated during the day as a result of work by the contractor and of his presence on the job.
Sidewalks and streets adjoining the property must be kept broom clean and free of waste, debris, trash and obstructions caused by work of the contractor, which will affect the condition and safety of streets, walks, SECTION 21 13 13 Page 13 utilities, and property.
3.3 UNDERGROUND PIPING INSTALLATION
The fire protection water main must be laid, and joints anchored, in accordance with NFPA 24 . Minimum depth of cover must be 900 mm or the frost line, whichever is deeper. The supply line must terminate inside the building with a flanged piece, the bottom of which must be set not less than 304 mm above the finished floor. A blind flange must be installed temporarily on top of the flanged piece to prevent the entrance of foreign matter into the supply line. A concrete thrust block must be provided at the elbow where the pipe turns up toward the floor. In addition, joints must be anchored in accordance with NFPA 24 . Buried steel components must be provided with a corrosion protective coating in accordance with AWWA C203. Piping more than 1500 mm outside the building walls must meet the requirements of Section 33 11 00 WATER UTILITY
DISTRIBUTION PIPING.
3.4 ABOVEGROUND PIPING INSTALLATION
The methods of fabrication and installation of the aboveground piping must fully comply with the requirements and recommended practices of NFPA 13 and this specification section.
3.4.1 Protection of Piping Against Earthquake Damage
Seismic restraint is required.
3.4.2 Piping in Exposed Areas
Install exposed piping without diminishing exit access widths, corridors or equipment access. Exposed horizontal piping, including drain piping, must be installed to provide maximum headroom.
3.4.3 Piping in Finished Areas
In areas with suspended or dropped ceilings and in areas with concealed spaces above the ceiling, piping must be concealed above ceilings. Piping must be inspected, hydrostatically tested and approved before being concealed. Risers and similar vertical runs of piping in finished areas must be concealed.
3.4.4 Pendent Sprinklers
a. Drop nipples to pendent sprinklers must consist of minimum 25-mm pipe with a reducing coupling into which the sprinkler must be threaded.
b. Where sprinklers are installed below suspended or dropped ceilings, drop nipples must be cut such that sprinkler ceiling plates or escutcheons are of a uniform depth throughout the finished space. The outlet of the reducing coupling must not extend below the underside of the ceiling.
c. Recessed pendent sprinklers must be installed such that the distance from the sprinkler deflector to the underside of the ceiling must not exceed the manufacturer's listed range and must be of uniform depth throughout the finished area.
d. Pendent sprinklers in suspended ceilings must be located in the center
SECTION 21 13 13 Page 14 of the tile (plus or minus 2 inches).
e. Where the maximum static or flowing pressure, whichever is greater at the sprinkler, applied other than through the fire department connection, exceeds 6.9 bar and a branch line above the ceiling supplies sprinklers in a pendent position below the ceiling, the cumulative horizontal length of an unsupported armover to a sprinkler or sprinkler drop must not exceed 300 mm for steel pipe.
3.4.5 Upright Sprinklers
Riser nipples or "sprigs" to upright sprinklers must contain no fittings between the branch line tee and the reducing coupling at the sprinkler.
3.4.6 Pipe Joints
Pipe joints must conform to NFPA 13 , except as modified herein. Not more than four threads must show after joint is made up. Welded joints will be permitted, only if welding operations are performed as required by NFPA 13 at the Contractor's fabrication shop, not at the project construction site. Flanged joints must be provided where indicated or required by NFPA 13 . Grooved pipe and fittings must be prepared in accordance with the manufacturer's latest published specification according to pipe material, wall thickness and size. Grooved couplings, fittings and grooving tools must be products of the same manufacturer. For copper tubing, pipe and groove dimensions must comply with the tolerances specified by the coupling manufacturer. The diameter of grooves made in the field must be measured using a "go/no-go" gauge, vernier or dial caliper, narrow-land micrometer, or other method specifically approved by the coupling manufacturer for the intended application. Groove width and dimension of groove from end of pipe must be measured and recorded for each change in grooving tool setup to verify compliance with coupling manufacturer's tolerances.
3.4.7 Reducers
Reductions in pipe sizes must be made with one-piece tapered reducing fittings. When standard fittings of the required size are not manufactured, single bushings of the face or hex type will be permitted.
Where used, face bushings must be installed with the outer face flush with the face of the fitting opening being reduced. Bushings cannot be used in elbow fittings, in more than one outlet of a tee, in more than two outlets of a cross, or where the reduction in size is less than 13 mm.
3.4.8 Pipe Penetrations
a. Cutting structural members for passage of pipes or for pipe-hanger fastenings will not be permitted. Pipes that must penetrate concrete or masonry walls or concrete floors must be core-drilled and provided with pipe sleeves. Each sleeve must be Schedule 40 galvanized steel, ductile-iron or cast-iron pipe and extend through its respective wall or floor and be cut flush with each wall surface. Sleeves must provide required clearance between the pipe and the sleeve per NFPA 13 .
The space between the sleeve and the pipe must be firmly packed with mineral wool insulation.
b. Where pipes and sleeves penetrate fire walls, fire partitions, or floors, pipes/sleeves must be firestopped in accordance with Section
07 84 00 FIRESTOPPING.
SECTION 21 13 13 Page 15
c. In penetrations that are not fire-rated or not a floor penetration, the space between the sleeve and the pipe must be sealed at both ends with plastic waterproof cement that will dry to a firm but pliable mass or with a mechanically adjustable segmented elastomer seal.
3.4.9 Escutcheons
Escutcheons must be provided for pipe penetration in finished areas of ceilings, floors and walls. Escutcheons must be securely fastened to the pipe at surfaces through which piping passes.
3.4.10 Inspector's Test Connection
Unless otherwise indicated, the test connection must consist of 25-mm pipe connected at the riser as a combination test and drain valve; a test valve located approximately 2 meters above the floor; a smooth bore brass outlet equivalent to the smallest orifice sprinkler used in the system; and a painted metal identification sign affixed to the valve with the words "Inspector's Test". All test connection piping must be inside of the building and penetrate the exterior wall at the location of the discharge orifice only. The discharge orifice must be located outside the building wall no more than 0.6 meters above finished grade, directed so as not to cause damage to adjacent construction or landscaping during full flow discharge, or to the sanitary sewer. Discharge to the exterior must not interfere with exiting from the facility. Water discharge or runoff must not cross the path of egress from the building. Do not discharge to the roof. Discharge to floor drains, janitor sinks or similar fixtures is not permitted.
Provide concrete splash blocks at all drain and inspector's test connection discharge locations if not discharging to a concrete surface.
Splash blocks must be large enough to mitigate erosion and not become dislodged during a full flow of the drain. Ensure all discharged water drains away from the facility and does not cause property damage.
3.4.11 Backflow Preventer
Locate within the building as indicated on the drawings.
Install backflow preventers so that the bottom of the assembly is a minimum of 150 mm above the finished floor/grade. Clearance around control valve handles must be minimum 150 mm above grade/finished floor and away from walls.
3.4.11.1 Test Connection
Provide downstream of the backflow prevention assembly UL 668 hose valves with 65-mm National Standard male hose threads with cap and chain.
Provide one valve for each 946 L/min of system demand or fraction thereof. Provide a permanent sign in accordance with paragraph entitled "Identification Signs" which reads, "Test Valve". Indicate location of test header. If an exterior connection, provide a control valve inside a heated mechanical room to prevent freezing.
3.4.12 Drains
a. Main drain piping must be provided to discharge at a safe point outside the building, no more than 0.6 meters above finished grade.
SECTION 21 13 13 Page 16
Provide a concrete splash block at drain outlet. Discharge to the exterior must not interfere with exiting from the facility. Water discharge or runoff must not cross the path of egress from the building.
b. Auxiliary drains must be provided as required by NFPA 13 . Auxiliary drains are permitted to discharge to a floor drain if the drain is sized to accommodate full flow (min 151 L/min). Discharge to service sinks or similar plumbing fixtures is not permitted.
3.4.13 Installation of Fire Department Connection
Connection must be mounted on the exterior wall approximately 900 mm above finished grade and adjacent to and on the sprinkler system side of the backflow preventer. The piping between the connection and the check valve must be provided with an automatic drip in accordance with NFPA 13 and piped to drain to the outside or a floor drain within the same room.
3.4.14 Identification Signs
Signs must be affixed to each control valve, inspector test valve, main drain, auxiliary drain, test valve, and similar valves as appropriate or as required by NFPA 13 . Main drain test results must be etched into main drain identification sign. Hydraulic design data must be etched into the nameplates and permanently affixed to each sprinkler riser as specified in NFPA 13 . Provide labeling on the surfaces of all feed and cross mains to show the pipe function (e.g., "Sprinkler System", "Fire Department Connection", "Standpipe") and normal valve position (e.g. "Normally Open", "Normally Closed"). For pipe sizes 100 mm and larger provide white painted stenciled letters and arrows, a minimum of 50 mm in height and visible from at least two sides when viewed from the floor. For pipe sizes less than 100 mm, provide white painted stenciled letters and arrows, a minimum of 18 mm in height and visible from the floor.
3.5 ELECTRICAL
Except as modified herein, electric equipment and wiring must be in accordance with Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM. Alarm signal wiring connected to the building fire alarm control system must be by the fire alarm installer.
3.6 PAINTING
Color code mark piping as specified in Section 09 90 00 PAINTS AND COATINGS.
3.7 FIELD QUALITY CONTROL
3.7.1 Test Procedures
Submit detailed test procedures, prepared and signed by the NICET Level III Fire Sprinkler Technician, and the representative of the installing company, and reviewed by the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .