Amend 0015.pdf

PDF 1 MB Posted

Attached to
BEQ Repair AS4212
Solicitation number
N4008525R2620
Issued by

About this file

This document is an Amendment of Solicitation/Modification of Contract for the Repair BEQ AS4212 project, issued by NAVFAC Mid-Atlantic. Amendment No. 0015 addresses two key clarification questions from potential bidders. First, it confirms that ELIN 0002 involves demolition work for HP455 and SHP456 (specifically the gear washrack and concrete foundation), and ELIN 0004 references parking lot work associated with AS4212, which is identified in drawings CD101 and CS101. Second, the amendment clarifies that Furniture, Fixtures, and Equipment (FF&E) is not required and should not be included as a bid item or part of the base bid.

The amendment maintains the original proposal receipt deadline of 1400 hours on 21 August 2025, with the solicitation number N40085-25-R-2620. Bidders are advised that failure to acknowledge this amendment may constitute grounds for proposal rejection. The document is part of a construction contract modification process, providing critical clarifications to ensure accurate bidding for the specified project.

View the file

Other files

File Type Posted
Amend 0021.pdf PDF
Amend 0020.pdf PDF
Amend 0019.pdf PDF
Amend 0018.pdf PDF
Amend 0017.pdf PDF
Amend 0016.pdf PDF
Amend 0013.pdf PDF
Amend 0014.pdf PDF
60040177.pdf PDF
60040178.pdf PDF
60040167.pdf PDF
Updated SUBMITTAL REGISTER.pdf PDF
60040172.pdf PDF
60040137.pdf PDF
Updated List of Drawings.pdf PDF
60040262.pdf PDF
60040179.pdf PDF
60040268.pdf PDF
Updated PROJECT TABLE OF CONTENTS.pdf PDF
60040164.pdf PDF
11 81 00.pdf PDF
60040186.pdf PDF
60040187.pdf PDF
60040189.pdf PDF
60040299.pdf PDF
07 60 00.pdf PDF
07 61 15.00 20.pdf PDF
60040174A.pdf PDF
60040250.pdf PDF
60040188.pdf PDF
05 51 33.pdf PDF
Amend 12 and spec combined.pdf PDF
Amend 0012.pdf PDF
Amend 0011.pdf PDF
Amend 0010.pdf PDF
Amend 0009.pdf PDF
60040202_PPI.pdf PDF
60040196_PPI.pdf PDF
60040201_PPI.pdf PDF
PROJECT.pdf PDF
60040198_PPI.pdf PDF
60040197_PPI.pdf PDF
SECTION 33 61 14.pdf PDF
60040199_PPI.pdf PDF
60040210_PPI.pdf PDF
Amend and cont sheet combined.pdf PDF
60040195_PPI.pdf PDF
60040290_PPI.pdf PDF
REGISTER.pdf PDF
60040194_PPI.pdf PDF
Show 40 more

Latest 50 of 61 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N40085-25-R-2620 Amendment 0015

CONTINUATION SHEET

1. QUESTION: In regard to the Repair BEQ AS4212 project, the pricing sheet issued in amendment 0012, ELIN 0002 references all associated work with the demolition of HP455 and SHP456. However, it appears there is no reference to SHP456 in the plans. Can the Government please confirm the building number associated with this ELIN for accurate pricing.

ELIN 0004 references all work associated with milling, overlaying, and striping of the parking lot at BEQ BB250. This ELIN was bid in a previous barracks bid; can the government please confirm what parking lot needs to be priced for ELIN 0004 so that correct parking lot can be priced.

ANSWER:

a) ELIN 002 Question: HP455 and SHP456 are correct. SHP456 is identified by keynote #5 on CD701. It is the gear washrack and concrete foundation for it.

b) ELIN 0004 incorrectly references BB250. The parking lot associated with AS4212 is identified in the drawings on CD101 and CS101.

2. QUESTION: There is a specification section 12 00 01.00 20 for FF&E. Will this be required? Will the bid form add a line for the HAR? If required, does the design costs be part of the base bid?

ANSWER: FF&E is not required. It should not be a bid item on the bid form and not required as part of base bid.

3. All other terms and conditions remain unchanged.

File details come from the government source that posted it. Updated .