AMENDMENT 0015.pdf

PDF 166 KB Posted

Attached to
P-381 MULTI-MISSION DRY DOCK #1, PORTSMOUTH NAVAL SHIPYARD (PNSY), KITTERY MAINE
Solicitation number
N4008520R0021
Issued by

About this file

This amendment modifies a solicitation for a design-bid-build project to construct additions to an existing dry dock at Portsmouth Naval Shipyard in Kittery, Maine. The project involves building two new dry dock bays labeled Dry Dock 1 North and Dry Dock 1 West to support maintenance and overhaul of Virginia-class submarines, with concrete floors, walls, center wall, new pump well systems, pump station building, crane rails, mooring hardware, utilities and appurtenances. Modifications will be made to the existing basin closure wall and Berths 1 and 11. The existing Dry Dock 1 will be renamed Dry Dock 1 East. The amendment provides updates to contract clauses and drawings, adds liquidated damages and a limitation of government obligation clause, and revises construction sequencing and phasing plans and milestones.

View the file

Other files

File Type Posted
Amendment 14 - 25 00 00.00 22.pdf PDF
Amendment 14 - Electrical dwgs.pdf PDF
AMENDMENT 0014.pdf PDF
Amendment 14 - Mechanical Dwgs.pdf PDF
Amendment 14 - Electrical One Line.pdf PDF
Amendment 14 - Fire Protection One Line.pdf PDF
Amendment 14 - Henderson Point Dwgs.pdf PDF
Amendment 14 - Nitrogren Overall Plan.pdf PDF
Amendment 14 - Panelboards.pdf PDF
Amendment 14 - 32 31 13.53.pdf PDF
Amendment 14 - Raychem RHW 2-hour fire-rated power cable.pdf PDF
Amendment 14 - Civil Site Dwgs.pdf PDF
Amendment 14 - 25 00 00.00 22_ASW_Control.pdf PDF
Amendment 14 - General Dwgs.pdf PDF
Amendment 13 - Hendersen Pt Site Dwgs.pdf PDF
Amendment 13 - General Dwgs.pdf PDF
Amendment 13 - Electrical Dwgs.pdf PDF
Amendment 13 - Mechanical Dwgs.pdf PDF
Amendment 13 - Structural Dwgs.pdf PDF
Amendment 13 - Geotech dwgs.pdf PDF
AMENDMENT 0013.pdf PDF
Amendment 0013 - Price Proposal Form (rev).pdf PDF
Amendment 13 - Civil Dwgs.pdf PDF
Amendment 13 - 40 95 00 App B - IO List.pdf PDF
Amendment 13 - Process dwgs.pdf PDF
AMENDMENT 0012.pdf PDF
Amendment 12 - Structural Drawings.pdf PDF
Amendment 12 - General Drawings.pdf PDF
Amendment 12 - 40 95 00 App B - IO List.pdf PDF
Amendment 12 - LightFixt_BOD_1_5_2021.pdf PDF
Amendment 12 - Pump Station and Utility Enclosure.pdf PDF
Amendment 12 - Electrical drawings.pdf PDF
Amendment 0011.pdf PDF
Amendment 10 - General dwgs.pdf PDF
Amendment 10 - Drydock 1 existing pumpwell valve arrangements drawings.pdf PDF
Amendment 10 - Geotech- Structural dwgs.pdf PDF
Amendment 10 - Architectural dwgs.pdf PDF
Amendment 10 - Electrical dwgs.pdf PDF
Amendment 10 - Mechanical.dwgs.pdf PDF
AMENDMENT 0010.pdf PDF
Amendment 10 - Civil dwgs.pdf PDF
Amendment 0009.pdf PDF
Amendment 8 - Structural.pdf PDF
Amendment 8 -mechanical.pdf PDF
01 50 00.00 22.pdf PDF
Amendment 8 - Geotech.pdf PDF
23 81 23.00 20.pdf PDF
Amendment 8 -Civil.pdf PDF
Amendment 8 -Structural Bld.pdf PDF
21 13 13.00 20.pdf PDF
Show 40 more

Latest 50 of 123 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

J 1 13

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable) 0015 10-Aug-2021

6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code

NAVFAC MID ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

See Item 6

NORFOLK VA 23511-3095

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.

N4008520R0021

9B. DATED (SEE ITEM 11)

31-Aug-2020

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

SOLICITATION NO. N40085-20-R-0021, DESIGN-BID-BUILD (DBB), P-381, MULTI MISSION DRY DOCK #1, PORTSMOUTH

NAVAL SHIPYARD, KITTERY, ME

The purpose of this amendment is to provide updates to contract clauses and updates to drawings and specifications.

See continuation Page(s).

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8) 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The following have been added by full text:

CONTINUATION PAGE

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amounts listed in the table below for each calendar day of delay until the work is completed or accepted.

Milestone

Title Liquidated Damages

1 Demob Vessel 1 Docking DD1E 21-Feb-22 $2,500 2 Remob following Vessel 1 Docking

DD1E

3-Mar-22

$2,500

3 Demob to support Vessel 1 Undocking DD1E on October, 29, 22-Oct-23 $2,500

4 Remob following Vessel 2 Docking DD1E on November 12, 2023

15-Nov-23 $2,500

5 Demob to support Vessel 2 Undocking DD1E on August 3, 2025

27-Jul-25 $2,500

6 Remob following Vessel 3 Docking DD1E on August 17, 2025

20-Aug-25 $2,500

7 DD1N Complete 28-Oct-26 $30,000 8 DD1N Certification Complete 26-Jan-27 $2,500 9 Demob to support Vessel 3

Undocking DD1E on May 3, 2027 26-Apr-27

$2,500

10 Remob following Vessel 4 Docking in DD1E on May 17, 2027

20-May-27 $2,500

11 DD1W Complete 2-Mar-28 $20,000 12 DD1W Certification Complete 31-May-28 $2,500

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

*The exercising of any options do not affect the liquidated damages listed above.

(End of clause)

252.232-7077 LIMITATION OF GOVERNMENT’S OBLIGATION (APR 2014)

(a) Contract line item(s) CLINS 001 through 013 (excluding any unexercised options) are incrementally funded.

For this/these item(s), the sum of $70,000,000 of the total price is presently available for payment and allotted to this contract. An allotment schedule is set forth in paragraph (j) of this clause.

(b) For item(s) identified in paragraph (a) of this clause, the Contractor agrees to perform up to the point at which the total amount payable by the Government, including reimbursement in the event of termination of those item(s) for the Government’s convenience, approximates the total amount currently allotted to the contract. The Contractor is not authorized to continue work on those item(s) beyond that point. The Government will not be obligated in any event to reimburse the Contractor in excess of the amount allotted to the contract for those item(s) regardless of anything to the contrary in the clause entitled “Termination for Convenience of the Government.” As used in this clause, the total amount payable by the Government in the event of termination of applicable contract line item(s) for convenience includes costs, profit, and estimated termination settlement costs for those item(s).

(c) Notwithstanding the dates specified in the allotment schedule in paragraph (j) of this clause, the Contractor will notify the Contracting Officer in writing at least ninety days prior to the date when, in the Contractor’s best judgment, the work will reach the point at which the total amount payable by the Government, including any cost for termination for convenience, will approximate 85 percent of the total amount then allotted to the contract for performance of the applicable item(s). The notification will state (1) the estimated date when that point will be reached and (2) an estimate of additional funding, if any, needed to continue performance of applicable line items up to the next scheduled date for allotment of funds identified in paragraph (j) of this clause, or to a mutually agreed upon substitute date. The notification will also advise the Contracting Officer of the estimated amount of additional funds that will be required for the timely performance of the item(s) funded pursuant to this clause, for a subsequent period as may be specified in the allotment schedule in paragraph (j) of this clause or otherwise agreed to by the parties. If after such notification additional funds are not allotted by the date identified in the Contractor’s notification, or by an agreed substitute date, the Contracting Officer will terminate any item(s) for which additional funds have not been allotted, pursuant to the clause of this contract entitled “Termination for Convenience of the Government.”

(d) When additional funds are allotted for continued performance of the contract line item(s) identified in paragraph (a) of this clause, the parties will agree as to the period of contract performance which will be covered by the funds. The provisions of paragraphs (b) through (d) of this clause will apply in like manner to the additional allotted funds and agreed substitute date, and the contract will be modified accordingly.

(e) If, solely by reason of failure of the Government to allot additional funds, by the dates indicated below, in amounts sufficient for timely performance of the contract line item(s) identified in paragraph (a) of this clause, the Contractor incurs additional costs or is delayed in the performance of the work under this contract and if additional funds are allotted, an equitable adjustment will be made in the price or prices (including appropriate target, billing, and ceiling prices where applicable) of the item(s), or in the time of delivery, or both. Failure to agree to any such equitable adjustment hereunder will be a dispute concerning a question of fact within the meaning of the clause entitled “Disputes.”

(f) The Government may at any time prior to termination allot additional funds for the performance of the contract line item(s) identified in paragraph (a) of this clause.

(g) The termination provisions of this clause do not limit the rights of the Government under the clause entitled “Default.” The provisions of this clause are limited to the work and allotment of funds for the contract line item(s) set forth in paragraph (a) of this clause. This clause no longer applies once the contract is fully funded except with regard to the rights or obligations of the parties concerning equitable adjustments negotiated under paragraphs (d) and (e) of this clause.

(h) Nothing in this clause affects the right of the Government to terminate this contract pursuant to the clause of this contract entitled “Termination for Convenience of the Government.”

(i) Nothing in this clause shall be construed as authorization of voluntary services whose acceptance is otherwise prohibited under 31 U.S.C. 1342.

(j) The parties contemplate that the Government will allot funds to this contract in accordance with the following schedule below. The amounts listed in FY25-FY27 are notional amounts used for bidding purposes and do not reflect the final negotiated contract total (these will be updated prior to award):

FY21: On execution of contract $ 70,000,000

FY22: 15 December 2021 $ 214,000,000

FY23: 16 January 2023 $ 390,000,000

FY24: 15 January 2024 $ 405,000,000

FY25: 15 January 2025 $ 300,000,000

FY26: 15 January 2026 $ 200,000,000

FY27: 15 January 2027 $ 152,477,644

52.216-4 Economic Price Adjustment-Labor and Material (JAN 2017)

(a) The Contractor shall notify the Contracting Officer if, at any time during contract performance, the rate of pay for labor (including fringe benefits) or the unit prices for material shown in the “Economic Price Adjustment Schedule” (attached hereto and included in the Contractor’s proposal submitted on June 22, 2021) either increase or decrease. The Contractor shall furnish this notice within 60 days after the increase or decrease, or within any additional period that the Contracting Officer may approve in writing, but not later than the date of final payment under this contract. The notice shall include the Contractor's proposal for an adjustment in the contract unit prices to be negotiated under paragraph (b) of this clause, and shall include, in the form required by the Contracting Officer, supporting data explaining the cause, effective date, and amount of the increase or decrease and the amount of the Contractor's adjustment proposal.

(b) Promptly after the Contracting Officer receives the notice and data under paragraph (a) of this clause, the Contracting Officer and the Contractor shall negotiate a price adjustment in the contract unit prices and its effective date. The Contracting Officer will make the adjustments at quarterly intervals throughout the contract performance. The Contracting Officer shall modify this contract (1) to include the price adjustment and its effective date and (2) to revise the labor rates (including fringe benefits) or unit prices of material as shown in the Schedule to reflect the increases or decreases resulting from the adjustment. The Contractor shall continue performance pending agreement on, or determination of, any adjustment and its effective date.

(c) Any price adjustment under this clause is subject to the following limitations:

(1) Any adjustment shall be limited to the effect on unit prices of the increases or decreases in the rates of pay for labor (including fringe benefits) or unit prices for material shown in the Schedule. There shall be no adjustment for-

(i) Supplies or services for which the production cost is not affected by such changes;

(ii) Changes in rates or unit prices other than those shown in the Schedule; or

(iii) Changes in the quantities of labor or material used from those shown in the Schedule for each item.

(2) No upward adjustment shall apply to supplies or services that are required to be delivered or performed before the effective date of the adjustment, unless the Contractor’s failure to deliver or perform according to the delivery schedule results from causes beyond the Contractor’s control and without its fault or negligence, within the meaning of the Default clause.

(3) Adjustments will occur at quarterly intervals throughout the contract performance.

(4) The increases in any contract unit price made under this clause shall not exceed 100 percent of the original unit price. There is no percentage limitation on the amount of decreases that may be made under this clause.

(d) The Contracting Officer may examine the Contractor’s books, records, and other supporting data relevant to the cost of labor (including fringe benefits) and material during all reasonable times until the end of 3 years after the date of final payment under this contract or the time periods specified in subpart 4.7 of the Federal Acquisition Regulation (FAR), whichever is earlier.

(End of clause)

CONTINUATION SHEET

SECTION 01 14 00.00 22 WORK RESTRICTIONS PNSY PROJECTS

1.19.4 Vibration Restrictions

Replace paragraph in its entirety with the following:

“During each critical shipyard operation timeframe, two separate zones for vibration limitations will be established. The first limitation of 0.5 in/sec is required to be met at the dry dock and dry dock complex. The second limitation of 2.0 in/sec is required to be met at the up righting facility.

Vibration monitoring is required in the vicinity of each receptor to ensure compliance during each critical shipyard operation timeframe.”

SECTION 01 45 00.00 22 QUALITY CONTROL (PWD ME)

1.5.2 Underwater QC Team

At the end of the first sentence delete “…..if underwater work is included in this contract”.

At the end of the paragraph add the following paragraphs:

“QC Diver inspections are required to verify in place work that cannot be verified by other means. Other means are visual inspection at low tides, video inspection provided by the production dive team, etc. Video inspection will not be accepted for critical elements that require dimensional and alignment verification. If video or other inspection is not sufficient the Contracting Officer reserves the right to request QC diver inspection. QC divers are not required to verify extent of demolition work or temporary elements of underwater work.

QC Diver inspections are required to verify in place permanent work that cannot be verified by other means.

Other means are visual inspection at low tides, video inspection provided by the production dive team, etc. Video inspection will not be accepted for critical elements that require dimensional and alignment verification. If video or other inspection is not sufficient the Contracting Officer reserves the right to request QC diver inspection.

QC Diver inspections are required for the following items if performed in the wet:

1. Reinforcing / Tremie concrete placements for the connections between the drilled shafts and precast monoliths

2. Reinforcing / Stitch pour connections between monoliths.

3. Reinforcing and “concrete struts” encased in the permanent construction proposed to be used between monoliths in lieu of using structural members as indicated on the contract drawings.

QC divers are not required to verify extent of demolition work, temporary tremies by the contractor, or temporary elements of underwater work including all sheeting, rock anchors, Rock Excavation or Dredging, Caisson Gate inspection, Superflood Inspection, temporary struts except as indicated above, concrete backfill, and jet grouting.

QC divers are not required for Temporary or Permanent Pump inspection, infill or outfall inspection or any commissioning work.”

3.2 Critical Submittal Process

SECTION 35 20 14.01 22 TEMPORARY REMOVABLE BOX COFFERDAM FOR SUPER FLOOD

Delete words “Removable Box” from the item title as well as associated items 1-3.

SECTION 01 50 00.00 22 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS (PWD ME)

1.3 Submittals

Under SD-01 Preconstruction Submittals delete:

“Drydock 1 Temporary Dewatering Pumping System Plan; G”

“Drydock 1 Temporary Drainage Pumping System Plan; G”

Under SD-03 Product Data delete:

“Drydock 1 Temporary Dewatering Pumping System; G”

“Drydock 1 Temporary Drainage Pumping System; G”

1.4 Construction Site Plan

Add the below paragraph:

1.4.4 Superflood Basin

Superflood ability must be maintained and achievable within the dry dock 1 and basin during all docking and undocking evolutions. Within 90 days of award provide anticipated method for supporting superflood for each evolution. (Example - Basin will remain in existing condition, West Closure Wall will be replaced with temporary cofferdam, Superflood will be achieved with use of Center Wall or Modified Center Wall, etc.) The means and methods for supporting superflood are the responsibility of the contractor but require acceptance from the Contracting Officer.

A minimum of 90 days prior to a docking or undocking the contractor must submit a letter notifying the contracting officer to any changes outside of the contract documents made or planned to be made to the structures that make up the basin prior to the docking or undocking. Those structures include: Berth 11, Berth 1, South Clouse Wall, DD1W entrance, and West Closure Wall. Changes outside of the contract documents may require back up calculations depending on the nature of the changes. Calculations are required to show capability of the superflood basin to support the structural loads and exfiltration impacts to the basin. These changes may also require interim testing evolutions of superflood prior to the completion of the phase. If required, testing and certification approval must occur 30 days prior to the completion of the phase.

1.4.4.1 Partial Demobilization During Vessel Movements

Seven days prior to a docking or undocking milestone partial demobilization is required to clear the route from existing Dry Dock 1 through the basin and out through the P-310/Dry Dock 1 West entrance structure. This includes, but is not limited to, the space in the basin, Berth 1, and the center wall.

Work in other areas outside of the path of undocking or docking is permitted to continue during the partial demobilization phase. These areas in general include Berth 11, utility and excavation work outside the crane rail envelope around Dry Dock 1, West Closure Wall area, Dry Dock 1 North footprint. The contractor shall submit list of work scopes that will be proposed for acceptance during this period by the Contracting Officer two weeks prior to each phase. Work scopes that affect docking or undocking efforts will be restricted.

All work inside the CIA area not previously approved to occur during the docking and undockings will be secured during those evolution. Each evolution is a 3 day timeframe for docking or undocking and superflood evolutions. Exact dates will be provided within one week of the docking or undocking.

2.3 Temporary Utilities

Delete paragraphs 2.3.1, 2.3.2 and 2.3.4 in their entirety and replace with the following:

2.3.1 Drydock 1 Temporary Dewatering Pumping System

Emergency Dewatering Pumps

Maintain the existing emergency dewatering pump system provided by the P310 project located in the drydock as indicated on the phasing drawings. The emergency Drydock 1 dewatering system must remain on site and operational until the permanent dewatering pumps have been field tested and certified as specified in Section 35 45 01. These pumps shall remain in place at all times during construction and discharge into the existing basin.

A plan of the system including all pumps, piping, and required appurtenances will be provided to the Contractor by the Government. The P381 Contractor will be responsible for all maintenance of this system throughout the duration of the project and shall provide services of factory trained and certified maintenance personnel. Provide maintenance services in accordance with manufacturer's recommended schedule. Remove emergency dewatering pump system in its' entirety at the completion of the project.

Primary Temporary Dewatering Pumps

Maintain the existing primary temporary dewatering pumps and piping system provided by the P310 project. The temporary pumps and piping systems shall be operated by the Shipyard. A plan of the system including all pumps, piping, and required appurtenances will be provided to the Contractor by the Government. The P381 Contractor will be responsible for all maintenance of this system throughout the duration of the project and shall provide services of factory trained and certified maintenance personnel. Provide maintenance services in accordance with manufacturer's recommended schedule. Remove temporary dewatering pump system in its' entirety at the completion of the project.

2.3.2 Drydock 1 Temporary Drainage Pumping System

Maintain the temporary drainage pump and piping system provided by the P310 project for Drydock 1 so that it operates continuously at all times once the existing drainage system is no longer able to remain operational due to the construction of P-381. A plan of the system including all pumps, piping, and required appurtenances shall be provided to the Contractor by the Government. The P381 Contractor will be responsible for all maintenance of this system throughout the duration of the project and shall provide services of factory trained and certified maintenance personnel. Provide maintenance services in accordance with manufacturer's recommended schedule. Remove temporary drainage system in its' entirety at the completion of the project.

2.3.4 Temporary power

The Contractor shall maintain the temporary power and backup power for the dewatering pumps from two independent sources of power during docking/undocking evolutions that is being provided by the P310 project.

The temporary drainage pumps are provided with temporary and backup power from two independent sources of power. In addition, a diesel generator that can power the drainage system and can be operational within 30 minutes of a loss of power is on site and shall remain on site at all times during construction.

Add the below paragraph:

2.3.6 Temporary Dry Dock Stair Access

The Contractor shall provide a temporary removable staging type stair tower for access to the dry dock floor when a vessel is in drydock. The intent is to allow the contractor access to the pump systems for maintenance or to respond if the pumps fail without requiring a Government escort.

The top and bottom of the stair shall be provided with a secure lockable chain link fence enclosure. The configuration of the fence enclosures shall be coordinated with the Government.

TEMPORARY SUPPORT OF EXCAVATION

The contract documents currently show temporary supports of excavation (SOE) that have been designed by the Designer of record.

These elements may be designed by the contractor to suit his means and methods of construction. The contractor’s designs must ensure that the existing structures being supported are not compromised negatively in any way. Additionally, the contractor’s designs of the temporary support of excavation shall not impact the permanent project’s geometry or structural capacities or impart loads on the structures that may compromise structural stability, integrity or capacity.

The contractor shall provide for review to the Government all SOE drawings and calculations signed and sealed by a professional engineer for review and approval.

The temporary supports of excavation include the elements on the following drawings:

BJ101 – BJ502

BK102-BK503

BS101

BN101-BN301

BL101

BW101

SECTION 35 20 14.01 22 TEMPORARY REMOVABLE BOX COFFERDAM FOR SUPER FLOOD

Delete the Specification Section in its’ entirety.

NAVFAC Dwg. No. 128123218

Y-026 - REMOVABLE BOX COFFERDAM FOR SUPER FLOODING - PLAN AND DETAILS - SHEET

Delete sheet in its’ entirety from the project

NAVFAC Dwg. No. 128123219

Y-027 - REMOVABLE BOX COFFERDAM FOR SUPER FLOODING - PLAN AND DETAILS - SHEET

NAVFAC Dwg. No. 128123220

Y-028 - REMOVABLE BOX COFFERDAM FOR SUPER FLOODING - PLAN AND DETAILS - SHEET

NAVFAC Dwg. No. 128123221

Y-029 - REMOVABLE BOX COFFERDAM FOR SUPER FLOODING - PLAN AND DETAILS - SHEET

On NAVFAC Dwg. No. 12822979

CHANGE G103 MILESTONE PLAN as follows:

Revised Milestones, Dates and associated major work element notes

On NAVFAC Dwg. No. 12822980

CHANGE G104 CONSTRUCTION SEQUENCING & PHASING GENERAL NOTES as follows:

Revised general phasing note 4.

Added general phasing notes 14 through 19.

On NAVFAC Dwg. No. 12822981

CHANGE G105 CONSTRUCTION SEQUENCING & PHASING PLAN – PHASE 1 as follows:

Revised Phase 1 dates from Contract NTP through October 2023.

Removed all references to blasting.

Removed all installation labels for DD1E temporary pumps.

Updated extend of hatching indicating areas & elements accessible for construction.

On NAVFAC Dwg. No. 12822982

CHANGE G106 CONSTRUCTION SEQUENCING & PHASING PLAN – PHASE 1 ENLARGEMENT as follows:

Removed all references to blasting.

Revised labels for DD1E temporary pumps to indicate by others.

Updated extend of hatching indicating areas & elements accessible for construction.

Removed note 10.

On NAVFAC Dwg. No. 12822983

CHANGE G107 CONSTRUCTION SEQUENCING & PHASING PLAN -PHASE 1A as follows:

Revised Phase 1A to Vessel 1 docking evolution to DD1E Revised Phase 1A dates to February 2022 to March 2022.

On NAVFAC Dwg. No. 12822984

CHANGE G108 CONSTRUCTION SEQUENCING & PHASING PLAN – PHASE 1B as follows:

Revised Phase 1B to Vessel 1 critical shipyard operations.

Revised Phase 1B dates to June 2022 to December 2022.

On NAVFAC Dwg. No. 12822985

CHANGE G109 CONSTRUCTION SEQUENCING & PHASING PLAN – PHASE 1C as follows:

Revised Phase 1C to Vessel 1 and 2 evolutions for DD1E.

Revised Phase 1C dates October 2023 to October 2023.

On NAVFAC Dwg. No. 12822986

CHANGE G110 CONSTRUCTION SEQUENCING & PHASING PLAN – PHASE 2 as follows:

Revised Phase 2 to represent phasing from the docking of Vessel 2 at DD1E (Milestone 4) through Milestone 5.

Revised Phase 2 dates to October 2023 to July 2025.

On NAVFAC Dwg. No. 12822987

CHANGE G111 CONSTRUCTION SEQUENCING & PHASING PLAN – PHASE 2A as follows:

Revised Phase 2A to Vessel 2 critical shipyard operations.

Revised Phase 2A dates to March 2024 to September 2024.

On NAVFAC Dwg. No. 12822988

CHANGE G112 CONSTRUCTION SEQUENCING & PHASING PLAN - PHASE 2B as follows:

Revised Phase 2B to Vessel 2 and 3 evolutions for DD1E.

Revised Phase 2B dates to July 2025 to August 2025.

On NAVFAC Dwg. No. 12822989

CHANGE G113 CONSTRUCTION SEQUENCING & PHASING PLAN – PHASE 3 as follows:

Revised Phase 3 to represent phasing for Milestone 6.

Revised Phase 3 dates to August 2025 to October 2026.

On NAVFAC Dwg. No. 12822990

CHANGE G114 CONSTRUCTION SEQUENCING & PHASING PLAN - PHASE 3A as follows:

Revised Phase 3A to Vessel 3 critical shipyard operations.

Revised Phase 3A dates to December 2025 to June 2026

On NAVFAC Dwg. No. 12822991

CHANGE G115 CONSTRUCTION SEQUENCING & PHASING PLAN - PHASE 4 as follows:

Revised Phase 4 to represent phasing from Milestone 7 through Milestone 9.

Revised Phase 4 dates as October 2026 to April 2027.

On NAVFAC Dwg. No. 12822992

CHANGE G116 CONSTRUCTION SEQUENCING & PHASING PLAN - PHASE 4A as follows:

Revised sheet to Phase 4A for certification and vessel evolution for DD1N.

Revised Phase 4A dates to October 2026 to January 2027.

On NAVFAC Dwg. No. 12822993

CHANGE G117 CONSTRUCTION SEQUENCING & PHASING PLAN - PHASE 5 as follows:

Revised Phase 5 to represent phasing from Milestone 10 through Milestone 12.

Revised Phase 5 dates to April 2027 to May 2028.

On NAVFAC Dwg. No. 12822994

CHANGE G118 CONSTRUCTION SEQUENCING & PHASING PLAN - PHASE 5A as follows:

Revised Phase 5A to Vessel 3 and 4 evolutions for DD1E.

Revised Phase 5A dates to April 2027 to May 2027.

On NAVFAC Dwg. No. 12822995

CHANGE G119 CONSTRUCTION SEQUENCING & PHASING PLAN - PHASE 5B as follows:

Revised Phase 5B to Vessel 4 critical shipyard operations.

Revised Phase 5B dates to September 2027 to March 2028.

On NAVFAC Dwg. No. xxxxxx

CHANGE G119A CONSTRUCTION SEQUENCING & PHASING PLAN – PHASE 5C as follows:

Added additional sheet Phase 5C representee phasing for vessel evolution for DD1W docking.

Dates for Phase 5C are March 2028 to May 2028.

---END OF AMENDMENT---