Q_AND_A_Responses_1.docx
DOCX document 27 KB Posted
- Attached to
- USNS ARCTIC Mid-Term Availability Federal contract opportunity
- Solicitation number
- N32205-18-R-4256
View the file
Other files for this federal contract opportunity
Show all 50
USNS ARCTIC Mid-Term Availability has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N32205-18-R-4256
QUESTIONS AND ANSWERS #1
The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.
QUESTION #1:
SPECIFICATION ITEM NO.: 103, PARAGRAPH / SECTION NO: 7.1, TITLE: ABS Tank Inspection and Testing; Paragraph 7.1 says to perform overall tank surveys on tanks listed in Reference 2.6. There is no Reference 2.6 listed. Please clarify.
ANSWER: Para 7.1 is in error; work item is revised to state refer to Enclosure 2.2.1.The new work item file name is 0103 ABS TANK INSPECTION AND TESTING REV-ARCTIC 2.
QUESTION #2:
SPECIFICATION ITEM NO.: 112, PARAGRAPH / SECTION NO: 7.1, TITLE: CHT Tanks Steel Replacement; Paragraph 7.1 says to perform the requirements of this work requirement following the removal of the coating system is complete (Work Item 110), and thickness measurements have identified areas of wasted steel. (Work Item 112). Should this reference to WI 112 be WI 111?
ANSWER: Correct, the referenced work item is 111. Work Item 112 has been revised and its new file name is 0112 A CHT TANKS STEEL REPLACEMENT REV-ARCTIC 1.
QUESTION #3:
SPECIFICATION ITEM NO.: 503; PARAGRAPH / SECTION NO: 7.1.6(a); TITLE: Replace 100 Feet of Piping; Both the title and paragraph 1 say 100 feet. Paragraph 7.1.6(a) indicates 200 feet. Which is correct?
ANSWER: Para 7.1.6(a) has been corrected to reflect 100 feet.
The work item has been revised and the new file name is 0503 A REPLACE 100 FT OF PIPING REV ARCTIC 1.
QUESTION #4
SPECIFICATION ITEM NO.: 504, PARAGRAPH / SECTION NO: various, TITLE: Port and Stbd RHIB Davit Inspection; Paragraphs 7.7.d and 7.7.e reference GFM, but paragraph 4 says none. Please clarify.
ANSWER: GFM has been added to Paragraph 4. Work item has been revised; new work item file name is 0504 A PORT AND STBD RHIB DAVIT INSPECTION REV-ARCTIC 1.
QUESTION #5
SPECIFICATION ITEM NO.: 003, PARAGRAPH / SECTION NO: 2.2.2, TITLE: Approach, Berth, and Mooring Requirements; There is nothing listed in enclosure 2.2.2. Please provide the listing?
ANSWER: Notational Arrival Conditions Added.
QUESTION #6
SPECIFICATION ITEM NO.: 113, PARAGRAPH / SECTION NO: 2.2 & 2.3, TITLE: Replace Sounding Tube Deck Socket Covers; References 2.2 and 2.3 were not provided with the references. Please provide.
ANSWER: Please see References provided.
QUESTION #7
SPECIFICATION ITEM NO.: PARAGRAPH / SECTION NO: Clause 52.211-11 (a), There is no amount listed for liquidated damages. Please provide?
ANSWER: Liquidated damages is in the amount of $186,436. 00 per calendar day of delay.