New A Work Item 1005
View the file
Other files
Show 40 more
Latest 50 of 60 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USNS ARCTIC
T-AOE 8
UNREP GEAR
N32205-18-R-4256
6 JUNE, 2018
ITEM NO. 1005
CATEGORY “A”
PHD/NSWC/KCS
STATION SIX ANTI SLACK DEVICE REPAIR SUPPORT. (Amend 1)
1.0
ABSTRACT:
This item describes support required to perform sheave replacement for the Station Six Anti Slack Device.
2.0
REFERENCES:
2.1 MSC DWG; 8391158, Station Six Ram Tensioner Work Platform.
3.0
ITEM LOCATION/DESCRIPTION:
3.1 Location/Quantity:
3.1.1 Location: Unrep Station Six
3.2 Description/Manufacturer's Data: None
4.0
GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICE:
4.1 Government Furnished Equipment (GFE): None
4.2 Government Furnished Materials (GFM): None
4.3 Government Furnished Services (GFS):
4.3.1 Port Hueneme Representative will provide technical support/guidance during the accomplishment of this work item.
5.0
NOTES:
5.1 The contractor and all subcontractors, regardless of tier, must consult the General Technical Requirements (GTRs) to determine applicability to this work item. In performance of this work item, the contractor and subcontractors, regardless of tier, must comply with the requirements of all applicable GTRs, including but not limited to GTRs 1 through 7, 22, 23, 24, 27, 28 and 29.
5.2 The contractor and all subcontractors, regardless of tier, are advised to review other work items under this contract, including but not limited to Work Items 011, 013, 014 and 021, to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in Work Item 001.
6.0 QUALITY ASSURANCE REQUIREMENTS: None additional
7.0
STATEMENT OF WORK REQUIRED:
7.1 Arrangement/Outfitting: None Additional.
7.2 Structural:
7.2.1 Provide analysis of Ref 1 to determine safe working load weight for pad eyes mounted to underlying support structure. Final calculations shall be provided via condition report.
7.2.2 Perform weight test of each pad eye using calculation results; test weight certificates shall be provided in weight test report.
7.2.3 Provide safe working load rate placard to be attached to working platform. The placard shall be mounted in a place identified by the MSCREP. Placard shall be six by eight in dimensions. Placard shall be permanently affixed by hardware.
7.2.4 Provide three hundred thirty-six hours of rigging support to PHD representative and ship’s crew for repairs.
7.3 Mechanical/Fluid: None Additional 7.4 Electrical: None additional
7.5 Electronics: None additional
7.6 Preparation of Drawings: None additional
7.7 Inspection/Test: Listed in Para 7.2 7.8 Painting: None Additional 7.9 Marking: None additional
7.10 Manufacturer’s Representative: None
8.0 GENERAL REQUIREMENTS: None additional