EUHW Attch 11 v2, Service Level Requirements FINAL.xlsx
XLSX spreadsheet 334 KB Posted
- Attached to
- NGEN-R End User Hardware as a Service and Supply
- Solicitation number
- N00039-18-R-0004
About this file
This document outlines service level requirements for the Naval Enterprise Network Program solicitation N00039-18-R-0004. The solicitation seeks end user hardware as a service and supply, including laptops, desktops, tablets, virtual desktops, thin/zero clients, and associated peripherals to be delivered to Department of the Navy locations. The service level requirements specify targets for order to delivery timelines based on device type and location, with most items to be delivered within 10-15 days domestically and 15 days overseas. Recall and replacement targets are also outlined for safety versus non-safety issues. Additional requirements include acknowledgement of orders within 24 hours, asset data transfers to the property system of record within 24 hours, and contract ordering application receipt responsiveness of 99.5%.
View the file
Other files
Show 40 more
Latest 50 of 62 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Title Page
| Naval Enterprise Network Program |
| UNITED STATES NAVY |
| Solicitation: N00039-18-R-0004 |
| Attachment 11, EUHW Service Level Requirements |
Date: 2 November 2018
| Program Executive Office Enterprise Information Systems |
| Program Manager, Naval Enterprise Networks |
| 1325 10th Street, SE, Suite 301 |
| Washington, DC 20374 |
EUHW SLRs End User Hardware (EUHW) Service Level Requirements (SLRs)
| SLR # | Service Category | SLR DESCRIPTIONS |
| SLR 37.1 | Order to Delivery | Order to Delivery - End User Hardware as a Service (EUHWaaS) & Purchased EUHW |
Deliver CONUS EUHWaaS and purchased EUHW devices(s) to the location specified in the order in ≤ 10 days.
Deliver OCONUS EUHWaaS and purchased EUHW devices(s) to the location specified in the order in ≤ 15 days.
How Measured: Contractor acknowledgement of an order and/or build-out for an as-a-service or purchased device shall be the measurement start point; Government acceptance of the order at specified base, building and room shall be the measurement end point.
Target ≥ 99.00% SLR 37.2 Order to Delivery Order to Delivery - EUHW Refresh
Deliver complete and accurate EUHW Refresh orders to the specified location no earlier than three (3) Government business days prior and no later than one (1) Government business day prior to the scheduled refresh date.
How Measured: Scheduled refresh dates will be compared to delivery dates for all EUHW devices required to execute the refresh.
Target ≥ 98.50% SLR 37.3 Order to Delivery Order to Delivery - Peripherals
Deliver peripheral(s) to the location specified in the order in ≤ 10 days CONUS and 15 days OCONUS.
How Measured: Contractor acknowledgement of an order shall be the measurement start point; Government acceptance of the order at specified base, building and room shall be the measurement end point.
Target ≥ 99.00% SLR 37.4 Order to Delivery Order to Delivery - Deployables
Deliver complete and accurate Pack-Up Kits (PUKs) to the location specified in the order ≤ 96 hours prior to the unit's scheduled deployment departure date/time.
How Measured: Scheduled departure dates for units will be compared to delivery dates for all ordered devices required to deploy.
Target ≥ 98.00% SLR 38 Acquisitions / Program Equipment Recall
Remove and replace recalled equipment in ≤ 24 hours for safety related recalls; ≤ 7 days for non-safety related recalls.
How Measured: Contractor receipt of notification from the COR to proceed with required recall actions, shall be the measurement start point; removal of recalled equipment and confirmation that replacement equipment has been shipped, shall be the measurement end point.
Targets:
Safety Recall = 100.00% Non-Safety Recall ≥ 98.50% SLR 39 Acquisitions / Program Contract Ordering Application (COA) Receipt Responsiveness
Acknowledge receipt of Government Owned and Managed Ordering (GOMO) Application orders in ≤ 24 hours.
How Measured: Contractor receipt of GOMO application orders shall be the measurement start point; Government receipt of the Contractor's order acknowledgement shall be the measurement end point.
Target ≥ 99.50% SLR 40 Acquisitions / Program Asset Record Management
Submit accurate and complete asset data files to the Accountable Property System of Record (APSR) in ≤ 24 hours.
How Measured: The date/time stamp for delivery of EUHWaaS, purchased EUHW, refreshed EUHW or decommissioned EUHW shall be the measurement start point; Government confirmation of the transfer of complete and accurate asset data to the SMIT contractor shall be the measurement end point.
Target ≥ 99.50% image1.png