Specification_-_09_6513_RESILIENT_BASE_AND_ACCESSORIES.pdf

PDF 97 KB Posted

Attached to
Restack of the William J. Green Federal Building
Solicitation number
GS-03-P-16-AZ-C-7004
Issued by

About this file

Specification 09 6513 Resilient Base and Accessories

View the file

Other files

File Type Posted
Amendment_0007.pdf PDF
Ta4.26_-_02_Enlarged_Plans_-_Conference_Room_05.pdf PDF
Amendment_0006.pdf PDF
Flow_Test.pdf PDF
23_0900_INSTRUMENTATION_AND_CONTROL_FOR_HVAC._-_Add__2.pdf PDF
S4-02_-_ENLARGED_PARTIAL_PLANS.pdf PDF
Amendment_0005.pdf PDF
Specification_-_Table_of_Contents.pdf PDF
10_2240_Folding_Glass-Panel_Partitions.pdf PDF
MS-502.pdf PDF
09_5113_acoustical_panel_ceilings.pdf PDF
23_2113_HYDRONIC_PIPING_-_Add__2.pdf PDF
MP-405.pdf PDF
01_1030_TELECOMMUNICATIONS_SYSTEMS_OVERVIEW.pdf PDF
08_8713_Window_Film_Type_01.pdf PDF
01_ARCHITECTURAL_-_Addendum_02.pdf PDF
Addendum_No_02_-_Cover_Sheet.pdf PDF
09_3033_stone_tiling.pdf PDF
10_1423_Panel_Signage.pdf PDF
MD-124.pdf PDF
MP-103_2.pdf PDF
M-001.pdf PDF
09_6813_tile_carpeting.pdf PDF
S3-01_-_TYPICAL_DETAILS.pdf PDF
MP-104.pdf PDF
MS-501.pdf PDF
10_2226_Operable_Partitions.pdf PDF
MD-123.pdf PDF
08_8713_Window_Film_Type_02.pdf PDF
09_3000_ceramic_tile.pdf PDF
10_2241_Vertically_Folding_Panel_Doors.pdf PDF
MD103.pdf PDF
MD501.pdf PDF
Pre-Alteration_Asbestos_Assessment.pdf PDF
Specification_-_23_0529_HANGERS_AND_SUPPORTS_FOR_HVAC_PIPING_AND_EQUIPMENT-Addendum__1.pdf PDF
Ty6-00.pdf PDF
Specification_-_01_1000_SUMMARY.pdf PDF
MH104.pdf PDF
Amendment_0004.pdf PDF
Construction_Sequencing_Diagrams.pdf PDF
Addendum_No_01_-_Cover_Sheet.pdf PDF
01_ARCHITECTURAL_-_Addendum_01.pdf PDF
MH103.pdf PDF
Specification_-_01_2400_OPTIONS.pdf PDF
Specification_-_Table_of_Contents.pdf PDF
Specification_-_09_5113_ACOUSTICAL_PANEL_CEILINGS.pdf PDF
MD104.pdf PDF
Amendment_0003.pdf PDF
Amendment_0002.pdf PDF
02_STRUCTURAL.pdf PDF
Show 40 more

Latest 50 of 68 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Green Federal Building Consolidation Project 600 Arch Street

Philadelphia, Pennsylvania

GSA # GS-03P-14-AZ-C-0020

RESILIENT BASE AND ACCESSORIES 096513 - 1

27 MAY 2016

PROPERTY OF THE U.S. GOVERNMENT - FOR OFFICIAL USE ONLY

Do not remove this notice - Properly destroy documents when no longer needed

SECTION 096513 - RESILIENT BASE AND ACCESSORIES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Resilient base.

1.3 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Samples for Initial Selection: For each type of product indicated.

C. Samples for Verification: For each type of product indicated, in manufacturer's standard-size Samples but not less than 12 inches long, of each resilient product color, texture, and pattern required.

1.4 QUALITY ASSURANCE

A. Fire-Test-Response Characteristics: As determined by testing identical products according to ASTM E 648 or NFPA 253 by a qualified testing agency.

1. Critical Radiant Flux Classification: Class I, not less than 0.45 W/sq. cm.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Store resilient products and installation materials in dry spaces protected from the weather, with ambient temperatures maintained within range recommended by manufacturer, but not less than 50 deg F or more than 90 deg F.

1.6 PROJECT CONDITIONS

A. Maintain ambient temperatures within range recommended by manufacturer, but not less than 70 deg F or more than 95 deg F, in spaces to receive resilient products during the following time periods:

RESILIENT BASE AND ACCESSORIES 096513 - 2

1. 48 hours before installation.

2. During installation.

3. 48 hours after installation.

B. Until Substantial Completion, maintain ambient temperatures within range recommended by manufacturer, but not less than 55 deg F or more than 95 deg F Insert temperature.

C. Install resilient products after other finishing operations, including painting, have been completed.

PART 2 - PRODUCTS

2.1 RESILIENT BASE

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. Allstate Rubber Corp.; Stoler Industries.

b. Armstrong World Industries, Inc.

c. Burke Mercer Flooring Products; Division of Burke Industries, Inc.

d. Endura Rubber Flooring; Division of Burke Industries, Inc.

e. Estrie Products International; American Biltrite (Canada) Ltd.

f. Flexco, Inc.

g. Johnsonite.

h. Mondo Rubber International, Inc.

i. Musson, R. C. Rubber Co.

j. Nora Rubber Flooring; Freudenberg Building Systems, Inc.

k. PRF USA, Inc.

l. Roppe Corporation, USA.

m. VPI, LLC; Floor Products Division.

B. Resilient Base Standard: ASTM F 1861.

1. Material Requirement: Type TS (rubber, vulcanized thermoset).

2. Manufacturing Method: Group I (solid, homogeneous).

3. Style: Straight (flat or toeless).

C. Minimum Thickness: 0.125 inch.

D. Height: 2-1/2 inches.

E. Lengths: Coils in manufacturer's standard length.

F. Outside Corners: Preformed.

G. Inside Corners: Job formed.

H. Finish: As selected by Architect from manufacturer's full range.

I. Colors and Patterns: As selected by Architect from full range of industry colors.

RESILIENT BASE AND ACCESSORIES 096513 - 3

2.2 INSTALLATION MATERIALS

A. Trowelable Leveling and Patching Compounds: Latex-modified, portland cement based or blended hydraulic-cement-based formulation provided or approved by manufacturer for applications indicated.

B. Adhesives: Water-resistant type recommended by manufacturer to suit resilient products and substrate conditions indicated.

1. Use adhesives that comply with the following limits for VOC content when calculated according to 40 CFR 59, Subpart D (EPA Method 24):

a. Cove Base Adhesives: Not more than 50 g/L.

b. Rubber Floor Adhesives: Not more than 60 g/L.

C. Stair-Tread-Nose Filler: Two-part epoxy compound recommended by resilient tread manufacturer to fill nosing substrates that do not conform to tread contours.

D. Metal Edge Strips: Extruded aluminum with mill finish of width shown, of height required to protect exposed edges of tiles, and in maximum available lengths to minimize running joints.

E. Floor Polish: Provide protective liquid floor polish products as recommended by resilient stair tread manufacturer.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, with Installer present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work.

B. Verify that finishes of substrates comply with tolerances and other requirements specified in other Sections and that substrates are free of cracks, ridges, depressions, scale, and foreign deposits that might interfere with adhesion of resilient products.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Prepare substrates according to manufacturer's written instructions to ensure adhesion of resilient products.

B. Concrete Substrates for Resilient Stair Treads and Accessories: Prepare according to

ASTM F 710.

1. Verify that substrates are dry and free of curing compounds, sealers, and hardeners.

2. Remove substrate coatings and other substances that are incompatible with adhesives and that contain soap, wax, oil, or silicone, using mechanical methods recommended by manufacturer. Do not use solvents.

RESILIENT BASE AND ACCESSORIES 096513 - 4

3. Alkalinity and Adhesion Testing: Perform tests recommended by manufacturer.

4. Moisture Testing: Perform tests recommended by manufacturer. Proceed with installation only after substrates pass testing.

C. Fill cracks, holes, and depressions in substrates with trowelable leveling and patching compound and remove bumps and ridges to produce a uniform and smooth substrate.

D. Do not install resilient products until they are same temperature as the space where they are to be installed.

1. Move resilient products and installation materials into spaces where they will be installed at least 48 hours in advance of installation.

E. Sweep and vacuum clean substrates to be covered by resilient products immediately before installation.

3.3 RESILIENT BASE INSTALLATION

A. Comply with manufacturer's written instructions for installing resilient base.

B. Apply resilient base to walls, columns, pilasters, casework and cabinets in toe spaces, and other permanent fixtures in rooms and areas where base is required.

C. Install resilient base in lengths as long as practicable without gaps at seams and with tops of adjacent pieces aligned.

D. Tightly adhere resilient base to substrate throughout length of each piece, with base in continuous contact with horizontal and vertical substrates.

E. Do not stretch resilient base during installation.

F. On masonry surfaces or other similar irregular substrates, fill voids along top edge of resilient base with manufacturer's recommended adhesive filler material.

G. Preformed Corners: Install preformed corners before installing straight pieces.

H. Job-Formed Corners:

1. Inside Corners: Use straight pieces of maximum lengths possible.

3.4 RESILIENT ACCESSORY INSTALLATION

A. Comply with manufacturer's written instructions for installing resilient accessories.

3.5 CLEANING AND PROTECTION

A. Comply with manufacturer's written instructions for cleaning and protection of resilient products.

B. Perform the following operations immediately after completing resilient product installation:

RESILIENT BASE AND ACCESSORIES 096513 - 5

1. Remove adhesive and other blemishes from exposed surfaces.

2. Sweep and vacuum surfaces thoroughly.

3. Damp-mop surfaces to remove marks and soil.

C. Protect resilient products from mars, marks, indentations, and other damage from construction operations and placement of equipment and fixtures during remainder of construction period.

D. Cover resilient products until Substantial Completion.

END OF SECTION 096513